Professional Documents
Culture Documents
23 Stone dust (HBG stone chips 2.36 mm and below ) 122.5 42.60 390.494 512.994
24 Stone Boulder 150 - 300mm 355 42.60 390.494 745.494
25 Supply of stone 150 -200 mm size 445 42.60 390.494 835.494
26 Boulder with minimum size of 300 mm for Pitching at Site 378 42.60 390.494 768.494
27 Lime (Slaked & Screened) 1322 - - 1322
28 Gravel 216.3 44 398.2609 614.5609
29 Sand for mortar 1280 42.60 390.494 1670.494
30 Sand for filling, blindage 1280 53.42 473.7352516574 1753.735251657
Cement (From Barathi Cement, Nallalingayapalli, 5960.00
35 Andrapradesh) 273 1186.39 7146.39
36 Steel Fe500 ( From Bellary, Karnataka) 51750.00 96 472.677 52222.677
37 20 mm metal SS5 1432 42.60 390.494 1822.494
38 40 mm metal SS5 1029 42.60 390.494 1419.494
39 10 mm metal SS5 977 42.60 390.494 1367.494
40 RR masonary (Hard Granite) 445 42.60 390.494 835.494
41 CR masonary 355 42.60 390.494 745.494
42 Bond stone 642 42.60 390.494 1032.494
43 Dry Stone for Apron or revetment 378 53.42 473.735 851.735
Material Average
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 546
Batching and Mixing Plant (a) 30 cum
P&M-002 Concrete Mixing cum/hour 20 hour 3134
capacity
Batching and Mixing Plant (b) 15 - 20 cum
P&M-003 Concrete Mixing cum/hour 13 hour 2547
capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1836
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 339
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 3457
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 438
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 398
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 398
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 4415
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 2859
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 1369
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1380
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 1194
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 30652
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 24206
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 20350
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 16494
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 3391
Soil Ordinary/Soil Marshy / Soil
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 hour 2182
Unsuitable
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 10133
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 21317
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 106
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 610
Clearing /Spreading /GSB
P&M-032 Motor Grader 3.35 mtr blade cum/hour 200/200/50/50 hour 3959
/WBM
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1504
Paver Finisher Hydrostatic with sensor control Paving of DBM/ BM/SDC/
P&M-034 cum/hour 40 hour 4577
100 TPH Premix
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 1669
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 4912
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 1552
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 220
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 160
Soil Compaction /BM
P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 788
Compaction
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1614
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 530
WMM, Hotmix etc.
Transportation of Concrete Mix
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 1592
to site
Transportation of Concrete Mix
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 7.28
to site
Transportation of Concrete Mix
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 1459
to site
Transportation of Concrete Mix
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 7.28
to site
P&M-053 Tractor Pulling capacity in HP 50 hour 620
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 38
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 965
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 4
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 2277
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1927
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 349
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 0
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 10109
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 4045
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 0
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 0
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 0
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 0
(C) Materials
M-009 Granular Material or hard murrum for GSB works at Site Cum 745
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 1082
Rate at
Plant
Description Unit
(HMP/Batch
Rate at Site
ing)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1473 1473
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1017 1017
M-020 Close graded Granular sub-base Material 2.36 mm cum 513 513
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 513 513
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 513 513
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1405 1405
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 1369 1369
M-089 Credit for excavated rock found suitable for use cum
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 807
M-092 Earth Cost or compensation for earth taken from private land cum 196
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab
M-093 metre 0
unit conforming to clause 915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 2548
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 807
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 77
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 11
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 7500
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 231
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 0
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 0
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced
M-155 metre 150
polymer/polymeric strips)
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 0
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 0
M-159 Sand bags (Cost of sand and Empty cement bag) nos 0
M-162 Seeds kg 0
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 17
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 496
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 885
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 45000
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 0
M-173 Steel helmet and cushion block on top of pile head during driving. kg 0
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 74
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 3450
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 6,159.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 7,747.00
PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Item 12.8 (A) cum 5,644.00
by Mixer
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Item 12.8 (G) cum 5,974.00
by Batching Plant
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 8,682.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 708.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 9,387.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 10,571.39
RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching
Item 14.1(C) cum
Plant 5,988.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 63,459.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 81,161.00
Metal, Sand Cartrage Cost as per SOR' 2020-21 of Annexure V in Page 38
Cost of bitumen 60/70, 80/100 and CRMB Grade and Bitumen Emulsion
Lead 76 76 76
Bitumen
Bitumen (Cationic
Sl (Cationic Bitumen (60/70
Particulars Emulsion)
No Emulsion) grade) V40
Packed - RS1
Packed SS1
1 Basic price of Bitumen 50620.00 50322.00 34950.00
4 Drum Deduction
This softawre is based on Standard Data book for analysis of Rates for Road and Bridge Works
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
2 Sand Lead
3 Metal Lead
4 Gravel Lead
Average Lead for Gravel 43.61
5 Borrow Soil
7 Cement Lead
8 Steel Lead
Metal Lead
Source to Project Road at 61+200 40.66
Lead if any 0.00
Quarry To CMP 40.66
Sand Lead
Source to Project Road at 61+200 40.66
Lead if any 0.00
Quarry To CMP 40.66
Bitumen Lead
IOCL, Chennai to CH:35+800 43.00
CH:35+800 to CH:61+200 CMP 24.20
Factory To CMP 67.20
Cement Lead
Nallalingayapalli to to CH:61+200 CMP 273.00
Total Lead 273.00
Steel Lead
Kamahi Steel Factory , Gummidipundi to
95.90
CH:61+200 CMP
Total Lead 95.90
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Loading and unloading of stone boulder / stone aggregates /
1.1
sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
1 Min
ii) Loading by front end loader 1 cum bucket capacity @ 25
13 Min
cum per hour
iii) Maneuvering, reversing, dumping and turning for return 2 Min
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 530.19 174.96 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 1379.89 455.36 P&M-017
b) Overheads @ 0.08 on (a) 50.43
c) Contractors profit @ 0.1 on (a+b) 68.08
Cost for 5.5 cum = a+b+c 748.83
Rate per cum = (a+b+c)/ 5.5 136.15
Note Unloading will be by tipping. say 136.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 530.19 212.08 P&M-048
Time taken for empty return trip. hour 0.290 530.19 153.76 P&M-048
b) Overheads @ 0.08 on (a) 29.27
c) Contractors profit @ 0.1 on (a+b) 39.51
cost for 100 t km = a+b+c 434.61
Rate per t.km = (a+b+c)/100 4.35
say 4.30
Katcha Track and Track in river bed / nallah bed and choe
1.4(III) Case III
bed.
Speed with load : 10 km / hour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 530.19 530.19 P&M-048
Time taken for empty return trip hour 0.670 530.19 355.23 P&M-048
b) Overheads @ 0.08 on (a) 70.83
c) Contractors profit @ 0.1 on (a+b) 95.63
Cost for 100 t .km = a+b+c 1051.88
Rate per t.Km = (a+b+c)/100 10.52
say 10.50
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 639.10 38.35 L-12
Mazdoor day 1.500 719.40 1079.10 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 835.49 919.04 M-002
c) Overheads @ 0.08 on (a+b) 162.92
d) Contractors profit @ 0.1 on (a+b+c) 219.94
Rate per cum = a+b+c+d 2419.35
say 2419.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 639.10 281.20 L-12
Mazdoor day 9.000 719.40 6474.60 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 610.07 4392.49 P&M-031
Air compressor 250 cfm hour 7.200 546.40 3934.07 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour hour 6.000 3390.68 20344.10 P&M-025
Tipper 10 tonne capacity for carriage of stone chips from
hour 6.000 530.19 3181.15 P&M-048
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Bitumen pressure distributor hour 6.000 1835.99 11015.96 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 788.34 4730.06 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 51155.00 552474.00 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum
cum 135.000 1822.49 246036.69 M-053
per sqm
d) Overheads @ 0.08 on (a+b+c) 69003.25
e) Contractors profit @ 0.1 on (a+b+c+d) 93154.39
Cost for 9000 sqm= a+b+c+d+e 1024698.31
Rate per sqm = (a+b+c+d+e)/9000 113.86
say 114.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 639.10 281.20 L-12
Mazdoor day 9.000 719.40 6474.60 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 610.07 4392.49 P&M-031
Air compressor 250 cfm hour 7.200 546.40 3934.07 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour hour 6.000 3390.68 20344.10 P&M-025
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tipper 10 tonne capacity for carriage of stone chips from
hour 6.000 530.19 3181.15 P&M-048
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 2277.05 13662.29 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 51155.00 460395.00 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum
cum 90.000 1753.49 157814.46 M-052
per sqm
d) Overheads @ 0.08 on (a+b+c) 55293.73
e) Contractors profit @ 0.1 on (a+b+c+d) 74646.54
Cost for 9000 sqm= a+b+c+d+e 821111.94
Rate per sqm = (a+b+c+d+e)/9000 91.23
say 91.00
1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
Note
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
5.15 516 Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix = 264
tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler.
Pneumatic tyred roller with individual wheel load not
hour 6.000 1746.86 10481.14 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 51453.33 996136.53 M-077
Fine aggregate 4.75 mm and below 87 % of total mix,80 x
2.2 x 0.87 = 153.12 tonnes. Taking density1.5,= 153.12/1.5 cum 102.080 1753.74 179021.29 M-005
= 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 3037.00 10690.24 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overheads @ 0.08 on (a+b+c) 98467.30
e) Contractors profit @ 0.1 on (a+b+c+d) 132930.85
Cost for 16000 sqm= a+b+c+d+e 1462239.34
Rate per sqm = (a+b+c+d+e)/16000 91.39
say 91.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor day 5.000 719.40 3597.00 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 51453.33 882939.20 M-077
Fine aggregate 3 mm and below 85 % of total mix, 60x 2.2 x
cum 74.800 1753.74 131179.40 M-005
0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 3037.00 8017.68 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
d) Overheads @ 0.08 on (a+b+c) 84472.26
e) Contractors profit @ 0.1 on (a+b+c+d) 114037.56
Cost for 30000 sqm= a+b+c+d+e 1254413.12
Rate per sqm = (a+b+c+d+e)/20000 62.72
say 63.00
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor day 5.000 719.40 3597.00 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler.
