You are on page 1of 277

Six Laning of Sriperumbudur to Karaipettai

Section of NH-4 (New NH-48) from Km 37+000


(Existing Km 37/000) to Km 71+015 (Existing Km
71/000), total length 34.015 Km on EPC Mode in
the state of Tamil Nadu under NHDP Phase-V :
Package-I
Conveyance
2021-2022 Total Cost at Site
Sl.No Description of Item Lead Qarry to CMP to
in Rs
SOR Rate Site

Hard Broken Granite Stone


1 90mm 443 42.60 390.494 833.494
2 80mm 493 42.60 390.494 883.494
3 75mm 495 42.60 390.494 885.494
4 63mm 640 42.60 390.494 1030.494
5 53mm 781 42.60 390.494 1171.494
6 50mm 661 42.60 390.494 1051.494
7 46.5mm 1050 42.60 390.494 1440.494
8 45mm 1050 42.60 390.494 1440.494
9 40mm 1029 42.60 390.494 1419.494
10 37.5mm 1072 42.60 390.494 1462.494
11 26.5mm 1011 42.60 390.494 1401.494
12 25mm 1011 42.60 390.494 1401.494
13 22.4mm 1470 42.60 390.494 1860.494
14 20mm 1432 42.60 390.494 1822.494
15 13.2mm 1363 42.60 390.494 1753.494
16 12mm 1329 42.60 390.494 1719.494
17 11.2mm 924 42.60 390.494 1314.494
18 10mm 977 42.60 390.494 1367.494
19 6.7mm 685 42.60 390.494 1075.494
20 6mm 685 42.60 390.494 1075.494
21 5.6mm 685 42.60 390.494 1075.494
22 4.75mm & below 606 42.60 390.494 996.494

23 Stone dust (HBG stone chips 2.36 mm and below ) 122.5 42.60 390.494 512.994
24 Stone Boulder 150 - 300mm 355 42.60 390.494 745.494
25 Supply of stone 150 -200 mm size 445 42.60 390.494 835.494
26 Boulder with minimum size of 300 mm for Pitching at Site 378 42.60 390.494 768.494
27 Lime (Slaked & Screened) 1322 - - 1322
28 Gravel 216.3 44 398.2609 614.5609
29 Sand for mortar 1280 42.60 390.494 1670.494
30 Sand for filling, blindage 1280 53.42 473.7352516574 1753.735251657
Cement (From Barathi Cement, Nallalingayapalli, 5960.00
35 Andrapradesh) 273 1186.39 7146.39
36 Steel Fe500 ( From Bellary, Karnataka) 51750.00 96 472.677 52222.677
37 20 mm metal SS5 1432 42.60 390.494 1822.494
38 40 mm metal SS5 1029 42.60 390.494 1419.494
39 10 mm metal SS5 977 42.60 390.494 1367.494
40 RR masonary (Hard Granite) 445 42.60 390.494 835.494
41 CR masonary 355 42.60 390.494 745.494
42 Bond stone 642 42.60 390.494 1032.494
43 Dry Stone for Apron or revetment 378 53.42 473.735 851.735
Material Average

Sl.No Materials Unit Rate


1 Aggregates below 5.6 mm Cum 754.74
2 Aggregates 22.4 mm to 2.36 mm Cum 1324.90
3 Aggregates 22.4 mm to 5.6 mm Cum 1451.61
4 Aggregates 45 mm to 2.8 mm Cum 1412.43
5 Aggregates 45 mm to 22.4 mm Cum 1497.66
6 Aggregates 53 mm to 2.8 mm Cum 1380.55
7 Aggregates 53 mm to 22.4 mm Cum 1405.49
8 Aggregates 63 mm to 2.8 mm Cum 1362.13
9 Aggregates 63 mm to 45 mm Cum 1226.89
10 Aggregates 10 mm to 5 mm Cum 1148.49
11 Aggregates 11.2 mm to 0.99 mm Cum 1059.71
12 Aggregates 13.2 mm to 0.99 mm Cum 1210.11
13 Aggregates 13.2mm to 5.60 mm Cum 1340.21
14 Aggregates 13.2 mm to 10 mm Cum 1538.74
15 Aggregates 20 mm to 10 mm Cum 1595.49
16 Aggregates 25 mm to 10 mm Cum 1605.64
17 Aggregates 19 mm to 6 mm Cum 1446.92
18 Aggregates 37.5 mm to 19 mm Cum 1589.69
19 Aggregates 37.5 mm to 25 mm Cum 1421.83
20 Aggregates 6mm nominal size Cum 1075.49
21 Aggregates 10 mm nominal size Cum 1367.49
22 Aggregates 13.2/12.5 mm nominal size Cum 1753.49
23 Aggregates 20 mm nominal size Cum 1822.49
24 Aggregates 25 mm nominal size Cum 1401.49
25 Aggregates 40 mm nominal size Cum 1419.49
26 Filter media avg of 150mm & 40mm (Hand broken) Cum 1082.49
27 Aggregates 45 mm to 22.4 mm (Hand Broken) Cum 1497.66
28 Aggregates 53 mm to 26.5 mm (Hand Broken) Cum 1369.33
29 Aggregates 53 mm to 22.4 mm (Hand Broken) Cum 1405.49
30 Aggregates 90 mm to 45 mm (Hand Broken) Cum 1092.12
31 Aggregates 63 mm to 45 mm (Hand Broken) Cum 1226.89
32 Aggregates 4.75 mm to 75 microns Cum 754.74
33 Aggregates 37.5 mm to 9.5 mm Cum 1567.05
34 Aggregates 9.5 mm to 75 microns Cum 1017.24
35 Aggregates 53 to 26.5 Cum 1341.07
36 Aggregates 26.5 to 4.75 Cum 1405.33
37 Aggergates 9.5 mm to 4.75 mm Cum 1118.09
38 Aggregates 2.36 mm and below (stone dust) Cum 512.99
39 Aggregates 53mm to 9.5 mm Cum 1473.35
40 Aggregates 26.5mm to 9.5 mm Cum 1580.12
41 Aggregates 9.5 mm to 2.36 mm Cum 1017.24
42 Aggregates 4.75mm to 2.36 mm Cum 754.74
Material Average
43 Aggregates 20mm SS 5 Cum 1822.49
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 546
Batching and Mixing Plant (a) 30 cum
P&M-002 Concrete Mixing cum/hour 20 hour 3134
capacity
Batching and Mixing Plant (b) 15 - 20 cum
P&M-003 Concrete Mixing cum/hour 13 hour 2547
capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1836

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 339

P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 3457

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 438

P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 26

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 398

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 398

P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 2189

P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 1460

P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 610

P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 4415

P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 2859

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 1369

P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1380

P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 1194

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 637

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1778

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 30652

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 24206

P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 20350

P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 16494

P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 3391
Soil Ordinary/Soil Marshy / Soil
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 hour 2182
Unsuitable
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 10133

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 21317

P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 530

P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 106

P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 610
Clearing /Spreading /GSB
P&M-032 Motor Grader 3.35 mtr blade cum/hour 200/200/50/50 hour 3959
/WBM
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1504
Paver Finisher Hydrostatic with sensor control Paving of DBM/ BM/SDC/
P&M-034 cum/hour 40 hour 4577
100 TPH Premix

P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 1669

0.75 m dia to 1.2 m dia Boring


P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 9352
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1747

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 4912
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 1552

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 220

P&M-041 Ripper Scarifying cum/hour 60 hour 48

P&M-042 Rotavator Scarifying cum/hour 25 hour 29

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 160
Soil Compaction /BM
P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 788
Compaction
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1614
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 530
WMM, Hotmix etc.
Transportation of Concrete Mix
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 1592
to site
Transportation of Concrete Mix
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 7.28
to site
Transportation of Concrete Mix
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 1459
to site
Transportation of Concrete Mix
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 7.28
to site
P&M-053 Tractor Pulling capacity in HP 50 hour 620

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 650

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 668

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 38

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 965

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 4

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 2277

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 530

P&M-061 Water Tanker Water Transport capacity in KL 6 km 42

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1927

Sl. No. Description of Machine Unit Rate

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 349
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 0

P&M-065 Belt conveyor system hour 0

P&M-066 Boat to carry atleast 20 persons hour 0

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 10109

P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 4045

P&M-069 Cold milling machine @ 20 cum per hour hour 0

P&M-070 Crane 5 tonne capacity hour 0

P&M-071 Crane 10 tonne capacity hour 0

P&M-072 Crane 15 tonne capacity hour 0

P&M-073 Crane 20 tonne capacity hour 0

P&M-074 Crane 40 T capacity hour 0

P&M-075 Crane with grab 0.75 cum capacity hour 338

P&M-076 Compressor with guniting equipment along with accessories hour 0

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 0

P&M-078 Epoxy Injection gun hour 0

P&M-079 Generator 33 KVA hour 637


P&M-080 Generator 100 KVA hour 1194

P&M-081 Generator 250 KVA hour 1108


Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic
P&M-082 hour 0
method of well sinking.
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 2000

P&M-084 Jack for Lifting 40 tonne lifting capacity. day 0

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 0

P&M-086 Plate compactor hour 178

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 0

P&M-088 Texturing machine (for rigid pavement) hour 2487

P&M-089 Truck Trailor 30 tonne capacity hour 0

P&M-090 Truck Trailor 30 tonne capacity hour 0

P&M-091 Tunnel Boring machine hour 0

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 0

P&M-093 Wet Mix Plant 100 TPH hour 0

P&M-094 Wet Mix Plant 75 TPH hour 2058


(B) Labour

Sl. No. Description of Labour Unit Rate

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 729.3

L-11 Mason (Ist class) day 947.1

L-12 Mate / Supervisor day 639.1

L-13 Mazdoor day 719.4

L-15 Mazdoor/Dresser/Sinker (Skilled) day 698.5

L-18 Painter I class day 756.8

(C) Materials

Sl. No. Description Unit Rate

M-004 Coarse sand at Mixing Plant cum 1670

M-005 Coarse sand at Site cum 1754

M-009 Granular Material or hard murrum for GSB works at Site Cum 745

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 1082

Rate at
Plant
Description Unit
(HMP/Batch
Rate at Site
ing)

M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1473 1473

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1017 1017

M-020 Close graded Granular sub-base Material 2.36 mm cum 513 513

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 513 513

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 513 513

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1405 1405

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 1369 1369

M-030 Aggregates below 5.6 mm cum 755 755

M-031 Aggregates 22.4 mm to 2.36 mm cum 1325 1325

M-034 Aggregates 45 mm to 22.4 mm cum 1498 1498

M-040 Aggregates 10 mm to 5 mm cum 1148 1148

M-043 Aggregates 13.2 mm to 5.6 mm cum 1340 1340

M-045 Aggregates 20 mm to 10 mm cum 1595 1595

M-046 Aggregates 25 mm to 10 mm cum 1606 1606

M-049 Aggregates 37.5 mm to 25 mm cum 1422 1422

M-051 Aggregates 10 mm nominal size cum 1367 1367

M-052 Aggregates 13.2/12.5 mm nominal size cum 1753 1753

M-053 Aggregates 20 mm nominal size cum 1822 1822


M-055 Aggregates 40 mm nominal size cum 1419 1419

Sl. No. Description Unit Rate

M-056 AC pipe 100 mm dia metre 47.1

M-072 Binding wire kg 50.30

M-074 Bitumen (VG 30 grade) tonne 51155

M-076 Bitumen (emulsion) RS 1 tonne 35783

M-077 Bitumen (emulsion) SS1 tonne 51453

M-081 Cement tonne 7146

M-082 Cold twisted bars (HYSD Bars) tonne 52223

M-084 Compressible Fibre Board(20mm thick) sqm 550

M-085 Connectors/ Staples each 0

M-086 Copper Plate(12m long x 250mmwide) kg 454

M-087 Corrosion resistant Structural steel tonne 41200

M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg

M-089 Credit for excavated rock found suitable for use cum

M-090 Curing compound liter 284

M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 807

M-092 Earth Cost or compensation for earth taken from private land cum 196
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab
M-093 metre 0
unit conforming to clause 915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 2548

M-095 Epoxy compound with accessories for preparing epoxy mortar kg 807

M-096 Epoxy mortar kg 0

M-097 Epoxy primer kg 256

M-098 Epoxy resin-hardner mix for prime coat kg 0

M-099 Flag of red color cloth 600 x 600 mm each 0

M-100 Flowering Plants each 0

M-101 Galvanised MS flat clamp nos 37

M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 77

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 44

M-104 Gelatin 80% kg 37

M-105 Geo grids sqm 0

M-106 Geomembrane sqm 0

M-107 Geonets sqm 0

M-108 Geotextile sqm 0

M-109 Geotextile filter fabric sqm 0

M-110 GI bolt 10 mm Dia nos 7

M-111 Grouting pump with agitator hour 292

M-112 Grass (Doob) kg 7.5

M-113 Grass (Fine) kg 7.5

M-114 HDPE pipes 75mm dia metre -

M-115 HDPE pipes 90mm dia metre -

M-116 Hedge plants each -


M-117 Helical pipes 600mm diameter metre -

M-118 Hot applied thermoplastic compound litre 223

M-119 HTS strand tonne 126012

M-120 Joint Sealant Compound kg 496

M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 11

M-122 LDO for steam curing litre 70

M-123 M.S. Clamps nos 20

M-124 M.S. Clamps kg 70

M-125 M.S.shoes @ 35 Kg per pile of 15 m kg 70

M-126 Mild Steel bars tonne 51750


Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and
upto 140mm assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements,
M-127 metre 0
support and control system, all steel sections protected against corrosion and installed by the manufacturer or his
authorised representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box
seal joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal,
M-128 metre 0
anchorage elements, support and control system, all steel sections protected against corrosion and installed by the
manufacturer or his authorised representative
M-129 Nipples 12mm nos 0

M-130 Nuts and bolts kg 70

M-131 Paint litre 360

M-132 Pavement Marking Paint litre 223.2

M-142 Pre-coated stone chips of 13.2 mm nominal size cum 1929

M-144 Pre-moulded asphalt filler board sqm 119

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 7500

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 231

M-152 Reflectorising glass beads kg 80

M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 0

M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 0
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced
M-155 metre 150
polymer/polymeric strips)
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 0

M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 0

M-158 Rivets each 0

M-159 Sand bags (Cost of sand and Empty cement bag) nos 0

M-160 Sapling 2 m high 25 mm dia each 128

M-161 Scrap tyres of size 900 x 20 nos 0

M-162 Seeds kg 0

M-163 Selected earth cum 0

M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 17

M-165 Sheathing duct metre 115

M-166 Shrubs each 0

M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 496

M-168 Sodium vapour lamp each 470

M-169 Square Rubble Coursed Stone cum 573

M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 885

M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 45000

M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 0
M-173 Steel helmet and cushion block on top of pile head during driving. kg 0

M-174 Steel pipe 25 mm external dia as per IS:1239 metre 0

M-175 Steel pipe 50 mm external dia as per IS:1239 metre 254

M-179 Structural Steel tonne 45000

M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 74

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 3450

M-188 Unstaked lime tonne 3037

M-189 Water KL 130

M-190 Water based cement paint litre 250.00

Overheads for Road Works 8%

Contractors profit for Road Works 10%


for input of Overheads or Contractors profit please type in collum
Overheads for Bridge Works 20%
C as like below
Contractors profit for Bridge Works 10%

Lead from Mixing Plant to working site 10.825 km

Lead for E/W borow area to site 44 km


Items
Summary of Rates calculated and used for analysis of rates of other items Unit Rate
No.
Item 8.9 Painting angle iron post two coats sqm 118.00

Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 6,159.00

Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 7,747.00

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Item 12.8 (A) cum 5,644.00
by Mixer
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
Item 12.8 (G) cum 5,974.00
by Batching Plant

Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 8,682.00

Item No. 3.13 Excavation for Structures (Manual Means) cum 708.00

Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 9,387.00

Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 10,571.39
RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching
Item 14.1(C) cum
Plant 5,988.00

Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 63,459.00

Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 81,161.00
Metal, Sand Cartrage Cost as per SOR' 2020-21 of Annexure V in Page 38

Lead Charges for Metal,


Lead Charges for
S.NO DISTANCE Sand,Gravel & Earth
Cement & Steel (MT)
(cum)

1 0-10 Km 11.13 6.96

2 10-20 Km 9.52 5.96

3 20-40 Km 8.2 5.13

4 40-80 Km 7.69 4.42

5 Above 80 Km 6.45 4.03


Rate for Conveyance for Bitumen

Cost of bitumen 60/70, 80/100 and CRMB Grade and Bitumen Emulsion

Lead 76 76 76
Bitumen
Bitumen (Cationic
Sl (Cationic Bitumen (60/70
Particulars Emulsion)
No Emulsion) grade) V40
Packed - RS1
Packed SS1
1 Basic price of Bitumen 50620.00 50322.00 34950.00

2 Transport Charges Lead from Factory 833 833.00 833.33

3 Storage charges on Basic Rate, 5% 0.00 0.00 0.00

4 Drum Deduction

5 Cost of Bitumen at site per MT 51453 51155 35783


DFR
Volume 5: Rate Analysis
Annexures

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge Works

This Software runs on Microsoft Excel

INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable

SUMMARY - In this sheet summary of all the rates analysized is presented

ANALYSIS- The analysis has been presented in 16 nos. of spread sheets

Worksheet- 2 : CHAPTER-2 SITE CLEARANCE

Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE

Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS

Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)

Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES

Worksheet- 12 : CHAPTER-12 FOUNDATIONS

Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE

Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE

Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS

Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION


Lead Calculation

Sl No Description of Item Calculation Lead


1 Bitumen Lead

Average Lead for Bitumen 75.90

2 Sand Lead

Average Lead for Sand 42.60


Lead for Metal (To Work Site) 10.82
TOTAL 53.42

3 Metal Lead

Lead for Metal (To CMP) 42.60


Lead for Metal (To Work Site) 10.82
TOTAL 53.42

4 Gravel Lead
Average Lead for Gravel 43.61

5 Borrow Soil

Average Lead for Borrow Soil 43.61

6 Bitumen Emulsion Lead

Average Lead for Bitumen 75.90

7 Cement Lead

Lead for Cement 273.00

8 Steel Lead

Lead for Steel 95.90


Lead Calculation

Metal Lead
Source to Project Road at 61+200 40.66
Lead if any 0.00
Quarry To CMP 40.66

Sand Lead
Source to Project Road at 61+200 40.66
Lead if any 0.00
Quarry To CMP 40.66

Bitumen Lead
IOCL, Chennai to CH:35+800 43.00
CH:35+800 to CH:61+200 CMP 24.20
Factory To CMP 67.20

Bitumen Emulsion Lead


IOCL, Chennai to CH:35+800 42.00
CH:35+800 to CH:61+200 CMP 25.40
Factory To CMP 67.40

Earth / Gravel Lead


Source to Project various sections of TCS-1 43.61
Lead if any 0.00
Total Lead 43.61

Cement Lead
Nallalingayapalli to to CH:61+200 CMP 273.00
Total Lead 273.00

Steel Lead
Kamahi Steel Factory , Gummidipundi to
95.90
CH:61+200 CMP
Total Lead 95.90
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Loading and unloading of stone boulder / stone aggregates /
1.1
sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
1 Min
ii) Loading by front end loader 1 cum bucket capacity @ 25
13 Min
cum per hour
iii) Maneuvering, reversing, dumping and turning for return 2 Min
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 530.19 174.96 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 1379.89 455.36 P&M-017
b) Overheads @ 0.08 on (a) 50.43
c) Contractors profit @ 0.1 on (a+b) 68.08
Cost for 5.5 cum = a+b+c 748.83
Rate per cum = (a+b+c)/ 5.5 136.15
Note Unloading will be by tipping. say 136.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 530.19 212.08 P&M-048
Time taken for empty return trip. hour 0.290 530.19 153.76 P&M-048
b) Overheads @ 0.08 on (a) 29.27
c) Contractors profit @ 0.1 on (a+b) 39.51
cost for 100 t km = a+b+c 434.61
Rate per t.km = (a+b+c)/100 4.35
say 4.30

1.4(II) Case II Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
Time taken for onward hanlage with load hour 0.500 530.19 265.10 P&M-048
Time taken for empty return trip hour 0.330 530.19 174.96 P&M-048
b) Overheads @ 0.08 on (a) 35.20
c) Contractors profit @ 0.1 on (a+b) 47.53
Cost for 100 t .km = a+b+c 522.79
Rate per t.Km = (a+b+c)/100 5.23
say 5.20

Katcha Track and Track in river bed / nallah bed and choe
1.4(III) Case III
bed.
Speed with load : 10 km / hour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 530.19 530.19 P&M-048
Time taken for empty return trip hour 0.670 530.19 355.23 P&M-048
b) Overheads @ 0.08 on (a) 70.83
c) Contractors profit @ 0.1 on (a+b) 95.63
Cost for 100 t .km = a+b+c 1051.88
Rate per t.Km = (a+b+c)/100 10.52
say 10.50
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 639.10 38.35 L-12
Mazdoor day 1.500 719.40 1079.10 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 835.49 919.04 M-002
c) Overheads @ 0.08 on (a+b) 162.92
d) Contractors profit @ 0.1 on (a+b+c) 219.94
Rate per cum = a+b+c+d 2419.35
say 2419.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor
Hour 6.000 21316.72 127900.34 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overheads @ 0.08 on (a+b+c) 62017.01
e) Contractors profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 600 cum = a+b+c+d+e 920952.66
Rate per cum = (a+b+c+d+e)*0.95/600 1458.18
say 1458.00
1. 800 cum of stone boulders are needed to get 600 cum of
Note
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a by-
product.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.7 Crushing of stone aggregates 20 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor including breaking of any size boulder. day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor
Hour 6.000 21316.72 127900.34 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overheads @ 0.08 on (a+b+c) 62017.01
e) Contractors profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 670 cum = a+b+c+d+e 920952.66
Rate per cum = (a+b+c+d+e)*0.90/670 1237.10
say 1237.00

1. 800 cum of stone boulders are needed to get 600 cum of


Note
stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.8 Crushing of stone aggregates 40 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor
Hour 6.000 21316.72 127900.34 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overheads @ 0.08 on (a+b+c) 62017.01
e) Contractors profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 750 cum = (a+b+c+d+e)x0.85 782809.76
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e)x0.85/750 1043.75
say 1044.00
1. 800 cum of stone boulders are needed to get 600 cum of
Note
stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
5.9 510 Surface Dressing

Providing and laying surface dressing as wearing course in


single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 639.10 281.20 L-12
Mazdoor day 9.000 719.40 6474.60 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 610.07 4392.49 P&M-031
Air compressor 250 cfm hour 7.200 546.40 3934.07 P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per hour hour 6.000 3390.68 20344.10 P&M-025
Tipper 10 tonne capacity for carriage of stone chips from
hour 6.000 530.19 3181.15 P&M-048
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Bitumen pressure distributor hour 6.000 1835.99 11015.96 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 788.34 4730.06 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 51155.00 552474.00 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum
cum 135.000 1822.49 246036.69 M-053
per sqm
d) Overheads @ 0.08 on (a+b+c) 69003.25
e) Contractors profit @ 0.1 on (a+b+c+d) 93154.39
Cost for 9000 sqm= a+b+c+d+e 1024698.31
Rate per sqm = (a+b+c+d+e)/9000 113.86
say 114.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 639.10 281.20 L-12
Mazdoor day 9.000 719.40 6474.60 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 610.07 4392.49 P&M-031
Air compressor 250 cfm hour 7.200 546.40 3934.07 P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per hour hour 6.000 3390.68 20344.10 P&M-025
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tipper 10 tonne capacity for carriage of stone chips from
hour 6.000 530.19 3181.15 P&M-048
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 2277.05 13662.29 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 51155.00 460395.00 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum
cum 90.000 1753.49 157814.46 M-052
per sqm
d) Overheads @ 0.08 on (a+b+c) 55293.73
e) Contractors profit @ 0.1 on (a+b+c+d) 74646.54
Cost for 9000 sqm= a+b+c+d+e 821111.94
Rate per sqm = (a+b+c+d+e)/9000 91.23
say 91.00
1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
Note
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
5.15 516 Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix = 264
tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler.
Pneumatic tyred roller with individual wheel load not
hour 6.000 1746.86 10481.14 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 51453.33 996136.53 M-077
Fine aggregate 4.75 mm and below 87 % of total mix,80 x
2.2 x 0.87 = 153.12 tonnes. Taking density1.5,= 153.12/1.5 cum 102.080 1753.74 179021.29 M-005
= 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 3037.00 10690.24 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overheads @ 0.08 on (a+b+c) 98467.30
e) Contractors profit @ 0.1 on (a+b+c+d) 132930.85
Cost for 16000 sqm= a+b+c+d+e 1462239.34
Rate per sqm = (a+b+c+d+e)/16000 91.39
say 91.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor day 5.000 719.40 3597.00 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 51453.33 882939.20 M-077
Fine aggregate 3 mm and below 85 % of total mix, 60x 2.2 x
cum 74.800 1753.74 131179.40 M-005
0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 3037.00 8017.68 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
d) Overheads @ 0.08 on (a+b+c) 84472.26
e) Contractors profit @ 0.1 on (a+b+c+d) 114037.56
Cost for 30000 sqm= a+b+c+d+e 1254413.12
Rate per sqm = (a+b+c+d+e)/20000 62.72
say 63.00
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor day 5.000 719.40 3597.00 L-13
b) Machinery
Mechanical broom hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Mobile slurry seal equipment hour 6.000 1503.75 9022.53 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment,bitumen emulsion hour 6.000 530.19 3181.15 P&M-048
and filler.
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 51453.33 651913.73 M-077
Fine aggregate 2.36 mm and below,82 % of total mix,36x
cum 43.300 512.99 22212.64 M-022
2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 3037.00 4798.46 M-188
Cost of water KL 12.000 130.00 1560.00 M-189
d) Overheads @ 0.08 on (a+b+c) 57015.35
e) Contractors profit @ 0.1 on (a+b+c+d) 76970.72
Cost for 24000 sqm= a+b+c+d+e 846677.93
Rate per sqm = (a+b+c+d+e)/24000 35.28
say 35.00
1.Tack coat, if required to be provided, before laying slurry
Note
seal may be measured and paid separately

5.17 518 Fog Spray


Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per hour tonne 6.000 1835.99 11015.96 P&M-004

c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 51453.33 405452.27 M-077
d) Overheads @ 0.08 on (a+b+c) 34051.35
e) Contractors profit @ 0.1 on (a+b+c+d) 45969.33
Cost for 10500 sqm= a+b+c+d+e 505662.60
Rate per sqm = (a+b+c+d+e)/10500 48.16
say 48.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor for precoating of grit day 4.000 719.40 2877.60 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 754.74 19812.03 M-024
Bitumenemulsion for precoating grit @ 2 % of grit,39.38 x
tonne 0.790 51453.33 40648.13 M-077
0.02
63440.02
6.04
say 6.00

5.21 522 Crack Prevention Courses


Stress Absorbing Membrane (SAM) crack width less than 6
Case - I
mm
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.