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 51453.33 651913.73 M-077
Fine aggregate 2.36 mm and below,82 % of total mix,36x
cum 43.300 512.99 22212.64 M-022
2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 3037.00 4798.46 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
d) Overheads @ 0.08 on (a+b+c) 57015.35
e) Contractors profit @ 0.1 on (a+b+c+d) 76970.72
Cost for 24000 sqm= a+b+c+d+e 846677.93
Rate per sqm = (a+b+c+d+e)/24000 35.28
say 35.00
1.Tack coat, if required to be provided, before laying slurry
Note
seal may be measured and paid separately
Bitumen emulsion pressure distributor @ 1750 sqm per hour tonne 6.000 1835.99 11015.96 P&M-004
c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 51453.33 405452.27 M-077
d) Overheads @ 0.08 on (a+b+c) 34051.35
e) Contractors profit @ 0.1 on (a+b+c+d) 45969.33
Cost for 10500 sqm= a+b+c+d+e 505662.60
Rate per sqm = (a+b+c+d+e)/10500 48.16
say 48.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor for precoating of grit day 4.000 719.40 2877.60 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 754.74 19812.03 M-024
Bitumenemulsion for precoating grit @ 2 % of grit,39.38 x
tonne 0.790 51453.33 40648.13 M-077
0.02
63440.02
6.04
say 6.00
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Hydraulic Chip spreader hour 6.000 3390.68 20344.10 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 788.34 4730.06 P&M-044
c) Material
Modified binder tonne 9.450 26356.18 249065.90 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 1075.49 112926.87 M-050
d) Overheads @ 0.08 on (a+b+c) 32759.32
e) Contractors profit @ 0.1 on (a+b+c+d) 44225.08
Cost for 10500 sqm= a+b+c+d+e 486475.87
Rate per sqm = (a+b+c+d+e)/10500 46.33
say 46.00
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfem capacity hour 6.000 546.40 3278.39 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Hydraulic Chip spreader hour 6.000 3390.68 20344.10 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 788.34 4730.06 P&M-044
c) Material
Modified binder tonne 15.750 26356.18 415109.84 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 1367.49 172304.24 M-051
d) Overheads @ 0.08 on (a+b+c) 50904.78
e) Contractors profit @ 0.1 on (a+b+c+d) 68721.46
Cost for 10500 sqm= a+b+c+d+e 755936.02
Rate per sqm = (a+b+c+d+e)/10500 71.99
say 72.00
Case IV Case - IV : Bitumen Impregnated Geotextile
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 639.10 357.90 L-12
Mazdoor day 12.000 719.40 8632.80 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 610.07 1708.19 P&M-031
Air compressor 250 cfem capacity hour 2.800 546.40 1529.92 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 1835.99 3671.99 P&M-004
Pneumatic roller hour 2.000 1746.86 3493.71 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per
tonne 3.680 0.00 0.00 M-075
sqm
Geotextile including 10 % for overlaps sqm 3850.000 0.00 0.00 M-108
d) Overheads @ 0.08 on (a+b+c) 1663.32
e) Contractors profit @ 0.1 on (a+b+c+d) 2245.48
Cost for 10500 sqm= a+b+c+d+e 24700.31
Rate per sqm = (a+b+c+d+e)/3500 7.06
say 7.00
Sub-
analysis Cement mortar1:2 (1cement :2 sand)
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.67 7146.39 4802.37
Sand cum 0.93 1753.74 1636.82
b) Labour
Mate day 0.04 639.10 25.56
Mazdoor day 0.90 719.40 647.46
Total Material and Labour = (a+b) 7112.00
Sub-
analysis Cement mortar1:6 (1cement :6 sand)
(D)
Unit = 1 cum
Taking output = 1 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Materials
Cement MT 0.29 7146.39 2058.16
Sand cum 1.20 1753.74 2104.48
b) Labour
Mate day 0.04 639.10 25.56
Mazdoor day 0.90 719.40 647.46
Total Material and Labour = (a+b) 4836.00
Stone masonry work in cement mortar 1:3 in foundation
12.7 1400
complete as drawing and Technical Specification
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 573.00 3151.50 M-169
Through and bond stone each 35.00 17.00 595.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Item 12.6
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 6159.00 9238.50
(A)
b) Labour
Mate day 0.66 639.10 421.81 L-12
Mason day 7.50 947.10 7103.25 L-11
Mazdoor day 9.00 719.40 6474.60 L-13
c) Overhead charges @ 0.2 on (a+b) 5396.93
d) Contractor's profit @ 0.1 on (a+b+c) 3238.16
Cost for 5 cum = a+b+c+d 35619.75
Rate per cum (a+b+c+d)/5 7123.95
say 7124.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 493.00 2711.50
Through and bond stone Nos 35.00 17.00 595.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A) cum 1.55 6159.00 9546.45
b) Labour
Mate day 0.62 639.10 396.24
Mason day 6.00 947.10 5682.60
Mazdoor day 9.00 719.40 6474.60
c) Overheads @ 0.2 on (a+b) 5081.28
d) Contractors profit @ 0.1 on (a+b+c) 3048.77
Cost for 5 cum = a+b+c+d 33536.44
Rate per cum (a+b+c+d)/5 6707.29
say 6707.00
The labour already considered in cement mortar has been
@ taken into account while proposing labour for masonry
works.
C Bottom Plug
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 7146.39 39662.46
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixer Kg 18.60 179.00 3329.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6819.00
10% extra cement may be added where under water
Note
concreting is involved.
Using Batching Plant, Transit Mixer and Crane/concrete
Case II
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 7146.39 317299.72
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 148.80 179.00 26635.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
T-Km 300L 7.28 23645.69 10.824610
Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5934.00
B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 639 204.51
Mazdoor day 8.00 719 5755.20
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2182 13092.74
c) Overheads @ 0.08 on (a+b) 1524.20
d) Contractors profit @ 0.1 on (a+b+c) 2057.66
Cost for 300 cum = a+b+c+d 22634.31
Rate per cum = (a+b+c+d)/300 75.45
say 75.00
Cost of dewatering upto 5% of (a+b) may be added, where
Note required. Assessment for dewatering shall be made as per
site conditions..
C RCC Grade M 30
II By Mechanical Means
A Bituminous course cum 558
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average
3.4 lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.) cum 316
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers,
3.6 trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to cum 76
the embankment location within all lifts and lead upto 1000m)
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000
metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and
3.7 loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in cum 101
accordance with requirements of lines, grades and cross sections.)
Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with
3.16 approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope cum 755
and compacting to meet requirement of table 300-2)
Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment
3.17 with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures cum 167
graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with
3.18 approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope cum 925
and compacted to meet requirement of table No. 300-2)
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix
plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface
A and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island
4.14 above road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407) cum 970
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch
type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
5.6 hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Reinforced Cement Concrete Crash Barrier with frication Slab Provision of an Reinforced cement
7.09 concrete crash barrier with frication slab at the approaches to bridge structures,constructed with M-40 Mtetre 14077
grade concretewith HYSD reinforcement conforming toIRC:112 and as per dimensions in theapproved
drawing and at locationsdirected by the Engineer, all as specified.(Area-0.185 Sqm. /Meter)
Reinforced Earth slab
belowfrication Retaining
andWall (ReinforcedSqm./Meter)
(Area-1.032 earth retaining Crash
walls have four main
Barrier withcomponents as under: a) Excavation for
frication Slab
foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material).
7.5 b) Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing elements. d)
Earthfill with granular material which is to be retained by the wall.)
Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-
100 cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75
mm dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the
8.15 drawings.) each 3342
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
8.21 painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes metre 1882
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
8.22 board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
8.27 street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)
(ii) each
66091
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
8.35 hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part each 586
4:1973)
CHAPTER-9
PIPE CULVERTS
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically
9.1 mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 6143
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row . (Laying
Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular material in
9.2 single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets . )
I Ordinary soil
B Mechanical Means
(i) Depth upto 3 m cum 105
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 2939
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
12.4 nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 6812
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical
12.8 specifications
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 119173
B Assuming depth of water 4.0 m and height of island 4.5 m. each 480046
Providing and constructing one span service road to reach island location from one pier location to another pier location
C metre 6376
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per drawing and
12.10 technical specification. tonne 98011
12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification
A Well curb
(i) RCC M20 Grade
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case I Using concrete mixer cum 9905
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8790
(ii) RCC M25 Grade
Case I Using concrete mixer cum 10538
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9881
(iii) RCC M35 Grade
Case I Using concrete mixer cum 10749
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10115
B Well steining
(I) PCC M15 Grade cum 8195
(ii) PCC M20 Grade cum 8953
(iii) RCC M20 Grade
Case I Using concrete mixer cum 9079
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8057
(iv) PCC M25 Grade
Case I Using concrete mixer cum 9527
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8509
(v) RCC M25 Grade
Case I Using concrete mixer cum 9660
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9058
(vi) PCC M30 Grade
Case I Using concrete mixer cum 9589
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8565
(vii) RCC M30 Grade
Case I Using concrete mixer cum 9695
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8674
(viii) RCC M35 Grade
Case I Using concrete mixer cum 9853
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9272
(ix) RCC M40 Grade 9362
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 9407
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8178
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 9748
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8515
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 9807
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8577
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 9946
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8713
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 9001
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7833
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 9326
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8154
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 9383
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8214
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 7450
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 8139
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 8661
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7735
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 8717
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7787
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 8524
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 7556
(ii) RCC Grade M25
Case I Using concrete Mixer cum 9111
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8148
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 9121
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8160
(iv) RCC Grade M35
Case I Using Concrete Mixer cum 9226
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8271
(v) RCC M40 Grade cum 8815
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.12 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 2006
(ii) Beyond 3m upto 10m depth metre 2753
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3637
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6822
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 8186
(v) Beyond 30m upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter 16209
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 19451
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 2984
(ii) Beyond 3m upto 10m depth metre 6983
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9222
b Add for dewatering @ 5% of cost, if required. metre 9684
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 17299
b Add 5% of cost for dewatering of the cost, if required metre 22705
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 21624
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 41104
b Add 5% of cost for dewatering, if required metre 51791
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 49324
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 7648
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 22164
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.13 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5665
(ii) Beyond 3m upto 10m depth metre 3746
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4949
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9284
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 11142
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22060
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 26471
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 3746
(ii) Beyond 3m upto 10m depth metre 5307
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 7010
b Add for dewatering @ 5% of cost, if required. metre 7360
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13149
b Add 5% of cost for dewatering on the cost, if required metre 17258
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 16436
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 31241
b Add 5% of cost for dewatering, if required metre 39363
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 37489
C Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 8688
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 28861
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.14 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 3501
(ii) Beyond 3m upto 10m depth metre 4282
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5655
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10605
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 12727
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3728
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 4474
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 4733
(ii) Beyond 3m upto 10m depth metre 7300
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9641
b Add for dewatering @ 5% of cost, if required. metre 10123
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 18085
b Add 5% of cost for dewatering on the cost, if required metre 23736
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 22606
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 42967
b Add 5% of cost for dewatering, if required metre 54138
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 51561
C Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 9053
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 32390
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil,
12.15 clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 3509
(ii) Beyond 3m upto 10m depth metre 4544
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6003
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11261
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 13513
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26755
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 32106
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 5103
(ii) Beyond 3m upto 10m depth metre 7689
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10155
b Add for dewatering @ 5% of cost, if required. metre 10662
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 19046
b Add 5% of cost for dewatering on the cost, if required metre 24998
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 23807
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 45249
b Add 5% of cost for dewatering, if required metre 57014
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 54299
C Soft rock ( 9m dia well )
(i) Depth upto 3m metre 10509
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 35730
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.16 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 4009
(ii) Beyond 3m upto 10m depth metre 4931
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6513
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12217
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 14660
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 29027
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 34832
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 5465
(ii) Beyond 3m upto 10m depth metre 8082
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10674
b Add for dewatering @ 5% of cost, if required. metre 11208
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20023
'b Add 5% of cost for dewatering on the cost, if required metre 26280
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 25028
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 47572
Summary of Rate Analysis
Item No. Descriptions Unit Rate
b Add 5% of cost for dewatering, if required metre 59940
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 57086
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 10290
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 38307
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.17 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 9018
(ii) Beyond 3m upto 10m depth metre 8160
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10777
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20214
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 24257
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 48024
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 57629
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 9963
(ii) Beyond 3m upto 10m depth metre 17391
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22968
b Add for dewatering @ 5% of cost, if required. metre 24117
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 43082
b Add 5% of cost for dewatering on the cost, if required metre 56546
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 53853
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 102356
b Add 5% of cost for dewatering, if required metre 128969
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 122827
C Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 22492
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 83327
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.18 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 18991
(ii) Beyond 3m upto 10m depth metre 23247
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 30701
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 57588
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 69105
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 136820
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 164184
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 24363
(ii) Beyond 3m upto 10m depth metre 40960
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 54095
b Add for dewatering @ 5% of cost, if required. metre 56800
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 101469
b Add 5% of cost for dewatering on the cost, if required metre 133178
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 126836
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 241075
b Add 5% of cost for dewatering, if required metre 303755
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 289290
C Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 50938
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 172407
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey
12.19 soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 4024
(ii) Beyond 3m upto 10m depth metre 4526
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5978
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11211
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 13453
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26634
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 31961
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 5596
(ii) Beyond 3m upto 10m depth metre 8938
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11804
b Add for dewatering @ 5% of cost, if required. metre 12394
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22140
b Add 5% of cost for dewatering on the cost, if required metre 29059
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 27675
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 52599
b Add 5% of cost for dewatering, if required metre 66274
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 63118
C Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 12370
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 38965
Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained
personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and
plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled
blasting of hard rock where required, staircases and 1 m wide landing plate forms with railing, arrangement for
12.20
compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.