Providing and laying of a stress absorbing membrane over a


cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfm hour 6.000 546.40 3278.39 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Hydraulic Chip spreader hour 6.000 3390.68 20344.10 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 788.34 4730.06 P&M-044
c) Material
Modified binder tonne 9.450 26356.18 249065.90 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 1075.49 112926.87 M-050
d) Overheads @ 0.08 on (a+b+c) 32759.32
e) Contractors profit @ 0.1 on (a+b+c+d) 44225.08
Cost for 10500 sqm= a+b+c+d+e 486475.87
Rate per sqm = (a+b+c+d+e)/10500 46.33
say 46.00

Stress Absorbing Membrane (SAM) with crack width 6 mm


Case - II
to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfem capacity hour 6.000 546.40 3278.39 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Hydraulic Chip spreader hour 6.000 3390.68 20344.10 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 788.34 4730.06 P&M-044
c) Material
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Modified binder tonne 11.550 26356.18 304413.88 M-078
Crushed stone chipping 11.2 mm size cum 105.000 1367.49 143586.87 M-051
d) Overheads @ 0.08 on (a+b+c) 39639.96
e) Contractors profit @ 0.1 on (a+b+c+d) 53513.94
Cost for 10500 sqm= a+b+c+d+e 588653.35
Rate per sqm = (a+b+c+d+e)/10500 56.06
say 56.00
Stress Absorbing Membrane (SAM) crack width above 9 mm
Case III
and cracked area above 50 %

Providing and laying a single coatn of a stress absorbing


membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 610.07 3660.41 P&M-031
Air compressor 250 cfem capacity hour 6.000 546.40 3278.39 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1835.99 11015.96 P&M-004
Hydraulic Chip spreader hour 6.000 3390.68 20344.10 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 788.34 4730.06 P&M-044
c) Material
Modified binder tonne 15.750 26356.18 415109.84 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 1367.49 172304.24 M-051
d) Overheads @ 0.08 on (a+b+c) 50904.78
e) Contractors profit @ 0.1 on (a+b+c+d) 68721.46
Cost for 10500 sqm= a+b+c+d+e 755936.02
Rate per sqm = (a+b+c+d+e)/10500 71.99
say 72.00
Case IV Case - IV : Bitumen Impregnated Geotextile

Providing and laying a bitumen impregnated geotextile layer


after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 639.10 357.90 L-12
Mazdoor day 12.000 719.40 8632.80 L-13
Mazdoor skilled day 2.000 698.50 1397.00 L-15
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 610.07 1708.19 P&M-031
Air compressor 250 cfem capacity hour 2.800 546.40 1529.92 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 1835.99 3671.99 P&M-004
Pneumatic roller hour 2.000 1746.86 3493.71 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per
tonne 3.680 0.00 0.00 M-075
sqm
Geotextile including 10 % for overlaps sqm 3850.000 0.00 0.00 M-108
d) Overheads @ 0.08 on (a+b+c) 1663.32
e) Contractors profit @ 0.1 on (a+b+c+d) 2245.48
Cost for 10500 sqm= a+b+c+d+e 24700.31
Rate per sqm = (a+b+c+d+e)/3500 7.06
say 7.00

As bitumen overlay construction shallfollow closely the fabric


placement on the same day, an output of 3500 sqm only
NOTE has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day

8.3 801 Printing new letter and figures of any shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 639 44.74
Painter Ist class day 1.25 757 946.00
Mazdoor day 0.50 719 359.70
b) Material
Paint Litre 0.50 360 180.00
c) Overheads @ 0.08 on (a+b) 122.43
d) Contractors profit @ 0.1 on (a+b+c) 165.29
Cost for 1600 cm = a+b+c+d 1818.16
Rate per cm height per letter = (a+b+c +d)/1600 1.14
say 1.10
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 639 76.69
Painter day 2.00 757 1513.60
Mazdoor day 1.00 719 719.40
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.00 223 1339.20
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add for scaffolding @ 1% of labour cost where required 13.39
c) Overheads @ 0.08 on (a+b) 292.98
d) Contractors profit @ 0.1 on (a+b+c) 395.53
Cost for 40 sqm = a+b+c+d 4350.79
Rate per sqm = (a+b+c+d)/40 108.77
say 109.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.03 639 19.17
Painter day 0.45 757 340.56
Mazdoor day 0.25 719 179.85
b) Material
Paint ready mixed approved brand. Litre 1.25 360 450.00
Add @ 1% on cost of material for scaffolding 4.50
c) Overheads @ 0.08 on (a+b) 79.53
d) Contractors profit @ 0.1 on (a+b+c) 107.36
Cost for 10 sqm = a+b+c+d 1180.97
Rate per sqm = (a+b+c+d)/10 118.10
say 118.00
Sub-
12.6 analysis Cement mortar1:3 (1cement :3 sand)
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.51 7146.39 3644.66
Sand cum 1.05 1753.74 1841.42
b) Labour
Mate day 0.04 639.10 25.56
Mazdoor day 0.90 719.40 647.46
Total Material and Labour = (a+b) 6159.00

Sub-
analysis Cement mortar1:2 (1cement :2 sand)
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.67 7146.39 4802.37
Sand cum 0.93 1753.74 1636.82
b) Labour
Mate day 0.04 639.10 25.56
Mazdoor day 0.90 719.40 647.46
Total Material and Labour = (a+b) 7112.00

Sub-
analysis Cement mortar1:6 (1cement :6 sand)
(D)
Unit = 1 cum
Taking output = 1 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Materials
Cement MT 0.29 7146.39 2058.16
Sand cum 1.20 1753.74 2104.48
b) Labour
Mate day 0.04 639.10 25.56
Mazdoor day 0.90 719.40 647.46
Total Material and Labour = (a+b) 4836.00
Stone masonry work in cement mortar 1:3 in foundation
12.7 1400
complete as drawing and Technical Specification
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 573.00 3151.50 M-169
Through and bond stone each 35.00 17.00 595.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Item 12.6
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 6159.00 9238.50
(A)
b) Labour
Mate day 0.66 639.10 421.81 L-12
Mason day 7.50 947.10 7103.25 L-11
Mazdoor day 9.00 719.40 6474.60 L-13
c) Overhead charges @ 0.2 on (a+b) 5396.93
d) Contractor's profit @ 0.1 on (a+b+c) 3238.16
Cost for 5 cum = a+b+c+d 35619.75
Rate per cum (a+b+c+d)/5 7123.95
say 7124.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 493.00 2711.50
Through and bond stone Nos 35.00 17.00 595.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A) cum 1.55 6159.00 9546.45
b) Labour
Mate day 0.62 639.10 396.24
Mason day 6.00 947.10 5682.60
Mazdoor day 9.00 719.40 6474.60
c) Overheads @ 0.2 on (a+b) 5081.28
d) Contractors profit @ 0.1 on (a+b+c) 3048.77
Cost for 5 cum = a+b+c+d 33536.44
Rate per cum (a+b+c+d)/5 6707.29
say 6707.00
The labour already considered in cement mortar has been
@ taken into account while proposing labour for masonry
works.

Stone masonry work in cement mortar 1:6 in foundation


12.7 (Add) 1400
complete as drawing and Technical Specification
Unit = cum
Taking output = 5 cum
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Stone cum 5.50 493.00 2711.50
Through and bond stone Nos 35.00 17.00 595.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D) cum 1.55 4836.00 7495.80
b) Labour
Mate day 0.62 639.10 396.24
Mason day 6.00 947.10 5682.60
Mazdoor day 9.00 719.40 6474.60
c) Overheads @ 0.2 on (a+b) 4671.15
d) Contractors profit @ 0.1 on (a+b+c) 2802.69
Cost for 5 cum = a+b+c+d 30829.58
Rate per cum (a+b+c+d)/5 6165.92
say 6166.00
The labour already considered in cement mortar has been
@ taken into account while proposing labour for masonry
works.

1500, 1700 Plain/Reinforced cement concrete in open foundation


12.8
& 2100 complete as per drawing and technical specifications
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 7146.39 29514.59
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 8.10 1419.49 11497.90
20 mm Aggregate cum 4.05 1822.49 7381.10
10 mm Aggregate cum 1.35 1367.49 1846.12
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 63 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,644.00
d) Formwork @ 4% on cost of concrete i.e.cost of material,
3385.81
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d) 17606.20
f) Contractors profit @ 0.1 on (a+b+c+d+e) 10563.72
Cost for 15 cum = a+b+c+d+e+f 116200.93
Rate per cum (a+b+c+d+e+f)/15 7746.73
say 7747.00
Nedle Vibrator is an item of minor T & P which is already
Note included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement MT 5.16 7146.39 36875.37
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,166.00
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 7146.39 37232.69
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,253.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 7146.39 297718.61
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Lead beyond 1 km, L-lead in km T-km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,549.00
d) Formwork @ 4% on cost of concrete i.e.cost of material,
26632.63
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d) 138489.67
f) Contractors profit @ 0.1 on (a+b+c+d+e) 83093.80
Cost for 120 cum = a+b+c+d+e+f 914031.83
Rate per cum = ( a+b+c+d+e+f )/120 7616.93
say 7617.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 7146.39 42806.88
Coarse sand cum 6.75 1753.74 11837.71
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,561.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 7146.39 342669.40
Coarse sand cum 54.00 1670.49 90206.68
40 mm Aggregate cum 43.20 1419.49 61322.14
20 mm Aggregate cum 43.20 1822.49 78731.74
10 mm Aggregate cum 21.60 1367.49 29537.87
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity lead beyond 1
T-Km 300L 7.28 23645.69 10.824610
Km, L - lead in Kilometer
098486
Concrete Pump hour 6 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,860.00
d) Formwork @ 3.75% of cost of concrete i.e.cost of
26369.43
material, labour and machinery
e) Overheads @ 0.2 on (a+b+c+d) 145910.87
f) Contractors profit @ 0.1 on (a+b+c+d+e) 87546.52
cost of 120 cum = a+b+c+d+e+f 963011.75
Rate per cum (a+b+c+d+e+f)/120 8025.10
say 8025.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 7146.39 43235.66
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,653.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.

Case II With Batching Plant, Transit Mixer and Conrete Pump


Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 7146.39 345742.35
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 193.52 179.00 34640.08
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity 1 cum hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity lead beyond 1
T-Km 300L 7.28 23645.69 10.824610
Km, L - lead in Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,238.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 7146.39 43450.05
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,604.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 7146.39 347314.55
Coarse sand cum 54.00 1670.49 90206.68
40 mm Aggregate cum 43.20 1419.49 61322.14
20 mm Aggregate cum 43.20 1822.49 78731.74
10 mm Aggregate cum 21.60 1367.49 29537.87
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity lead beyond 1
T-Km 300L 7.28 23645.69 10.824610
Km, L - lead in Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,899.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.10 7146.39 43592.98
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,677.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 7146.39 348743.83
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity lead beyond 1
T-Km 300L 7.28 23645.69 10.824610
Km, L - lead in Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,974.00
d) Formwork @ 3% on cost of concrete i.e.cost of material,
21505.23
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d) 147669.24
f) Contractors profit @ 0.1 on (a+b+c+d+e) 88601.54
cost of 120 cum = a+b+c+d+e+f 974616.96
Rate per cum (a+b+c+d+e+f)/120 8121.81
say 8122.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 6153.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
Note:
cement may be added for achieving desired slump of
concrete.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 7146.39 45236.65
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,786.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 50.64 7146.39 361893.19
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 202.56 179.00 36258.24
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity lead beyond 1
T-Km 300L 7.28 23645.69 10.824610
Km, L - lead in Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,386.00
d) Formwork @ 3% on cost of concrete i.e.cost of material,
22987.46
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d) 157847.20
f) Contractors profit @ 0.1 on (a+b+c+d+e) 94708.32
cost of 120 cum = a+b+c+d+e+f 1041791.53
Rate per cum (a+b+c+d+e+f)/120 8681.60
say 8682.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 6577.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
Note:
cement may be added for achieving desired slump of
concrete.

1200, 1500 Plain/Reinforced cement concrete, in well foundation


12.11
& 1700 complete as per drawing and technical specification

C Bottom Plug
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 7146.39 39662.46
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixer Kg 18.60 179.00 3329.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6819.00
10% extra cement may be added where under water
Note
concreting is involved.
Using Batching Plant, Transit Mixer and Crane/concrete
Case II
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 7146.39 317299.72
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 148.80 179.00 26635.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
T-Km 300L 7.28 23645.69 10.824610
Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5934.00

(ii) PCC Grade M25

Case I Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.99 7146.39 42806.88
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Admixer Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7065.00
Using Batching Plant, Transit Mixer and Crane/concrete
Case II
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 7146.39 342169.15
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
T-Km 300L 7.28 23645.69 10.824610
Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6177.00

(iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 7146.39 43450.05
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixer Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7108.00
Using Batching Plant, Transit Mixer and Crane/concrete
Case II
pump
Unit = cum
Taking output = 120 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Material
Cement MT 48.64 7146.39 347600.41
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
T-Km 300L 7.28 23645.69 10.824610
Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6223.00
(iv) PCC Grade M35

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.29 7146.39 44950.79
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixer Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7208.00
Using Batching Plant, Transit Mixer and Crane/concrete
Case II
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.28 7146.39 359320.49
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixer Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
T-Km 300L 7.28 23645.69 10.824610
Kilometer
098486
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6320.00
Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making 33699.23
arrangements for under water concreteing with tremie pipe..

d) Overheads @ 0.2 on (a+b+c) 158414.72


e) Contractors profit @ 0.1 on (a+b+c+d) 95048.83
cost of 120 cum = a+b+c+d+e 1045537.16
Rate per cum (a+b+c+d+e)/120 8712.81
Say 8713.00
F Well cap
iv) RCC Grade M35
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 7146.39 361893.19
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader(capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
L=
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6.00 437.58 2625.49
Formwork @ 3% of (a+b+c) 21899.71
d) Overheads @ 0.2 on (a+b+c) 150378.00
e) Contractors profit @ 0.1 on (a+b+c+d) 90226.80
cost of 120 cum = a+b+c+d+e 992494.83
Rate per cum (a+b+c+d+e)/120 8270.79
Say 8271.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
Note
cement may be added for achieving desired slump of
concrete.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaning earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.320 639.10 204.51 L-12
Mazdoor day 8.000 719.40 5755.20 L-13
b) Overheads @ 0.08 on (a) 476.78
c) Contractors profit @ 0.1 on (a+b) 643.65
Cost for 10 cum = a+b+c 7080.14
Rate per cum = (a+b+c)/10 708.01
say 708.00
Cost of dewatering may be added where required upto 10 %
Note of labour cost Assessment for dewatering shall be made as
per site conditions..

B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 639 204.51
Mazdoor day 8.00 719 5755.20
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2182 13092.74
c) Overheads @ 0.08 on (a+b) 1524.20
d) Contractors profit @ 0.1 on (a+b+c) 2057.66
Cost for 300 cum = a+b+c+d 22634.31
Rate per cum = (a+b+c+d)/300 75.45
say 75.00
Cost of dewatering upto 5% of (a+b) may be added, where
Note required. Assessment for dewatering shall be made as per
site conditions..

Section Supplying, fitting and placing HYSD bar reinforcement in


13.6 1600 & sub-structure complete as per drawing and technical
2200 specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage MT 1.05 52222.68 54833.81
Binding wire kg 6.00 50.00 300.00
b) Labour for cutting, bending, shifting to site, tying and
placing in position
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.34 639.10 217.29
Blacksmith day 2.00 729.30 1458.60
Mazdoor day 6.50 719.40 4676.10
c) Overheads @ 0.2 on (a+b) 12297.16
d) Contractors profit @ 0.1 on (a+b+c) 7378.30
Rate for per MT (a+b+c+d) 81161.26
say 81161.00
1500 Furnishing and Placing Reinforced/Prestressed cement
14.1 &1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 7146.39 292430.28
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 1591.73 23876.02
L=
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6.00 437.58 2625.49
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 660528.00

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
660528.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 132105.60
e) Overheads @ 0.2 on (a+b+c+d) 158526.72
f) Contractors profit @ 0.1 on (a+b+c+d+e) 95116.03
Cost for 15 cum = a+b+c+d+e+f 1046276.35
Rate per cum (a+b+c+d+e+f)/120 8718.97
say 8719.00
B RCC Grade M25

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 7146.39 342669.40
Coarse sand cum 54.20 1670.49 90540.77
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 1591.73 23876.02
L=
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6.00 437.58 2625.49
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 711101.00
For formwork and staging add the following:
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for
711101.00
120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 142220.20
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overheads @ 0.2 on (a+b+c+d) 170664.24
f) Contractors profit @ 0.1 on (a+b+c+d+e) 102398.54
Cost for 15 cum= a+b+c+d+e+f 1126383.98
Rate per cum (a+b+c+d+e+f)/120 9386.53
say 9387.00

C RCC Grade M 30

Case II Using Batching Plant, Transit Mixer and Concrete Pump.


Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 7146.39 348672.37
Coarse sand cum 54.60 1670.49 91208.97
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 19.00 719.40 13668.60
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 1591.73 23876.02
L=
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6.00 437.58 2625.49
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 718517.00
For formwork and staging add the following:

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
718517.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 143703.40
e) Overheads @ 0.2 on (a+b+c+d) 172444.08
f) Contractors profit @ 0.1 on (a+b+c+d+e) 103466.45
Cost for 15 cum = a+b+c+d+e+f 1138130.93
Rate per cum (a+b+c+d+e+f)/120 9484.42
say 9484.00
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP) 7185.00
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP) 5988.00

E PSC Grade M-40


Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 7146.39 46094.22
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Admixture @ 0.4% of cement kg 25.80 179.00 4618.20
b) Labour
Mate day 0.96 639.10 613.54
Mason day 2.00 947.10 1894.20
Mazdoor day 22.00 719.40 15826.80
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum 109241.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 7146.39 368753.72
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture @ 0.4% of cement kg 206.40 179.00 36945.60
Admixer Kg 216.00 179.00 38664.00
b) Labour
Mate day 0.94 639.10 600.75
Mason day 3.50 947.10 3314.85
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 1591.73 23876.02
L=
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.28 23645.69 10.824610
098486
Concrete Pump hour 6.00 437.58 2625.49
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 814437.00
For formwork and staging add the following:
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for
814437.00
120 cum
d) Formwork and staging 18 % of (a+b+c) 18.00 146598.66
e) Overheads @ 0.2 on (a+b+c+d) 192207.13
f) Contractors profit @ 0.1 on (a+b+c+d+e) 115324.28
Cost for 15 cum= a+b+c+d+e+f 1268567.07
Rate per cum (a+b+c+d+e+f)/120 10571.39
say 10571.00
1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
Note
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.
14.2 1600 Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage
Binding wire MT 1.05 52222.68 54833.81
b) Labour for cutting, bending, tying and placing in position Kg 8.00 50.00 400.00
Mate
Blacksmith day 0.44 639.10 281.20
Mazdoor day 3.00 729.30 2187.90
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) day 8.00 719.40 5755.20
63459.00
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-2
SITE CLEARANCE
Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.3 materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150 mm in thickness.)

(ii) By Mechanical Means


A In area of light jungle hectare 56730
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary,
2.4 sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and
lead of 1000 metres)

II By Mechanical Means for items No. 202( b) & ( c)


A Cement Concrete Grade M-15 & M-20 cum 690
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a
2.5 lead of 1000 metres, stacking serviceable and unserviceable materials separately)

II By Mechanical Means
A Bituminous course cum 558
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average
3.4 lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.) cum 316

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers,
3.6 trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to cum 76
the embankment location within all lifts and lead upto 1000m)

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000
metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and
3.7 loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in cum 101
accordance with requirements of lines, grades and cross sections.)

Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with
3.16 approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope cum 755
and compacting to meet requirement of table 300-2)

Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment
3.17 with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures cum 167
graded and compacted to meet requirement of table 300-2)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with
3.18 approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope cum 925
and compacted to meet requirement of table No. 300-2)

3.19 Compacting Original Ground


Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the
Case-I subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.) cum 108

Case-II :Compacting original ground supporting embankment cum 55


Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to
3.24 specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))

A Mechanical means metre 108


B Manual Means metre 177
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste material.
(Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
3.36 thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified cum 131
in IRC: SP: 58-2001 and as per approved plans.)

CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix
plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface
A and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )

(i) for grading- I Material cum 2195


Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper
4.12 to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with cum 2230
vibratory roller to achieve the desired density.)

Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island
4.14 above road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407) cum 970

4.15 Construction of Shoulders (A. Earthen Shoulders)


CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
5.1 clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.) sqm 40

5.2 Tack coat


Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the
rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical
broom. sqm 11

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch
type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
5.6 hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)

(i) for Grading I ( 40 mm nominal size ) cum 10100


Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @
5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
5.8 to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects)

(i) for Grading-I ( 13 mm nominal size ) cum 10834


Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
5.14 size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, sqm 817
pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Reinforced Cement Concrete Crash Barrier with frication Slab Provision of an Reinforced cement
7.09 concrete crash barrier with frication slab at the approaches to bridge structures,constructed with M-40 Mtetre 14077
grade concretewith HYSD reinforcement conforming toIRC:112 and as per dimensions in theapproved
drawing and at locationsdirected by the Engineer, all as specified.(Area-0.185 Sqm. /Meter)
Reinforced Earth slab
belowfrication Retaining
andWall (ReinforcedSqm./Meter)
(Area-1.032 earth retaining Crash
walls have four main
Barrier withcomponents as under: a) Excavation for
frication Slab
foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material).
7.5 b) Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing elements. d)
Earthfill with granular material which is to be retained by the wall.)

(i) Facing elements of RCC sqm 1738


(ii) Assembling, joining and laying of reinforcing elements.
A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 212
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
8.1 beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)

A Using Concrete Mixer metre 422


B Using Concrete Batching and Mixing Plant metre 836
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on
Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising
8.13 glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The sqm 691
finished surface to be level, uniform and free from streaks and holes.)

Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-
100 cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75
mm dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the
8.15 drawings.) each 3342

Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
8.21 painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes metre 1882
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
8.22 board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)

(i) M 40 grade concrete metre 5205


8.23 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be
A galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical metre 2943
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
8.27 street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)

(i) For Fixing in Median each 83101


For fixing in Footpath

(ii) each

66091
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
8.35 hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part each 586
4:1973)

CHAPTER-9
PIPE CULVERTS
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically
9.1 mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 6143

Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row . (Laying
Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular material in
9.2 single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets . )

B 1200 mm dia metre 9844


Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding in double row . (Laying
Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for culverts on first class bedding of granular material in
9.3 double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets . )

A 1000 mm dia metre 10427


B 1200 mm dia metre 19954
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
12.1 dressing of sides and bottom and backfilling with approved material.)

I Ordinary soil
B Mechanical Means
(i) Depth upto 3 m cum 105
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 2939
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
12.4 nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 6812

Plain/Reinforced cement concrete in open foundation complete as per drawing and technical
12.8 specifications

A PCC Grade M15 cum 7747


D PCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8025
E RCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8147
G RCC Grade M30
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8161
H RCC Grade M35
Case I Using Concrete Mixer cum 9226
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8271
Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.
12.9

A Assuming depth of water 1.0 m and height of island to be 1.25m. each 119173
B Assuming depth of water 4.0 m and height of island 4.5 m. each 480046
Providing and constructing one span service road to reach island location from one pier location to another pier location
C metre 6376

Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per drawing and
12.10 technical specification. tonne 98011
12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification
A Well curb
(i) RCC M20 Grade
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case I Using concrete mixer cum 9905
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8790
(ii) RCC M25 Grade
Case I Using concrete mixer cum 10538
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9881
(iii) RCC M35 Grade
Case I Using concrete mixer cum 10749
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10115
B Well steining
(I) PCC M15 Grade cum 8195
(ii) PCC M20 Grade cum 8953
(iii) RCC M20 Grade
Case I Using concrete mixer cum 9079
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8057
(iv) PCC M25 Grade
Case I Using concrete mixer cum 9527
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8509
(v) RCC M25 Grade
Case I Using concrete mixer cum 9660
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9058
(vi) PCC M30 Grade
Case I Using concrete mixer cum 9589
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8565
(vii) RCC M30 Grade
Case I Using concrete mixer cum 9695
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8674
(viii) RCC M35 Grade
Case I Using concrete mixer cum 9853
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9272
(ix) RCC M40 Grade 9362
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 9407
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8178
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 9748
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8515
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 9807
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8577
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 9946
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8713
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 9001
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7833
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 9326
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8154
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 9383
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8214
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 7450
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 8139
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 8661
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7735
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 8717
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7787
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 8524
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 7556
(ii) RCC Grade M25
Case I Using concrete Mixer cum 9111
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8148
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 9121
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8160
(iv) RCC Grade M35
Case I Using Concrete Mixer cum 9226
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8271
(v) RCC M40 Grade cum 8815
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.12 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 2006
(ii) Beyond 3m upto 10m depth metre 2753
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3637
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6822
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 8186
(v) Beyond 30m upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter 16209
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 19451
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 2984
(ii) Beyond 3m upto 10m depth metre 6983
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9222
b Add for dewatering @ 5% of cost, if required. metre 9684
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 17299
b Add 5% of cost for dewatering of the cost, if required metre 22705
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 21624
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 41104
b Add 5% of cost for dewatering, if required metre 51791
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 49324
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 7648
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 22164
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.13 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5665
(ii) Beyond 3m upto 10m depth metre 3746
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4949
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9284
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 11142
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22060
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 26471
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 3746
(ii) Beyond 3m upto 10m depth metre 5307
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 7010
b Add for dewatering @ 5% of cost, if required. metre 7360
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13149
b Add 5% of cost for dewatering on the cost, if required metre 17258
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 16436
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 31241
b Add 5% of cost for dewatering, if required metre 39363
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 37489
C Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 8688
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 28861
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.14 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 3501
(ii) Beyond 3m upto 10m depth metre 4282
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5655
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10605
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 12727
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3728
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 4474
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 4733
(ii) Beyond 3m upto 10m depth metre 7300
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9641
b Add for dewatering @ 5% of cost, if required. metre 10123
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 18085
b Add 5% of cost for dewatering on the cost, if required metre 23736
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 22606
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 42967
b Add 5% of cost for dewatering, if required metre 54138
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 51561
C Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 9053
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 32390
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil,
12.15 clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 3509
(ii) Beyond 3m upto 10m depth metre 4544
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6003
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11261
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 13513
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26755
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 32106
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 5103
(ii) Beyond 3m upto 10m depth metre 7689
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10155
b Add for dewatering @ 5% of cost, if required. metre 10662
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 19046
b Add 5% of cost for dewatering on the cost, if required metre 24998
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 23807
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 45249
b Add 5% of cost for dewatering, if required metre 57014
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 54299
C Soft rock ( 9m dia well )
(i) Depth upto 3m metre 10509
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 35730
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.16 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 4009
(ii) Beyond 3m upto 10m depth metre 4931
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6513
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12217
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 14660
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 29027
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 34832
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 5465
(ii) Beyond 3m upto 10m depth metre 8082
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10674
b Add for dewatering @ 5% of cost, if required. metre 11208
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20023
'b Add 5% of cost for dewatering on the cost, if required metre 26280
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 25028
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 47572
Summary of Rate Analysis
Item No. Descriptions Unit Rate
b Add 5% of cost for dewatering, if required metre 59940
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 57086
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 10290
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 38307
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.17 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 9018
(ii) Beyond 3m upto 10m depth metre 8160
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10777
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20214
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 24257
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 48024
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 57629
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 9963
(ii) Beyond 3m upto 10m depth metre 17391
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22968
b Add for dewatering @ 5% of cost, if required. metre 24117
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 43082
b Add 5% of cost for dewatering on the cost, if required metre 56546
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 53853
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 102356
b Add 5% of cost for dewatering, if required metre 128969
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 122827
C Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 22492
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 83327
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.18 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 18991
(ii) Beyond 3m upto 10m depth metre 23247
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 30701
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 57588
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 69105
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 136820
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 164184
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 24363
(ii) Beyond 3m upto 10m depth metre 40960
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 54095
b Add for dewatering @ 5% of cost, if required. metre 56800
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 101469
b Add 5% of cost for dewatering on the cost, if required metre 133178
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 126836
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 241075
b Add 5% of cost for dewatering, if required metre 303755
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 289290
C Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 50938
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 172407
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey
12.19 soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 4024
(ii) Beyond 3m upto 10m depth metre 4526
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5978
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11211
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 13453
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26634
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 31961
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 5596
(ii) Beyond 3m upto 10m depth metre 8938
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11804
b Add for dewatering @ 5% of cost, if required. metre 12394
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 22140
b Add 5% of cost for dewatering on the cost, if required metre 29059
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 27675
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 52599
b Add 5% of cost for dewatering, if required metre 66274
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 63118
C Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 12370
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 38965
Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained
personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and
plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled
blasting of hard rock where required, staircases and 1 m wide landing plate forms with railing, arrangement for
12.20
compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.

12.21 Sand filling in wells complete as per drawing and technical specifications cum 2939
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out as per
12.22 detailed drawing tonne 84599

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.23 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm) metre 10005
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.24 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) metre 16382

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and
12.25 removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm) metre 20709

Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and & Technical
12.26 Specification (Pile diameter - 750 mm) metre #VALUE!

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.27 Specification (Pile diameter - 1000 mm) metre #VALUE!

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.28 Specification (Pile diameter - 1200 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.29 Specification (Pile Diameter=500 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.30 Specification (Pile Diameter=750 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.31 Specification (Pile Diameter=1000 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.32 Specification (Size of pile - 300 mm x 300 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.33 Specification (Size of pile - 500 mm x 500 mm) metre #VALUE!

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
12.34 Specification (Size of pile - 750 mm x 750 mm) metre #VALUE!

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
12.35 column 400 x 250 mm (ISHB Series) ) metre 5193

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
12.36 column 450 x 250 mm (ISHB Series) ) metre 5858
12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 8462
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7631
B RCC Grade M25
(i) Using concrete mixer. cum 9032
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8200
C RCC Grade M30
(i) Using concrete mixer. cum 9103
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8272
D RCC Grade M35
(i) Using concrete mixer. cum 9254
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8422
12.39 Levelling course for Pile cap cum 7324
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical
12.40 specifications tonne 80739

CHAPTER-13
SUB-STRUCTURE
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical
13.5 specifications
G RCC Grade M30
(p) Height upto 5m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8674
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and
13.6 technical specifications tonne 81164
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
13.8 towards drawing foce. Complete as per drawing and Technical specifications each 137

Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
13.9 specification
A Granular material cum 1932
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than
600 mm with smaller size towards the soil and bigger size towards the wall and provided over the
13.10 entire surface behind abutment, wing wall and return wall to the full height compacted to a firm cum 2503
condition complete as per drawing and technical specification.

CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing
14.1 and Technical Specification
C RCC Grade M 30
Case II Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9484
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
14.2 drawing and technical specifications tonne 83768

Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as
14.4 per drawing and Technical Specifications cum 14329

14.9 Drainage Spouts complete as per drawing and Technical specification each 2163
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10 specification cum 7450

Reinforced cement concrete approach slab including reinforcement and formwork complete as per
14.11 drawing and Technical specification cum 12232

Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete
surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
14.16 metre 214

14.18 Filler joint


Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing
(ii) & Technical Specification. metre 198
CHAPTER-1
CARRIAGE OF MATERIALS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.1 Loading and Unloading of Stone Boulder/Stone cum
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 530.19 174.96 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 1379.89 455.36 P&M-017
cum/hour
b) Overhead charges @ 0.08 on (a) 50.43
c) Contractor's profit @ 0.1 on (a+b) 68.08
Cost for 5.5 cum = a+b+c 748.83
Rate per cum = (a+b+c)/ 5.5 136.15
Note Unloading will be by tipping. say 136.00
1.2 Loading and Unloading of Boulders by Manual Means

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 639.10 70.30 L-12
Mazdoor for loading and unloading day 0.750 719.40 539.55 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 530.19 397.64 P&M-048
c) Overhead charges @ 0.08 on (a+b) 80.60
d) Contractor's profit @ 0.1 on (a+b+c) 108.81
Cost for5.5 cum = a+b+c+d 1196.90
Rate per cum = (a+b+c+d)/5.5 217.62
Note Unloading will be by tipping. say 218.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor for loading and unloading day 2.000 719.40 1438.80 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 965.46 1930.92 P&M-057
c) Overhead charges @ 0.08 on (a+b) 273.67
d) Contractor's profit @ 0.1 on (a+b+c) 369.45
Cost for10 tonnes = a+b+c+d 4063.97
Rate per tonnes = (a+b+c+d)/10 406.40
say 406.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced Road


Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 530.19 212.08 P&M-048
Time taken for empty return trip. hour 0.290 530.19 153.76 P&M-048
b) Overhead charges @ 0.08 on (a) 29.27
c) Contractor's profit @ 0.1 on (a+b) 39.51
cost for 100 t km = a+b+c 434.61
Rate per t.km = (a+b+c)/100 4.35
say 4.30

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 530.19 265.10 P&M-048
Time taken for empty return trip hour 0.330 530.19 174.96 P&M-048
b) Overhead charges @ 0.08 on (a) 35.20
c) Contractor's profit @ 0.1 on (a+b) 47.53
Cost for 100 t .km = a+b+c 522.79
Rate per t.Km = (a+b+c)/100 5.23
say 5.20
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and Choe
Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 530.19 530.19 P&M-048
Time taken for empty return trip hour 0.670 530.19 355.23 P&M-048
b) Overhead charges @ 0.08 on (a) 70.83
c) Contractor's profit @ 0.1 on (a+b) 95.63
Cost for 100 t .km = a+b+c 1051.88
Rate per t.Km = (a+b+c)/100 10.52
say 10.50
1.5 Hand Broken Stone Aggregates 63 mm Nominal Size

Supply of quarried stone, hand breaking into coarse


aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 639.10 38.35 L-12
Mazdoor day 1.500 719.40 1079.10 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 835.49 919.04 M-002
c) Overhead charges @ 0.08 on (a+b) 162.92
d) Contractor's profit @ 0.1 on (a+b+c) 219.94
Rate per cum = a+b+c+d 2419.35
say 2419.00
1.6 Crushing of Stone Aggregates 13.2 mm Nominal Size.

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 21316.72 127900.34 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overhead charges @ 0.08 on (a+b+c) 62017.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 600 cum = a+b+c+d+e 920952.66
Rate per cum = (a+b+c+d+e)*0.95/600 1458.18

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 1458.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
1.7 Crushing of Stone Aggregates 20 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor including breaking of any size boulder. day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 21316.72 127900.34 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overhead charges @ 0.08 on (a+b+c) 62017.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 670 cum = a+b+c+d+e 920952.66
Rate per cum = (a+b+c+d+e)*0.90/670 1237.10
say 1237.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and


secondary crushing units.
1.8 Crushing of Stone Aggregates 40 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 639.10 485.72 L-12
Mazdoor Skilled day 2.000 0.00 0.00 L-14
Mazdoor day 17.000 719.40 12229.80 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 745.49 596395.20 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 21316.72 127900.34 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1379.89 27597.78 P&M-017
Tipper 5.5 cum capacity Hour 20.000 530.19 10603.85 P&M-048
d) Overhead charges @ 0.08 on (a+b+c) 62017.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 83722.97
Cost for 750 cum = (a+b+c+d+e)x0.85 782809.76
Rate per cum = (a+b+c+d+e)x0.85/750 1043.75
say 1044.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and


secondary crushing units.

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


CHAPTER-2
SITE CLEARANCE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 4415.18 44151.82 P&M-014
stumps
Tractor-trolley hour 1.000 620.49 620.49 P&M-053
c) Overhead charges @ 0.08 on (a+b) 3820.17
d) Contractor's profit @ 0.1 on (a+b+c) 5157.23
Rate per Hectare = a+b+c+d 56729.57
say 56730.00
2.5 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Unit = cum
Taking output = 1 cum
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.300 719.40 215.82 L-13
b) Machinery
Tractor-trolley hour 0.380 620.49 235.79 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 668.25 11.36 P&M-055
c) Overhead charges @ 0.08 on (a+b) 37.55
d) Contractor's profit @ 0.1 on (a+b+c) 50.69
Rate per cum = a+b+c+d 557.60
say 558.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.015 639.10 9.59 L-12
Mazdoor including loading and unloading day 0.225 719.40 161.87 L-13
b) Machinery
Tractor-trolley hour 0.300 620.49 186.15 P&M-053
c) Overhead charges @ 0.08 on (a+b) 28.61
d) Contractor's profit @ 0.1 on (a+b+c) 38.62
Cost for 10 m = a+b+c+d 424.83
Rate per metre = (a+b+c+d)/10 42.48
say 42.00
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 2182.12 13092.74 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 530.19 8483.08 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1845.26
d) Contractor's profit @ 0.1 on (a+b+c) 2491.10
Cost for 360 cum = a+b+c+d 27402.10
Rate per cum = (a+b+c+d)/360 76.12
say 76.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator CK-
90 and Tippers with Disposal upto 1000 metres.

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 2182.12 13092.74 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 530.19 5832.11 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1633.18
d) Contractor's profit @ 0.1 on (a+b+c) 2204.80
Cost for 240 cum = a+b+c+d 24252.76
Rate per cum = (a+b+c+d)/240 101.05
say 101.00
3.8 301 Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.400 639.10 255.64 L-12
Mazdoor for trimming slopes including mannul loading day 10.000 719.40 7194.00 L-13
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 2182.12 13092.74 P&M-026
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 530.19 3446.25 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 18.000 0.00 0.00 M-089
per cent of excavated quantity
c) Overhead charges @ 0.08 on (a+b) 1919.09
d) Contractor's profit @ 0.1 on (a+b+c) 2590.77
Cost for 36 cum = a+b+c+d 28498.49
Rate per cum = (a+b+c+d)/36 791.62
say 792.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 639.10 1048.12 L-12
Mazdoor including loading in truck day 16.000 719.40 11510.40 L-13
Chiseller day 24.000 0.00 0.00 L-05
Blacksmith day 1.000 729.30 729.30 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 530.19 1537.56 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 8.000 0.00 0.00 M-089
per cent of excavated
c) Overhead charges @ 0.08 on (a+b) 1186.03
d) Contractor's profit @ 0.1 on (a+b+c) 1601.14
Cost for 16 cum = a+b+c+d 17612.55
Rate per cum = (a+b+c+d)/16 1100.78
say 1101.00
Note 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 301 Excavation in Hard Rock (controlled blasting) with disposal
upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 639.10 140.60 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Driller day 2.000 0.00 0.00 L-06
Blaster day 0.500 0.00 0.00 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 4415.18 26491.09 P&M-014
Air compressor, 250 cfm with 2 jack hammers hour 6.000 546.40 3278.39 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 530.19 4347.58 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 37.00 2331.00 M-104
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 25.48 25683.84 M-094 /100
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 0.00 0.00 M-089
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 3635.50
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 0.08 on (a+b+c) 6107.64
e) Contractor's profit @ 0.1 on (a+b+c+d) 8245.32
Cost for 180 cum = a+b+c+d+e 90698.50
Rate per cum = (a+b+c+d+e)/180 503.88
say 504.00
Note 1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 301 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 639.10 51.13 L-12
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 2182.12 13092.74 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 530.19 7231.82 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1745.16
d) Contractor's profit @ 0.1 on (a+b+c) 2355.96
Cost for 300 cum = a+b+c+d 25915.61
Rate per cum = (a+b+c+d)/300 86.39
say 86.00
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 639.10 51.13 L-12
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour hour 6.000 2182.12 13092.74 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 530.19 8673.95 P&M-048
c) Overhead charges @ 0.08 on (a+b) 1860.53
d) Contractor's profit @ 0.1 on (a+b+c) 2511.71
Cost for 360 cum = a+b+c+d 27628.86
Rate per cum = (a+b+c+d)/360 76.75
say 77.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303

Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)

a) Labour
Mate day 0.600 639.10 383.46 L-12
Mazdoor day 15.000 719.40 10791.00 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 546.40 3278.39 P&M-001
hour
Dozer, 80 HP hour 6.000 4415.18 26491.09 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 37.00 1554.00 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 25.48 17122.56 M-094 /100
of 125 gms each
d) Overhead charges @ 0.08 on (a+b+c) 5431.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 7333.18
Cost for 400 sqm = a+b+c+d+e 80665.01
Rate per sqm = (a+b+c+d+e)/400 201.66
say 202.00
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.320 639.10 204.51 L-12
Mazdoor day 8.000 719.40 5755.20 L-13
b) Overhead charges @ 0.08 on (a) 476.78
c) Contractor's profit @ 0.1 on (a+b) 643.65
Cost for 10 cum = a+b+c 7080.14
Rate per cum = (a+b+c)/10 708.01
say 708.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 639.10 204.51 L-12
Mazdoor day 8.000 719.40 5755.20 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 2182.12 13092.74 P&M-026

d) Contractor's profit @ 0.1 on (a+b+c) 1905.25


Cost for 300 cum = a+b+c+d 20957.70
Rate per cum = (a+b+c+d)/300 69.86
say 70.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 639.10 255.64 L-12
Mazdoor day 10.000 719.40 7194.00 L-13
b) Overhead charges @ 0.08 on (a) 595.97
c) Contractor's profit @ 0.1 on (a+b) 804.56
Cost for 10 cum = a+b+c 8850.17
Rate per cum = (a+b+c)/10 885.02
say 885.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) B Mechanical Means

Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 639.10 153.38 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 2182.12 13092.74 P&M-026
c) Overhead charges @ 0.08 on (a+b) 1405.00
d) Contractor's profit @ 0.1 on (a+b+c) 1896.75
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 216 cum = a+b+c+d 20864.28
Rate per cum = (a+b+c+d)/216 96.59
say 97.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 639.10 338.72 L-12
ii) Driller day 0.840 0.00 0.00 L-06
iii) Blaster day 0.400 0.00 0.00 L-03
iv) Mazdoor day 12.000 719.40 8632.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 546.40 364.27 P&M-001
per hour
c) Material
Blasting Material kg 3.500 37.00 129.50 M-104
Detonator electric each 14.000 25.48 356.72 M-094 /100

d) Overhead charges @ 0.08 on (a+b+c) 785.76


e) Contractor's profit @ 0.1 on (a+b+c+d) 1060.78
Cost for 10 cum = a+b+c+d+e 11668.55
Rate per cum = (a+b+c+d+e)/10 1166.85
say 1167.00
Note Cost of dewatering @ 10 per cent of labour cost may be
added, where required Assessment for dewatering shall be
made as per site conditions.
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor day 5.000 719.40 3597.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 546.40 5463.99 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 0.08 on (a+b) 735.10
d) Contractor's profit @ 0.1 on (a+b+c) 992.39
Cost for 10 cum = a+b+c+d 10916.31
Rate per cum = (a+b+c+d)/10 1091.63
say 1092.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 639.10 255.64 L-12
Mazdoor day 10.000 719.40 7194.00 L-13
b) Machinery
Tractor-trolley hour 2.670 620.49 1656.70 P&M-053
c) Material
Selected earth for refilling cum 5.000 0.00 0.00 M-163
d) Overhead charges @ 0.08 on (a+b+c) 728.51
e) Contractor's profit @ 0.1 on (a+b+c+d) 983.48
Cost for 10 cum = a+b+c+d+e 10818.33
Rate per cum = ( a+b+c+d+e)/ 10 1081.83
say 1082.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.13 (v) B Mechanical Means

a) Labour
i) Mate day 0.080 639.10 51.13 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 719.40 1438.80 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 2182.12 370.96 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 530.19 238.59 P&M-048
c) Material
Selected earth for refilling cum 5.000 0.00 0.00 M-163
d) Overhead charges @ 0.08 on (a+b+c) 167.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 226.74
Cost for 10 cum = a+b+c+d+e 2494.18
Rate per cum = (a+b+c+d+e)/10 249.42
say 249.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.14 305.4.3 Scarifying Existing Granular Surface to a Depth of 50 mm by
Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 639.10 127.82 L-12
Mazdoor including loading and unloading day 5.000 719.40 3597.00 L-13
b) Machinery
Tractor-trolley hour 1.670 620.49 1036.21 P&M-053
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.08 on (a+b+c) 380.88
e) Contractor's profit @ 0.1 on (a+b+c+d) 514.19
Cost for 100 sqm = a+b+c+d 5656.11
Rate per sqm = (a+b+c+d)/100 56.56
say 57.00
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50 mm
by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.250 719.40 179.85 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 668.25 53.46 P&M-055
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 1379.89 275.98 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 530.19 121.94 P&M-048
c) Overhead charges @ 0.08 on (a+b) 51.01
d) Contractor's profit @ 0.1 on (a+b+c) 68.86
Cost for 100 sqm = a+b+c+d 757.50
Rate per sqm = (a+b+c+d)/100 7.57
say 8.00
3.16 305 Construction of Embankment with Material obtained from
Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 2182.12 3644.15 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 4.25 29644.22 Lead
=43.61 km
& P&M-058

Add 10 per cent of cost of carriage to cover cost of 2964.42


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 4415.18 2207.59 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 3959.08 3959.08 P&M-032
Water tanker6 KL capacity hour 4.000 530.19 2120.77 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 2277.05 2277.05 P&M-059
c) Material
Cost of water KL 24.000 130.00 3120.00 M-189
Compensation for earth taken from private land cum 100.000 128.60 12860.00 M-092
d) Overhead charges @ 0.08 on (a+b+c) 5083.38
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 6862.56
Cost for 100 cum = a+b+c+d+e 75488.18
Rate per cum = (a+b+c+d+e)/100 754.88
say 755.00
3.16 305 Construction of Embankment with Material obtained from
Borrowpits- Selected Earthfill
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 2182.12 3644.15 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 4.25 29644.22 Lead
=43.61 km
& P&M-058

Add 10 per cent of cost of carriage to cover cost of 2964.42


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 4415.18 2207.59 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 3959.08 3959.08 P&M-032
Water tanker6 KL capacity hour 4.000 530.19 2120.77 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 2277.05 2277.05 P&M-059
c) Material
Cost of water KL 24.000 130.00 3120.00 M-189
Compensation for earth taken from private land cum 100.000 196.30 19630.00 M-092
d) Overhead charges @ 0.08 on (a+b+c) 5624.98
e) Contractor's profit @ 0.1 on (a+b+c+d) 7593.72
Cost for 100 cum = a+b+c+d+e 83530.94
Rate per cum = (a+b+c+d+e)/100 835.31
say 835.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 2182.12 3644.15 P&M-026
per hour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tipper 10 tonne capacity tonne.km 175xL 4.25 32423.37 Lead
=43.61 km
& P&M-058

Add 10 per cent of cost of carriage to cover cost of 3242.34


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 4415.18 2207.59 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 3959.08 7918.16 P&M-032
Water tanker with 6 km lead hour 4.000 530.19 2120.77 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 2277.05 2846.31 P&M-059
c) Material
Cost of water KL 24.000 130.00 3120.00 M-189
Compensation for earth taken from private land cum 100.000 196.30 19630.00 M-092
d) Overhead charges @ 0.08 on (a+b+c) 6231.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 8412.94
Cost for 100 cum = a+b+c+d+e 92542.39
Rate per cum = (a+b+c+d+e)/100 925.42
say 925.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 639.10 6.39 L-12
Mazdoor for dressing of bed and side of drain day 0.250 719.40 179.85 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 2182.12 720.10 P&M-026
metres per hour
c) Overhead charges @ 0.08 on (a+b) 72.51
d) Contractor's profit @ 0.1 on (a+b+c) 97.88
Cost for 10 metres = a+b+c+d 1076.73
Rate per metre = (a+b+c+d)/10 107.67
say 108.00
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
3.36 Suggesti Embankment Construction with Flyash/Pond ash available
ve from coal or lignite burning Thermal Plants as waste
material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 2182.12 0.00 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 4.25 0.00 Lead =0
km & P&M-
058
Add 10 per cent of cost of carriagefor loading and 0.00
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 4415.18 7947.33 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 3959.08 14252.68 P&M-032
Water tanker6 KL capacity hour 12.000 530.19 6362.31 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 2277.05 8197.37 P&M-059
c) Overhead charges @ 0.08 on (a+b) 3179.16
d) Contractor's profit @ 0.1 on (a+b+c) 4291.87
Cost for 360 cum = a+b+c+d 47210.58
Rate per cum = (a+b+c+d)/360 131.14
say 131.00
Note 1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-1)

A Plant Mix Method


Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 639.10 255.64 L-12
Mazdoor skilled day 2.000 698.50 1397.00 L-15
Mazdoor day 8.000 719.40 5755.20 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 2058.26 12349.54 P&M-093
Electric generator 125 KVA hour 6.000 1193.51 7161.07 P&M-018
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 530.19 2385.87 P&M-060
hour
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 10 tonne tonne.km 450 x L 4.25 20694.68 Lead
=10.82461
0098486
km & P&M-
058
Add 10 per cent of cost of carriage to cover loading and 2069.47
unloading
Motor Grader 110 HP hour 6.000 3959.08 23754.47 P&M-032
Vibratory roller 8-10 t hour 6.000 2277.05 13662.29 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 9.5 mm @ 50 per cent cum 144.000 1473.35 212162.56 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 1017.24 57982.91 M-017
2.36 mm below @ 30 per cent cum 86.400 512.99 44322.68 M-020
Cost of water KL 27.000 130.00 3510.00 M-189
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.08 on (a+b+c) 33259.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 44900.21
Cost for 225 cum = a+b+c+d+e 493902.34
Rate per cum = (a+b+c+d+e)/225 2195.12
say 2195.00
4.12 406 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.

Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 639.10 306.77 L-12
Mazdoor skilled day 2.000 698.50 1397.00 L-15
Mazdoor day 10.000 719.40 7194.00 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 2058.26 13584.50 P&M-094
Electric generator 125 KVA hour 6.000 1193.51 7161.07 P&M-018
Front end loader 1 cum capacity hour 6.000 1379.89 8279.33 P&M-017
Paver finisher hour 6.000 1669.30 10015.77 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 2277.05 8880.49 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 530.19 1590.58 P&M-060
Tipper tonne.km 495 x L 4.25 22764.15 Lead
=10.82461
0098486
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 2276.41
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1497.66 133441.57 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1324.90 157398.49 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 512.99 45707.77 M-022
Cost of water KL 18.000 130.00 2340.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 33787.03
e) Contractor's profit @ 0.1 on (a+b+c+d) 45612.49
Cost for 225 cum = a+b+c+d+e 501737.41
Rate per cum = (a+b+c+d+e)/225 2229.94
say 2230.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..
4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 639.10 102.26 L-12
Mazdoor day 4.000 719.40 2877.60 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 530.19 530.19 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 178.27 1069.65 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 2182.12 1091.06 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 4.25 9727.01 Lead
=43.61 km
& P&M-058

Add 10 per cent of cost of transportation to cover cost 972.70


of loading and unloading
c) Material
Cost of water KL 6.000 130.00 780.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 1372.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 1852.25
Cost for 21 cum = a+b+c+d+e 20374.75
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/ 21 970.23
say 970.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.0 to
4.5 per cent by weight of total mix and filler, transporting the
hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all
respects.

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 639.10 536.84 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 719.40 11510.40 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 698.50 3492.50 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 24205.94 145235.63 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 4577.25 27463.50 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1107.85 6647.08 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1379.89 8279.33 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.25 20694.68 Lead
=10.82461
0098486
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 2069.47
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 788.34 3074.54 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 2277.05 8880.49 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1613.73 6293.54 P&M-045
roller.
c) Materials
Bitumen @ 4.69 per cent of weight of mix tonne 21.105 51155.00 1079626.28 M-074

Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1421.83 89845.27 M-049
25 - 10 mm 13 per cent cum 37.340 1605.64 59954.48 M-046
10 -4.75 mm 19 per cent cum 54.580 1148.49 62684.80 M-040
4.75 mm and below 44 per cent cum 126.390 754.74 95392.09 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3037.00 26178.94 M-188
or
(i) For Grading I ( 40 mm nominal size )
d) Overhead charges @ 0.08 on (a+b+c) 132628.79
e) Contractor's profit @ 0.1 on (a+b+c+d) 179048.87
Cost for 205 cum = a+b+c+d+e 1969537.52
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 10100.19
say 10100.00
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Reinforced Cement Concrete Crash Barrier
7.09
with frication Slab

Provision of an Reinforced cement concrete crash


barrier with frication slab at the approaches to
bridge structures,constructed with M-40 grade
concretewith HYSD reinforcement conforming
toIRC:112 and as per dimensions in theapproved
drawing and at locationsdirected by the Engineer,
all as specified.(Area-0.185 Sqm. /Meter)
belowfrication slab and (Area-1.032 Sqm./Meter)
Crash Barrier with frication Slab

Unit = Linear meter


Taking output = 10 m
a) M 40 grade concrete
PCC M 15 grade concrete (Area-0.185 Sqm. cu.m
/Meter) below frication slab 0.55 5644.00 3104.20

RCC M 40 grade concrete (Area- 1.032 Sqm. cu.m


/Meter) 10.32 6786.98 70041.58

b) Labour
Mate day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
c) Material
Steel (80 Kg / Cum) Kg 0.826 52222.68 43115.04
d) Overhead charges 0.08 on (a+b+c) 9479.66
e) Contractor's profit 0.1 on (a+b+c+d) 12797.54
Cost for 10 meter = a+b+c+d+e 140772.91
Rate per metre = (a+b+c+d)/10 14077.00

7.5 3100 Reinforced Earth Structures


Reinforced earth Structures have four main
components as under:
a) Excavation for foundation, foundation
concrete and cement concrete grooved seating in
the foundation for facing elements (facia
material).

b) Facia material and its placement.


c) Assembling, joining with facing elements
and laying of the reinforcing elements.

d) Earth fill with granular material which is to


be retained by the wall.
Each component is analysed separately as
under:
considering Average height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of reinforcing
elements.
A With reinforcing element of steel / Aluminium
strips / polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 639.10 230.08 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
Mazdoor skilled day 3.000 698.50 2095.50 L-15

Page 1 of 277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick
as per clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 0.00 0.00 M-154
or
2.Copper Strips metre 450*1.1 0.00 0.00 M-153
or
3.Aluminium Strips metre 450*1.1 0.00 0.00 M-157
or
4.Stainless steel strips metre 450*1.1 0.00 0.00 M-156
or
5.Glass reinforced polymer/fibre reinforced metre 450*1.1 150.00 74250.00 M-155
polymer/polymeric strips
@ Any one of the above alternative may be
adopted as per approved design.
Add 10 per cent of the cost of reinforcing strip
towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements
with the facia pannels, overlaps, heat bonding or
extension.