12.21 Sand filling in wells complete as per drawing and technical specifications cum 2939
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out as per
12.22 detailed drawing tonne 84599
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.23 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm) metre 10005
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.24 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) metre 16382
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.25 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm) metre 20709
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and & Technical
12.26 Specification (Pile diameter - 750 mm) metre #VALUE!
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.27 Specification (Pile diameter - 1000 mm) metre #VALUE!
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.28 Specification (Pile diameter - 1200 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.29 Specification (Pile Diameter=500 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.30 Specification (Pile Diameter=750 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.31 Specification (Pile Diameter=1000 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.32 Specification (Size of pile - 300 mm x 300 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.33 Specification (Size of pile - 500 mm x 500 mm) metre #VALUE!
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.34 Specification (Size of pile - 750 mm x 750 mm) metre #VALUE!
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
12.35 column 400 x 250 mm (ISHB Series) ) metre 5193
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
12.36 column 450 x 250 mm (ISHB Series) ) metre 5858
12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 8462
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7631
B RCC Grade M25
(i) Using concrete mixer. cum 9032
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8200
C RCC Grade M30
(i) Using concrete mixer. cum 9103
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8272
D RCC Grade M35
(i) Using concrete mixer. cum 9254
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8422
12.39 Levelling course for Pile cap cum 7324
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical
12.40 specifications tonne 80739
CHAPTER-13
SUB-STRUCTURE
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical
13.5 specifications
G RCC Grade M30
(p) Height upto 5m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8674
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and
13.6 technical specifications tonne 81164
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
13.8 towards drawing foce. Complete as per drawing and Technical specifications each 137
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
13.9 specification
A Granular material cum 1932
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than
600 mm with smaller size towards the soil and bigger size towards the wall and provided over the
13.10 entire surface behind abutment, wing wall and return wall to the full height compacted to a firm cum 2503
condition complete as per drawing and technical specification.
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing
14.1 and Technical Specification
C RCC Grade M 30
Case II Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9484
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
14.2 drawing and technical specifications tonne 83768
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as
14.4 per drawing and Technical Specifications cum 14329
14.9 Drainage Spouts complete as per drawing and Technical specification each 2163
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10 specification cum 7450
Reinforced cement concrete approach slab including reinforcement and formwork complete as per
14.11 drawing and Technical specification cum 12232
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete
surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
14.16 metre 214
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 639.10 70.30 L-12
Mazdoor for loading and unloading day 0.750 719.40 539.55 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 530.19 397.64 P&M-048
c) Overhead charges @ 0.08 on (a+b) 80.60
d) Contractor's profit @ 0.1 on (a+b+c) 108.81
Cost for5.5 cum = a+b+c+d 1196.90
Rate per cum = (a+b+c+d)/5.5 217.62
Note Unloading will be by tipping. say 218.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor for loading and unloading day 2.000 719.40 1438.80 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 965.46 1930.92 P&M-057
c) Overhead charges @ 0.08 on (a+b) 273.67
d) Contractor's profit @ 0.1 on (a+b+c) 369.45
Cost for10 tonnes = a+b+c+d 4063.97
Rate per tonnes = (a+b+c+d)/10 406.40
say 406.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 4415.18 44151.82 P&M-014
stumps
Tractor-trolley hour 1.000 620.49 620.49 P&M-053
c) Overhead charges @ 0.08 on (a+b) 3820.17
d) Contractor's profit @ 0.1 on (a+b+c) 5157.23
Rate per Hectare = a+b+c+d 56729.57
say 56730.00
2.5 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Unit = cum
Taking output = 1 cum
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.300 719.40 215.82 L-13
b) Machinery
Tractor-trolley hour 0.380 620.49 235.79 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 668.25 11.36 P&M-055
c) Overhead charges @ 0.08 on (a+b) 37.55
d) Contractor's profit @ 0.1 on (a+b+c) 50.69
Rate per cum = a+b+c+d 557.60
say 558.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.015 639.10 9.59 L-12
Mazdoor including loading and unloading day 0.225 719.40 161.87 L-13
b) Machinery
Tractor-trolley hour 0.300 620.49 186.15 P&M-053
c) Overhead charges @ 0.08 on (a+b) 28.61
d) Contractor's profit @ 0.1 on (a+b+c) 38.62
Cost for 10 m = a+b+c+d 424.83
Rate per metre = (a+b+c+d)/10 42.48
say 42.00
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 2182.12 13092.74 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 530.19 8483.08 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1845.26
d) Contractor's profit @ 0.1 on (a+b+c) 2491.10
Cost for 360 cum = a+b+c+d 27402.10
Rate per cum = (a+b+c+d)/360 76.12
say 76.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator CK-
90 and Tippers with Disposal upto 1000 metres.
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 530.19 8673.95 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1860.53
d) Contractor's profit @ 0.1 on (a+b+c) 2511.71
Cost for 360 cum = a+b+c+d 27628.86
Rate per cum = (a+b+c+d)/360 76.75
say 77.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a) Labour
Mate day 0.600 639.10 383.46 L-12
Mazdoor day 15.000 719.40 10791.00 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 546.40 3278.39 P&M-001
hour
Dozer, 80 HP hour 6.000 4415.18 26491.09 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 37.00 1554.00 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 25.48 17122.56 M-094 /100
of 125 gms each
d) Overhead charges @ 0.08 on (a+b+c) 5431.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 7333.18
Cost for 400 sqm = a+b+c+d+e 80665.01
Rate per sqm = (a+b+c+d+e)/400 201.66
say 202.00
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.320 639.10 204.51 L-12
Mazdoor day 8.000 719.40 5755.20 L-13
b) Overhead charges @ 0.08 on (a) 476.78
c) Contractor's profit @ 0.1 on (a+b) 643.65
Cost for 10 cum = a+b+c 7080.14
Rate per cum = (a+b+c)/10 708.01
say 708.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 639.10 204.51 L-12
Mazdoor day 8.000 719.40 5755.20 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 2182.12 13092.74 P&M-026
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 2182.12 13092.74 P&M-026
c) Overhead charges @ 0.08 on (a+b) 1405.00
d) Contractor's profit @ 0.1 on (a+b+c) 1896.75
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 216 cum = a+b+c+d 20864.28
Rate per cum = (a+b+c+d)/216 96.59
say 97.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 639.10 338.72 L-12
ii) Driller day 0.840 0.00 0.00 L-06
iii) Blaster day 0.400 0.00 0.00 L-03
iv) Mazdoor day 12.000 719.40 8632.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 546.40 364.27 P&M-001
per hour
c) Material
Blasting Material kg 3.500 37.00 129.50 M-104
Detonator electric each 14.000 25.48 356.72 M-094 /100
a) Labour
i) Mate day 0.080 639.10 51.13 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 2182.12 370.96 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 530.19 238.59 P&M-048
c) Material
Selected earth for refilling cum 5.000 0.00 0.00 M-163
d) Overhead charges @ 0.08 on (a+b+c) 167.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 226.74
Cost for 10 cum = a+b+c+d+e 2494.18
Rate per cum = (a+b+c+d+e)/10 249.42
say 249.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.14 305.4.3 Scarifying Existing Granular Surface to a Depth of 50 mm by
Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor including loading and unloading day 5.000 719.40 3597.00 L-13
b) Machinery
Tractor-trolley hour 1.670 620.49 1036.21 P&M-053
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.08 on (a+b+c) 380.88
e) Contractor's profit @ 0.1 on (a+b+c+d) 514.19
Cost for 100 sqm = a+b+c+d 5656.11
Rate per sqm = (a+b+c+d)/100 56.56
say 57.00
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50 mm
by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.250 719.40 179.85 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 668.25 53.46 P&M-055
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 1379.89 275.98 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 530.19 121.94 P&M-048
c) Overhead charges @ 0.08 on (a+b) 51.01
d) Contractor's profit @ 0.1 on (a+b+c) 68.86
Cost for 100 sqm = a+b+c+d 757.50
Rate per sqm = (a+b+c+d)/100 7.57
say 8.00
3.16 305 Construction of Embankment with Material obtained from
Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 2182.12 3644.15 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 4.25 29644.22 Lead
=43.61 km
& P&M-058
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 2182.12 0.00 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 4.25 0.00 Lead =0
km & P&M-
058
Add 10 per cent of cost of carriagefor loading and 0.00
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 4415.18 7947.33 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 3959.08 14252.68 P&M-032
Water tanker6 KL capacity hour 12.000 530.19 6362.31 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 2277.05 8197.37 P&M-059
c) Overhead charges @ 0.08 on (a+b) 3179.16
d) Contractor's profit @ 0.1 on (a+b+c) 4291.87
Cost for 360 cum = a+b+c+d 47210.58
Rate per cum = (a+b+c+d)/360 131.14
say 131.00
Note 1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-1)
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 639.10 306.77 L-12
Mazdoor skilled day 2.000 698.50 1397.00 L-15
Mazdoor day 10.000 719.40 7194.00 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 2058.26 13584.50 P&M-094
Electric generator 125 KVA hour 6.000 1193.51 7161.07 P&M-018
Front end loader 1 cum capacity hour 6.000 1379.89 8279.33 P&M-017
Paver finisher hour 6.000 1669.30 10015.77 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 2277.05 8880.49 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 530.19 1590.58 P&M-060
Tipper tonne.km 495 x L 4.25 22764.15 Lead
=10.82461
0098486
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 2276.41
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1497.66 133441.57 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1324.90 157398.49 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 512.99 45707.77 M-022
Cost of water KL 18.000 130.00 2340.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 33787.03
e) Contractor's profit @ 0.1 on (a+b+c+d) 45612.49
Cost for 225 cum = a+b+c+d+e 501737.41
Rate per cum = (a+b+c+d+e)/225 2229.94
say 2230.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..
4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 530.19 530.19 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 178.27 1069.65 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 2182.12 1091.06 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 4.25 9727.01 Lead
=43.61 km
& P&M-058
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 639.10 536.84 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 719.40 11510.40 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 698.50 3492.50 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 24205.94 145235.63 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 4577.25 27463.50 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1107.85 6647.08 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.25 20694.68 Lead
=10.82461
0098486
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 2069.47
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 788.34 3074.54 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 2277.05 8880.49 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1613.73 6293.54 P&M-045
roller.
c) Materials
Bitumen @ 4.69 per cent of weight of mix tonne 21.105 51155.00 1079626.28 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1421.83 89845.27 M-049
25 - 10 mm 13 per cent cum 37.340 1605.64 59954.48 M-046
10 -4.75 mm 19 per cent cum 54.580 1148.49 62684.80 M-040
4.75 mm and below 44 per cent cum 126.390 754.74 95392.09 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3037.00 26178.94 M-188
or
(i) For Grading I ( 40 mm nominal size )
d) Overhead charges @ 0.08 on (a+b+c) 132628.79
e) Contractor's profit @ 0.1 on (a+b+c+d) 179048.87
Cost for 205 cum = a+b+c+d+e 1969537.52
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 10100.19
say 10100.00
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Reinforced Cement Concrete Crash Barrier
7.09
with frication Slab
b) Labour
Mate day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
c) Material
Steel (80 Kg / Cum) Kg 0.826 52222.68 43115.04
d) Overhead charges 0.08 on (a+b+c) 9479.66
e) Contractor's profit 0.1 on (a+b+c+d) 12797.54
Cost for 10 meter = a+b+c+d+e 140772.91
Rate per metre = (a+b+c+d)/10 14077.00
Page 1 of 277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick
as per clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 0.00 0.00 M-154
or
2.Copper Strips metre 450*1.1 0.00 0.00 M-153
or
3.Aluminium Strips metre 450*1.1 0.00 0.00 M-157
or
4.Stainless steel strips metre 450*1.1 0.00 0.00 M-156
or
5.Glass reinforced polymer/fibre reinforced metre 450*1.1 150.00 74250.00 M-155
polymer/polymeric strips
@ Any one of the above alternative may be
adopted as per approved design.