Type 5 5.Glass reinforced polymer/fibre reinforced


polymer/polymeric strips
c) Overhead charges @ 0.08 on (a+b) 6471.36
d) Contractor's profit @ 0.1 on (a+b+c) 8089.20

Cost of 450 m = a+b+c+d 95452.53


Rate per metre =(a+b+c+d)/450 212.12
say 212.00
7.5(i) B With reinforcing elements of synthetic geogrids

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 639.10 230.08 L-12
Mazdoor day 6.000 719.40 4316.40 L-13
Mazdoor skilled day 3.000 698.50 2095.50 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and sqm 300.000 74.00 22200.00 M-181
approved design and specifications.
Add 10 per cent of the cost of reinforcing 2220.00
elements (synthetic geogrids) for accessories
like tie-strips, nuts and bolts and loops/lugs
for joining reinforcing elements with the
facia pannels, overlaps and other protective
elements for synthetic geogrids.

c) Overhead charges @ 0.08 on (a+b) 2484.96


d) Contractor's profit @ 0.1 on (a+b+c) 3354.69

Cost of 300 sqm of Synthetic geogrids = a+b+c+d 36901.63

Rate per sqm = (a+b+c+d)/ 300 123.01


say 123.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour

Page 2 of 277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.180 639.10 115.04 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
Mazdoor skilled day 1.500 698.50 1047.75 L-15
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 610.07 3660.41 P&M-013

c) Material
Pre-cast RCC M-35 facing elements of size cu.m 13.500 6577.00 88789.50 Item 12.8
as per design and 18 cm thick for 75 sqm. (H)
(Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 81161.00 30841.18 Item 13.6

Add 2 per cent of cost of facia pannels, for all 2392.61


necessary temporary form work, scaffolding and
provision of loops/lugs for lifting of pannels and
joining the reinforcing elements.

d) Overhead charges @ 0.08 on (a+b) 558.51


e) Contractor's profit @ 0.1 on (a+b+d) 753.99

Cost for 75 sqm = a+b+c+d+e 130317.19


Rate per sqm = (a+b+c+d+e)/ 75 1737.56
say 1738.00

Page 3 of 277
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mason day 1.000 947.10 947.10 L-11
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 530.19 3181.15 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 2546.78 4074.84 P&M-003
Water tanker6 KL capacity hour 5.000 530.19 2650.96 P&M-060
Tipper 5.5 cum capacity hour 6.000 530.19 3181.15 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1822.49 39712.14 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 1670.49 18208.38 M-004
Cement 11 per cent tonne 5.700 7146.39 40734.42 M-081
Cost of water KL 30.000 130.00 3900.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 9448.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 12755.41
Cost for 360 meter = a+b+c+d+e 140309.51
Rate per metre = (a+b+c+d+e)/360 389.75
say 390.00
Rate fro 52.29 Cum of Concrete 836.00
8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel

Construction of cement concrete kerb with channel with top


and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
A Using Concrete Mixer
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 639.10 460.15 L-12
Mason day 2.000 947.10 1894.20 L-11
Mazdoor day 16.000 719.40 11510.40 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 530.19 3181.15 P&M-029
hour 6.000
and channel
Concrete mixer 0.48/0.28 hour 16.000 398.22 6371.57 P&M-009
Water tanker6 KL capacity hour 6.000 530.19 3181.15 P&M-060
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1822.49 66685.06 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 1753.74 32093.36 M-005
Cement 10 per cent tonne 9.010 7146.39 64388.97 M-081
Cost of water KL 36.000 130.00 4680.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 15555.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 21000.17
Cost for 360 meter = a+b+c+d+e 231001.86
Rate per metre = (a+b+c+d+e)/300 770.01
say 770.00
8.2 B Using Concrete Batching and Mixing Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mason day 1.000 947.10 947.10 L-11
Mazdoor day 2.000 719.40 1438.80 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 530.19 3181.15 P&M-029
hour 6.000
and channel
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 2546.78 6876.29 P&M-003
Water tanker6 KL capacity hour 6.000 530.19 3181.15 P&M-060
Tipper of 5.5 cum capacity hour 6.000 530.19 3181.15 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1822.49 66685.06 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 1670.49 30570.04 M-004
Cement 10 per cent tonne 9.010 7146.39 64388.97 M-081
Cost of water KL 36.000 130.00 4680.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 14816.51
e) Contractor's profit @ 0.1 on (a+b+c+d) 20002.29
Cost for 300 meter = a+b+c+d+e 220025.22
Rate per metre = (a+b+c+d+e)/300 733.42
say 733.00
8.3 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade

(i)
Hindi ( Matras commas and the like not to be measured and
paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 639.10 76.69 L-12
Painter day 2.000 756.80 1513.60 L-18
Mazdoor day 1.000 719.40 719.40 L-13
b) Material
Paint Litre 0.700 360.00 252.00 M-131
c) Overhead charges @ 0.08 on (a+b) 204.94
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 276.66
Cost for 1600 cm = a+b+c+d 3043.29
Rate per cm height per letter = (a+b+c+ d)/1600 1.90
say 1.90
8.3 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter Ist class day 1.250 756.80 946.00 L-18
Mazdoor day 0.500 719.40 359.70 L-13
b) Material
Paint Litre 0.500 360.00 180.00 M-131
c) Overhead charges @ 0.08 on (a+b) 122.43
d) Contractor's profit @ 0.1 on (a+b+c) 165.29
Cost for 1600 cm = a+b+c+d 1818.16
Rate per cm height per letter = (a+b+c +d)/1600 1.14
say 1.10
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
708.00 152.93 Item No.
i) Excavation for foundation cum 0.216
3.13
ii) Cement concrete M15 grade cum 0.120 7747.00 929.64 Item 12.8
(A)
iii) Painting angle iron post two coats sqm 0.430 118.00 50.74 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.250 719.40 179.85 L-13
b) Material

Mild steel angle iron 75 x 75 x 6 mm kg 19.000 45.00 855.00 M-179


/1000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 8820.00 3087.00 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 8820.00 1375.92 M-061
or
( iii ) 60 cm circular sqm 0.283 8820.00 2496.06 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 8820.00 4233.60 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 8820.00 2381.40 M-061
or
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(vi ) 60 cm x 60 cm square sqm 0.360 8820.00 3175.20 M-061
or
( vii ) 90 cm high octagon sqm 0.672 8820.00 5927.04 M-061
c) Machinery
Tractor-trolley hour 0.010 620.49 6.20 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 0.08 on (a+b+c) 330.76
e) Contractor's profit @ 0.1 on (a+b+c+d) 446.52
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6045.03
say 6045.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 0.08 on (a+b+c) 193.87
e) Contractor's profit @ 0.1 on (a+b+c+d) 261.72
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4012.27
say 4012.00
( iii ) 60 cm circular
d) Overhead charges @ 0.08 on (a+b+c) 283.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 382.70
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5342.99
say 5343.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 0.08 on (a+b+c) 422.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 570.35
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7407.19
say 7407.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 0.08 on (a+b+c) 274.31
e) Contractor's profit @ 0.1 on (a+b+c+d) 370.32
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5206.78
say 5207.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 0.08 on (a+b+c) 337.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 456.05
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6149.81
say 6150.00
( vii ) 90 cm high octagon
d) Overhead charges @ 0.08 on (a+b+c) 557.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 753.24
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 9419.00
say 9419.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

3. The depth of foundation and quantity of cement concrete


in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

Direction and Place Identification Signs upto 0.9 sqm Size


8.5 801
Board.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing

Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.216 708.00 152.93 Item No.
3.13
ii) Cement concrete M15 grade cum 0.120 7747.00 929.64 Item 12.8
(A)
iii) Painting angle iron post two coats sqm 0.430 118.00 50.74 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.200 719.40 143.88 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 45.00 855.00 M-179
kg 19.000
metres long /1000
Aluminium sheeting fixed with encapsulated lens type 8820.00 7938.00 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 620.49 12.41 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 716.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 967.21
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 11772.66
Rate per sqm (for sign having area upto 0.9 sqm) =
13080.73
(I+ii+iii+a+b+c+d+e)/0.90
say 13081.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more than
8.6 801
0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation cum 0.430 708.00 304.44 Item No.
3.13
ii) Cement concrete M15 grade cum 0.240 7747.00 1859.28 Item 12.8
(A)
iii) Painting angle iron post 2 coats sqm 0.860 118.00 101.48 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 639.10 6.39 L-12
Mazdoor day 0.300 719.40 215.82 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 45.00 1710.00 M-179
kg 38.000
metres long, 2 nos /1000
Aluminium sheeting fixed with encapsulated lens type 8820.00 13230.00 M-061
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 620.49 12.41 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 1196.19
e) Contractor's profit @ 0.1 on (a+b+c+d) 1637.08
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 20273.09
Rate per sqm ( for sign having area more than 0.9 sqm) =
22525.66
( i+ii+iii+a+b+c+d+e)/1.50
say 22526.00
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 639.10 153.38 L-12
Blacksmith day 2.000 729.30 1458.60 L-02
Mazdoor including for handling & fixing at site. day 4.000 719.40 2877.60 L-13
b) Material
Aluminium alloy/galvanised steel including 5 per cent 79069.00 83022.45 M-060
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
830.22
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
12577.90
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 610.07 1830.21 P&M-013
Truck hour 0.500 965.46 482.73 P&M-057
d) Overhead charges @ 0.08 on (a+b+c) 8258.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 11149.17
Rate per tonne = (a+b+c+d+e) 122640.92
say 122641.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 639.10 12.78 L-12
Blacksmith day 0.100 729.30 72.93 L-02
Mazdoor day 0.150 719.40 107.91 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 16954.00 16954.00 M-059
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
1.94
ladders, pulleys, ropes etc
c) Overhead charges @ 0.08 on (a+b) 1371.96
d) Contractor's profit @ 0.1 on (a+b+c) 1852.15
Rate per sqm = (a+b+c+d) 20373.68
say 20374.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
Note
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 639.10 76.69 L-12
Painter day 2.000 756.80 1513.60 L-18
Mazdoor day 1.000 719.40 719.40 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 223.20 1339.20 M-132
Add for scaffolding @ 1 per cent of labour cost where
13.39
required
Add @ 5 per cent cost of labour and materials to 182.44
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.08 on (a+b) 307.58
d) Contractor's profit @ 0.1 on (a+b+c) 415.23
Cost for 40 sqm = a+b+c+d 4567.54
Rate per sqm = (a+b+c+d)/40 114.19
say 114.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Painter day 0.450 756.80 340.56 L-18
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 360.00 450.00 M-131
Add @ 1 per cent on cost of material for scaffolding 4.50
Add @ 5 per cent cost of labour and materials to 49.48
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.08 on (a+b) 83.48
d) Contractor's profit @ 0.1 on (a+b+c) 112.70
Cost for 10 sqm = a+b+c+d 1239.75
Rate per sqm= (a+b+c+d)/10 123.98
say 124.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Painter day 0.500 756.80 378.40 L-18
Mazdoor day 0.200 719.40 143.88 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 360.00 540.00 M-131
Add @ 1 per cent on cost of material for scaffolding 5.40
Add @ 5 per cent cost of labour and materials to 54.07
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.08 on (a+b) 91.27
d) Contractor's profit @ 0.1 on (a+b+c) 123.22
Cost for 10 sqm = a+b+c+d 1355.42
Rate per sqm = (a+b+c+d)/10 135.54
say 136.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.11 803
on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 639.10 57.52 L-12
Painter day 0.550 756.80 416.24 L-18
Mazdoor day 1.550 719.40 1115.07 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 223.20 330.34 M-132
c) Overhead charges @ 0.08 on (a+b) 153.53
d) Contractor's profit @ 0.1 on (a+b+c) 207.27
Cost for 10 sqm = a+b+c+d 2279.97
Rate per sqm= (a+b+c+d)/10 228.00
say 228.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter day 0.350 756.80 264.88 L-18
Mazdoor day 1.350 719.40 971.19 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Road marking paint Litre 1.480 223.20 330.34 M-132
c) Overhead charges @ 0.08 on (a+b) 128.89
d) Contractor's profit @ 0.1 on (a+b+c) 174.00
Cost for 10 sqm = a+b+c+d 1914.04
Rate per sqm = (a+b+c+d)/10 191.40
say 191.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.12 803
on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 639.10 38.35 L-12
Painter Ist class day 0.300 756.80 227.04 L-18
Mazdoor day 1.250 719.40 899.25 L-13
b) Material
Road marking paint Litre 0.900 223.20 200.88 M-132
c) Overhead charges @ 0.08 on (a+b) 109.24
d) Contractor's profit @ 0.1 on (a+b+c) 147.48
Cost for 10 sqm = a+b+c+d 1622.23
Rate per sqm = (a+b+c+d)/10 162.22
say 162.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 639.10 44.74 L-12
Painter Ist class day 0.350 756.80 264.88 L-18
Mazdoor day 1.350 719.40 971.19 L-13
b) Material
Road marking Paint Litre 0.900 223.20 200.88 M-132
c) Overhead charges @ 0.08 on (a+b) 118.53
d) Contractor's profit @ 0.1 on (a+b+c) 160.02
Cost for 10 sqm= a+b+c+d 1760.24
Rate per sqm = (a+b+c+d)/10 176.02
say 176.00

Road Marking with Hot Applied Thermoplastic Compound


8.13 803
with Reflectorising Glass Beads on Bituminous Surface

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.

Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 639.10 19.17 L-12
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.750 719.40 539.55 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 159.75 1597.52 P&M-043
Tractor-trolley hour 0.500 620.49 310.24 P&M-053
c) Material
Hot applied thermoplastic compound Litre 1500.000 223.00 334500.00 M-118
Reflectorising glass beads kg 150.000 80.00 12000.00 M-152
d) Overhead charges @ 0.08 on (a+b+c) 27917.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 37688.38
Cost for 600 sqm = a+b+c+d+e 414572.19
Rate per sqm = a+b+c+d+e)/600 690.95
say 691.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.15 805 Road Delineators

Supplying and installation of delineators (road way


indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.

Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor for fixing day 1.000 719.40 719.40 L-13
b) Material
Cost of approved type of delineators from ISI certified 807.00 24210.00 M-091
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2421.00
c) Overhead charges @ 0.08 on (a+b) 2190.08
d) Contractor's profit @ 0.1 on (a+b+c) 2956.60
Cost for 30 Nos. delineators = (a+b+ c+d) 32522.65
Rate per delineators = (a+b+c+d) /30 1084.09
say 1084.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

Tubular Steel Railing on Precast RCC Posts, 1.2 m High


8.21 808
Above Ground Level
+
Unit = Running metre
Taking output = 10metres

i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296 708.00 917.57 Item No.
3.13
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 7747.00 5020.06 Item 12.8
cum 0.648
x 0.3 (A)
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres 8719.00 2790.08 Item
cum 0.320
each 14.1(A)
iv) Painting of pipe sqm 4.710 118.00 555.78 Item 8.9
a) Labour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.014 639.10 8.95 L-12
Mazdoor day 0.350 719.40 251.79 L-13
Plumber day 0.010 729.30 7.29 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 253.53 7605.90 M-175
c) Machinery
Tractor-trolley hour 0.250 620.49 155.12 P&M-053
d) Overhead charges @ 0.08 on (a+b+c) 642.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 867.14
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 18822.00
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1882.20
say 1882.00
8.22 809 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier for
bridge structures , constructed with M-40 grade concrete
with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with
pre-moulded asphalt filler board, keyed to the structure on
which it is built and installed as per design given in the
enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as
specified
Unit = Linear metre
Taking output = 10 m
(i) a) M 40 grade concrete

M 40 grade concrete cum 3.000 10571.00 31713.00 Item


14.1(A)
b) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 52222.68 14622.35 M-082
Pre-moulded asphalt filler board sqm 0.320 118.88 38.04 M-144
d) Overhead charges @ 0.2 on (b+c) 3081.07
e) Contractor's profit @ 0.1 on (b+c+d) 1848.64
Cost for 10 metre = a+b+c+d+e 52048.07
Rate per metre = (a+b+c+d+e)/10 5204.81
say 5205.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810
Unit = Running metre
Taking output = 4.5 metre length
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.060 639.10 38.35 L-12
Blacksmith day 0.500 729.30 364.65 L-02
Mazdoor day 1.000 719.40 719.40 L-13
b) Machinery
Tractor-trolley hour 0.100 620.49 62.05 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 45.00 1854.45 M-179
kg 41.210
railing,4.5 m in length /1000
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 45.00 3985.20 M-179
kg 88.560
16.4 kg per metre /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 45.00 730.80 M-179
kg 16.240
16.4 kg per metre /1000
Nuts and bolts kg 20.000 70.00 1400.00 M-130
Add 25 per cent of the cost of material for fabrication, nuts,
1992.61
bolts and washers etc.)
d) Overhead charges @ 0.08 on (a+b+c) 891.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 1203.93
Cost for 4.5 metre = a+b+c+d+e 13243.24
Rate per metre = (a+b+c+d+e)/4.5 2942.94
say 2943.00
Suggesti
8.35 Road Markers/Road Stud with Lense Reflector
ve
Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Material
Aluminium studs 100 x 100 mm fitted with lense 434.70 21735.00 M-062
each 50.000
reflectors
Add 10 per cent of cost of material for fixing and installation 2173.50

c) Overhead charges @ 0.08 on (a+b) 1972.28


d) Contractor's profit @ 0.1 on (a+b+c) 2662.57
Cost for 50 studs = a+b+c+d 29288.32
Rate per studs = (a+b+c+d)/50 585.77
say 586.00
8.22 809 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier for
bridge structures , constructed with M-30 grade concrete
with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with
pre-moulded asphalt filler board, keyed to the structure on
which it is built and installed as per design given in the
enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as
specified
Unit = Linear metre
Taking output = 10 m
(i) a) M 30 grade concrete
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
M 30 grade concrete cum 2.700 6153.00 16613.10
b) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.105 52222.68 5457.27 M-082
Pre-moulded asphalt filler board sqm 0.320 118.88 38.04 M-144
d) Overhead charges @ 0.08 on (b+c) 1828.27
e) Contractor's profit @ 0.1 on (b+c+d) 2468.16
Cost for 10 metre = a+b+c+d+e 27149.81
Rate per metre = (a+b+c+d+e)/10 2714.98
say 2715.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
Reinforced Cement Concrete Crash Barrier as per
8.22 811 A
New Data Book
Provision of an Reinforced cement concrete new
jersey crash barrier at the medians, constructed
with M-30 grade concrete with HYSD
reinforcement conforming to IRC:119(Fig.-26) and
dowel bars 25 mm dia, 450 mm long at expansion
joints filled with pre-moulded asphalt filler board
etc..,, as per approved drawing and at locations
directed by the Engineer, all as specified

(Area-0.261 Sqm./Meter, Double


Face)

Unit = Linear metre


Taking output = 20 m
a) M 30 grade concrete & HYSD steel
(i)
reinforcement
9484.00 49506.48 Item No.
M 30 grade concrete (Rate taken from Dir - 9.14 C,
cum 5.220
use item Sl.No. 14.1 including OH & CP) Case II
HYSD steel reinforcement including dowel 80739.00 M-082
bars (Rate taken from chapter 12 Sl.No. 12.4 tonne 0.209 16874.45
including OH & CP)
b) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
c) Material
Pre-moulded asphalt filler board sqm 0.250 118.88 29.72 M-144
d) Overhead charges 61.97
e) Contractor's profit 83.67
Cost for 20 metre = a+b+c+d+e 67301.26
Rate per metre = (a+b+c+d+e)/20 3365.06
3365.00
i) Excavation and backfilling are incidental to work
Note
and not to be measured separately.
ii) Rate for RCC M 30 may be taken from chapter-
12 on foundation on super structure.
CHAPTER-9
PIPE CULVERTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 639.10 409.02 L-12
Mason day 1.000 947.10 947.10 L-11
Mazdoor day 15.000 719.40 10791.00 L-13
b) Material
40mm Aggregate at site cum 13.800 1419.49 19589.02 M-055
Sand at site cum 6.900 1753.74 12100.77 M-005
Cement at site tonne 3.300 7146.39 23583.09 M-081
Cost of water KL 18.000 130.00 2340.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 398.22 2389.34 P&M-009
Generator set 33 KVA hour 6.000 636.69 3820.16 P&M-079
Water tanker6 KL capacity hour 3.000 530.19 1590.58 P&M-060
d) Overhead charges @ 0.08 on (a+b+c) 6204.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 8376.49
Cost for 15 cum = a+b+c+d+e 92141.37
Rate per cum = (a+b+c+d+e)/15 6142.76
say 6143.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 / Prestressed
Concrete Pipe on First Class Bedding in Single Row .

Laying Reinforced cement concrete pipe NP4/prestressed


concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length each )

9.2 B 1200 mm dia


a) Labour
Mate day 0.280 639.10 178.95 L-12
Mason day 1.000 947.10 947.10 L-11
Mazdoor day 6.000 719.40 4316.40 L-13
b) Material
Sand at site cum 0.090 1753.74 157.84 M-005
Cement at site tonne 0.070 7146.39 500.25 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 7500.00 93750.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 745.49 3727.47 M-009
bedding
c) Overhead charges @ 0.08 on (a+b) 8286.24
d) Contractor's profit @ 0.1 on (a+b+c) 11186.42
Cost for 12.5 metres = a+b+c+d 123050.67
Rate per metre= (a+b+c+d)/12.5 9844.05
say 9844.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 / Prestressed
Concrete Pipe on First Class Bedding in Double Row .

Laying Reinforced cement concrete pipe NP4 / prestressed


concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length each
in two rows.)
9.3 B 1200 mm dia
a) Labour
Mate day 0.560 639.10 357.90 L-12
Mason day 2.000 947.10 1894.20 L-11
Mazdoor day 12.000 719.40 8632.80 L-13
b) Material
Sand at site cum 0.180 1753.74 315.67 M-005
Cement at site tonne 0.140 7146.39 1000.49 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 7500.00 187500.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 745.49 10250.54 M-009
bedding
c) Overhead charges @ 0.08 on (a+b) 16796.13
d) Contractor's profit @ 0.1 on (a+b+c) 22674.77
Cost for 12.5 metres = a+b+c+d 249422.51
Rate per metre= (a+b+c+d)/12.5 19953.80
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 19954.00
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
CHAPTER-11
HORTICULTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
11.1 307 Spreading of Sludge Farm Yard Manure or/and good Earth

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 639.10 25.56 L-12
Mazdoor day 1.000 719.40 719.40 L-13
b) Overhead charges @ 0.08 on (a) 59.60
c) Contractor's profit @ 0.1 on (a+b) 80.46
Cost for 15 cum= a+b+c 885.02
Rate per cum = (a+b+c)/15 59.00
say 59.00
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 639.10 108.65 L-12
Mazdoor for grassing day 0.750 719.40 539.55 L-13
Mazdoor for maintenance for 30 days day 1.000 719.40 719.40 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
c) Material
Doob grass kg 100.000 7.50 750.00 M-112
d) Overhead charges @ 0.08 on (a+b+c) 190.62
e) Contractor's profit @ 0.1 on (a+b+c+d) 257.33
Cost for 100 sqm = a+b+c+d+e 2830.64
Rate per sqm= (a+b+c+d+e)/100 28.31
say 28.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 639.10 140.60 L-12
Mazdoor for grassing. day 1.250 719.40 899.25 L-13
for maintenance for 30 days day 1.000 719.40 719.40 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 530.19 397.64 P&M-060
c) Material
Doob grass kg 200.000 7.50 1500.00 M-112
d) Overhead charges @ 0.08 on (a+b+c) 292.55
e) Contractor's profit @ 0.1 on (a+b+c+d) 394.94
Cost for 100 sqm = a+b+c+d+e 4344.39
Rate per sqm = (a+b+c+d+e)/100 43.44
say 43.00
Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.3 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 639.10 95.87 L-12
Mazdoor for preparation of ground day 0.500 719.40 359.70 L-13
Mali for fetching doobs grass roots and grassing at 15 day 1.000 0.00 0.00 L-09
cm apart

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
Tractor with tiller hour 0.010 620.49 6.20 P&M-053
c) Material
Supply of farm yard manure at site of work cum 0.180 496.00 89.28 M-167
Fine grass kg 100.000 7.50 750.00 M-113
d) Overhead charges @ 0.08 on (a+b+c) 125.29
e) Contractor's profit @ 0.1 on (a+b+c+d) 169.14
Cost for 100 sqm = a+b+c+d+e 1860.58
Rate per sqm = (a+b+c+d+e)/100 18.61
say 19.00
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 0.00 0.00 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 530.19 7952.88 P&M-060
c) Material
Cost of water KL 90.000 130.00 11700.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 1572.23
e) Contractor's profit @ 0.1 on (a+b+c+d) 2122.51
Cost for 100 sqm = a+b+c+d+e 23347.63
Rate per sqm = (a+b+c+d+e)/100 233.48
say 233.00
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 639.10 159.78 L-12
Mazdoor for preparation of ground day 1.000 719.40 719.40 L-13
Mali for fetching doobs grass roots hedges and day 1.500 0.00 0.00 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
Tractor with tiller hour 0.010 620.49 6.20 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 496.00 297.60 M-167
per 100 sqm
Fine grass kg 100.000 7.50 750.00 M-113
d) Overhead charges @ 0.08 on (a+b+c) 175.85
e) Contractor's profit @ 0.1 on (a+b+c+d) 237.39
Cost for 100 sqm = a+b+c+d+e 2611.31
Rate per sqm = (a+b+c+d+e)/100 26.11
say 26.00
11.6 307 Maintenance of Lawns with Fine Grassing for the First Year

Maintenance of lawns with fine grassing for the first year


including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mali day 10.000 0.00 0.00 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 530.19 10603.85 P&M-060
c) Material
Cost of water KL 60.000 130.00 7800.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 1472.31
e) Contractor's profit @ 0.1 on (a+b+c+d) 1987.62
Cost for 100 sqm = a+b+c+d+e 21863.77
Rate per sqm = (a+b+c+d+e)/100 218.64
say 219.00
11.7 307 Planting and Maintaining of Permanent Hedges
(a) Planting permanent hedges including digging of trenches

Planting permanent hedges including digging of trenches, 60


cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a) Labour
Mate day 1.400 639.10 894.74 L-12
Mazdoor for digging of trench 60 cm wide and 45 cm day 10.000 719.40 7194.00 L-13
deep
Mazdoor for refilling the excavated earth mixed with day 4.000 719.40 2877.60 L-13
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 - #VALUE! M-116
Supply of farm yard manure at site of work cum 4.670 496.00 2316.32 M-167
Pesticide kg 0.250 447.00 111.75 M-136
Cost of water KL 3.000 130.00 390.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 100 metres = a+b+c+d+e #VALUE!
Rate per metre = a+b+c+d+e)/100 #VALUE!
say #VALUE!
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 639.10 1917.30 L-12
Mazdoor day 30.000 719.40 21582.00 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 530.19 2650.96 P&M-060
c) Material
Manure sludge/Farm yard manure cum 2.000 496.00 992.00 M-167
Pesticide kg 0.500 447.00 223.50 M-136
Cost of water KL 30.000 130.00 3900.00 M-189
Cost of hedge plants @ 10 per cent casualty each 68.000 - #VALUE! M-116
d) Overhead charges @ 0.08 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 100 metres = a+b+c+d+e #VALUE!
Rate per metre = a+b+c+d+e)/100 #VALUE!
say #VALUE!

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
11.8 307 Planting and Maintaining of Flowering Plants and Shrubs

(a) Planting flowering plants and shrubs in central verge

Unit = Running metres 200 plants and 800 shrubs in two


rows in one km length of road where width of verge is 3m
and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 639.10 766.92 L-12
Mazdoor day 12.000 719.40 8632.80 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 530.19 3181.15 P&M-060
c) Material
Plants each 200.000 0.00 0.00 M-100
Shrubs each 800.000 0.00 0.00 M-166
Manure sludge/Farm yard manure cum 63.640 496.00 31565.44 M-167
Pesticide kg 0.500 447.00 223.50 M-136
Cost of water KL 36.000 130.00 4680.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 3923.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 5297.38
Rate per Km = (a+b+c+d+e) 58271.18
say 58271.00
11.8 (b) Maintenance of flowering plants and shrubs in central verge
for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 639.10 23007.60 L-12
Mazdoor day 365.000 719.40 262581.00 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 530.19 47717.30 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 496.00 4960.00 M-167
Cost of water KL 180.000 130.00 23400.00 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 0.00 0.00 M-100
Shrubs each 80.000 0.00 0.00 M-166
Pesticides kg 1.500 447.00 670.50 M-136
d) Overhead charges @ 0.08 on (a+b+c) 28986.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 39132.33
Rate per Km for one year = (a+b+c+d+e) 430455.65
say 430456.00
11.9 307 Planting of Trees and their Maintenance for one Year

Planting of trees by the road side (Avenue trees) in 0.60 m


dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 639.10 1086.47 L-12
Mazdoor for planting day 2.000 719.40 1438.80 L-13
Mazdoor for maintenance for one year day 15.000 719.40 10791.00 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 530.19 1060.38 P&M-060
c) Material

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sapling 2 m high 25 mm dia each 10.000 128.00 1280.00 M-160
Farm yard manure cum 0.940 496.00 466.24 M-167
Pesticide kg 0.500 447.00 223.50 M-136
Cost of water KL 12.000 130.00 1560.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 1432.51
e) Contractor's profit @ 0.1 on (a+b+c+d) 1933.89
Cost for 10 trees = a+b+c+d+e 21272.80
Rate per trees = (a+b+c+d+e)/10 2127.28
say 2127.00
11.10 308 Renovation Lawns including, Weeding, Forking the Ground,
Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 639.10 76.69 L-12
Mazdoor day 3.000 719.40 2158.20 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 530.19 265.10 P&M-060
c) Material
Cost of water KL 3.000 130.00 390.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 231.20
e) Contractor's profit @ 0.1 on (a+b+c+d) 312.12
Cost for 100 sqm = a+b+c+d+e 3433.31
Rate per sqm = (a+b+c+d+e) 34.33
say 34.00
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 496.00 496.00 M-167
screened, loading, carriage, unloading and stacking at
site
b) Overhead charges @ 0.08 on (a) 39.68
c) Contractor's profit @ 0.1 on (a+b) 53.57
Rate per cum = (a+b+c) 589.25
589.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000
store/site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per quintal = a+b+c
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Cost of sludge including carriage, loading, unloading cum 1.000
and stacking at site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per cum = a+b+c
11.14 New Half Brick Circular Tree Guard, in 2nd Class Brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 639.10 31.96 L-12
Mason day 0.250 947.10 236.78 L-11
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
Brick 2nd class including carriage each 230.000 7.50 1725.00 M-079
Cement mortar 1:6 cum 0.025 4836.00 120.90 Item 12.6
(D)
c) Overhead charges @ 0.08 on (a+b) 183.56
d) Contractor's profit @ 0.1 on (a+b+c) 247.80
Rate per tree Guard = a+b+c+d 2725.84
say 2726.00
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 639.10 1.28 L-12
Mason day 0.050 947.10 47.36 L-11
Mazdoor day 0.050 719.40 35.97 L-13
b) Material
Brick 2nd class including carriage each 50.000 7.50 375.00 M-079
c) Overhead charges @ 0.08 on (a+b) 36.77
d) Contractor's profit @ 0.1 on (a+b+c) 49.64
Cost for 10 metre = a+b+c+d 546.01
Rate per metre = (a+b+c+d)/10 54.60
say 55.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per Design
from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 639.10 12.78 L-12
Blacksmith day 0.150 729.30 109.40 L-02
Mazdoor day 0.070 719.40 50.36 L-13
b) Material
Empty bitumen drum each 1.000 0.00 0.00 M-172

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
MS sheet 50 x 0.5 mm kg 0.650 45.00 29.25 M-179
/1000
Rivets 6 mm dia and 10 mm in length each 22.000 0.00 0.00 M-158
d) Overhead charges @ 0.08 on (a+b+c) 16.14
e) Contractor's profit @ 0.1 on (a+b+c+d) 21.79
Rate for each tree guard = a+b+c+d 239.72
say 240.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects

Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 639.10 25.56 L-12
Blacksmith day 0.200 729.30 145.86 L-02
Mazdoor 0.200 719.40 143.88 L-13
b) Material
Empty bitumen drum each 1.500 0.00 0.00 M-172
MS sheet50 x 0.5 mm kg 0.650 45.00 29.25 M-179
/1000
Rivets 6 mm dia and 10 mm in length each 50.000 0.00 0.00 M-158
MSplate30 x 3 mm kg 1.300 45.00 58.50 M-179
/1000
c) Overhead charges @ 0.08 on (a+b) 32.24
d) Contractor's profit @ 0.1 on (a+b+c) 43.53
Rate for each tree guard = a+b+c+d 478.83
say 479.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 639.10 287.60 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 729.30 1458.60 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 719.40 1798.50 L-13
b) Material
Angle, tees, channels etc quintal 1.050 4500.00 4725.00 M-179 /10
Deduct the cost of scrap quintal 0.050 (1500.00) (75.00) M-179/10/3

Add 5 per cent of cost of material for welding rods and other 232.50
welding accessories
c) Overhead charges @ 0.08 on (a+b) 674.18
d) Contractor's profit @ 0.1 on (a+b+c) 910.14
Rate per quintal = a+b+c+d 10011.51
say 10012.00
11.19 New Tree Guard with MS Iron

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 639.10 31.96 L-12
Blacksmith day 0.250 729.30 182.33 L-02
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 45.00 864.00 M-179
/1000
MS iron 25 x 3 mm kg 9.600 45.00 432.00 M-179
/1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 620.49 24.82 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 118.00 208.86 Item 8.9
e) Overhead charges @ 0.08 on (a+b+c) 137.20
f) Contractor's profit @ 0.1 on (a+b+c+e) 185.21
Rate per tree guard =a+b+c+d+e+f 2246.22
say 2246.00
Note 1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 New Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 639.10 31.96 L-12
Blacksmith day 0.250 729.30 182.33 L-02
Welder day 0.250 729.30 182.33 L-02
Mazdoor day 0.250 719.40 179.85 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 45.00 607.50 M-179
/1000
MS iron 25 x 3 mm kg 18.000 45.00 810.00 M-179
/1000
Steel wire 3 mm dia kg 6.000 0.00 0.00 M-192
Add 5 per cent of cost of material for riveting, bolting 70.88
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 620.49 24.82 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 118.00 177.00 Item 8.9
e) Overhead charges @ 0.08 on (a+b+c) 167.17
f) Contractor's profit @ 0.1 on (a+b+c+e) 225.68
Rate per tree guard = a+b+c+d+e+f 2659.50
say 2660.00
11.21 New Compensatory Afforestation

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 639.10 1597.75 L-12
Mazdoor day 25.000 719.40 17985.00 L-13
ii) For Maintenance for one year
Mate day 5.000 639.10 3195.50 L-12
Mazdoor day 50.000 719.40 35970.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 2859.33 28593.34 P&M-015
Water tanker6 KL capacity (for planting) hour 3.000 530.19 1590.58 P&M-060
Water tanker6 KL capacity (for maintenance) hour 25.000 530.19 13254.81 P&M-060
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 102.40 29696.00 M-160 x
0.8
Add 10 per cent of sapling each 29.000 102.40 2969.60 M-160 x
0.8
Decayed farm yard/sludge manure (planting) cum 60.900 496.00 30206.40 M-167
Decayed farm yard/sludge manure (maintenance) cum 4.000 496.00 1984.00 M-167
Pesticides for planting kg 0.500 447.00 223.50 M-136
Pesticides for maintenance kg 1.500 447.00 670.50 M-136
Cost of water KL 18.000 130.00 2340.00 M-189
d) Overhead charges @ 0.08 on (a+b+c) 13622.16
e) Contractor's profit @ 0.1 on (a+b+c+d) 18389.91
Rate per hectare = a+b+c+d+e 202289.04
say 202289.00
Note Cost of fencing to be provided as per size of plot and
approved design, measured and paid separately

Sheladia Associates inc., in Association with Vax Consultants Pvt. Ltd.,


CHAPTER-12
FOUNDATIONS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 639.10 89.47
Mazdoor day 3.50 719.40 2517.90
b) Overhead charges @ 0.2 on (a) 521.47
c) Contractor's profit @ 0.1 on (a+b) 312.88
Cost for 10 cum = a+b+c 3441.73
Rate per cum = (a+b+c)/10 344.17
say 344.00
Note 1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 639.10 204.51
Mazdoor day 8.00 719.40 5755.20
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2182.12 13092.74
c) Overhead charges @ 0.2 on (a+b) 3810.49
d) Contractor's profit @ 0.1 on (a+b+c) 2286.29
Cost for 240 cum = a+b+c+d 25149.23
Rate per cum = (a+b+c+d)/240 104.79
say 105.00
12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation
1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7146.39 29514.59
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 8.10 1419.49 11497.90
20 mm Aggregate cum 4.05 1822.49 7381.10
10 mm Aggregate cum 1.35 1367.49 1846.12
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 63 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 5644.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 3385.81
material, labour and machinery

e) Overhead charges @ 0.2 on (a+b+c+d) 17606.20


f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10563.72
Cost for 15 cum = a+b+c+d+e+f 116200.93
Rate per cum = (a+b+c+d+e+f)/15 7746.73
say 7747.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7146.39 36875.37
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 6166.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 3699.19
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 19235.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 11541.48
Cost for 15 cum = a+b+c+d+e+f 126956.31
Rate per cum = (a+b+c+d+e+f)/15 8463.75
say 8464.00
12.8 C RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7146.39 37232.69
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3751.39
e) Overhead charges @ 0.2 on (a+b+c+d) 19507.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 11704.35
Cost for 15 cum = a+b+c+d+e+f 128747.84
Rate per cum = ( a+b+c+d+e+f )/15 8583.19
say 8583.00
12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7146.39 297718.61
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 km, L-lead in km tonne.km 300L 7.28 23645.69

Concrete Pump hour 6 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 5549.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 5770.96 26632.63
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 138489.67
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 83093.80
Cost for 120 cum = a+b+c+d+e+f 914031.83
Rate per cum = ( a+b+c+d+e+f )/120 7616.93
say 7617.00
12.8 D PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7146.39 42806.88
Coarse sand cum 6.75 1753.74 11837.71
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 6561.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3690.43
e) Overhead charges @ 0.2 on (a+b+c+d) 20420.35
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12252.21
Cost for 15 cum = a+b+c+d+e+f 134774.32
Rate per cum = ( a+b+c+d+e+f )/15 8984.95
say 8985.00
12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7146.39 342669.40
Coarse sand cum 54.00 1670.49 90206.68
40 mm Aggregate cum 43.20 1419.49 61322.14
20 mm Aggregate cum 43.20 1822.49 78731.74
10 mm Aggregate cum 21.60 1367.49 29537.87
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 5860.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. cost 26369.43
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 145910.87
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 87546.52
cost of 120 cum = a+b+c+d+e+f 963011.75
Rate per cum = (a+b+c+d+e+f)/120 8025.10
say 8025.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.8 E RCC Grade M25
12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7146.39 345742.35
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity 1 cum hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 5949.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 26768.98
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 148121.69
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 88873.01
cost of 120 cum = a+b+c+d+e+f 977603.15
Rate per cum (a+b+c+d+e+f )/120 8146.69
say 8147.00
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7146.39 348743.83
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Concrete Pump hour 6.00 437.58 2625.49
Per Cum Basic Cost of Labour, Material & Machinery 5974.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 25089.43
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 148386.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89031.65
cost of 120 cum = a+b+c+d+e+f 979348.11
Rate per cum (a+b+c+d+e+f )/120 8161.23
say 8161.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Per Cum Basic Cost of Labour, Material & Machinery 6786.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 3053.66
e) Overhead charges @ 0.2 on (a+b+c+d) 20968.49
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12581.10
cost of 15 cum = a+b+c+d+e+f 138392.06
Rate per cum = (a+b+c+d+e+f)/15 9226.14
say 9226.00
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7146.39 361893.19
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 6084.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of 21899.71
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 150378.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 90226.80
cost of 120 cum = a+b+c+d+e+f 992494.83
Rate per cum = (a+b+c+d+e+f)/120 8270.79
say 8271.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 1200.0 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m dia.
Well.
A Assuming depth of water 1.0 m and height of island to be
1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 196.3 49310.56
Sand bags each 750.00 0.00 0.00
b) Labour
Mate day 0.40 639.10 255.64
Mazdoor for filling sand bags, stitching and placing day 15.00 719.40 10791.00
c) Machinery
Crane with grab 1 cum capacity hour 20.00 1459.77 29195.30
Consumables @ 2.5 per cent of (c) above 729.88
d) Overhead charges @ 0.2 on (a+b+c) 18056.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 10833.89
Rate per No. (a+b+c+d+e) 119172.75
say 119173.00
Note It is assumed that earth will be available within the working
space of crane with grab bucket.
12.9 B Assuming depth of water 4.0 m and height of island 4.5 m.

Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 196.30 177518.02
Sand bags each 6000.00 0.00 0.00
Wooden ballies 8" Dia and 9 m long each 95.00 0.00 0.00
Wooden ballies 2" Dia for bracing metre 190.00 0.00 0.00
b) Labour
Mate day 5.60 639.10 3578.96
Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 719.40 12949.20

Mazdoor for bracing with 2" dia ballies day 12.00 719.40 8632.80
Mazdoor for filling sand bags, stitching and placing day 110.00 719.40 79134.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Machinery
Crane with grab 1 cum capacity hour 50.00 1459.77 72988.26
Consumables and other arrangements for piling ballies @ 8870.03
2.5 per cent of (a+b+c).
d) Overhead charges @ 0.2 on (a+b+c) 72734.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 43640.55
Rate per No. (a+b+c+d+e) 480046.07
say 480046.00
Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 C Providing and constructing one span service road to reach
island location from one pier location to another pier location

Assuming span length 30 m, width of service road 10m and


depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 196.30 88335.00
Sand bags each 300.00 0.00 0.00
b) Labour
Mate day 0.24 639.10 153.38
Mazdoor for filling sand bags, stitching and placing day 6.00 719.40 4316.40
c) Machinery
Front end Loader 1 cum capacity hour 27.00 1379.89 37257.00
Tipper 5.5 cum capacity hour 28.00 530.19 14845.38
d) Overhead charges @ 0.2 on (a+b+c) 28981.43
e) Contractor's profit @ 0.1 on (a+b+c+d) 17388.86
Cost for 30 m (a+b+c+d+e) 191277.46
Rate per m (a+b+c+d+e)/30 6375.92
say 6376.00
12.10 1200 & Providing and Laying Cutting Edge of Mild Steel weighing 40
1900 kg per metre for Well Foundation complete as per Drawing
and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 45000.00 47250.00
cent wastage
Nuts & bolts Kg 20.00 70.00 1400.00
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 639.10 843.61
Fitter day 5.50 0.00 0.00
Blacksmith day 5.50 729.30 4011.15
Welder day 5.50 729.30 4011.15
Mazdoor day 16.50 719.40 11870.10
Electrodes, cutting gas and other consumables @ 10 per 4865.00
cent of cost of (a) above
c) Overhead charges @ 0.2 on (a+b) 14850.20
d) Contractor's profit @ 0.1 on (a+b+c) 8910.12
Rate per MT (a+b+c+d) 98011.34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 98011.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation
1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1250.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1500.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 900.43
Rate perm (a+b+c+d+e+f) 9904.75
say 9905.00
12.11 A (i) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5549.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1109.80
e) Overhead charges @ 0.2 on (a+b+c+d) 1331.76
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 799.06
Rate perm (a+b+c+d+e+f) 8789.62
say 8790.00
12.11 A (ii) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6653.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1330.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1596.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 958.03
Rate perm (a+b+c+d+e+f) 10538.35
say 10538.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 6238.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1247.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1497.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 898.27
Rate perm (a+b+c+d+e+f) 9880.99
say 9881.00
12.11 A (iii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6786.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1357.20
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 0.2 on (a+b+c+d) 1628.64
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 977.18
Rate perm (a+b+c+d+e+f) 10749.02
say 10749.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 6386.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1277.20
e) Overhead charges @ 0.2 on (a+b+c+d) 1532.64
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 919.58
Rate perm (a+b+c+d+e+f) 10115.42
say 10115.00
Note. If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5644.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 564.40
e) Overhead charges @ 0.2 on (a+b+c+d) 1241.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 745.01
Rate perm (a+b+c+d+e+f) 8195.09
say 8195.00
12.11 B (ii) PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6166.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 616.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1356.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 813.91
Rate perm (a+b+c+d+e+f) 8953.03
say 8953.00
12.11 B (iii) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 625.30
e) Overhead charges @ 0.2 on (a+b+c+d) 1375.66
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 825.40
Rate perm (a+b+c+d+e+f) 9079.36
say 9079.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 5549.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 554.90
e) Overhead charges @ 0.2 on (a+b+c+d) 1220.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 732.47
Rate perm (a+b+c+d+e+f) 8057.15
say 8057.00
12.11 B (iv) PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6561.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 656.10
e) Overhead charges @ 0.2 on (a+b+c+d) 1443.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 866.05
Rate perm (a+b+c+d+e+f) 9526.57
say 9527.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery 5860.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 586.00
e) Overhead charges @ 0.2 on (a+b+c+d) 1289.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 773.52
Rate perm (a+b+c+d+e+f) 8508.72
say 8509.00
'12.11 B (v) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6653.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 665.30
e) Overhead charges @ 0.2 on (a+b+c+d) 1463.66
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 878.20
Rate perm (a+b+c+d+e+f) 9660.16
say 9660.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery 6238.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 623.80
e) Overhead charges @ 0.2 on (a+b+c+d) 1372.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 823.42
Rate perm (a+b+c+d+e+f) 9057.58
say 9058.00
'12.11 B (vi) PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6604.00
(a+b+c)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) formwork @ 10 per cent of the cost of concrete 660.40
e) Overhead charges @ 0.2 on (a+b+c+d) 1452.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 871.73
Rate perm (a+b+c+d+e+f) 9589.01
say 9589.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery 5899.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 589.90
e) Overhead charges @ 0.2 on (a+b+c+d) 1297.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 778.67
Rate perm (a+b+c+d+e+f) 8565.35
say 8565.00
'12.11 B (vii) RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6677.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 667.70
e) Overhead charges @ 0.2 on (a+b+c+d) 1468.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 881.36
Rate perm (a+b+c+d+e+f) 9695.00
say 9695.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 5974.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 597.40
e) Overhead charges @ 0.2 on (a+b+c+d) 1314.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 788.57
Rate perm (a+b+c+d+e+f) 8674.25
say 8674.00
'12.11 B (viii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6786.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 678.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1492.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 895.75
Rate perm (a+b+c+d+e+f) 9853.27
say 9853.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 6386.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 638.60
e) Overhead charges @ 0.2 on (a+b+c+d) 1404.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 842.95
Rate perm (a+b+c+d+e+f) 9272.47
say 9272.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
'12.11 B (ix) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7146.39 368753.72
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture kg 206.00 179.00 36874.00
b) Labour
Mate day 0.84 639.10 536.84
Meson day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 51582.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost 77372.48
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 170219.47
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 102131.68
cost of 120 cum = a+b+c+d+e+f 1123448.48
Rate per cum = (a+b+c+d+e+f)/120 9362.07
say 9362.00
12.11 C C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7146.39 39662.46
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixture Kg 18.60 179.00 3329.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 610.07 3660.41

Per Cum Basic Cost of Labour, Material & Machinery 6819.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4620.62
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 21380.58


e) Contractor's profit @ 0.1 on (a+b+c+d) 12828.35
cost of 15 cum = a+b+c+d+e 141111.85
Rate per cum = (a+b+c+d+e)/15 9407.46
say 9407.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 7146.39 317299.72
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture Kg 148.80 179.00 26635.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 31383.39
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 148688.20


e) Contractor's profit @ 0.1 on (a+b+c+d) 89212.92
cost of 120 cum = a+b+c+d+e 981342.11
Rate per cum = (a+b+c+d+e)/120 8177.85
say 8178.00
'12.11 C (ii) PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7146.39 42806.88
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixture Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 610.07 3660.41
pipe
Per Cum Basic Cost of Labour, Material & Machinery 7065.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4804.69
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 22153.68


e) Contractor's profit @ 0.1 on (a+b+c+d) 13292.21
cost of 15 cum = a+b+c+d+e 146214.29
Rate per cum = (a+b+c+d+e)/15 9747.62
say 9748.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7146.39 342169.15
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 6177.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 32841.66
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 154812.94


Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 92887.76
cost of 120 cum = a+b+c+d+e 1021765.41
Rate per cum = (a+b+c+d+e)/120 8514.71
say 8515.00
'12.11 C (iii) PCC Grade M30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7146.39 43450.05
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixture Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 610.07 3660.41
pipe
Per Cum Basic Cost of Labour, Material & Machinery 7108.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4836.85
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 22288.75


e) Contractor's profit @ 0.1 on (a+b+c+d) 13373.25
cost of 15 cum = a+b+c+d+e 147105.73
Rate per cum = (a+b+c+d+e)/15 9807.05
say 9807.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7146.39 347600.41
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 6223.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 33113.23
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 155953.50


e) Contractor's profit @ 0.1 on (a+b+c+d) 93572.10
cost of 120 cum = a+b+c+d+e 1029293.13
Rate per cum = (a+b+c+d+e)/120 8577.44
say 8577.00
'12.11 C (iv) PCC Grade M35
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7146.39 44950.79
Coarse sand cum 6.75 1753.74 11837.71
40 mm Aggregate cum 5.40 1419.49 7665.27
20 mm Aggregate cum 5.40 1822.49 9841.47
10 mm Aggregate cum 2.70 1367.49 3692.23
Admixture Kg 21.60 179.00 3866.40
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 610.07 3660.41
pipe
Per Cum Basic Cost of Labour, Material & Machinery 7208.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4911.89
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 22603.90


e) Contractor's profit @ 0.1 on (a+b+c+d) 13562.34
cost of 15 cum = a+b+c+d+e 149185.76
Rate per cum = (a+b+c+d+e)/15 9945.72
say 9946.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7146.39 359320.49
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Admixture Kg 172.80 179.00 30931.20
b) Labour
Mate day 0.88 639.10 562.41
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 7.28 23645.69
lead in Kilometer

Concrete Pump hour 6.00 437.58 2625.49


Per Cum Basic Cost of Labour, Material & Machinery 6320.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 33699.23
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 158414.72


e) Contractor's profit @ 0.1 on (a+b+c+d) 95048.83
cost of 120 cum = a+b+c+d+e 1045537.16
Rate per cum = (a+b+c+d+e)/120 8712.81
say 8713.00
12.11 D Intermediate plug
(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6819.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1363.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 818.28
Rate per cum = (a+b+c+d+e) 9001.08
say 9001.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1186.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 712.08
Rate per cum = (a+b+c+d+e) 7832.88
say 7833.00
'12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 7065.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1413.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 847.80
Rate per cum = (a+b+c+d+e) 9325.80
say 9326.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery 6177.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1235.40
e) Contractor's profit @ 0.1 on (a+b+c+d) 741.24
Rate per cum = (a+b+c+d+e) 8153.64
say 8154.00
'12.11 D (iii) Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 7108.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1421.60
e) Contractor's profit @ 0.1 on (a+b+c+d) 852.96
Rate per cum = (a+b+c+d+e) 9382.56
say 9383.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery 6223.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1244.60
e) Contractor's profit @ 0.1 on (a+b+c+d) 746.76
Rate per cum = (a+b+c+d+e) 8214.36
say 8214.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5644.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1128.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 677.28
Rate per cum = (a+b+c+d+e) 7450.08
say 7450.00
'12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6166.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1233.20
e) Contractor's profit @ 0.1 on (a+b+c+d) 739.92
Rate per cum = (a+b+c+d+e) 8139.12
say 8139.00
'12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6561.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1312.20
e) Contractor's profit @ 0.1 on (a+b+c+d) 787.32
Rate per cum = (a+b+c+d+e) 8660.52
say 8661.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 5860.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1172.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 703.20
Rate per cum = (a+b+c+d+e) 7735.20
say 7735.00
'12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6604.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1320.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 792.48
Rate per cum = (a+b+c+d+e) 8717.28
say 8717.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery 5899.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 1179.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 707.88
Rate per cum = (a+b+c+d+e) 7786.68
say 7787.00
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7146.39 36589.52
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Form Work @ 4 per cent of a+b+c 3725.67
d) Overhead charges @ 0.2 on (a+b+c) 19373.47
e) Contractor's profit @ 0.1 on (a+b+c+d) 11624.08
cost of 15 cum = a+b+c+d+e 127864.89
Rate per cum = (a+b+c+d+e)/15 8524.33
say 8524.00
12.11 F (i) Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7146.39 292430.28
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader (capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Formwork @ 4 per cent of (a+b+c) 26421.10
d) Overhead charges @ 0.2 on (a+b+c) 137389.70
e) Contractor's profit @ 0.1 on (a+b+c+d) 82433.82
cost of 120 cum = a+b+c+d+e 906772.02
Rate per cum = (a+b+c+d+e)/120 7556.43
say 7556.00
12.11 F (ii) RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7146.39 43235.66
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Form Work @ 3.75 per cent of a+b+c 3742.04
d) Overhead charges @ 0.2 on (a+b+c) 20705.97
e) Contractor's profit @ 0.1 on (a+b+c+d) 12423.58
cost of 15 cum = a+b+c+d+e 136659.42
Rate per cum = (a+b+c+d+e)/15 9110.63
say 9111.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7146.39 345885.28
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader (capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Formwork @ 3.75 per cent of ( a+b+c) 26774.34
d) Overhead charges @ 0.2 on (a+b+c) 148151.35
e) Contractor's profit @ 0.1 on (a+b+c+d) 88890.81
cost of 120 cum = a+b+c+d+e 977798.89
Rate per cum = (a+b+c+d+e)/120 8148.32
say 8148.00
12.11 F (iii) RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7146.39 43592.98
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Formwork @ 3.5 per cent of (a+b+c) 3505.08
d) Overhead charges @ 0.2 on (a+b+c) 20730.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 12438.03
cost of 15 cum = a+b+c+d+e 136818.29
Rate per cum = (a+b+c+d+e)/15 9121.22
say 9121.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7146.39 348672.37
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader (capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Formwork @ 3.5 per cent of (a+b+c) 25086.93
d) Overhead charges @ 0.2 on (a+b+c) 148371.28
e) Contractor's profit @ 0.1 on (a+b+c+d) 89022.77
cost of 120 cum = a+b+c+d+e 979250.48
Rate per cum = (a+b+c+d+e)/120 8160.42
say 8160.00
12.11 F (iv) RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 947.10 1420.65
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
Formwork @ 3 per cent of (a+b+c) 3053.66
d) Overhead charges @ 0.2 on (a+b+c) 20968.49
e) Contractor's profit @ 0.1 on (a+b+c+d) 12581.10
cost of 15 cum = a+b+c+d+e 138392.06
Rate per cum = (a+b+c+d+e)/15 9226.14
say 9226.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7146.39 361893.19
Coarse sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
b) Labour
Mate day 0.84 639.10 536.84
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader (capacity 1 cum) hour 6.00 1379.89 8279.33
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Formwork @ 3 per cent of (a+b+c) 21899.71
d) Overhead charges @ 0.2 on (a+b+c) 150378.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 90226.80
cost of 120 cum = a+b+c+d+e 992494.83
Rate per cum = (a+b+c+d+e)/120 8270.79
say 8271.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F (v) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7146.39 373041.56
Coarse Sand cum 54.00 1670.49 90206.68
20 mm Aggregate cum 64.80 1822.49 118097.61
10 mm Aggregate cum 43.20 1367.49 59075.74
Admixture kg 206.00 179.00 36874.00
b) Labour
Mate day 0.84 639.10 536.84
Mason day 3.00 947.10 2841.30
Mazdoor day 18.00 719.40 12949.20
c) Machinery
Batching Plant hour 6.00 3133.69 18802.15
Generator 100 KVA hour 6.00 1193.51 7161.07
Loader 1 cum capacity hour 6.00 1379.89 8279.33
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1591.73 23876.02
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 7.28 23645.69