Add 10 per cent of the cost of reinforcing strip
towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements
with the facia pannels, overlaps, heat bonding or
extension.
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 639.10 230.08 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
Mazdoor skilled day 3.000 698.50 2095.50 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and sqm 300.000 74.00 22200.00 M-181
approved design and specifications.
Add 10 per cent of the cost of reinforcing 2220.00
elements (synthetic geogrids) for accessories
like tie-strips, nuts and bolts and loops/lugs
for joining reinforcing elements with the
facia pannels, overlaps and other protective
elements for synthetic geogrids.
Page 2 of 277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.180 639.10 115.04 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
Mazdoor skilled day 1.500 698.50 1047.75 L-15
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 610.07 3660.41 P&M-013
c) Material
Pre-cast RCC M-35 facing elements of size cu.m 13.500 6577.00 88789.50 Item 12.8
as per design and 18 cm thick for 75 sqm. (H)
(Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 81161.00 30841.18 Item 13.6
Page 3 of 277
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mason day 1.000 947.10 947.10 L-11
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 530.19 3181.15 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 2546.78 4074.84 P&M-003
Water tanker6 KL capacity hour 5.000 530.19 2650.96 P&M-060
Tipper 5.5 cum capacity hour 6.000 530.19 3181.15 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1822.49 39712.14 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 1670.49 18208.38 M-004
Cement 11 per cent tonne 5.700 7146.39 40734.42 M-081
Cost of water KL 30.000 130.00 3900.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 9448.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 12755.41
Cost for 360 meter = a+b+c+d+e 140309.51
Rate per metre = (a+b+c+d+e)/360 389.75
say 390.00
Rate fro 52.29 Cum of Concrete 836.00
8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel
(i)
Hindi ( Matras commas and the like not to be measured and
paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 639.10 76.69 L-12
Painter day 2.000 756.80 1513.60 L-18
Mazdoor day 1.000 719.40 719.40 L-13
b) Material
Paint Litre 0.700 360.00 252.00 M-131
c) Overhead charges @ 0.08 on (a+b) 204.94
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 276.66
Cost for 1600 cm = a+b+c+d 3043.29
Rate per cm height per letter = (a+b+c+ d)/1600 1.90
say 1.90
8.3 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter Ist class day 1.250 756.80 946.00 L-18
Mazdoor day 0.500 719.40 359.70 L-13
b) Material
Paint Litre 0.500 360.00 180.00 M-131
c) Overhead charges @ 0.08 on (a+b) 122.43
d) Contractor's profit @ 0.1 on (a+b+c) 165.29
Cost for 1600 cm = a+b+c+d 1818.16
Rate per cm height per letter = (a+b+c +d)/1600 1.14
say 1.10
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
708.00 152.93 Item No.
i) Excavation for foundation cum 0.216
3.13
ii) Cement concrete M15 grade cum 0.120 7747.00 929.64 Item 12.8
(A)
iii) Painting angle iron post two coats sqm 0.430 118.00 50.74 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.216 708.00 152.93 Item No.
3.13
ii) Cement concrete M15 grade cum 0.120 7747.00 929.64 Item 12.8
(A)
iii) Painting angle iron post two coats sqm 0.430 118.00 50.74 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.200 719.40 143.88 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 45.00 855.00 M-179
kg 19.000
metres long /1000
Aluminium sheeting fixed with encapsulated lens type 8820.00 7938.00 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 620.49 12.41 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 716.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 967.21
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 11772.66
Rate per sqm (for sign having area upto 0.9 sqm) =
13080.73
(I+ii+iii+a+b+c+d+e)/0.90
say 13081.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more than
8.6 801
0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation cum 0.430 708.00 304.44 Item No.
3.13
ii) Cement concrete M15 grade cum 0.240 7747.00 1859.28 Item 12.8
(A)
iii) Painting angle iron post 2 coats sqm 0.860 118.00 101.48 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.300 719.40 215.82 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 45.00 1710.00 M-179
kg 38.000
metres long, 2 nos /1000
Aluminium sheeting fixed with encapsulated lens type 8820.00 13230.00 M-061
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 620.49 12.41 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 1196.19
e) Contractor's profit @ 0.1 on (a+b+c+d) 1637.08
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 20273.09
Rate per sqm ( for sign having area more than 0.9 sqm) =
22525.66
( i+ii+iii+a+b+c+d+e)/1.50
say 22526.00
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 639.10 153.38 L-12
Blacksmith day 2.000 729.30 1458.60 L-02
Mazdoor including for handling & fixing at site. day 4.000 719.40 2877.60 L-13
b) Material
Aluminium alloy/galvanised steel including 5 per cent 79069.00 83022.45 M-060
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
830.22
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
12577.90
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 610.07 1830.21 P&M-013
Truck hour 0.500 965.46 482.73 P&M-057
d) Overhead charges @ 0.08 on (a+b+c) 8258.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 11149.17
Rate per tonne = (a+b+c+d+e) 122640.92
say 122641.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 639.10 12.78 L-12
Blacksmith day 0.100 729.30 72.93 L-02
Mazdoor day 0.150 719.40 107.91 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 16954.00 16954.00 M-059
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
1.94
ladders, pulleys, ropes etc
c) Overhead charges @ 0.08 on (a+b) 1371.96
d) Contractor's profit @ 0.1 on (a+b+c) 1852.15
Rate per sqm = (a+b+c+d) 20373.68
say 20374.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
Note
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 639.10 76.69 L-12
Painter day 2.000 756.80 1513.60 L-18
Mazdoor day 1.000 719.40 719.40 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 223.20 1339.20 M-132
Add for scaffolding @ 1 per cent of labour cost where
13.39
required
Add @ 5 per cent cost of labour and materials to 182.44
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.08 on (a+b) 307.58
d) Contractor's profit @ 0.1 on (a+b+c) 415.23
Cost for 40 sqm = a+b+c+d 4567.54
Rate per sqm = (a+b+c+d)/40 114.19
say 114.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Painter day 0.450 756.80 340.56 L-18
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 360.00 450.00 M-131
Add @ 1 per cent on cost of material for scaffolding 4.50
Add @ 5 per cent cost of labour and materials to 49.48
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.08 on (a+b) 83.48
d) Contractor's profit @ 0.1 on (a+b+c) 112.70
Cost for 10 sqm = a+b+c+d 1239.75
Rate per sqm= (a+b+c+d)/10 123.98
say 124.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Painter day 0.500 756.80 378.40 L-18
Mazdoor day 0.200 719.40 143.88 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 360.00 540.00 M-131
Add @ 1 per cent on cost of material for scaffolding 5.40
Add @ 5 per cent cost of labour and materials to 54.07
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.08 on (a+b) 91.27
d) Contractor's profit @ 0.1 on (a+b+c) 123.22
Cost for 10 sqm = a+b+c+d 1355.42
Rate per sqm = (a+b+c+d)/10 135.54
say 136.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.11 803
on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 639.10 57.52 L-12
Painter day 0.550 756.80 416.24 L-18
Mazdoor day 1.550 719.40 1115.07 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 223.20 330.34 M-132
c) Overhead charges @ 0.08 on (a+b) 153.53
d) Contractor's profit @ 0.1 on (a+b+c) 207.27
Cost for 10 sqm = a+b+c+d 2279.97
Rate per sqm= (a+b+c+d)/10 228.00
say 228.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter day 0.350 756.80 264.88 L-18
Mazdoor day 1.350 719.40 971.19 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Road marking paint Litre 1.480 223.20 330.34 M-132
c) Overhead charges @ 0.08 on (a+b) 128.89
d) Contractor's profit @ 0.1 on (a+b+c) 174.00
Cost for 10 sqm = a+b+c+d 1914.04
Rate per sqm = (a+b+c+d)/10 191.40
say 191.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.12 803
on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 639.10 38.35 L-12
Painter Ist class day 0.300 756.80 227.04 L-18
Mazdoor day 1.250 719.40 899.25 L-13
b) Material
Road marking paint Litre 0.900 223.20 200.88 M-132
c) Overhead charges @ 0.08 on (a+b) 109.24
d) Contractor's profit @ 0.1 on (a+b+c) 147.48
Cost for 10 sqm = a+b+c+d 1622.23
Rate per sqm = (a+b+c+d)/10 162.22
say 162.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter Ist class day 0.350 756.80 264.88 L-18
Mazdoor day 1.350 719.40 971.19 L-13
b) Material
Road marking Paint Litre 0.900 223.20 200.88 M-132
c) Overhead charges @ 0.08 on (a+b) 118.53
d) Contractor's profit @ 0.1 on (a+b+c) 160.02
Cost for 10 sqm= a+b+c+d 1760.24
Rate per sqm = (a+b+c+d)/10 176.02
say 176.00
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.750 719.40 539.55 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 159.75 1597.52 P&M-043
Tractor-trolley hour 0.500 620.49 310.24 P&M-053
c) Material
Hot applied thermoplastic compound Litre 1500.000 223.00 334500.00 M-118
Reflectorising glass beads kg 150.000 80.00 12000.00 M-152
d) Overhead charges @ 0.08 on (a+b+c) 27917.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 37688.38
Cost for 600 sqm = a+b+c+d+e 414572.19
Rate per sqm = a+b+c+d+e)/600 690.95
say 691.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.15 805 Road Delineators
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor for fixing day 1.000 719.40 719.40 L-13
b) Material
Cost of approved type of delineators from ISI certified 807.00 24210.00 M-091
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2421.00
c) Overhead charges @ 0.08 on (a+b) 2190.08
d) Contractor's profit @ 0.1 on (a+b+c) 2956.60
Cost for 30 Nos. delineators = (a+b+ c+d) 32522.65
Rate per delineators = (a+b+c+d) /30 1084.09
say 1084.00
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296 708.00 917.57 Item No.
3.13
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 7747.00 5020.06 Item 12.8
cum 0.648
x 0.3 (A)
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres 8719.00 2790.08 Item
cum 0.320
each 14.1(A)
iv) Painting of pipe sqm 4.710 118.00 555.78 Item 8.9
a) Labour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.014 639.10 8.95 L-12
Mazdoor day 0.350 719.40 251.79 L-13
Plumber day 0.010 729.30 7.29 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 253.53 7605.90 M-175
c) Machinery
Tractor-trolley hour 0.250 620.49 155.12 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 642.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 867.14
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 18822.00
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1882.20
say 1882.00
8.22 809 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier for
bridge structures , constructed with M-40 grade concrete
with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with
pre-moulded asphalt filler board, keyed to the structure on
which it is built and installed as per design given in the
enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as
specified
Unit = Linear metre
Taking output = 10 m
(i) a) M 40 grade concrete
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 0.00 0.00 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 530.19 7952.88 P&M-060
c) Material
Cost of water KL 90.000 130.00 11700.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 1572.23
e) Contractor's profit @ 0.1 on (a+b+c+d) 2122.51
Cost for 100 sqm = a+b+c+d+e 23347.63
Rate per sqm = (a+b+c+d+e)/100 233.48
say 233.00
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 639.10 159.78 L-12
Mazdoor for preparation of ground day 1.000 719.40 719.40 L-13
Mali for fetching doobs grass roots hedges and day 1.500 0.00 0.00 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
Tractor with tiller hour 0.010 620.49 6.20 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 496.00 297.60 M-167
per 100 sqm
Fine grass kg 100.000 7.50 750.00 M-113
d) Overhead charges @ 0.08 on (a+b+c) 175.85
e) Contractor's profit @ 0.1 on (a+b+c+d) 237.39
Cost for 100 sqm = a+b+c+d+e 2611.31
Rate per sqm = (a+b+c+d+e)/100 26.11
say 26.00
11.6 307 Maintenance of Lawns with Fine Grassing for the First Year
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
c) Material
Cost of water KL 3.000 130.00 390.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 231.20
e) Contractor's profit @ 0.1 on (a+b+c+d) 312.12
Cost for 100 sqm = a+b+c+d+e 3433.31
Rate per sqm = (a+b+c+d+e) 34.33
say 34.00
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 496.00 496.00 M-167
screened, loading, carriage, unloading and stacking at
site
b) Overhead charges @ 0.08 on (a) 39.68
c) Contractor's profit @ 0.1 on (a+b) 53.57
Rate per cum = (a+b+c) 589.25
589.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000
store/site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per quintal = a+b+c
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 639.10 1.28 L-12
Mason day 0.050 947.10 47.36 L-11
Mazdoor day 0.050 719.40 35.97 L-13
b) Material
Brick 2nd class including carriage each 50.000 7.50 375.00 M-079
c) Overhead charges @ 0.08 on (a+b) 36.77
d) Contractor's profit @ 0.1 on (a+b+c) 49.64
Cost for 10 metre = a+b+c+d 546.01
Rate per metre = (a+b+c+d)/10 54.60
say 55.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per Design
from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 639.10 12.78 L-12
Blacksmith day 0.150 729.30 109.40 L-02
Mazdoor day 0.070 719.40 50.36 L-13
b) Material
Empty bitumen drum each 1.000 0.00 0.00 M-172
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 639.10 25.56 L-12
Blacksmith day 0.200 729.30 145.86 L-02
Mazdoor 0.200 719.40 143.88 L-13
b) Material
Empty bitumen drum each 1.500 0.00 0.00 M-172
MS sheet50 x 0.5 mm kg 0.650 45.00 29.25 M-179
/1000
Rivets 6 mm dia and 10 mm in length each 50.000 0.00 0.00 M-158
MSplate30 x 3 mm kg 1.300 45.00 58.50 M-179
/1000
c) Overhead charges @ 0.08 on (a+b) 32.24
d) Contractor's profit @ 0.1 on (a+b+c) 43.53
Rate for each tree guard = a+b+c+d 478.83
say 479.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 639.10 287.60 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 729.30 1458.60 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 719.40 1798.50 L-13
b) Material
Angle, tees, channels etc quintal 1.050 4500.00 4725.00 M-179 /10
Deduct the cost of scrap quintal 0.050 (1500.00) (75.00) M-179/10/3
Add 5 per cent of cost of material for welding rods and other 232.50
welding accessories
c) Overhead charges @ 0.08 on (a+b) 674.18
d) Contractor's profit @ 0.1 on (a+b+c) 910.14
Rate per quintal = a+b+c+d 10011.51
say 10012.00
11.19 New Tree Guard with MS Iron
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 639.10 31.96 L-12
Blacksmith day 0.250 729.30 182.33 L-02
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 45.00 864.00 M-179
/1000
MS iron 25 x 3 mm kg 9.600 45.00 432.00 M-179
/1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 620.49 24.82 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 118.00 208.86 Item 8.9
e) Overhead charges @ 0.08 on (a+b+c) 137.20
f) Contractor's profit @ 0.1 on (a+b+c+e) 185.21
Rate per tree guard =a+b+c+d+e+f 2246.22
say 2246.00
Note 1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 New Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 639.10 31.96 L-12
Blacksmith day 0.250 729.30 182.33 L-02
Welder day 0.250 729.30 182.33 L-02
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 45.00 607.50 M-179
/1000
MS iron 25 x 3 mm kg 18.000 45.00 810.00 M-179
/1000
Steel wire 3 mm dia kg 6.000 0.00 0.00 M-192
Add 5 per cent of cost of material for riveting, bolting 70.88
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 620.49 24.82 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 118.00 177.00 Item 8.9
e) Overhead charges @ 0.08 on (a+b+c) 167.17
f) Contractor's profit @ 0.1 on (a+b+c+e) 225.68
Rate per tree guard = a+b+c+d+e+f 2659.50
say 2660.00
11.21 New Compensatory Afforestation
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7146.39 297718.61
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 km, L-lead in km tonne.km 300L 7.28 23645.69
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7146.39 342669.40
Coarse sand cum 54.00 1670.49 90206.68
40 mm Aggregate cum 43.20 1419.49 61322.14
20 mm Aggregate cum 43.20 1822.49 78731.74
10 mm Aggregate cum 21.60 1367.49 29537.87
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7146.39 345742.35
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity 1 cum hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7146.39 348743.83
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Machinery 5974.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 25089.43
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 148386.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89031.65
cost of 120 cum = a+b+c+d+e+f 979348.11
Rate per cum (a+b+c+d+e+f )/120 8161.23
say 8161.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 6786.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 3053.66
e) Overhead charges @ 0.2 on (a+b+c+d) 20968.49
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12581.10
cost of 15 cum = a+b+c+d+e+f 138392.06
Rate per cum = (a+b+c+d+e+f)/15 9226.14
say 9226.00
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7146.39 361893.19
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 196.30 177518.02
Sand bags each 6000.00 0.00 0.00
Wooden ballies 8" Dia and 9 m long each 95.00 0.00 0.00
Wooden ballies 2" Dia for bracing metre 190.00 0.00 0.00
b) Labour
Mate day 5.60 639.10 3578.96
Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 719.40 12949.20
Mazdoor for bracing with 2" dia ballies day 12.00 719.40 8632.80
Mazdoor for filling sand bags, stitching and placing day 110.00 719.40 79134.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Machinery
Crane with grab 1 cum capacity hour 50.00 1459.77 72988.26
Consumables and other arrangements for piling ballies @ 8870.03
2.5 per cent of (a+b+c).
d) Overhead charges @ 0.2 on (a+b+c) 72734.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 43640.55
Rate per No. (a+b+c+d+e) 480046.07
say 480046.00
Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 C Providing and constructing one span service road to reach
island location from one pier location to another pier location
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 45000.00 47250.00
cent wastage
Nuts & bolts Kg 20.00 70.00 1400.00
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 639.10 843.61
Fitter day 5.50 0.00 0.00
Blacksmith day 5.50 729.30 4011.15
Welder day 5.50 729.30 4011.15
Mazdoor day 16.50 719.40 11870.10
Electrodes, cutting gas and other consumables @ 10 per 4865.00
cent of cost of (a) above
c) Overhead charges @ 0.2 on (a+b) 14850.20
d) Contractor's profit @ 0.1 on (a+b+c) 8910.12
Rate per MT (a+b+c+d) 98011.34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 98011.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation
1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7146.39 368753.72
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture kg 206.00 179.00 36874.00
b) Labour
Mate day 0.84 639.10 536.84
Meson day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 7.28 23645.69
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7146.39 292430.28
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader (capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7146.39 373041.56
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture kg 206.00 179.00 36874.00
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 7.28 23645.69
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 12228.00 15285.00 16049.00
22nd m 7.5% 13145.00 16431.00 17253.00
23rd m 7.5% 14131.00 17664.00 18547.00
24th m 7.5% 15191.00 18989.00 19938.00
25th m 7.5% 16330.00 20413.00 21434.00
26th m 7.5% 17555.00 21944.00 23041.00
27th m 7.5% 18872.00 23590.00 24770.00
28th m 7.5% 20287.00 25359.00 26627.00
29th m 7.5% 21809.00 27261.00 28624.00
30th m 7.5% 23445.00 29306.00 30771.00
Total Cost from 20m upto 30m 172993.00 216242.00 227054.00
Avg Rate per metre 17299.00 21624.00 22705.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 25790.00 30948.00 32495.00
32nd 10% 28369.00 34043.00 35745.00
33rd m 10% 31206.00 37447.00 39319.00
34th m 10% 34327.00 41192.00 43252.00
35th m 10% 37760.00 45312.00 47578.00
36th m 10% 41536.00 49843.00 52335.00
37th m 10% 45690.00 54828.00 57569.00
38th m 10% 50259.00 60311.00 63327.00
39th m 10% 55285.00 66342.00 69659.00
40th m 10% 60814.00 72977.00 76626.00
Total Cost from 30m upto 40m 411036.00 493243.00 517905.00
Avg Rate per metre 41104.00 49324.00 51791.00
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 639.10 587.97
Sinker ( skilled ) day 3.00 698.50 2095.50
Sinking helper ( semi-skilled ) day 20.00 0.00 0.00
Diver day 0.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 338.47 1353.87
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 349.49 1223.22
Consumables in sinking @ 10 per cent of (b) 257.71
Add for dewatering @ of 5 per cent of (a+b), if required 275.91
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 9294.00 11618.00 12199.00
32nd 7.5% 9991.00 12489.00 13113.00
33rd m 7.5% 10740.00 13425.00 14096.00
34th m 7.5% 11546.00 14433.00 15155.00
35th m 7.5% 12412.00 15515.00 16291.00
36th m 7.5% 13343.00 16679.00 17513.00
37th m 7.5% 14344.00 17930.00 18827.00
38th m 7.5% 15420.00 19275.00 20239.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
39th m 7.5% 16577.00 20721.00 21757.00
40th m 7.5% 17820.00 22275.00 23389.00
Total Cost from 30m upto 40m 131487.00 164360.00 172579.00
Avg Rate per metre 13149.00 16436.00 17258.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 19602.00 23522.00 24698.00
32nd 10% 21562.00 25874.00 27168.00
33rd m 10% 23718.00 28462.00 29885.00
34th m 10% 26090.00 31308.00 32873.00
35th m 10% 28699.00 34439.00 36161.00