Concrete Pump hour 6.00 437.58 2625.49


Formwork @ 3 per cent on cost of concrete i.e. cost of 23340.38
material, labour and machinery
d) Overhead charges @ 0.2 on (a+b+c) 160270.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 96162.37
cost of 120 cum = a+b+c+d+e 1057786.04
Rate per cum = (a+b+c+d+e)/120 8814.88
say 8815.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.12 Section Sinking of 6 m external diameter well (other than pneumatic
1200 method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 639.10 76.69
Sinker ( skilled ) day 1.00 698.50 698.50
Sinking helper ( semi-skilled ) day 2.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 338.47 676.94
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 67.69
c) Overhead charges @ 0.2 on (a+b) 303.96
d) Contractor's profit @ 0.1 on (a+b+c) 182.38
Rate per metre = (a+b+c+d) 2006.16
say 2006.00
12.12 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 639.10 95.87
Sinker day 1.25 698.50 873.13
Sinking helper ( semi-skilled ) day 2.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 338.47 1015.40
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 101.54
c) Overhead charges @ 0.2 on (a+b) 417.19
d) Contractor's profit @ 0.1 on (a+b+c) 250.31
Rate per metre = (a+b+c+d) 2753.43
say 2753.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 2891.00
12th m 5% 3036.00
13th m 5% 3188.00
14th m 5% 3347.00
15th m 5% 3514.00
16th m 5% 3690.00
17th m 5% 3875.00
18th m 5% 4069.00
19th m 5% 4272.00
20th m 5% 4486.00
Total Cost from 10m upto 20m 36368.00
Avg Rate per metre 3637.00
12.12 A (iv) Beyond 20m upto 30 m
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 4822.00 5786.00
22nd m 7.5% 5184.00 6221.00
23rd m 7.5% 5573.00 6688.00
24th m 7.5% 5991.00 7189.00
25th m 7.5% 6440.00 7728.00
26th m 7.5% 6923.00 8308.00
27th m 7.5% 7442.00 8930.00
28th m 7.5% 8000.00 9600.00
29th m 7.5% 8600.00 10320.00
30th m 7.5% 9245.00 11094.00
Total Cost from 20m upto 30m 68220.00 81864.00
Avg Rate per metre 6822.00 8186.00
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
31st m 10% 10170.00 12204.00
32nd 10% 11187.00 13424.00
33rd m 10% 12306.00 14767.00
34th m 10% 13537.00 16244.00
35th m 10% 14891.00 17869.00
36th m 10% 16380.00 19656.00
37th m 10% 18018.00 21622.00
38th m 10% 19820.00 23784.00
39th m 10% 21802.00 26162.00
40th m 10% 23982.00 28778.00
Total Cost from 30m upto 40m 162093.00 194510.00
Avg Rate per metre 16209.00 19451.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 639.10 95.87
Sinker ( skilled ) day 1.50 698.50 1047.75
Sinking helper ( semi-skilled ) day 2.25 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 338.47 1015.40
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 101.54
c) Overhead charges @ 0.2 on (a+b) 452.11
d) Contractor's profit @ 0.1 on (a+b+c) 271.27
Rate per metre = (a+b+c+d) 2983.94
say 2984.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 639.10 191.73
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinker day 3.00 698.50 2095.50
Sinking helper ( semi-skilled ) day 4.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 349.49 698.99
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 272.98
c) Overhead charges @ 0.2 on (a+b) 1058.00
d) Contractor's profit @ 0.1 on (a+b+c) 634.80
Rate per metre = (a+b+c+d) 6982.80
say 6983.00
12.12 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 7332.00 7699.00
12th m 5% 7699.00 8084.00
13th m 5% 8084.00 8488.00
14th m 5% 8488.00 8912.00
15th m 5% 8912.00 9358.00
16th m 5% 9358.00 9826.00
17th m 5% 9826.00 10317.00
18th m 5% 10317.00 10833.00
19th m 5% 10833.00 11375.00
20th m 5% 11375.00 11944.00
Total Cost from 10m upto 20m 92224.00 96836.00
Avg Rate per metre 9222.00 9684.00
12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 12228.00 15285.00 16049.00
22nd m 7.5% 13145.00 16431.00 17253.00
23rd m 7.5% 14131.00 17664.00 18547.00
24th m 7.5% 15191.00 18989.00 19938.00
25th m 7.5% 16330.00 20413.00 21434.00
26th m 7.5% 17555.00 21944.00 23041.00
27th m 7.5% 18872.00 23590.00 24770.00
28th m 7.5% 20287.00 25359.00 26627.00
29th m 7.5% 21809.00 27261.00 28624.00
30th m 7.5% 23445.00 29306.00 30771.00
Total Cost from 20m upto 30m 172993.00 216242.00 227054.00
Avg Rate per metre 17299.00 21624.00 22705.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 25790.00 30948.00 32495.00
32nd 10% 28369.00 34043.00 35745.00
33rd m 10% 31206.00 37447.00 39319.00
34th m 10% 34327.00 41192.00 43252.00
35th m 10% 37760.00 45312.00 47578.00
36th m 10% 41536.00 49843.00 52335.00
37th m 10% 45690.00 54828.00 57569.00
38th m 10% 50259.00 60311.00 63327.00
39th m 10% 55285.00 66342.00 69659.00
40th m 10% 60814.00 72977.00 76626.00
Total Cost from 30m upto 40m 411036.00 493243.00 517905.00
Avg Rate per metre 41104.00 49324.00 51791.00
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 639.10 587.97
Sinker ( skilled ) day 3.00 698.50 2095.50
Sinking helper ( semi-skilled ) day 20.00 0.00 0.00
Diver day 0.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 338.47 1353.87
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 349.49 1223.22
Consumables in sinking @ 10 per cent of (b) 257.71
Add for dewatering @ of 5 per cent of (a+b), if required 275.91

c) Overhead charges @ 0.2 on (a+b) 1158.84


d) Contractor's profit @ 0.1 on (a+b+c) 695.30
Rate per metre = (a+b+c+d) 7648.33
say 7648.00
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 37.00 148.00
Electric Detonators each 18.00 25.48 458.64
b) Labour
Mate day 1.56 639.10 997.00
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 12.00 719.40 8632.80
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire & running charges of compressor with pneumatic hour 2.00 349.49 698.99
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 757.68
Consumables in sinking @ 10 per cent of cost of (b). 272.98
d) Overhead charges @ 0.2 on (a+b+c) 3358.18
e) Contractor's profit @ 0.1 on (a+b+c+d) 2014.91
Rate per metre = (a+b+c+d+e) 22163.97
say 22164.00
12.13 Section Sinking of 7 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 639.10 95.87
Sinker ( skilled ) day 1.25 698.50 873.13
Sinking helper ( semi-skilled ) day 2.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 338.47 1100.02
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 110.00
c) Overhead charges @ 0.2 on (a+b) 435.80
d) Contractor's profit @ 0.1 on (a+b+c) 217.90
Rate per metre = (a+b+c+d) 2832.71
12.13 A (ii) Beyond 3m upto 10m depth 5665.43
Rate of sinking = 0.22 m per hour. say 5665.00
a) Labour
Mate day 0.18 639.10 115.04
Sinker day 1.50 698.50 1047.75
Sinking helper ( semi-skilled ) day 3.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 338.47 1523.10
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 152.31
c) Overhead charges @ 0.2 on (a+b) 567.64
d) Contractor's profit @ 0.1 on (a+b+c) 340.58
Rate per metre = (a+b+c+d) 3746.43
say 3746.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 3934.00
12th m 5% 4131.00
13th m 5% 4338.00
14th m 5% 4555.00
0.165 15th m 5% 4783.00
16th m 5% 5022.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
17th m 5% 5273.00
18th m 5% 5537.00
19th m 5% 5814.00
20th m 5% 6105.00
Total Cost from 10m upto 20m 49492.00
Avg Rate per metre 4949.00
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge
21st m 7.5% 6563.00 7876.00
22nd m 7.5% 7055.00 8466.00
23rd m 7.5% 7584.00 9101.00
24th m 7.5% 8153.00 9784.00
25th m 7.5% 8764.00 10517.00
26th m 7.5% 9421.00 11305.00
27th m 7.5% 10128.00 12154.00
28th m 7.5% 10888.00 13066.00
29th m 7.5% 11705.00 14046.00
30th m 7.5% 12583.00 15100.00
Total Cost from 20m upto 30m 92844.00 111415.00
Avg Rate per metre 9284.00 11142.00
12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 13841.00 16609.00
32nd 10% 15225.00 18270.00
33rd m 10% 16748.00 20098.00
34th m 10% 18423.00 22108.00
35th m 10% 20265.00 24318.00
36th m 10% 22292.00 26750.00
37th m 10% 24521.00 29425.00
38th m 10% 26973.00 32368.00
39th m 10% 29670.00 35604.00
40th m 10% 32637.00 39164.00
Total Cost from 30m upto 40m 220595.00 264714.00
Avg Rate per metre 22060.00 26471.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 639.10 115.04
Sinker ( skilled ) day 1.50 698.50 1047.75
Sinking helper ( semi-skilled ) day 3.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 338.47 1523.10
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 152.31
d) Overhead charges @ 0.2 on (a+b) 567.64
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 0.1 on (a+b+c) 340.58
Rate per metre = (a+b+c+d) 3746.43
say 3746.00
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 639.10 166.17
Sinker day 2.00 698.50 1397.00
Sinking helper ( semi-skilled ) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 349.49 203.08
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 223.39
c) Overhead charges @ 0.2 on (a+b) 804.09
d) Contractor's profit @ 0.1 on (a+b+c) 482.45
Rate per metre = (a+b+c+d) 5306.98
say 5307.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 5572.00 5851.00
12th m 5% 5851.00 6144.00
13th m 5% 6144.00 6451.00
14th m 5% 6451.00 6774.00
15th m 5% 6774.00 7113.00
16th m 5% 7113.00 7469.00
17th m 5% 7469.00 7842.00
18th m 5% 7842.00 8234.00
19th m 5% 8234.00 8646.00
20th m 5% 8646.00 9078.00
Total Cost from 10m upto 20m 70096.00 73602.00
Avg Rate per metre 7010.00 7360.00
12.13 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 9294.00 11618.00 12199.00
32nd 7.5% 9991.00 12489.00 13113.00
33rd m 7.5% 10740.00 13425.00 14096.00
34th m 7.5% 11546.00 14433.00 15155.00
35th m 7.5% 12412.00 15515.00 16291.00
36th m 7.5% 13343.00 16679.00 17513.00
37th m 7.5% 14344.00 17930.00 18827.00
38th m 7.5% 15420.00 19275.00 20239.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
39th m 7.5% 16577.00 20721.00 21757.00
40th m 7.5% 17820.00 22275.00 23389.00
Total Cost from 30m upto 40m 131487.00 164360.00 172579.00
Avg Rate per metre 13149.00 16436.00 17258.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 19602.00 23522.00 24698.00
32nd 10% 21562.00 25874.00 27168.00
33rd m 10% 23718.00 28462.00 29885.00
34th m 10% 26090.00 31308.00 32873.00
35th m 10% 28699.00 34439.00 36161.00
36th m 10% 31569.00 37883.00 39777.00
37th m 10% 34726.00 41671.00 43755.00
38th m 10% 38199.00 45839.00 48131.00
39th m 10% 42019.00 50423.00 52944.00
40th m 10% 46221.00 55465.00 58238.00
Total Cost from 30m upto 40m 312405.00 374886.00 393630.00
Avg Rate per metre 31241.00 37489.00 39363.00
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 639.10 370.68
Sinker ( skilled ) day 4.00 698.50 2794.00
Sinking helper ( semi-skilled ) day 10.00 0.00 0.00
Diver day 0.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 338.47 1523.10
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 349.49 1310.60
Consumables in sinking @ 10 per cent of (b) 283.37
Add for dewatering @ of 5 per cent of (a+b), if required 299.92

c) Overhead charges @ 0.2 on (a+b) 1316.33


d) Contractor's profit @ 0.1 on (a+b+c) 789.80
Rate per metre = (a+b+c+d) 8687.80
say 8688.00
12.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 37.00 259.00
Electric Detonators each 30.00 25.48 764.40
b) Labour
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 1.60 639.10 1022.56
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 18.00 719.40 12949.20
Mazdoor (Skilled) day 4.00 698.50 2794.00
Diver day 0.50 0.00 0.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 349.49 698.99
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 974.78
Consumables in sinking @ 10 per cent of cost of (b). 370.46
d) Overhead charges @ 0.2 on (a+b+c) 4372.84
e) Contractor's profit @ 0.1 on (a+b+c+d) 2623.70
Rate per metre = (a+b+c+d+e) 28860.72
say 28861.00
12.14 Section Sinking of 8 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 639.10 115.04
Sinker ( skilled ) day 1.50 698.50 1047.75
Sinking helper ( semi-skilled ) day 3.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 338.47 1353.87
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 135.39
c) Overhead charges @ 0.2 on (a+b) 530.41
d) Contractor's profit @ 0.1 on (a+b+c) 318.25
Rate per metre = (a+b+c+d) 3500.70
say 3501.00
12.14 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 639.10 159.78
Sinker day 1.75 698.50 1222.38
Sinking helper ( semi-skilled ) day 3.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 338.47 1692.34
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 169.23
c) Overhead charges @ 0.2 on (a+b) 648.74
d) Contractor's profit @ 0.1 on (a+b+c) 389.25
Rate per metre = (a+b+c+d) 4281.71
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 4282.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 4496.00
12th m 5% 4721.00
13th m 5% 4957.00
14th m 5% 5205.00
15th m 5% 5465.00
16th m 5% 5738.00
17th m 5% 6025.00
18th m 5% 6326.00
19th m 5% 6642.00
20th m 5% 6974.00
Total Cost from 10m upto 20m 56549.00
Avg Rate per metre 5655.00
12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 7497.00 8996.00
22nd m 7.5% 8059.00 9671.00
23rd m 7.5% 8663.00 10396.00
24th m 7.5% 9313.00 11176.00
25th m 7.5% 10011.00 12013.00
26th m 7.5% 10762.00 12914.00
27th m 7.5% 11569.00 13883.00
28th m 7.5% 12437.00 14924.00
29th m 7.5% 13370.00 16044.00
30th m 7.5% 14373.00 17248.00
Total Cost from 20m upto 30m 106054.00 127265.00
Avg Rate per metre 10605.00 12727.00
12.14 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 15810.00 18972.00
32nd 10% 17391.00 20869.00
33rd m 10% 19130.00 22956.00
34th m 10% 21043.00 25252.00
35th m 10% 23147.00 27776.00
36th m 10% 25462.00 30554.00
37th m 10% 28008.00 33610.00
38th m 10% 30809.00 36971.00
39th m 10% 33890.00 40668.00
40th m 10% 37279.00 44735.00
Total Cost from 30m upto 40m 37279.00 44735.00
Avg Rate per metre 3728.00 4474.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 639.10 140.60
Sinker ( skilled ) day 2.00 698.50 1397.00
Sinking helper ( semi-skilled ) hour 3.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of 5.50 338.47 1861.57
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 186.16
c) Overhead charges @ 0.2 on (a+b) 717.07
d) Contractor's profit @ 0.1 on (a+b+c) 430.24
Rate per metre = (a+b+c+d) 4732.64
say 4733.00
12.14 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 639.10 204.51
Sinker day 2.50 698.50 1746.25
Sinking helper ( semi-skilled ) day 4.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 349.49 1223.22
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 325.40
c) Overhead charges @ 0.2 on (a+b) 1106.04
d) Contractor's profit @ 0.1 on (a+b+c) 663.62
Rate per metre = (a+b+c+d) 7299.86
say 7300.00
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 7665.00 8048.00
12th m 5% 8048.00 8450.00
13th m 5% 8450.00 8873.00
14th m 5% 8873.00 9317.00
15th m 5% 9317.00 9783.00
16th m 5% 9783.00 10272.00
17th m 5% 10272.00 10786.00
18th m 5% 10786.00 11325.00
19th m 5% 11325.00 11891.00
20th m 5% 11891.00 12486.00
Total Cost from 10m upto 20m 96410.00 101231.00
Avg Rate per metre 9641.00 10123.00
12.14 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 12783.00 15979.00 16778.00
32nd 7.5% 13742.00 17178.00 18037.00
33rd m 7.5% 14773.00 18466.00 19389.00
34th m 7.5% 15881.00 19851.00 20844.00
35th m 7.5% 17072.00 21340.00 22407.00
36th m 7.5% 18352.00 22940.00 24087.00
37th m 7.5% 19728.00 24660.00 25893.00
38th m 7.5% 21208.00 26510.00 27836.00
39th m 7.5% 22799.00 28499.00 29924.00
40th m 7.5% 24509.00 30636.00 32168.00
Total Cost from 30m upto 40m 180847.00 226059.00 237363.00
Avg Rate per metre 18085.00 22606.00 23736.00
12.14 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 26960.00 32352.00 33970.00
32nd 10% 29656.00 35587.00 37366.00
33rd m 10% 32622.00 39146.00 41103.00
34th m 10% 35884.00 43061.00 45214.00
35th m 10% 39472.00 47366.00 49734.00
36th m 10% 43419.00 52103.00 54708.00
37th m 10% 47761.00 57313.00 60179.00
38th m 10% 52537.00 63044.00 66196.00
39th m 10% 57791.00 69349.00 72816.00
40th m 10% 63570.00 76284.00 80098.00
Total Cost from 30m upto 40m 429672.00 515605.00 541384.00
Avg Rate per metre 42967.00 51561.00 54138.00
12.14 C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 639.10 434.59
Sinker ( skilled ) day 4.00 698.50 2794.00
Sinking helper ( semi-skilled ) day 12.00 0.00 0.00
Diver day 1.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 338.47 1692.34
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 349.49 1310.60
Consumables in sinking @ 10 per cent of (b) 300.29
Add for dewatering @ of 5 per cent of (a+b), if required 326.59

c) Overhead charges @ 0.2 on (a+b) 1371.68


Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 823.01
Rate per metre = (a+b+c+d) 9053.10
say 9053.00
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 37.00 296.00
Electric Detonators each 32.00 25.48 815.36
b) Labour
Mate day 1.09 639.10 696.62
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 20.00 719.40 14388.00
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 349.49 698.99
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 1030.42
Consumables in sinking @ 10 per cent of cost of (b). 1787.86
d) Overhead charges @ 0.2 on (a+b+c) 4907.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 2944.57
Rate per metre = (a+b+c+d+e) 32390.23
say 32390.00
12.15 Section Sinking of 9 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 639.10 121.43
Sinker ( skilled ) day 1.50 698.50 1047.75
Sinking helper ( semi-skilled ) day 3.25 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 338.47 1353.87
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 135.39
c) Overhead charges @ 0.2 on (a+b) 531.69
d) Contractor's profit @ 0.1 on (a+b+c) 319.01
Rate per metre = (a+b+c+d) 3509.14
say 3509.00
12.15 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.27 639.10 172.56
Sinker day 1.75 698.50 1222.38
Sinking helper ( semi-skilled ) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 338.47 1861.57
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 186.16
c) Overhead charges @ 0.2 on (a+b) 688.53
d) Contractor's profit @ 0.1 on (a+b+c) 413.12
Rate per metre = (a+b+c+d) 4544.31
say 4544.00
12.15 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 4772.00
12th m 5% 5011.00
13th m 5% 5262.00
14th m 5% 5525.00
15th m 5% 5801.00
16th m 5% 6091.00
17th m 5% 6396.00
18th m 5% 6716.00
19th m 5% 7052.00
20th m 5% 7405.00
Total Cost from 10m upto 20m 60031.00
Avg Rate per metre 6003.00
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 7960.38 9552.00
22nd m 7.5% 8557.00 10268.00
23rd m 7.5% 9199.00 11039.00
24th m 7.5% 9889.00 11867.00
25th m 7.5% 10631.00 12757.00
26th m 7.5% 11428.00 13714.00
27th m 7.5% 12285.00 14742.00
28th m 7.5% 13206.00 15847.00
29th m 7.5% 14196.00 17035.00
30th m 7.5% 15261.00 18313.00
Total Cost from 20m upto 30m 112612.38 135134.00
Avg Rate per metre 11261.00 13513.00
12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 16787.10 20145.00
32nd 10% 18466.00 22159.00
33rd m 10% 20313.00 24376.00
34th m 10% 22344.00 26813.00
35th m 10% 24578.00 29494.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
36th m 10% 27036.00 32443.00
37th m 10% 29740.00 35688.00
38th m 10% 32714.00 39257.00
39th m 10% 35985.00 43182.00
40th m 10% 39584.00 47501.00
Total Cost from 30m upto 40m 267547.10 321058.00
Avg Rate per metre 26755.00 32106.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 639.10 153.38
Sinker ( skilled ) day 2.25 698.50 1571.63
Sinking helper ( semi-skilled ) day 3.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 338.47 1946.19
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 194.62
c) Overhead charges @ 0.2 on (a+b) 773.16
d) Contractor's profit @ 0.1 on (a+b+c) 463.90
Rate per metre = (a+b+c+d) 5102.88
say 5103.00
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 639.10 217.29
Sinker day 2.50 698.50 1746.25
Sinking helper ( semi-skilled ) day 5.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 338.47 2200.04
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 349.49 1310.60
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 351.06
c) Overhead charges @ 0.2 on (a+b) 1165.05
d) Contractor's profit @ 0.1 on (a+b+c) 699.03
Rate per metre = (a+b+c+d) 7689.32
say 7689.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 8073.00 8477.00
12th m 5% 8477.00 8901.00
13th m 5% 8901.00 9346.00
14th m 5% 9346.00 9813.00
15th m 5% 9813.00 10304.00
16th m 5% 10304.00 10819.00
17th m 5% 10819.00 11360.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
18th m 5% 11360.00 11928.00
19th m 5% 11928.00 12524.00
20th m 5% 12524.00 13150.00
Total Cost from 10m upto 20m 101545.00 106622.00
Avg Rate per metre 10155.00 10662.00
12.15 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 13463.00 16829.00 17670.00
32nd 7.5% 14473.00 18091.00 18996.00
33rd m 7.5% 15558.00 19448.00 20420.00
34th m 7.5% 16725.00 20906.00 21951.00
35th m 7.5% 17979.00 22474.00 23598.00
36th m 7.5% 19327.00 24159.00 25367.00
37th m 7.5% 20777.00 25971.00 27270.00
38th m 7.5% 22335.00 27919.00 29315.00
39th m 7.5% 24010.00 30013.00 31514.00
40th m 7.5% 25811.00 32264.00 33877.00
Total Cost from 30m upto 40m 190458.00 238074.00 249978.00
Avg Rate per metre 19046.00 23807.00 24998.00
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 28392.00 34070.00 35774.00
32nd 10% 31231.00 37477.00 39351.00
33rd m 10% 34354.00 41225.00 43286.00
34th m 10% 37789.00 45347.00 47614.00
35th m 10% 41568.00 49882.00 52376.00
36th m 10% 45725.00 54870.00 57614.00
37th m 10% 50298.00 60358.00 63376.00
38th m 10% 55328.00 66394.00 69714.00
39th m 10% 60861.00 73033.00 76685.00
40th m 10% 66947.00 80336.00 84353.00
Total Cost from 30m upto 40m 452493.00 542992.00 570143.00
Avg Rate per metre 45249.00 54299.00 57014.00
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 639.10 485.72
Sinker ( skilled ) day 4.00 698.50 2794.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper ( semi-skilled ) day 14.00 0.00 0.00
Diver day 1.20 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 338.47 2200.04
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 349.49 1397.97
Consumables in sinking @ 10 per cent of (b) 359.80
Add for dewatering @ of 5 per cent of (a+b), if required 723.75

c) Overhead charges @ 0.2 on (a+b) 1592.26


d) Contractor's profit @ 0.1 on (a+b+c) 955.35
Rate per metre = (a+b+c+d) 10508.89
say 10509.00
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 37.00 370.00
Electric Detonators each 40.00 25.48 1019.20
b) Labour
Mate day 1.17 639.10 747.75
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 22.00 719.40 15826.80
Mazdoor (Skilled) day 4.00 698.50 2794.00
Diver day 1.00 0.00 0.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 338.47 2369.27
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 349.49 873.73
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 1130.58
Consumables in sinking @ 10 per cent of cost of (b). 1936.85
d) Overhead charges @ 0.2 on (a+b+c) 5413.64
e) Contractor's profit @ 0.1 on (a+b+c+d) 3248.18
Rate per metre = (a+b+c+d+e) 35730.00
say 35730.00
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 639.10 127.82
Sinker ( skilled ) day 1.50 698.50 1047.75
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper ( semi-skilled ) day 3.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 338.47 1692.34
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 169.23
c) Overhead charges @ 0.2 on (a+b) 607.43
d) Contractor's profit @ 0.1 on (a+b+c) 364.46
Rate per metre = (a+b+c+d) 4009.03
say 4009.00
12.16 A (ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 639.10 198.12
Sinker day 2.00 698.50 1397.00
Sinking helper ( semi-skilled ) day 4.25 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 338.47 1946.19
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 194.62
c) Overhead charges @ 0.2 on (a+b) 747.19
d) Contractor's profit @ 0.1 on (a+b+c) 448.31
Rate per metre = (a+b+c+d) 4931.42
say 4931.00
12.16 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 5178.00
12th m 5% 5437.00
13th m 5% 5709.00
14th m 5% 5994.00
15th m 5% 6294.00
16th m 5% 6609.00
17th m 5% 6939.00
18th m 5% 7286.00
19th m 5% 7650.00
20th m 5% 8033.00
Total Cost from 10m upto 20m 65129.00
Avg Rate per metre 6513.00
12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 8635.00 10362.00
22nd m 7.5% 9283.00 11140.00
23rd m 7.5% 9979.00 11975.00
24th m 7.5% 10727.00 12872.00
25th m 7.5% 11532.00 13838.00
26th m 7.5% 12397.00 14876.00
27th m 7.5% 13327.00 15992.00
28th m 7.5% 14327.00 17192.00
29th m 7.5% 15402.00 18482.00
30th m 7.5% 16557.00 19868.00
Total Cost from 20m upto 30m 122166.00 146597.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Avg Rate per metre 12217.00 14660.00
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 18213.00 21856.00
32nd 10% 20034.00 24041.00
33rd m 10% 22037.00 26444.00
34th m 10% 24241.00 29089.00
35th m 10% 26665.00 31998.00
36th m 10% 29332.00 35198.00
37th m 10% 32265.00 38718.00
38th m 10% 35492.00 42590.00
39th m 10% 39041.00 46849.00
40th m 10% 42945.00 51534.00
Total Cost from 30m upto 40m 290265.00 348317.00
Avg Rate per metre 29027.00 34832.00
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 639.10 159.78
Sinker ( skilled ) day 2.50 698.50 1746.25
Sinking helper ( semi-skilled ) day 5.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 203.08
c) Overhead charges @ 0.2 on (a+b) 827.98
d) Contractor's profit @ 0.1 on (a+b+c) 496.79
Rate per metre = (a+b+c+d) 5464.68
say 5465.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 639.10 255.64
Sinker day 3.00 698.50 2095.50
Sinking helper ( semi-skilled ) day 5.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 349.49 1397.97
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 342.88
c) Overhead charges @ 0.2 on (a+b) 1224.56
d) Contractor's profit @ 0.1 on (a+b+c) 734.74
Rate per metre = (a+b+c+d) 8082.09
say 8082.00
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 8486.00 8910.00
12th m 5% 8910.00 9356.00
13th m 5% 9356.00 9824.00
14th m 5% 9824.00 10315.00
15th m 5% 10315.00 10831.00
16th m 5% 10831.00 11373.00
17th m 5% 11373.00 11942.00
18th m 5% 11942.00 12539.00
19th m 5% 12539.00 13166.00
20th m 5% 13166.00 13824.00
Total Cost from 10m upto 20m 106742.00 112080.00
Avg Rate per metre 10674.00 11208.00
12.16 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 14153.00 17691.00 18576.00
32nd 7.5% 15214.00 19018.00 19969.00
33rd m 7.5% 16355.00 20444.00 21466.00
34th m 7.5% 17582.00 21978.00 23077.00
35th m 7.5% 18901.00 23626.00 24807.00
36th m 7.5% 20319.00 25399.00 26669.00
37th m 7.5% 21843.00 27304.00 28669.00
38th m 7.5% 23481.00 29351.00 30819.00
39th m 7.5% 25242.00 31553.00 33131.00
40th m 7.5% 27135.00 33919.00 35615.00
Total Cost from 30m upto 40m 200225.00 250283.00 262798.00
Avg Rate per metre 20023.00 25028.00 26280.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 29849.00 35819.00 37610.00
32nd 10% 32834.00 39401.00 41371.00
33rd m 10% 36117.00 43340.00 45507.00
34th m 10% 39729.00 47675.00 50058.75
35th m 10% 43702.00 52442.00 55064.10
36th m 10% 48072.00 57686.00 60570.30
37th m 10% 52879.00 63455.00 66627.75
38th m 10% 58167.00 69800.00 73290.00
39th m 10% 63984.00 76781.00 80620.05
40th m 10% 70382.00 84458.00 88680.90
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total Cost from 30m upto 40m 475715.00 570857.00 599399.85
Avg Rate per metre 47572.00 57086.00 59940.00
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 639.10 549.63
Sinker ( skilled ) day 4.00 698.50 2794.00
Sinking helper ( semi-skilled ) day 16.00 0.00 0.00
Diver day 1.40 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 338.47 2369.27
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 349.49 1485.34
Consumables in sinking @ 10 per cent of (b) 385.46
Add for dewatering @ 5 per cent of cost, if required 212.00
c) Overhead charges @ 0.2 on (a+b) 1559.14
d) Contractor's profit @ 0.1 on (a+b+c) 935.48
Rate per metre = (a+b+c+d) 10290.33
say 10290.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 37.00 407.00
Electric Detonators each. 44.00 25.48 1121.12
b) Labour
Mate day 1.27 639.10 811.66
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 24.00 719.40 17265.60
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 338.47 2876.97
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 349.49 1048.48
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 196.27
Consumables in sinking @ 10 per cent of cost of (b+c). 2499.30