36th m 10% 31569.00 37883.00 39777.00
37th m 10% 34726.00 41671.00 43755.00
38th m 10% 38199.00 45839.00 48131.00
39th m 10% 42019.00 50423.00 52944.00
40th m 10% 46221.00 55465.00 58238.00
Total Cost from 30m upto 40m 312405.00 374886.00 393630.00
Avg Rate per metre 31241.00 37489.00 39363.00
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 639.10 370.68
Sinker ( skilled ) day 4.00 698.50 2794.00
Sinking helper ( semi-skilled ) day 10.00 0.00 0.00
Diver day 0.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 338.47 1523.10
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 349.49 1310.60
Consumables in sinking @ 10 per cent of (b) 283.37
Add for dewatering @ of 5 per cent of (a+b), if required 299.92
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 13463.00 16829.00 17670.00
32nd 7.5% 14473.00 18091.00 18996.00
33rd m 7.5% 15558.00 19448.00 20420.00
34th m 7.5% 16725.00 20906.00 21951.00
35th m 7.5% 17979.00 22474.00 23598.00
36th m 7.5% 19327.00 24159.00 25367.00
37th m 7.5% 20777.00 25971.00 27270.00
38th m 7.5% 22335.00 27919.00 29315.00
39th m 7.5% 24010.00 30013.00 31514.00
40th m 7.5% 25811.00 32264.00 33877.00
Total Cost from 30m upto 40m 190458.00 238074.00 249978.00
Avg Rate per metre 19046.00 23807.00 24998.00
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 28392.00 34070.00 35774.00
32nd 10% 31231.00 37477.00 39351.00
33rd m 10% 34354.00 41225.00 43286.00
34th m 10% 37789.00 45347.00 47614.00
35th m 10% 41568.00 49882.00 52376.00
36th m 10% 45725.00 54870.00 57614.00
37th m 10% 50298.00 60358.00 63376.00
38th m 10% 55328.00 66394.00 69714.00
39th m 10% 60861.00 73033.00 76685.00
40th m 10% 66947.00 80336.00 84353.00
Total Cost from 30m upto 40m 452493.00 542992.00 570143.00
Avg Rate per metre 45249.00 54299.00 57014.00
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 639.10 485.72
Sinker ( skilled ) day 4.00 698.50 2794.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper ( semi-skilled ) day 14.00 0.00 0.00
Diver day 1.20 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 338.47 2200.04
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 349.49 1397.97
Consumables in sinking @ 10 per cent of (b) 359.80
Add for dewatering @ of 5 per cent of (a+b), if required 723.75
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 14153.00 17691.00 18576.00
32nd 7.5% 15214.00 19018.00 19969.00
33rd m 7.5% 16355.00 20444.00 21466.00
34th m 7.5% 17582.00 21978.00 23077.00
35th m 7.5% 18901.00 23626.00 24807.00
36th m 7.5% 20319.00 25399.00 26669.00
37th m 7.5% 21843.00 27304.00 28669.00
38th m 7.5% 23481.00 29351.00 30819.00
39th m 7.5% 25242.00 31553.00 33131.00
40th m 7.5% 27135.00 33919.00 35615.00
Total Cost from 30m upto 40m 200225.00 250283.00 262798.00
Avg Rate per metre 20023.00 25028.00 26280.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 29849.00 35819.00 37610.00
32nd 10% 32834.00 39401.00 41371.00
33rd m 10% 36117.00 43340.00 45507.00
34th m 10% 39729.00 47675.00 50058.75
35th m 10% 43702.00 52442.00 55064.10
36th m 10% 48072.00 57686.00 60570.30
37th m 10% 52879.00 63455.00 66627.75
38th m 10% 58167.00 69800.00 73290.00
39th m 10% 63984.00 76781.00 80620.05
40th m 10% 70382.00 84458.00 88680.90
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total Cost from 30m upto 40m 475715.00 570857.00 599399.85
Avg Rate per metre 47572.00 57086.00 59940.00
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 639.10 549.63
Sinker ( skilled ) day 4.00 698.50 2794.00
Sinking helper ( semi-skilled ) day 16.00 0.00 0.00
Diver day 1.40 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 338.47 2369.27
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 349.49 1485.34
Consumables in sinking @ 10 per cent of (b) 385.46
Add for dewatering @ 5 per cent of cost, if required 212.00
c) Overhead charges @ 0.2 on (a+b) 1559.14
d) Contractor's profit @ 0.1 on (a+b+c) 935.48
Rate per metre = (a+b+c+d) 10290.33
say 10290.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 37.00 407.00
Electric Detonators each. 44.00 25.48 1121.12
b) Labour
Mate day 1.27 639.10 811.66
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 24.00 719.40 17265.60
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 338.47 2876.97
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 349.49 1048.48
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 196.27
Consumables in sinking @ 10 per cent of cost of (b+c). 2499.30
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 30454.00 38068.00 39971.00
32nd 7.5% 32738.00 40923.00 42969.00
33rd m 7.5% 35193.00 43991.00 46191.00
34th m 7.5% 37832.00 47290.00 49655.00
35th m 7.5% 40669.00 50836.00 53378.00
36th m 7.5% 43719.00 54649.00 57381.00
37th m 7.5% 46998.00 58748.00 61685.00
38th m 7.5% 50523.00 63154.00 66312.00
39th m 7.5% 54312.00 67890.00 71285.00
40th m 7.5% 58385.00 72981.00 76630.00
Total Cost from 30m upto 40m 430823.00 538530.00 565457.00
Avg Rate per metre 43082.00 53853.00 56546.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 64224.00 77069.00 80922.00
32nd 10% 70646.00 84775.00 89014.00
33rd m 10% 77711.00 93253.00 97916.00
34th m 10% 85482.00 102578.00 107707.00
35th m 10% 94030.00 112836.00 118478.00
36th m 10% 103433.00 124120.00 130326.00
37th m 10% 113776.00 136531.00 143358.00
38th m 10% 125154.00 150185.00 157694.00
39th m 10% 137669.00 165203.00 173463.00
40th m 10% 151436.00 181723.00 190809.00
Total Cost from 30m upto 40m 1023561 1228273 1289687
Avg Rate per metre 102356.00 122827.00 128969.00
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 639.10 607.15
Sinker ( skilled ) day 4.25 698.50 2968.63
Sinking helper (semi-skilled) day 18.00 0.00 0.00
Diver day 1.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 338.47 2707.74
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 349.49 1572.72
Consumables in sinking @ 10 per cent of (b) 428.05
Add for dewatering @ 5 per cent of cost, if required 235.43
c) Overhead charges @ 0.2 on (a+b) 1703.94
d) Contractor's profit @ 0.1 on (a+b+c) 1022.36
Cost for 0.5m = a+b+c+d 11246.00
Rate per metre = (a+b+c+d)/0.50 22492.00
say 22492.00
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 37.00 444.00
Electric Detonators each. 48.00 25.48 1223.04
b) Labour
Mate day 1.35 639.10 862.79
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 26.00 719.40 18704.40
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 349.49 1223.22
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 230.39
Consumables in sinking @ 10 per cent of cost of (b+c). 2696.91
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
31st m 7.5% 71724.00 89655.00 94138.00
32nd 7.5% 77103.00 96379.00 101198.00
33rd m 7.5% 82886.00 103608.00 108788.00
34th m 7.5% 89102.00 111378.00 116947.00
35th m 7.5% 95785.00 119731.00 125718.00
36th m 7.5% 102969.00 128711.00 135147.00
37th m 7.5% 110692.00 138365.00 145283.00
38th m 7.5% 118994.00 148743.00 156180.00
39th m 7.5% 127919.00 159899.00 167894.00
40th m 7.5% 137513.00 171891.00 180486.00
Total Cost from 30m upto 40m 1014687 1268360 1331779
Avg Rate per metre 101469.00 126836.00 133178.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 151264.00 181517.00 190593.00
32nd 10% 166390.00 199668.00 209651.00
33rd m 10% 183029.00 219635.00 230617.00
34th m 10% 201332.00 241598.00 253678.00
35th m 10% 221465.00 265758.00 279046.00
36th m 10% 243612.00 292334.00 306951.00
37th m 10% 267973.00 321568.00 337646.00
38th m 10% 294770.00 353724.00 371410.00
39th m 10% 324247.00 389096.00 408551.00
40th m 10% 356672.00 428006.00 449406.00
Total Cost from 30m upto 40m 2410754 2892904 3037549
Avg Rate per metre 241075.00 289290.00 303755.00
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 639.10 677.45
Sinker ( skilled ) day 4.50 698.50 3143.25
Sinking helper (semi-skilled) day 20.00 0.00 0.00
Diver day 1.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 349.49 1660.09
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 504.48
Add for dewatering @ 5 per cent, if required 277.46
c) Overhead charges @ 0.2 on (a+b) 1929.48
d) Contractor's profit @ 0.1 on (a+b+c) 1157.69
Cost for 0.25m = a+b+c+d 12734.57
Rate per metre = (a+b+c+d)/0.25 50938.27
say 50938.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 37.00 518.00
Electric detonator each. 56.00 25.48 1426.88
b) Labour
Mate day 1.44 639.10 920.30
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 28.00 719.40 20143.20
Mazdoor (Skilled) day 4.50 698.50 3143.25
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 338.47 4230.84
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 349.49 1397.97
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 281.44
Consumables in sinking @ 10 per cent of (c). 591.03
d) Overhead charges @ 0.2 on (a+b+c) 6530.58
e) Contractor's profit @ 0.1 on (a+b+c+d) 3918.35
Cost for 0.25m = a+b+c+d+e 43101.85
Rate per metre = (a+b+c+d+e)/0.25 172407.39
say 172407.00
12.19 1200 Sinking of Twin D Type well (other than pneumatic method
of sinking) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking
is reckoned from bed level.
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 15650.00 19563.00 20541.00
32nd 7.5% 16824.00 21030.00 22082.00
33rd m 7.5% 18086.00 22608.00 23738.00
34th m 7.5% 19442.00 24303.00 25518.00
35th m 7.5% 20900.00 26125.00 27431.00
36th m 7.5% 22468.00 28085.00 29489.00
37th m 7.5% 24153.00 30191.00 31701.00
38th m 7.5% 25964.00 32455.00 34078.00
39th m 7.5% 27911.00 34889.00 36633.00
40th m 7.5% 30004.00 37505.00 39380.00
Total Cost from 30m upto 40m 221402.00 276754.00 290591.00
Avg Rate per metre 22140.00 27675.00 29059.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 33004.00 39605.00 41585.00
32nd 10% 36304.00 43565.00 45743.00
33rd m 10% 39934.00 47921.00 50317.00
34th m 10% 43927.00 52712.00 55348.00
35th m 10% 48320.00 57984.00 60883.00
36th m 10% 53152.00 63782.00 66971.00
37th m 10% 58467.00 70160.00 73668.00
38th m 10% 64314.00 77177.00 81036.00
39th m 10% 70745.00 84894.00 89139.00
40th m 10% 77820.00 93384.00 98053.00
Total Cost from 30m upto 40m 525987.00 631184.00 662743.00
Avg Rate per metre 52599.00 63118.00 66274.00
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 639.10 549.63
Sinker ( skilled ) day 4.50 698.50 3143.25
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper (semi-skilled) day 15.00 0.00 0.00
Diver day 1.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 338.47 2819.43
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 349.49 2096.96
Consumables in sinking @ 10 per cent of (b) 491.64
Add for dewatering @ 5 per cent, if required 270.40
c) Overhead charges @ 0.2 on (a+b) 1874.26
d) Contractor's profit @ 0.1 on (a+b+c) 1124.56
Rate per metre = (a+b+c+d) 12370.12
say 12370.00
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 37.00 370.00
Electric detonators each. 40.00 25.48 1019.20
b) Labour
Mate day 1.34 639.10 856.39
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 25.00 719.40 17985.00
Mazdoor (Skilled) day 4.25 698.50 2968.63
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 349.49 1048.48
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 1312.16
Consumables in sinking @ 10 per cent of (b). 574.53
d) Overhead charges @ 0.2 on (a+b+c) 5903.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 3542.29
Rate per metre = (a+b+c+d+e) 38965.16
say 38965.00
12.20 1200 Pneumatic sinking of wells with equipment of approved
design, drawing and specifications worked by competent
and trained personnel and comprising of compression and
decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of
fresh air to working chambers, check valves, exhaust valves,
shafts made from steel plates of riveted construction not less
than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing, arrangement
for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations
and compliance with safety precautions as per IS:4138, all
as per clause1207.6 of MoRTH Specifications.
Unit - 1 cum
Taking output = 5 cum
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 8682.00 69456.00
equipment (Dimensions as per ground conditions).
Rate may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 52222.68 25066.88
Blasting material
Gelatine 80 per cent Kg 1.50 37.00 55.50
Electric detonators each 6.00 25.48 152.88
b) Labour
Medical Officer day 0.50 0.00 0.00
Para medical personnel day 1.00 714.00 714.00
Mate day 1.86 639.10 1188.73
Driller day 1.00 0.00 0.00
Blaster day 0.50 0.00 0.00
Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 719.40 21582.00
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 698.50 6985.00
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 45000.00 47250.00
b) Labour
Mate day 1.24 639.10 792.48
Fitter day 6.00 0.00 0.00
Blacksmith day 5.00 569.00 2845.00
Welder day 5.00 729.30 3646.50
Mazdoor day 10.00 719.40 7194.00
Electrodes, cutting gas and other consumables @ 5 2362.50
per cent on cost a (a) above.
c) Overhead charges @ 0.2 on (a+b) 12818.10
d) Contractor's profit @ 0.1 on (a+b+c) 7690.86
Rate for per MT (a+b+c+d) 84599.44
say 84599.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 8713.00 57680.06
a) Material
Cement tonne 5.12 7146.39 36589.52
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 100 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71
a) Material
Cement tonne 5.99 7146.39 42806.88
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 125 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71
a) Material
Cement tonne 6.10 7146.39 43592.98
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 100 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71
a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1670.49 11275.83
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 125 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71
Remarks/
Input ref.
L-12
L-13
L-12
L-13
P&M-026
M-081
M-005
M-055
M-053
M-051
Remarks/
Input ref.
L-12
L-11
L-13
P&M-009
P&M-019
M-081
M-005
M-055
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-005
M-053
M-051
Remarks/
Input ref.
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-005
Remarks/
Input ref.
M-055
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-055
M-053
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.
M-081
M-004
M-053
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-004
M-053
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
Remarks/
Input ref.
P&M-007
M-081
M-005
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
Remarks/
Input ref.
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-092
M-159
L-12
L-13
P&M-012
M-092
M-159
M-194
M-193
L-12
L-13
L-13
L-13
Remarks/
Input ref.
P&M-012
M-092
M-159
L-12
L-13
P&M-017
P&M-048
M-179
M-130
L-12
L-08
L-02
L-02
L-13
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.
M-081
M-004
M-053
M-051
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
Lead=
10.824610
098486 ,
P&M-050
P&M-007
M-081
M-005
M-055
M-053
M-051
M-180
L-12
L-11
L-13
Remarks/
Input ref.
P&M-009
P&M-079
P&M-013
M-081
M-004
M-053
M-051
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
Remarks/
Input ref.
M-005
M-055
M-053
M-051
M-180
L-12
L-11
L-13
P&M-009
P&M-079
P&M-013
M-081
M-004
M-053
M-051
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.
M-081
M-005
M-055
M-053
M-051
M-180
L-12
L-11
L-13
P&M-009
P&M-079
P&M-013
M-081
M-004
M-053
M-051
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
Remarks/
Input ref.
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-005
M-055
M-053
M-051
M-180
L-12
L-11
L-13
P&M-009
P&M-079
P&M-013
M-081
M-004
M-053
M-051
Remarks/
Input ref.
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.
Remarks/
Input ref.
M-081
M-005
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
Remarks/
Input ref.
M-051
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-005
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
Remarks/
Input ref.
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-005
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
Remarks/
Input ref.
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-005
M-053
M-051
L-12
L-11
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
Remarks/
Input ref.
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
M-081
M-004
M-053
M-051
M-180
L-12
L-11
L-13
P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
Remarks/
Input ref.
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
P&M-075
Remarks/
Input ref.
P&M-063
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
Remarks/
Input ref.
L-12
L-06
L-03
L-13
L-15
L-07
P&M-075
P&M-063
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
Remarks/
Input ref.
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
P&M-075
P&M-063
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
Remarks/
Input ref.
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
L-07
P&M-075
P&M-063
L-12
L-15
Remarks/
Input ref.
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
Remarks/
Input ref.
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
Remarks/
Input ref.
P&M-075
P&M-063
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
Remarks/
Input ref.
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
L-14
L-07
P&M-075
P&M-063
Remarks/
Input ref.
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
P&M-075
P&M-063
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
Remarks/
Input ref.
L-12
L-15
L-14
P&M-075
L-12
L-15
L-14
P&M-075
P&M-063
Remarks/
Input ref.
L-12
L-15
Remarks/
Input ref.
L-14
L-07
P&M-075
P&M-063
M-104
M-094/100
L-12
L-06
L-03
L-13
L-15
P&M-075
P&M-063
Remarks/
Input ref.
Item 12.8
(H)
M-082
M-104
M-094/100
L-16
L-19
L-12
L-06
L-03
L-13
L-15
L-07
P&M-082
P&M-038
P&M-001
P&M-072
P&M-066
P&M-066
P&M-079
P&M-048
Remarks/
Input ref.
M-006
L-12
L-13
M-179
L-12
L-08
L-01
L-02
L-13
Item 12.11
(C) iv
P&M-036
Remarks/
Input ref.
P&M-013
P&M-017
P&M-048
M-071
L-12
L-13
Item 12.11
(C) iv
P&M-036
P&M-013
P&M-017
P&M-048
M-071
L-12
L-13
Remarks/
Input ref.
Item 12.11
(C) iv
P&M-036
P&M-013
P&M-017
P&M-048
M-071
L-12
L-13
Item 12.11
(C) iv
M-080
M-124
M-173
P&M-085
P&M-070
L-12
L-13
Remarks/
Input ref.
Item 12.11
(C) iv
M-080
M-124
M-173
P&M-085
P&M-070
P&M-013
L-12
L-13
Remarks/
Input ref.
Item 12.11
(C) iv
M-080
M-124
M-173
P&M-085
P&M-070
L-12
L-13
Item 12.11
(F) iv
M-080
M-125
M-173
P&M-073
P&M-092
L-12
L-13
Remarks/
Input ref.
Item 12.11
(F) iv
M-080
M-125
M-173
P&M-074
P&M-092
L-12
L-13
Item 12.11
(F) iv
M-080
M-125
Remarks/
Input ref.
M-173
P&M-011
P&M-092
L-12
L-13
Item 12.11
(F) iv
M-080
M-125
M-173
P&M-071
P&M-092
L-12
L-13
Remarks/
Input ref.
Item 12.11
(F) iv
M-080
M-125
M-173
P&M-073
P&M-092
L-12
L-13
Item 12.11
(F) iv
M-080
M-125
M-173
P&M-073
P&M-092
L-12
L-13
Remarks/
Input ref.
M-179
P&M-071
P&M-092
L-12
L-13
M-179
P&M-071
P&M-092
L-12
L-13
Remarks/
Input ref.
M-081
M-005
M-053
M-051
L-12
L-10
L-13
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
L-10
L-13
L-13
P&M-002
P&M-080
P&M-017
Remarks/
Input ref.
P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007
M-081
M-005
M-053
M-051
L-12
L-10
L-13
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
L-10
L-13
L-13
Remarks/
Input ref.
P&M-002
P&M-018
P&M-017
P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007
M-081
M-005
M-053
M-051
L-12
L-10
L-13
L-13
P&M-009
P&M-079
M-081
M-004
M-053
M-051
L-12
Remarks/
Input ref.
L-10
L-13
L-13
P&M-002
P&M-080
P&M-017
P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007
M-081
M-005
M-053
M-051
L-12
L-10
L-13
L-13
P&M-009
P&M-079
M-081
M-004
Remarks/
Input ref.
M-053
M-051
L-12
L-10
L-13
L-13
P&M-002
P&M-018
P&M-017
P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007
M-081
M-005
M-055
M-053
M-051
L-12
L-10
L-13
P&M-009
P&M-079
Remarks/
Input ref.
M-082
M-072
L-12
L-02
L-13
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 5974.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 597.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 1314.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 788.57
Rate perm (a+b+c+d+e+f) 8674.25
say 8674.00
13.6 Section Supplying, fitting and placing HYSD bar reinforcement in
1600 & sub-structure complete as per drawing and Technical
2200 Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 52222.68 54833.81 M-082
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 47.10 1483.65 M-056
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 639.10 204.51 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 719.40 5035.80 L-13
Mazdoor (Skilled) day 1.00 698.50 698.50 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1082.49 12989.93 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 530.19 31.81 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 3792.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 2275.27
cost for 10 cum of Fiter Media = a+b+c+d+e 25027.93
Rate per cum = (a+b+c+d+e)/10 2502.79
say 2503.00
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7146.39 36589.52 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.86 639.10 549.63 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 18628.40
e) Overhead charges @ 0.2 on (a+b+c+d) 22354.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13412.45
Cost for 15 cum = a+b+c+d+e+f 147536.93
Rate per cum = (a+b+c+d+e+f)/15 9835.80
say 9836.00
14.1A (q) Height 5m to 10m
Case I (i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7146.39 292430.28 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.84 639.10 536.84 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 18.00 719.40 12949.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 132105.60
e) Overhead charges @ 0.2 on (a+b+c+d) 158526.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95116.03
Cost for 120 cum = a+b+c+d+e+f 1046276.35
Rate per cum = (a+b+c+d+e+f)/120 8718.97
say 8719.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 165132.00
e) Overhead charges @ 0.2 on (a+b+c+d) 165132.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 99079.20
Cost for 120 cum = a+b+c+d+e+f 1089871.20
Rate per cum = (a+b+c+d+e+f)/120 9082.26
say 9082.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 198158.40
e) Overhead charges @ 0.2 on (a+b+c+d) 171737.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103042.37
Cost for 120 cum = a+b+c+d+e+f 1133466.05
Rate per cum = (a+b+c+d+e+f)/120 9445.55
say 9446.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 165132.00
e) Overhead charges @ 0.2 on (a+b+c+d) 165132.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 99079.20
Cost for 120 cum = a+b+c+d+e+f 1089871.20
Rate per cum = (a+b+c+d+e+f)/120 9082.26
say 9082.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 198158.40
e) Overhead charges @ 0.2 on (a+b+c+d) 171737.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103042.37
Cost for 120 cum = a+b+c+d+e+f 1133466.05
Rate per cum = (a+b+c+d+e+f)/120 9445.55
say 9446.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 231184.80
e) Overhead charges @ 0.2 on (a+b+c+d) 178342.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107005.54
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 120 cum = a+b+c+d+e+f 1177060.90
Rate per cum = (a+b+c+d+e+f)/120 9808.84
say 9809.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7146.39 42806.88 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.86 639.10 549.63 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 19872.00
e) Overhead charges @ 0.2 on (a+b+c+d) 23846.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14307.84
Cost for 15 cum = a+b+c+d+e+f 157386.24
Rate per cum = (a+b+c+d+e+f)/15 10492.42
say 10492.00
14.1B (q) Height 5m to 10m
Case I (i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 7146.39 342669.40 M-081
Coarse sand cum 54.20 1670.49 90540.77 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.84 639.10 536.84 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 18.00 719.40 12949.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 142220.20
e) Overhead charges @ 0.2 on (a+b+c+d) 170664.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 102398.54
Cost for 120 cum = a+b+c+d+e+f 1126383.98
Rate per cum = (a+b+c+d+e+f)/120 9386.53
say 9387.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 177775.25
e) Overhead charges @ 0.2 on (a+b+c+d) 177775.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106665.15
Cost for 120 cum = a+b+c+d+e+f 1173316.65
Rate per cum = (a+b+c+d+e+f)/120 9777.64
say 9778.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 213330.30
e) Overhead charges @ 0.2 on (a+b+c+d) 184886.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110931.76
Cost for 120 cum = a+b+c+d+e+f 1220249.32
Rate per cum = (a+b+c+d+e+f)/120 10168.74