d) Overhead charges @ 0.2 on (a+b+c) 5804.08


e) Contractor's profit @ 0.1 on (a+b+c+d) 3482.45
Rate per metre = (a+b+c+d+e) 38306.93
say 38307.00
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 639.10 134.21
Sinker ( skilled ) day 1.50 698.50 1047.75
Sinking helper (semi-skilled) day 3.30 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 203.08
d) Overhead charges @ 0.2 on (a+b+c) 683.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 409.90
Cost for 0.5m = a+b+c+d 4508.92
Rate per metre = (a+b+c+d)/0.50 9017.83
say 9018.00
12.17 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 639.10 204.51
Sinker day 2.00 698.50 1397.00
Sinking helper (semi-skilled) day 4.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 338.47 1353.87
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 135.39
c) Overhead charges @ 0.2 on (a+b+c) 618.15
d) Contractor's profit @ 0.1 on (a+b+c+d) 370.89
Cost for 0.5m = a+b+c+d 4079.82
Rate per metre = (a+b+c+d)/0.50 8159.63
say 8160.00
12.17 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 8568.00
12th m 5% 8996.00
13th m 5% 9446.00
14th m 5% 9918.00
15th m 5% 10414.00
16th m 5% 10935.00
17th m 5% 11482.00
18th m 5% 12056.00
19th m 5% 12659.00
20th m 5% 13292.00
Total Cost from 10m upto 20m 107766.00
Avg Rate per metre 10777.00
12.17 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
21st m 7.5% 14289.00 17147.00
22nd m 7.5% 15361.00 18433.00
23rd m 7.5% 16513.00 19816.00
24th m 7.5% 17751.00 21301.00
25th m 7.5% 19082.00 22898.00
26th m 7.5% 20513.00 24616.00
27th m 7.5% 22051.00 26461.00
28th m 7.5% 23705.00 28446.00
29th m 7.5% 25483.00 30580.00
30th m 7.5% 27394.00 32873.00
Total Cost from 20m upto 30m 202142.00 242571.00
Avg Rate per metre 20214.00 24257.00
12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 30133.00 36160.00
32nd 10% 33146.00 39775.00
33rd m 10% 36461.00 43753.00
34th m 10% 40107.00 48128.00
35th m 10% 44118.00 52942.00
36th m 10% 48530.00 58236.00
37th m 10% 53383.00 64060.00
38th m 10% 58721.00 70465.00
39th m 10% 64593.00 77512.00
40th m 10% 71052.00 85262.00
Total Cost from 30m upto 40m 480244.00 576293.00
Avg Rate per metre 48024.00 57629.00
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 639.10 166.17
Sinker ( skilled ) day 2.50 698.50 1746.25
Sinking helper (semi-skilled) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 338.47 1692.34
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 169.23
c) Overhead charges @ 0.2 on (a+b) 754.80
d) Contractor's profit @ 0.1 on (a+b+c) 452.88
Cost for 0.5m = a+b+c+d 4981.66
Rate per metre = (a+b+c+d)/0.50 9963.33
say 9963.00
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 639.10 274.81
Sinker day 3.50 698.50 2444.75
Sinking helper (semi-skilled) day 5.75 0.00 0.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 349.49 1485.34
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 351.61
c) Overhead charges @ 0.2 on (a+b) 1317.47
d) Contractor's profit @ 0.1 on (a+b+c) 790.48
Cost for 0.5m = a+b+c+d 8695.27
Rate per metre = (a+b+c+d)/0.50 17390.54
say 17391.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 18260.00 19173.00
12th m 5% 19173.00 20132.00
13th m 5% 20132.00 21139.00
14th m 5% 21139.00 22196.00
15th m 5% 22196.00 23306.00
16th m 5% 23306.00 24471.00
17th m 5% 24471.00 25695.00
18th m 5% 25695.00 26980.00
19th m 5% 26980.00 28329.00
20th m 5% 28329.00 29745.00
Total Cost from 10m upto 20m 229681.00 241165.00
Avg Rate per metre 22968.00 24117.00
12.17 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 30454.00 38068.00 39971.00
32nd 7.5% 32738.00 40923.00 42969.00
33rd m 7.5% 35193.00 43991.00 46191.00
34th m 7.5% 37832.00 47290.00 49655.00
35th m 7.5% 40669.00 50836.00 53378.00
36th m 7.5% 43719.00 54649.00 57381.00
37th m 7.5% 46998.00 58748.00 61685.00
38th m 7.5% 50523.00 63154.00 66312.00
39th m 7.5% 54312.00 67890.00 71285.00
40th m 7.5% 58385.00 72981.00 76630.00
Total Cost from 30m upto 40m 430823.00 538530.00 565457.00
Avg Rate per metre 43082.00 53853.00 56546.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 64224.00 77069.00 80922.00
32nd 10% 70646.00 84775.00 89014.00
33rd m 10% 77711.00 93253.00 97916.00
34th m 10% 85482.00 102578.00 107707.00
35th m 10% 94030.00 112836.00 118478.00
36th m 10% 103433.00 124120.00 130326.00
37th m 10% 113776.00 136531.00 143358.00
38th m 10% 125154.00 150185.00 157694.00
39th m 10% 137669.00 165203.00 173463.00
40th m 10% 151436.00 181723.00 190809.00
Total Cost from 30m upto 40m 1023561 1228273 1289687
Avg Rate per metre 102356.00 122827.00 128969.00
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 639.10 607.15
Sinker ( skilled ) day 4.25 698.50 2968.63
Sinking helper (semi-skilled) day 18.00 0.00 0.00
Diver day 1.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 338.47 2707.74
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 349.49 1572.72
Consumables in sinking @ 10 per cent of (b) 428.05
Add for dewatering @ 5 per cent of cost, if required 235.43
c) Overhead charges @ 0.2 on (a+b) 1703.94
d) Contractor's profit @ 0.1 on (a+b+c) 1022.36
Cost for 0.5m = a+b+c+d 11246.00
Rate per metre = (a+b+c+d)/0.50 22492.00
say 22492.00
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 37.00 444.00
Electric Detonators each. 48.00 25.48 1223.04
b) Labour
Mate day 1.35 639.10 862.79
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 26.00 719.40 18704.40
Mazdoor (Skilled) day 4.00 698.50 2794.00
c) Machinery
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 349.49 1223.22
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 230.39
Consumables in sinking @ 10 per cent of cost of (b+c). 2696.91

d) Overhead charges @ 0.2 on (a+b+c) 6312.69


e) Contractor's profit @ 0.1 on (a+b+c+d) 3787.61
Cost for 0.5m = a+b+c+d 41663.72
Rate per metre = (a+b+c+d)/0.50 83327.45
say 83327.00
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 639.10 140.60
Sinker ( skilled ) day 1.75 698.50 1222.38
Sinking helper (semi-skilled) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 338.47 2030.81
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 203.08
c) Overhead charges @ 0.2 on (a+b) 719.37
d) Contractor's profit @ 0.1 on (a+b+c) 431.62
Cost for 0.25m = a+b+c+d 4747.86
Rate per metre = (a+b+c+d)/0.25 18991.43
say 18991.00
12.18 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 639.10 236.47
Sinker day 2.50 698.50 1746.25
Sinking helper (semi-skilled) day 4.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 338.47 2200.04
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 220.00
c) Overhead charges @ 0.2 on (a+b) 880.55
d) Contractor's profit @ 0.1 on (a+b+c) 528.33
Cost for 0.25m = a+b+c+d 5811.64
Rate per metre = (a+b+c+d)/0.25 23246.57
say 23247.00
12.18 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
11th m 5% 24409.00
12th m 5% 25629.00
13th m 5% 26910.45
14th m 5% 28255.97
15th m 5% 29668.77
16th m 5% 31152.21
17th m 5% 32709.82
18th m 5% 34345.31
19th m 5% 36062.58
20th m 5% 37865.71
Total Cost from 10m upto 20m 307008.82
Avg Rate per metre 30701.00
12.18 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 40706.00 48847.00
22nd m 7.5% 43759.00 52511.00
23rd m 7.5% 47041.00 56449.00
24th m 7.5% 50569.00 60683.00
25th m 7.5% 54362.00 65234.00
26th m 7.5% 58439.00 70127.00
27th m 7.5% 62822.00 75386.00
28th m 7.5% 67534.00 81041.00
29th m 7.5% 72599.00 87119.00
30th m 7.5% 78044.00 93653.00
Total Cost from 20m upto 30m 575875.00 691050.00
Avg Rate per metre 57588.00 69105.00
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 85848.00 103018.00
32nd 10% 94433.00 113320.00
33rd m 10% 103876.00 124651.00
34th m 10% 114264.00 137117.00
35th m 10% 125690.00 150828.00
36th m 10% 138259.00 165911.00
37th m 10% 152085.00 182502.00
38th m 10% 167294.00 200753.00
39th m 10% 184023.00 220828.00
40th m 10% 202425.00 242910.00
Total Cost from 30m upto 40m 1368197 1641838
Avg Rate per metre 136820.00 164184.00
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 639.10 191.73
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinker ( skilled ) day 3.00 698.50 2095.50
Sinking helper (semi-skilled) day 4.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 338.47 2115.42
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 211.54
c) Overhead charges @ 0.2 on (a+b) 922.84
d) Contractor's profit @ 0.1 on (a+b+c) 553.70
Cost for 0.25m = a+b+c+d 6090.74
Rate per metre = (a+b+c+d)/0.25 24362.94
say 24363.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 639.10 306.77
Sinker day 3.75 698.50 2619.38
Sinking helper (semi-skilled) day 6.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 338.47 2819.43
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 349.49 1572.72
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 439.22
c) Overhead charges @ 0.2 on (a+b) 1551.50
d) Contractor's profit @ 0.1 on (a+b+c) 930.90
Cost for 0.25m = a+b+c+d 10239.91
Rate per metre = (a+b+c+d)/0.25 40959.65
say 40960.00
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 43008.00 45158.00
12th m 5% 45158.00 47416.00
13th m 5% 47416.00 49787.00
14th m 5% 49787.00 52276.00
15th m 5% 52276.00 54890.00
16th m 5% 54890.00 57635.00
17th m 5% 57635.00 60517.00
18th m 5% 60517.00 63543.00
19th m 5% 63543.00 66720.00
20th m 5% 66720.00 70056.00
Total Cost from 10m upto 20m 540950.00 567998.00
Avg Rate per metre 54095.00 56800.00
12.18 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
31st m 7.5% 71724.00 89655.00 94138.00
32nd 7.5% 77103.00 96379.00 101198.00
33rd m 7.5% 82886.00 103608.00 108788.00
34th m 7.5% 89102.00 111378.00 116947.00
35th m 7.5% 95785.00 119731.00 125718.00
36th m 7.5% 102969.00 128711.00 135147.00
37th m 7.5% 110692.00 138365.00 145283.00
38th m 7.5% 118994.00 148743.00 156180.00
39th m 7.5% 127919.00 159899.00 167894.00
40th m 7.5% 137513.00 171891.00 180486.00
Total Cost from 30m upto 40m 1014687 1268360 1331779
Avg Rate per metre 101469.00 126836.00 133178.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 151264.00 181517.00 190593.00
32nd 10% 166390.00 199668.00 209651.00
33rd m 10% 183029.00 219635.00 230617.00
34th m 10% 201332.00 241598.00 253678.00
35th m 10% 221465.00 265758.00 279046.00
36th m 10% 243612.00 292334.00 306951.00
37th m 10% 267973.00 321568.00 337646.00
38th m 10% 294770.00 353724.00 371410.00
39th m 10% 324247.00 389096.00 408551.00
40th m 10% 356672.00 428006.00 449406.00
Total Cost from 30m upto 40m 2410754 2892904 3037549
Avg Rate per metre 241075.00 289290.00 303755.00
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 639.10 677.45
Sinker ( skilled ) day 4.50 698.50 3143.25
Sinking helper (semi-skilled) day 20.00 0.00 0.00
Diver day 1.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 349.49 1660.09
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 504.48
Add for dewatering @ 5 per cent, if required 277.46
c) Overhead charges @ 0.2 on (a+b) 1929.48
d) Contractor's profit @ 0.1 on (a+b+c) 1157.69
Cost for 0.25m = a+b+c+d 12734.57
Rate per metre = (a+b+c+d)/0.25 50938.27
say 50938.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 37.00 518.00
Electric detonator each. 56.00 25.48 1426.88
b) Labour
Mate day 1.44 639.10 920.30
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 28.00 719.40 20143.20
Mazdoor (Skilled) day 4.50 698.50 3143.25
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 338.47 4230.84
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 349.49 1397.97
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 281.44
Consumables in sinking @ 10 per cent of (c). 591.03
d) Overhead charges @ 0.2 on (a+b+c) 6530.58
e) Contractor's profit @ 0.1 on (a+b+c+d) 3918.35
Cost for 0.25m = a+b+c+d+e 43101.85
Rate per metre = (a+b+c+d+e)/0.25 172407.39
say 172407.00
12.19 1200 Sinking of Twin D Type well (other than pneumatic method
of sinking) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking
is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 639.10 127.82
Sinker ( skilled ) day 1.25 698.50 873.13
Sinking helper (semi-skilled) day 3.75 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 338.47 1861.57
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 186.16
c) Overhead charges @ 0.2 on (a+b) 609.73
d) Contractor's profit @ 0.1 on (a+b+c) 365.84
Rate per metre = (a+b+c+d) 4024.25
say 4024.00
12.19 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.30 639.10 191.73
Sinker day 1.50 698.50 1047.75
Sinking helper (semi-skilled) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 338.47 1990.19
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 199.02
c) Overhead charges @ 0.2 on (a+b) 685.74
d) Contractor's profit @ 0.1 on (a+b+c) 411.44
Rate per metre = (a+b+c+d) 4525.87
say 4526.00
12.19 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 4752.00
12th m 5% 4990.00
13th m 5% 5240.00
14th m 5% 5502.00
15th m 5% 5777.00
16th m 5% 6066.00
17th m 5% 6369.00
18th m 5% 6687.00
19th m 5% 7021.00
20th m 5% 7372.00
Total Cost from 10m upto 20m 59776.00
Avg Rate per metre 5978.00
12.19 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 7925.00 9510.00
22nd m 7.5% 8519.00 10223.00
23rd m 7.5% 9158.00 10990.00
24th m 7.5% 9845.00 11814.00
25th m 7.5% 10583.00 12700.00
26th m 7.5% 11377.00 13652.00
27th m 7.5% 12230.00 14676.00
28th m 7.5% 13147.00 15776.00
29th m 7.5% 14133.00 16960.00
30th m 7.5% 15193.00 18232.00
Total Cost from 20m upto 30m 112110.00 134533.00
Avg Rate per metre 11211.00 13453.00
12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 16712.00 20054.00
32nd 10% 18383.00 22060.00
33rd m 10% 20221.00 24265.00
34th m 10% 22243.00 26692.00
35th m 10% 24467.00 29360.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
36th m 10% 26914.00 32297.00
37th m 10% 29605.00 35526.00
38th m 10% 32566.00 39079.00
39th m 10% 35823.00 42988.00
40th m 10% 39405.00 47286.00
Total Cost from 30m upto 40m 266339.00 319607.00
Avg Rate per metre 26634.00 31961.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 639.10 166.17
Sinker ( skilled ) day 2.50 698.50 1746.25
Sinking helper (semi-skilled) day 4.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 338.47 2115.42
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 211.54
c) Overhead charges @ 0.2 on (a+b) 847.88
d) Contractor's profit @ 0.1 on (a+b+c) 508.73
Rate per metre = (a+b+c+d) 5595.98
say 5596.00
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 639.10 287.60
Sinker day 3.25 698.50 2270.13
Sinking helper (semi-skilled) day 6.00 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 338.47 2257.58
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 349.49 1572.72
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 383.03
c) Overhead charges @ 0.2 on (a+b) 1354.21
d) Contractor's profit @ 0.1 on (a+b+c) 812.53
Rate per metre = (a+b+c+d) 8937.78
say 8938.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 9385.00 9854.00
12th m 5% 9854.00 10347.00
13th m 5% 10347.00 10864.00
14th m 5% 10864.00 11407.00
15th m 5% 11407.00 11977.00
16th m 5% 11977.00 12576.00
17th m 5% 12576.00 13205.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
18th m 5% 13205.00 13865.00
19th m 5% 13865.00 14558.00
20th m 5% 14558.00 15286.00
Total Cost from 10m upto 20m 118038.00 123939.00
Avg Rate per metre 11804.00 12394.00
12.19 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 15650.00 19563.00 20541.00
32nd 7.5% 16824.00 21030.00 22082.00
33rd m 7.5% 18086.00 22608.00 23738.00
34th m 7.5% 19442.00 24303.00 25518.00
35th m 7.5% 20900.00 26125.00 27431.00
36th m 7.5% 22468.00 28085.00 29489.00
37th m 7.5% 24153.00 30191.00 31701.00
38th m 7.5% 25964.00 32455.00 34078.00
39th m 7.5% 27911.00 34889.00 36633.00
40th m 7.5% 30004.00 37505.00 39380.00
Total Cost from 30m upto 40m 221402.00 276754.00 290591.00
Avg Rate per metre 22140.00 27675.00 29059.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 33004.00 39605.00 41585.00
32nd 10% 36304.00 43565.00 45743.00
33rd m 10% 39934.00 47921.00 50317.00
34th m 10% 43927.00 52712.00 55348.00
35th m 10% 48320.00 57984.00 60883.00
36th m 10% 53152.00 63782.00 66971.00
37th m 10% 58467.00 70160.00 73668.00
38th m 10% 64314.00 77177.00 81036.00
39th m 10% 70745.00 84894.00 89139.00
40th m 10% 77820.00 93384.00 98053.00
Total Cost from 30m upto 40m 525987.00 631184.00 662743.00
Avg Rate per metre 52599.00 63118.00 66274.00
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 639.10 549.63
Sinker ( skilled ) day 4.50 698.50 3143.25
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper (semi-skilled) day 15.00 0.00 0.00
Diver day 1.50 0.00 0.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 338.47 2819.43
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 349.49 2096.96
Consumables in sinking @ 10 per cent of (b) 491.64
Add for dewatering @ 5 per cent, if required 270.40
c) Overhead charges @ 0.2 on (a+b) 1874.26
d) Contractor's profit @ 0.1 on (a+b+c) 1124.56
Rate per metre = (a+b+c+d) 12370.12
say 12370.00
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 37.00 370.00
Electric detonators each. 40.00 25.48 1019.20
b) Labour
Mate day 1.34 639.10 856.39
Driller day 2.00 0.00 0.00
Blaster day 0.25 0.00 0.00
Mazdoor day 25.00 719.40 17985.00
Mazdoor (Skilled) day 4.25 698.50 2968.63
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 338.47 3384.68
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 349.49 1048.48
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 1312.16
Consumables in sinking @ 10 per cent of (b). 574.53
d) Overhead charges @ 0.2 on (a+b+c) 5903.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 3542.29
Rate per metre = (a+b+c+d+e) 38965.16
say 38965.00
12.20 1200 Pneumatic sinking of wells with equipment of approved
design, drawing and specifications worked by competent
and trained personnel and comprising of compression and
decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of
fresh air to working chambers, check valves, exhaust valves,
shafts made from steel plates of riveted construction not less
than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing, arrangement
for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations
and compliance with safety precautions as per IS:4138, all
as per clause1207.6 of MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 8682.00 69456.00
equipment (Dimensions as per ground conditions).
Rate may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 52222.68 25066.88
Blasting material
Gelatine 80 per cent Kg 1.50 37.00 55.50
Electric detonators each 6.00 25.48 152.88
b) Labour
Medical Officer day 0.50 0.00 0.00
Para medical personnel day 1.00 714.00 714.00
Mate day 1.86 639.10 1188.73
Driller day 1.00 0.00 0.00
Blaster day 0.50 0.00 0.00
Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 719.40 21582.00
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 698.50 6985.00
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

Diver day 4.00 0.00 0.00


c) Machinery
(i) Induction, deinduction and erection of plant and hour 6.00 0.00 0.00
equipment including all components and accessories
for pneumatic method of well sinking.

Induction and deinduction L.S 100000.00


Erection at site and commissioning L.S 150000.00
Usage of plant and equipment for pneumatic method of hour 6.00 4911.80 29470.82
well sinking
Air compressor 250 cfm, 2 nos. hour 2x6 546.40 6556.79
Hire and running charges of crane of 15 tonne capacity hour 6.00 0.00 0.00

Motorised barge of 20 tonne capacity hour 6.00 0.00 0.00


Boat to carry atleast 20 persons hour 6.00 0.00 0.00
Electric generating set 33 KVA hour 6.00 636.69 3820.16
Tipper 10 tonne capacity hour 6.00 530.19 3181.15
d) Overhead charges @ 0.2 on (a+b+c) 69754.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 41852.87
Cost for 5 cum = a+b+c+d+e (see notes below)
Rate per cum = (a+b+c+d+e)/5
Note 1.The cost of induction, deinduction and erection of
equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will
be added to the cost indicated at (1) above to arrive at the
final rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.
12.21 1207 Sand Filling in Wells complete as per Drawing and Technical
Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 1670.49 2004.59
b) Labour
Mate day 0.01 639.10 6.39
Mazdoor day 0.30 719.40 215.82
c) Overhead charges @ 0.2 on (a+b) 445.36
d) Contractor's profit @ 0.1 on (a+b+c) 267.22
Rate per cum (a+b+c+d) 2939.38
say 2939.00
12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm thick
1900 for Steining of Wells including Fabricating and Setting out as
per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 45000.00 47250.00
b) Labour
Mate day 1.24 639.10 792.48
Fitter day 6.00 0.00 0.00
Blacksmith day 5.00 569.00 2845.00
Welder day 5.00 729.30 3646.50
Mazdoor day 10.00 719.40 7194.00
Electrodes, cutting gas and other consumables @ 5 2362.50
per cent on cost a (a) above.
c) Overhead charges @ 0.2 on (a+b) 12818.10
d) Contractor's profit @ 0.1 on (a+b+c) 7690.86
Rate for per MT (a+b+c+d) 84599.44
say 84599.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 8713.00 57680.06

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 9352.45 56114.71
power unit and complete accessories including shifting
from one bore location to another.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire and running charges of light crane for lowering hour 0.50 610.07 305.03
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.30 1379.89 413.97
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 530.19 159.06
bore hole
Bentonite kg 300.00 34.65 10395.00
c) Labour
Mate/Supervisor day 0.14 639.10 89.47
Mazdoor day 3.50 719.40 2517.90
d) Overhead charges @ 0.2 on (b+c) 13999.03
e) Contractor's profit @ 0.1 on (b+c+d) 8399.42
Cost for 15 m = a+b+c+d+d+e 150073.65
Rate per metre (a+b+c+d+e)/15 10004.91
say 10005.00
12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
1100,16 Reinforcement complete as per Drawing and Technical
00 & Specifications and removal of excavated earth with all lifts
1700 and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 8713.00 68397.05

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 9352.45 56114.71
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 610.07 305.03
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.40 1379.89 551.96
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 530.19 212.08
bore hole
Bentonite kg 350.00 34.65 12127.50
c) Labour
Mate/Supervisor day 0.16 639.10 102.26
Mazdoor day 4.00 719.40 2877.60
d) Overhead charges @ 0.2 on (b+c) 14458.23
e) Contractor's profit @ 0.1 on (b+c+d) 8674.94
Cost for 10 m = a+b+c+d+d+e 163821.35
Rate per metre (a+b+c+d+e)/10 16382.14
say 16382.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
PCC Grade M35 cum 10.17 8713.00 88611.21

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 9352.45 56114.71
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 610.07 305.03
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 1379.89 689.94
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 530.19 265.10
bore hole
Bentonite kg 385.00 34.65 13340.25
c) Labour
Mate/Supervisor day 0.18 639.10 115.04
Mazdoor day 4.50 719.40 3237.30
d) Overhead charges @ 0.2 on (b+c) 14813.48
e) Contractor's profit @ 0.1 on (b+c+d) 8888.09
Cost for 9 m = a+b+c+d+d+e 186380.15
Rate per metre (a+b+c+d+e)/9 20708.91
say 20709.00
12.26 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 8713.00 153871.58

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 #VALUE! #VALUE!
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 70.00 4900.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 0.00 0.00
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 0.00 0.00
acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 0.00 0.00
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 40 m = a+b+c+d+e #VALUE!
Rate per metre (a+b+c+d+e)/40 #VALUE!
say #VALUE!
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 8713.00 205191.15

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 #VALUE! #VALUE!
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 70.00 4900.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 0.00 0.00
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 0.00 0.00
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 0.00 0.00
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 610.07 305.03
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 639.10 102.26
Mazdoor day 4.00 719.40 2877.60
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 30 m = a+b+c+d+e #VALUE!
Rate per metre (a+b+c+d+e)/30 #VALUE!
say #VALUE!
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
PCC Grade M35 cum 22.61 8713.00 197000.93

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 #VALUE! #VALUE!
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 70.00 4900.00
iii) Steel helmet on top of casing head during driving Kg 50.00 0.00 0.00
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 0.00 0.00
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 0.00 0.00
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 639.10 115.04
Mazdoor day 4.50 719.40 3237.30
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 20 m = a+b+c+d+e #VALUE!
Rate per metre (a+b+c+d+e)/20 #VALUE!
say #VALUE!
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 8271.00 97432.38

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 #VALUE! #VALUE!
b) M.S. shoes Kg 105.00 70.00 7350.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane20 t capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d) Labour
Mate/Supervisor day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 60 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/60 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 8271.00 182623.68

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 #VALUE! #VALUE!
b) M.S. shoes Kg 70.00 70.00 4900.00
c) Steel helmet and cushion block on top of pile head Kg 40.00 0.00 0.00
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d) Labour
Mate/Supervisor day 0.16 639.10 102.26
Mazdoor day 4.00 719.40 2877.60
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 50 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/50 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.40 8271.00 259709.40

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 #VALUE! #VALUE!
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 70.00 4900.00
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Steel helmet and cushion block on top of pile head Kg 50.00 0.00 0.00
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 2189.07 13134.41
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d) Labour
Mate/Supervisor day 0.20 639.10 127.82
Mazdoor day 5.00 719.40 3597.00
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 40 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/40 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.32 1100&17 Driven precast vertical M35 grade R.C.C. Piles excluding
00 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 8271.00 44663.40
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 240.00 #VALUE! #VALUE!
b) M. S shoes kg 105.00 70.00 7350.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 60 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/60 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 8271.00 103387.50
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 160.00 #VALUE! #VALUE!
b) M. S shoes kg 70.00 70.00 4900.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.16 639.10 102.26
Mazdoor day 4.00 719.40 2877.60
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 50 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/50 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 8271.00 186097.50
plug vide item no. 13.11( F ) (IV)
b ) Material
Pile shoes
a) C I shoes kg 160.00 #VALUE! #VALUE!
b) M. S shoes kg 70.00 70.00 4900.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.18 639.10 115.04
Mazdoor day 4.50 719.40 3237.30
Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) #VALUE!
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 40 m = a+b+c+d+e+f #VALUE!
Rate per metre (a+b+c+d+e+f)/40 #VALUE!
say #VALUE!
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing and &
1900 Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 45000.00 271800.00
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and other accessories.
c) Labour
Mate/Supervisor day 0.12 639.10 76.69
Mazdoor day 3.00 719.40 2158.20
Add 0.5 per cent of (a+b+c) for providing steel 1370.17
helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.
d) Overhead charges @ 0.2 on (a+b+c) 55081.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 33048.61
Cost for 70 m = a+b+c+d+e 363534.69
Rate per metre (a+b+c+d+e)/70 5193.35
say 5193.00
12.36 1100 Driven Vertical Steel Piles complete as per Drawing and &
&1900 Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 tonnes 5.83 45000.00 262350.00
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
c) Labour
Mate/Supervisor day 0.14 639.10 89.47
Mazdoor day 3.50 719.40 2517.90
Add 0.5 per cent of (a+b+c) for providing steel 1324.79
helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

d) Overhead charges @ 0.2 on (a+b+c) 53256.43


e) Contractor's profit @ 0.1 on (a+b+c+d) 31953.86
Cost for 60 m = a+b+c+d+e 351492.45
Rate per metre (a+b+c+d+e)/60 5858.21
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5858.00
12.37 1100 Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00
b) Lateral load test tonne 1.00 5000.00
Note Although, this item is incidental to work and is not required to
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
12.38 1100, Cement Concrete for Reinforced Concrete in Pile Cap
1500 complete as per Drawing and Technical Specification
&1700
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 7146.39 36589.52
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 0.00 0.00
Mazdoor for concreting day 20.00 719.40 14388.00
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator (capacity 33 KVA) hour 6.00 636.69 3820.16
Formwork @ 4 per cent on cost of concrete i.e. cost 3698.64
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 19232.93
e) Contractor's profit @ 0.1 on (a+b+c+d) 11539.76
Cost for 15 cum = a+b+c+d+e 126937.31
Rate per metre (a+b+c+d+e)/15 8462.49
say 8462.00
12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.12 7146.39 36589.52
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 100 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71

Concrete Pump hour 0.75 437.58 328.19


Formwork @ 4 per cent on cost of concrete i.e. cost 3335.19
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 17343.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 10405.81
Cost for 15 cum = a+b+c+d+e 114463.87
Rate per metre (a+b+c+d+e)/15 7630.92
say 7631.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 7146.39 42806.88
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 0.00 0.00
Mazdoor for concreting day 20.00 719.40 14388.00
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator (capacity 33 KVA) hour 6.00 636.69 3820.16
Formwork @ 4 per cent on cost of concrete i.e. cost 3947.33
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 20526.14
e) Contractor's profit @ 0.1 on (a+b+c+d) 12315.68
Cost for 15 cum = a+b+c+d+e 135472.50
Rate per metre (a+b+c+d+e)/15 9031.50
say 9032.00
12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.99 7146.39 42806.88
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 125 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71