say 10169.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 177775.25
e) Overhead charges @ 0.2 on (a+b+c+d) 177775.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106665.15
Cost for 120 cum = a+b+c+d+e+f 1173316.65
Rate per cum = (a+b+c+d+e+f)/120 9777.64
say 9778.00
14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 213330.30
e) Overhead charges @ 0.2 on (a+b+c+d) 184886.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110931.76
Cost for 120 cum = a+b+c+d+e+f 1220249.32
Rate per cum = (a+b+c+d+e+f)/120 10168.74
say 10169.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 248885.35
e) Overhead charges @ 0.2 on (a+b+c+d) 191997.27
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 115198.36
Cost for 120 cum = a+b+c+d+e+f 1267181.98
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/120 10559.85
say 10560.00
14.1 C RCC Grade M 30
14.1C Case II Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7146.39 348672.37 M-081
Coarse sand cum 54.60 1670.49 91208.97 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.88 639.10 562.41 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 19.00 719.40 13668.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 143703.40
e) Overhead charges @ 0.2 on (a+b+c+d) 172444.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103466.45
Cost for 120 cum = a+b+c+d+e+f 1138130.93
Rate per cum = (a+b+c+d+e+f)/120 9484.42
say 9484.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 179629.25
e) Overhead charges @ 0.2 on (a+b+c+d) 179629.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107777.55
Cost for 120 cum = a+b+c+d+e+f 1185553.05
Rate per cum = (a+b+c+d+e+f)/120 9879.61
say 9880.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 215555.10
e) Overhead charges @ 0.2 on (a+b+c+d) 186814.42
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112088.65
Cost for 120 cum = a+b+c+d+e+f 1232975.17
Rate per cum = (a+b+c+d+e+f)/120 10274.79
say 10275.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 179629.25
e) Overhead charges @ 0.2 on (a+b+c+d) 179629.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107777.55
Cost for 120 cum = a+b+c+d+e+f 1185553.05
Rate per cum = (a+b+c+d+e+f)/120 9879.61
say 9880.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 215555.10
e) Overhead charges @ 0.2 on (a+b+c+d) 186814.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112088.65
Cost for 120 cum = a+b+c+d+e+f 1232975.17
Rate per cum = (a+b+c+d+e+f)/120 10274.79
say 10275.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 251480.95
e) Overhead charges @ 0.2 on (a+b+c+d) 193999.59
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116399.75
Cost for 120 cum = a+b+c+d+e+f 1280397.29
Rate per cum = (a+b+c+d+e+f)/120 10669.98
say 10670.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7146.39 45236.65 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.90 639.10 575.19 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 21.00 719.40 15107.40 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case I
(p) Height upto 5m
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 18456.12
e) Overhead charges @ 0.2 on (a+b+c+d) 24198.02
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14518.81
Cost for 15 cum = a+b+c+d+e+f 159706.96
Rate per cum = (a+b+c+d+e+f)/15 10647.13
say 10647.00
14.1D (q) Height 5m to 10m
Case I (i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7146.39 361893.19 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.88 639.10 562.41 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 19.00 719.40 13668.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 131532.48
e) Overhead charges @ 0.2 on (a+b+c+d) 172453.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103472.22
Cost for 120 cum = a+b+c+d+e+f 1138194.39
Rate per cum = (a+b+c+d+e+f)/120 9484.95
say 9485.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 168069.28
e) Overhead charges @ 0.2 on (a+b+c+d) 179761.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107856.63
Cost for 120 cum = a+b+c+d+e+f 1186422.97
Rate per cum = (a+b+c+d+e+f)/120 9886.86
say 9887.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 204606.08
e) Overhead charges @ 0.2 on (a+b+c+d) 187068.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112241.05
Cost for 120 cum = a+b+c+d+e+f 1234651.55
Rate per cum = (a+b+c+d+e+f)/120 10288.76
say 10289.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 168069.28
e) Overhead charges @ 0.2 on (a+b+c+d) 179761.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107856.63
Cost for 120 cum = a+b+c+d+e+f 1186422.97
Rate per cum = (a+b+c+d+e+f)/120 9886.86
say 9887.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 204606.08
e) Overhead charges @ 0.2 on (a+b+c+d) 187068.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112241.05
Cost for 120 cum = a+b+c+d+e+f 1234651.55
Rate per cum = (a+b+c+d+e+f)/120 10288.76
say 10289.00
14.1D (r) Height above 10m
Case II
(ii)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 241142.88
e) Overhead charges @ 0.2 on (a+b+c+d) 194375.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116625.47
Cost for 120 cum = a+b+c+d+e+f 1282880.12
Rate per cum = (a+b+c+d+e+f)/120 10690.67
say 10691.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case II cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 277679.68
e) Overhead charges @ 0.2 on (a+b+c+d) 201683.14
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 121009.88
Cost for 120 cum = a+b+c+d+e+f 1331108.70
Rate per cum = (a+b+c+d+e+f)/120 11092.57
say 11093.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 350753.28
e) Overhead charges @ 0.2 on (a+b+c+d) 216297.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 129778.71
Cost for 120 cum = a+b+c+d+e+f 1427565.85
Rate per cum = (a+b+c+d+e+f)/120 11896.38
say 11896.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 423826.88
e) Overhead charges @ 0.2 on (a+b+c+d) 230912.58
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 138547.55
Cost for 120 cum = a+b+c+d+e+f 1524023.00
Rate per cum = (a+b+c+d+e+f)/120 12700.19
say 12700.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 7146.39 46094.22 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
Admixture @ 0.4 per cent of cement kg 25.80 179.00 4618.20 M-180
b) Labour
Mate day 0.96 639.10 613.54 L-12
Mason day 2.00 947.10 1894.20 L-11
Mazdoor day 22.00 719.40 15826.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 21848.20
e) Overhead charges @ 0.2 on (a+b+c+d) 26217.84
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15730.70
Cost for 15 cum = a+b+c+d+e+f 173037.74
Rate per cum = (a+b+c+d+e+f)/15 11535.85
say 11536.00
14.1E (q) Height 5m to 10m
Case I (i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7146.39 368753.72 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
Admixture @ 0.4 per cent of cement kg 206.40 179.00 36945.60 M-180
b) Labour
Mate day 0.94 639.10 600.75 L-12
Mason day 3.50 947.10 3314.85 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 775773.00
cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 775773.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 139639.14
e) Overhead charges @ 0.2 on (a+b+c+d) 183082.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 109849.46
Cost for 15 cum = a+b+c+d+e+f 1208344.02
Rate per cum = (a+b+c+d+e+f)/120 10069.53
say 10070.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 178427.79
e) Overhead charges @ 0.2 on (a+b+c+d) 190840.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 114504.09
Cost for 120 cum = a+b+c+d+e+f 1259545.04
Rate per cum = (a+b+c+d+e+f)/120 10496.21
say 10496.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 217216.44
e) Overhead charges @ 0.2 on (a+b+c+d) 198597.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119158.73
Cost for 120 cum = a+b+c+d+e+f 1310746.06
Rate per cum = (a+b+c+d+e+f)/120 10922.88
say 10923.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 178427.79
e) Overhead charges @ 0.2 on (a+b+c+d) 190840.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 114504.09
Cost for 120 cum = a+b+c+d+e+f 1259545.04
Rate per cum = (a+b+c+d+e+f)/120 10496.21
say 10496.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 217216.44
e) Overhead charges @ 0.2 on (a+b+c+d) 198597.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119158.73
Cost for 120 cum = a+b+c+d+e+f 1310746.06
Rate per cum = (a+b+c+d+e+f)/120 10922.88
say 10923.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 256005.09
e) Overhead charges @ 0.2 on (a+b+c+d) 206355.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 123813.37
Cost for 120 cum = a+b+c+d+e+f 1361947.08
Rate per cum = (a+b+c+d+e+f)/120 11349.56
say 11350.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 7450.00 7450.00 Item 12.8
formworks (A)
Rate per cum say 7450.00
14.11 1500,16
00,1700
& 2704
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 5974.00 5974.00 Item 12.8
concrete in item 12.8(G)by using batching plant, (G)
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) 119.48
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 63459.00 3172.95 Item 14.2 A
14.2(Excluding OH & CP)
b) Overhead charges @ 0.2 on (a) 1853.29
c) Contractor's profit @ 0.1 on(a+b) 1111.97
Rate per cum (a+b+c) 12232
say 12232.00
Note The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.
Unit = sqm
Taking output = 10 sqm
a) Labour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.01 639.10 6.39 L-12
Painter day 0.25 756.80 189.20 L-18
Mazdoor (Skilled) day 0.25 698.50 174.63 L-15
b) Material
Water based paint of approved quality for cement Litres 5.00 250.00 1250.00 M-190
concrete surface
c) Overhead charges @ 0.2 on (a+b) 324.04
d) Contractor's profit @ 0.1 on (a+b+c) 194.43
Cost for 10 sqm (a+b+c+d) 2138.69
Rate per sqm (a+b+c+d)/10 213.87
say 214.00
14.18 (ii) Providing & fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 639.10 5.11 L-12
Mazdoor day 0.10 719.40 71.94 L-13
Mazdoor (Skilled) day 0.10 698.50 69.85 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 sqm 3.00 550.00 1650.00 M-084
cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 0.2 on (a+b) 359.38
d) Contractor's profit @ 0.1 on (a+b+c) 215.63
Cost for 12 m = (a+b+c+d) 2371.91
Rate per m = (a+b+c+d)/12 197.66
say 198.00
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.4 2504 Providing and laying Pitching on slopes laid over prepared
filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 745.49 745.49 M-003
Stone spalls of minimum 25 mm size cum 0.20 614.56 122.91 M-008
b) Labour
Mate day 0.04 639.10 25.56 L-12
Mason day 0.35 947.10 331.49 L-11
Mazdoor day 0.75 719.40 539.55 L-13
c) Overhead charges @ 0.2 on (a+b) 353.00
d) Contractor's profit @ 0.1 on (a+b+c) 211.80
Rate per cum = (a+b+c+d) 2329.81
say 2330.00
15.5 2504 Providing and laying Filter material underneath pitching in
slopes complete as per drawing and Technical specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 1082.49 1298.99 M-012
b) Labour
Mate day 0.05 639.10 31.96 L-12
Mazdoor (Skilled) day 0.25 698.50 174.63 L-15
Mazdoor * day 1.00 719.40 719.40 L-13
c) Overhead charges @ 0.2 on (a+b) 444.99
d) Contractor's profit @ 0.1 on (a+b+c) 267.00
Rate per cum = (a+b+c+d) 2936.96
say 2937.00
Includes Mazdoor required for trimming of slope to proper
profile and preparation of bed.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than
40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 745.49 745.49 M-003
Stone Spalls cum 0.20 614.56 122.91 M-008
b) Labour
Mate day 0.05 639.10 31.96 L-12
Mason day 0.25 947.10 236.78 L-11
Mazdoor day 1.00 719.40 719.40 L-13
Add 1 per cent of cost of (a+b) for trimming and 18.57
preparation of bed.
c) Overhead charges @ 0.2 on (a+b) 375.02
d) Contractor's profit @ 0.1 on (a+b+c) 225.01
Rate per cum = (a+b+c+d) 2475.13
say 2475.00
Preparation of Detailed Project Report for Rehabilitation and Upgradation DDPR
to 4 lane with paved shoulder configuration of National Highway 227 Volume 6: Rate Analysis
in the state of Tamil Nadu. Annexures
CHAPTER-16
REPAIR AND REHABILITATION
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.18 Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.20 639.10 127.82 L-12
Mazdoor day 5.00 719.40 3597.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 620.49 620.49 P&M-053
c) Overhead charges @ 0.2 on (a+b) 869.06
d) Contractor's profit @ 0.1 on (a+b+c) 521.44
Cost for 10 m = a+b+c+d 5735.81
Rate per metre = (a+b+c+d)/10 573.58
say 574.00
Note The rate for the provision of new railing may be adopted
from the chapter on superstructure.