Concrete Pump hour 0.75 437.58 328.19


Formwork @ 4 per cent on cost of concrete i.e. cost 3583.89
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 18636.22
e) Contractor's profit @ 0.1 on (a+b+c+d) 11181.73
Cost for 15 cum = a+b+c+d+e 122999.07
Rate per metre (a+b+c+d+e)/15 8199.94
say 8200.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 7146.39 43592.98
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 0.00 0.00
Mazdoor for concreting day 20.00 719.40 14388.00
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator (capacity 33 KVA) hour 6.00 636.69 3820.16
Formwork @ 4 per cent on cost of concrete i.e. cost 3978.78
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 20689.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 12413.79
Cost for 15 cum = a+b+c+d+e 136551.66
Rate per metre (a+b+c+d+e)/15 9103.44
say 9103.00
'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.10 7146.39 43592.98
Coarse sand cum 6.75 1670.49 11275.83
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 100 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71

Concrete Pump hour 0.75 437.58 328.19


Formwork @ 4 per cent on cost of concrete i.e. cost 3615.33
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 18799.73
e) Contractor's profit @ 0.1 on (a+b+c+d) 11279.84
Cost for 15 cum = a+b+c+d+e 124078.23
Rate per metre (a+b+c+d+e)/15 8272
say 8272.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1753.74 11837.71
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.90 639.10 575.19
Mason day 1.50 0.00 0.00
Mazdoor day 20.00 719.40 14388.00
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator (capacity 33 KVA) hour 6.00 636.69 3820.16
Formwork @ 4 per cent on cost of concrete i.e. cost 4044.52
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 21031.53
e) Contractor's profit @ 0.1 on (a+b+c+d) 12618.92
Cost for 15 cum = a+b+c+d+e 138808.09
Rate per metre (a+b+c+d+e)/15 9253.87
say 9254.00
'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.33 7146.39 45236.65
Coarse sand cum 6.75 1670.49 11275.83
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
20 mm Aggregate cum 8.10 1822.49 14762.20
10 mm Aggregate cum 5.40 1367.49 7384.47
b) Labour
Mate day 0.16 639.10 102.26
Mason day 0.38 0.00 0.00
Mazdoor for concreting day 2.50 719.40 1798.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 719.40 719.40
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 3133.69 2350.27
Generator 125 KVA hour 0.75 1193.51 895.13
Loader (capacity 1 cum) hour 0.75 1379.89 1034.92
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1591.73 3183.47
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.28 2955.71

Concrete Pump hour 0.75 437.58 328.19


Formwork @ 4 per cent on cost of concrete i.e. cost 3681.08
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 19141.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 11484.97
Cost for 15 cum = a+b+c+d+e 126334.66
Rate per metre (a+b+c+d+e)/15 8422.31
say 8422.00
12.39 1100&17 Levelling Course for Pile cap
00
Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7146.39 29514.59
Coarse sand cum 6.75 1753.74 11837.71
40 mm aggregate cum 8.10 1419.49 11497.90
20 mm Aggregate cum 4.05 1822.49 7381.10
10 mm Aggregate cum 1.35 1367.49 1846.12
b) Labour
Mate day 0.86 639.10 549.63
Mason day 1.50 0.00 0.00
Mazdoor day 20.00 719.40 14388.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34
Generator 33 KVA hour 6.00 636.69 3820.16
d) Overhead charges @ 0.2 on (a+b+c) 16644.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 9986.95
Cost for 15 cum = a+b+c+d+e 109856.40
Rate per metre (a+b+c+d+e)/15 7324
say 7324.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing and
Technical Specifications.
Unit = 1 MT
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 52222.68 54833.81

Binding wire Kg 6.00 50.30 301.80


b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate day 0.40 639.10 255.64
Blacksmith day 2.00 729.30 1458.60
Mazdoor day 6.00 719.40 4316.40
12233.25
7339.95
80739.45
say 80739.00
CHAPTER-12
FOUNDATIONS

Remarks/
Input ref.

L-12
L-13

L-12
L-13

P&M-026

M-081
M-005
M-055
M-053
M-051
Remarks/
Input ref.

L-12
L-11
L-13

P&M-009
P&M-019

M-081
M-005
M-055
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-005
M-053
M-051
Remarks/
Input ref.

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-005
Remarks/
Input ref.

M-055
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-055
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.

M-081
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
Remarks/
Input ref.

P&M-007

M-081
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
Remarks/
Input ref.

P&M-050
Lead=
10.824610
098486 km
P&M-007

M-092
M-159

L-12
L-13

P&M-012

M-092
M-159
M-194
M-193

L-12
L-13

L-13
L-13
Remarks/
Input ref.

P&M-012

M-092
M-159

L-12
L-13

P&M-017
P&M-048

M-179

M-130

L-12
L-08
L-02
L-02
L-13
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.
Remarks/
Input ref.

M-081
M-004
M-053
M-051
M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
Lead=
10.824610
098486 ,
P&M-050
P&M-007

M-081
M-005
M-055
M-053
M-051
M-180

L-12
L-11
L-13
Remarks/
Input ref.

P&M-009
P&M-079
P&M-013

M-081
M-004
M-053
M-051
M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
Remarks/
Input ref.

M-005
M-055
M-053
M-051
M-180

L-12
L-11
L-13

P&M-009
P&M-079
P&M-013

M-081
M-004
M-053
M-051
M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.

M-081
M-005
M-055
M-053
M-051
M-180

L-12
L-11
L-13

P&M-009
P&M-079
P&M-013

M-081
M-004
M-053
M-051
M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
Remarks/
Input ref.

P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-005
M-055
M-053
M-051
M-180

L-12
L-11
L-13

P&M-009
P&M-079
P&M-013

M-081
M-004
M-053
M-051
Remarks/
Input ref.

M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.
Remarks/
Input ref.

M-081
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
Remarks/
Input ref.

M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051
Remarks/
Input ref.

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051
Remarks/
Input ref.

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
Remarks/
Input ref.

L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007

M-081
M-004
M-053
M-051
M-180

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017
P&M-049
P&M-050
Lead=
10.824610
098486 km
P&M-007
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
Remarks/
Input ref.

L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15

P&M-075
Remarks/
Input ref.

P&M-063

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063

M-104
M-094/100
Remarks/
Input ref.

L-12
L-06
L-03
L-13
L-15
L-07

P&M-075

P&M-063

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063
Remarks/
Input ref.

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15

P&M-075

P&M-063

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
Remarks/
Input ref.

L-14
L-07

P&M-075

P&M-063

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15
L-07

P&M-075

P&M-063

L-12
L-15
Remarks/
Input ref.

L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14
Remarks/
Input ref.

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15
Remarks/
Input ref.

P&M-075

P&M-063

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
Remarks/
Input ref.

L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
L-14
L-07

P&M-075

P&M-063
Remarks/
Input ref.

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15

P&M-075

P&M-063

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075
Remarks/
Input ref.

L-12
L-15
L-14

P&M-075

L-12
L-15
L-14

P&M-075

P&M-063
Remarks/
Input ref.

L-12
L-15
Remarks/
Input ref.

L-14
L-07

P&M-075

P&M-063

M-104
M-094/100

L-12
L-06
L-03
L-13
L-15

P&M-075

P&M-063
Remarks/
Input ref.

Item 12.8
(H)

M-082

M-104
M-094/100

L-16
L-19
L-12
L-06
L-03
L-13

L-15

L-07

P&M-082

P&M-038

P&M-001
P&M-072

P&M-066
P&M-066
P&M-079
P&M-048
Remarks/
Input ref.

M-006

L-12
L-13

M-179

L-12
L-08
L-01
L-02
L-13

Item 12.11
(C) iv

P&M-036
Remarks/
Input ref.

P&M-013

P&M-017
P&M-048

M-071

L-12
L-13

Item 12.11
(C) iv

P&M-036

P&M-013

P&M-017
P&M-048

M-071

L-12
L-13
Remarks/
Input ref.

Item 12.11
(C) iv

P&M-036

P&M-013

P&M-017
P&M-048

M-071

L-12
L-13

Item 12.11
(C) iv

M-080
M-124
M-173

P&M-085

P&M-070

L-12
L-13
Remarks/
Input ref.

Item 12.11
(C) iv

M-080
M-124
M-173

P&M-085

P&M-070

P&M-013

L-12
L-13
Remarks/
Input ref.

Item 12.11
(C) iv

M-080
M-124
M-173

P&M-085

P&M-070

L-12
L-13

Item 12.11
(F) iv

M-080
M-125
M-173

P&M-073
P&M-092

L-12
L-13
Remarks/
Input ref.

Item 12.11
(F) iv

M-080
M-125
M-173

P&M-074
P&M-092

L-12
L-13

Item 12.11
(F) iv

M-080
M-125
Remarks/
Input ref.

M-173

P&M-011
P&M-092

L-12
L-13

Item 12.11
(F) iv

M-080
M-125
M-173

P&M-071
P&M-092

L-12
L-13
Remarks/
Input ref.

Item 12.11
(F) iv

M-080
M-125
M-173

P&M-073
P&M-092

L-12
L-13

Item 12.11
(F) iv

M-080
M-125
M-173

P&M-073
P&M-092

L-12
L-13
Remarks/
Input ref.

M-179

P&M-071
P&M-092

L-12
L-13

M-179

P&M-071
P&M-092

L-12
L-13
Remarks/
Input ref.

M-081
M-005
M-053
M-051

L-12
L-10
L-13
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
L-10
L-13
L-13

P&M-002
P&M-080
P&M-017
Remarks/
Input ref.

P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007

M-081
M-005
M-053
M-051

L-12
L-10
L-13
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
L-10
L-13
L-13
Remarks/
Input ref.

P&M-002
P&M-018
P&M-017

P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007

M-081
M-005
M-053
M-051

L-12
L-10
L-13
L-13

P&M-009
P&M-079

M-081
M-004
M-053
M-051

L-12
Remarks/
Input ref.

L-10
L-13
L-13

P&M-002
P&M-080
P&M-017

P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007

M-081
M-005
M-053
M-051

L-12
L-10
L-13
L-13

P&M-009
P&M-079

M-081
M-004
Remarks/
Input ref.

M-053
M-051

L-12
L-10
L-13
L-13

P&M-002
P&M-018
P&M-017

P&M-049
Lead
=10.82461
0098486
km & P&M-
050
P&M-007

M-081
M-005
M-055
M-053
M-051

L-12
L-10
L-13

P&M-009
P&M-079
Remarks/
Input ref.

M-082

M-072

L-12
L-02
L-13
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 5974.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 597.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 1314.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 788.57
Rate perm (a+b+c+d+e+f) 8674.25
say 8674.00
13.6 Section Supplying, fitting and placing HYSD bar reinforcement in
1600 & sub-structure complete as per drawing and Technical
2200 Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 52222.68 54833.81 M-082

Binding wire kg 6.00 50.30 301.80 M-072


b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate day 0.34 639.10 217.29 L-12
Blacksmith day 2.00 729.30 1458.60 L-02
Mazdoor day 6.50 719.40 4676.10 L-13
c) Overhead charges @ 0.2 on (a+b) 12297.52
d) Contractor's profit @ 0.1 on (a+b+c) 7378.51
Rate for per MT (a+b+c+d) 81163.64
say 81164.00
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm dia
AC pipe, extending through the full width of the structure
with slope of 1V :20H towards drawing foce. Complete as
per drawing and Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 47.10 1483.65 M-056

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 20.00 600.00 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 4.71 47.10 M-056/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 6159.00 307.95 Item 12.6
(A)
b) Labour
Mate day 0.03 639.10 19.17 L-12
Mason day 0.50 947.10 473.55 L-11
Mazdoor day 0.25 719.40 179.85 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.2 on (a+b) 622.25
d) Contractor's profit @ 0.1 on (a+b+c) 373.35
Cost for 30 m = a+b+c+d 4106.88
Rate per m (a+b+c+d)/30 136.90
say 137.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 710.1.4. Back filling behind abutment, wing wall and return wall
of complete as per drawing and Technical Specification
IRC:78 &
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 639.10 178.95 L-12
Mazdoor day 7.00 719.40 5035.80 L-13
b) Material
Granular material cum 12.00 745.49 8945.93 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 178.27 445.69 P&M-086
Water Tanker hour 0.05 530.19 26.51 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 2926.57
e) Contractor's profit @ 0.1 on (a+b+c+d) 1755.94
Cost for 10 cum of granular backfill = a+b+c+d+e 19315.39
Rate per cum = (a+b+c+d+e)/10 1931.54
say 1932.00
13.10 710.1.4. Providing and laying of Filter media with granular
of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of MoRTH
and specifications to a thickness of not less than 600 mm with
2200 smaller size towards the soil and bigger size towards the
wall and provided over the entire surface behind abutment,
wing wall and return wall to the full height compacted to a
firm condition complete as per drawing and Technical
Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 639.10 204.51 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 719.40 5035.80 L-13
Mazdoor (Skilled) day 1.00 698.50 698.50 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1082.49 12989.93 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 530.19 31.81 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 3792.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 2275.27
cost for 10 cum of Fiter Media = a+b+c+d+e 25027.93
Rate per cum = (a+b+c+d+e)/10 2502.79
say 2503.00
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7146.39 36589.52 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.86 639.10 549.63 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 18628.40
e) Overhead charges @ 0.2 on (a+b+c+d) 22354.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13412.45
Cost for 15 cum = a+b+c+d+e+f 147536.93
Rate per cum = (a+b+c+d+e+f)/15 9835.80
say 9836.00
14.1A (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 23285.50
e) Overhead charges @ 0.2 on (a+b+c+d) 23285.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13971.30
Cost for 15 cum = a+b+c+d+e+f 153684.30
Rate per cum = (a+b+c+d+e+f)/15 10245.62
say 10246.00
14.1A (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 27942.60
e) Overhead charges @ 0.2 on (a+b+c+d) 24216.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14530.15
Cost for 15 cum = a+b+c+d+e+f 159831.67
Rate per cum = (a+b+c+d+e+f)/15 10655.44
say 10655.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 23285.50
e) Overhead charges @ 0.2 on (a+b+c+d) 23285.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13971.30
Cost for 15 cum = a+b+c+d+e+f 153684.30
Rate per cum = (a+b+c+d+e+f)/15 10245.62
say 10246.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 27942.60
e) Overhead charges @ 0.2 on (a+b+c+d) 24216.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14530.15
Cost for 15 cum = a+b+c+d+e+f 159831.67
Rate per cum = (a+b+c+d+e+f)/15 10655.44
say 10655.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 93142.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 32599.70
e) Overhead charges @ 0.2 on (a+b+c+d) 25148.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15089.00
Cost for 15 cum = a+b+c+d+e+f 165979.04
Rate per cum = (a+b+c+d+e+f)/15 11065.27
say 11065.00
14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7146.39 292430.28 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.84 639.10 536.84 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 18.00 719.40 12949.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 132105.60
e) Overhead charges @ 0.2 on (a+b+c+d) 158526.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95116.03
Cost for 120 cum = a+b+c+d+e+f 1046276.35
Rate per cum = (a+b+c+d+e+f)/120 8718.97
say 8719.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 165132.00
e) Overhead charges @ 0.2 on (a+b+c+d) 165132.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 99079.20
Cost for 120 cum = a+b+c+d+e+f 1089871.20
Rate per cum = (a+b+c+d+e+f)/120 9082.26
say 9082.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 198158.40
e) Overhead charges @ 0.2 on (a+b+c+d) 171737.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103042.37
Cost for 120 cum = a+b+c+d+e+f 1133466.05
Rate per cum = (a+b+c+d+e+f)/120 9445.55
say 9446.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 165132.00
e) Overhead charges @ 0.2 on (a+b+c+d) 165132.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 99079.20
Cost for 120 cum = a+b+c+d+e+f 1089871.20
Rate per cum = (a+b+c+d+e+f)/120 9082.26
say 9082.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 198158.40
e) Overhead charges @ 0.2 on (a+b+c+d) 171737.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103042.37
Cost for 120 cum = a+b+c+d+e+f 1133466.05
Rate per cum = (a+b+c+d+e+f)/120 9445.55
say 9446.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 660528.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 231184.80
e) Overhead charges @ 0.2 on (a+b+c+d) 178342.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107005.54
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 120 cum = a+b+c+d+e+f 1177060.90
Rate per cum = (a+b+c+d+e+f)/120 9808.84
say 9809.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7146.39 42806.88 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.86 639.10 549.63 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 19872.00
e) Overhead charges @ 0.2 on (a+b+c+d) 23846.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14307.84
Cost for 15 cum = a+b+c+d+e+f 157386.24
Rate per cum = (a+b+c+d+e+f)/15 10492.42
say 10492.00
14.1B (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 24840.00
e) Overhead charges @ 0.2 on (a+b+c+d) 24840.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14904.00
Cost for 15 cum = a+b+c+d+e+f 163944.00
Rate per cum = (a+b+c+d+e+f)/15 10929.60
say 10930.00
14.1B (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 29808.00
e) Overhead charges @ 0.2 on (a+b+c+d) 25833.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15500.16
Cost for 15 cum = a+b+c+d+e+f 170501.76
Rate per cum = (a+b+c+d+e+f)/15 11366.78
say 11367.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Formwork and staging 25 per cent of (a+b+c) 25.00 24840.00
e) Overhead charges @ 0.2 on (a+b+c+d) 24840.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14904.00
Cost for 15 cum = a+b+c+d+e+f 163944.00
Rate per cum = (a+b+c+d+e+f)/15 10929.60
say 10930.00
14.1B (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 29808.00
e) Overhead charges @ 0.2 on (a+b+c+d) 25833.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15500.16
Cost for 15 cum = a+b+c+d+e+f 170501.76
Rate per cum = (a+b+c+d+e+f)/15 11366.78
say 11367.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 99360.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 34776.00
e) Overhead charges @ 0.2 on (a+b+c+d) 26827.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16096.32
Cost for 15 cum = a+b+c+d+e+f 177059.52
Rate per cum = (a+b+c+d+e+f)/15 11803.97
say 11804.00
14.1B Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 7146.39 342669.40 M-081
Coarse sand cum 54.20 1670.49 90540.77 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.84 639.10 536.84 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 18.00 719.40 12949.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 142220.20
e) Overhead charges @ 0.2 on (a+b+c+d) 170664.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 102398.54
Cost for 120 cum = a+b+c+d+e+f 1126383.98
Rate per cum = (a+b+c+d+e+f)/120 9386.53
say 9387.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 177775.25
e) Overhead charges @ 0.2 on (a+b+c+d) 177775.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106665.15
Cost for 120 cum = a+b+c+d+e+f 1173316.65
Rate per cum = (a+b+c+d+e+f)/120 9777.64
say 9778.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 213330.30
e) Overhead charges @ 0.2 on (a+b+c+d) 184886.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110931.76
Cost for 120 cum = a+b+c+d+e+f 1220249.32
Rate per cum = (a+b+c+d+e+f)/120 10168.74
say 10169.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 177775.25
e) Overhead charges @ 0.2 on (a+b+c+d) 177775.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106665.15
Cost for 120 cum = a+b+c+d+e+f 1173316.65
Rate per cum = (a+b+c+d+e+f)/120 9777.64
say 9778.00
14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 213330.30
e) Overhead charges @ 0.2 on (a+b+c+d) 184886.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110931.76
Cost for 120 cum = a+b+c+d+e+f 1220249.32
Rate per cum = (a+b+c+d+e+f)/120 10168.74
say 10169.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 711101.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 248885.35
e) Overhead charges @ 0.2 on (a+b+c+d) 191997.27
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 115198.36
Cost for 120 cum = a+b+c+d+e+f 1267181.98
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/120 10559.85
say 10560.00
14.1 C RCC Grade M 30
14.1C Case II Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7146.39 348672.37 M-081
Coarse sand cum 54.60 1670.49 91208.97 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.88 639.10 562.41 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 19.00 719.40 13668.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 143703.40
e) Overhead charges @ 0.2 on (a+b+c+d) 172444.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103466.45
Cost for 120 cum = a+b+c+d+e+f 1138130.93
Rate per cum = (a+b+c+d+e+f)/120 9484.42
say 9484.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 179629.25
e) Overhead charges @ 0.2 on (a+b+c+d) 179629.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107777.55
Cost for 120 cum = a+b+c+d+e+f 1185553.05
Rate per cum = (a+b+c+d+e+f)/120 9879.61
say 9880.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 215555.10
e) Overhead charges @ 0.2 on (a+b+c+d) 186814.42
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112088.65
Cost for 120 cum = a+b+c+d+e+f 1232975.17
Rate per cum = (a+b+c+d+e+f)/120 10274.79
say 10275.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 179629.25
e) Overhead charges @ 0.2 on (a+b+c+d) 179629.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107777.55
Cost for 120 cum = a+b+c+d+e+f 1185553.05
Rate per cum = (a+b+c+d+e+f)/120 9879.61
say 9880.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 215555.10
e) Overhead charges @ 0.2 on (a+b+c+d) 186814.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112088.65
Cost for 120 cum = a+b+c+d+e+f 1232975.17
Rate per cum = (a+b+c+d+e+f)/120 10274.79
say 10275.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 718517.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 251480.95
e) Overhead charges @ 0.2 on (a+b+c+d) 193999.59
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116399.75
Cost for 120 cum = a+b+c+d+e+f 1280397.29
Rate per cum = (a+b+c+d+e+f)/120 10669.98
say 10670.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7146.39 45236.65 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
b) Labour
Mate day 0.90 639.10 575.19 L-12
Mason day 1.50 947.10 1420.65 L-11
Mazdoor day 21.00 719.40 15107.40 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case I
(p) Height upto 5m
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 18456.12
e) Overhead charges @ 0.2 on (a+b+c+d) 24198.02
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14518.81
Cost for 15 cum = a+b+c+d+e+f 159706.96
Rate per cum = (a+b+c+d+e+f)/15 10647.13
say 10647.00
14.1D (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00


15 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 23582.82
e) Overhead charges @ 0.2 on (a+b+c+d) 25223.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15134.02
Cost for 15 cum = a+b+c+d+e+f 166474.20
Rate per cum = (a+b+c+d+e+f)/15 11098.28
say 11098.00
14.1D (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00


15 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 28709.52
e) Overhead charges @ 0.2 on (a+b+c+d) 26248.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15749.22
Cost for 15 cum = a+b+c+d+e+f 173241.45
Rate per cum = (a+b+c+d+e+f)/15 11549.43
say 11549.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 23582.82
e) Overhead charges @ 0.2 on (a+b+c+d) 25223.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15134.02
Cost for 15 cum = a+b+c+d+e+f 166474.20
Rate per cum = (a+b+c+d+e+f)/15 11098.28
say 11098.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 28709.52
e) Overhead charges @ 0.2 on (a+b+c+d) 26248.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15749.22
Cost for 15 cum = a+b+c+d+e+f 173241.45
Rate per cum = (a+b+c+d+e+f)/15 11549.43
say 11549.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 33836.22
e) Overhead charges @ 0.2 on (a+b+c+d) 27274.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16364.43
Cost for 15 cum = a+b+c+d+e+f 180008.69
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/15 12000.58
say 12001.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case I cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 38962.92
e) Overhead charges @ 0.2 on (a+b+c+d) 28299.38
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16979.63
Cost for 15 cum = a+b+c+d+e+f 186775.93
Rate per cum = (a+b+c+d+e+f)/15 12451.73
say 12452.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 49216.32
e) Overhead charges @ 0.2 on (a+b+c+d) 30350.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 18210.04
Cost for 15 cum = a+b+c+d+e+f 200310.42
Rate per cum = (a+b+c+d+e+f)/15 13354.03
say 13354.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 102534.00
15 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 59469.72
e) Overhead charges @ 0.2 on (a+b+c+d) 32400.74
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 19440.45
Cost for 15 cum = a+b+c+d+e+f 213844.91
Rate per cum = (a+b+c+d+e+f)/15 14256.33
say 14256.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7146.39 361893.19 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
b) Labour
Mate day 0.88 639.10 562.41 L-12
Mason day 3.00 947.10 2841.30 L-11
Mazdoor day 19.00 719.40 13668.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 131532.48
e) Overhead charges @ 0.2 on (a+b+c+d) 172453.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 103472.22
Cost for 120 cum = a+b+c+d+e+f 1138194.39
Rate per cum = (a+b+c+d+e+f)/120 9484.95
say 9485.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 168069.28
e) Overhead charges @ 0.2 on (a+b+c+d) 179761.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107856.63
Cost for 120 cum = a+b+c+d+e+f 1186422.97
Rate per cum = (a+b+c+d+e+f)/120 9886.86
say 9887.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 204606.08
e) Overhead charges @ 0.2 on (a+b+c+d) 187068.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112241.05
Cost for 120 cum = a+b+c+d+e+f 1234651.55
Rate per cum = (a+b+c+d+e+f)/120 10288.76
say 10289.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 168069.28
e) Overhead charges @ 0.2 on (a+b+c+d) 179761.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 107856.63
Cost for 120 cum = a+b+c+d+e+f 1186422.97
Rate per cum = (a+b+c+d+e+f)/120 9886.86
say 9887.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 204606.08
e) Overhead charges @ 0.2 on (a+b+c+d) 187068.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112241.05
Cost for 120 cum = a+b+c+d+e+f 1234651.55
Rate per cum = (a+b+c+d+e+f)/120 10288.76
say 10289.00
14.1D (r) Height above 10m
Case II
(ii)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 241142.88
e) Overhead charges @ 0.2 on (a+b+c+d) 194375.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116625.47
Cost for 120 cum = a+b+c+d+e+f 1282880.12
Rate per cum = (a+b+c+d+e+f)/120 10690.67
say 10691.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case II cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 277679.68
e) Overhead charges @ 0.2 on (a+b+c+d) 201683.14
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 121009.88
Cost for 120 cum = a+b+c+d+e+f 1331108.70
Rate per cum = (a+b+c+d+e+f)/120 11092.57
say 11093.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 350753.28
e) Overhead charges @ 0.2 on (a+b+c+d) 216297.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 129778.71
Cost for 120 cum = a+b+c+d+e+f 1427565.85
Rate per cum = (a+b+c+d+e+f)/120 11896.38
say 11896.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 730736.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 423826.88
e) Overhead charges @ 0.2 on (a+b+c+d) 230912.58
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 138547.55
Cost for 120 cum = a+b+c+d+e+f 1524023.00
Rate per cum = (a+b+c+d+e+f)/120 12700.19
say 12700.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 7146.39 46094.22 M-081
Coarse sand cum 6.75 1753.74 11837.71 M-005
20 mm Aggregate cum 8.10 1822.49 14762.20 M-053
10 mm Aggregate cum 5.40 1367.49 7384.47 M-051
Admixture @ 0.4 per cent of cement kg 25.80 179.00 4618.20 M-180
b) Labour
Mate day 0.96 639.10 613.54 L-12
Mason day 2.00 947.10 1894.20 L-11
Mazdoor day 22.00 719.40 15826.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 398.22 2389.34 P&M-009
Generator 33 KVA hour 6.00 636.69 3820.16 P&M-079
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 21848.20
e) Overhead charges @ 0.2 on (a+b+c+d) 26217.84
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15730.70
Cost for 15 cum = a+b+c+d+e+f 173037.74
Rate per cum = (a+b+c+d+e+f)/15 11535.85
say 11536.00
14.1E (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 27310.25
e) Overhead charges @ 0.2 on (a+b+c+d) 27310.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16386.15
Cost for 15 cum = a+b+c+d+e+f 180247.65
Rate per cum = (a+b+c+d+e+f)/15 12016.51
say 12017.00
14.1E (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 32772.30
e) Overhead charges @ 0.2 on (a+b+c+d) 28402.66
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 17041.60
Cost for 15 cum = a+b+c+d+e+f 187457.56
Rate per cum = (a+b+c+d+e+f)/15 12497.17
say 12497.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 27310.25
e) Overhead charges @ 0.2 on (a+b+c+d) 27310.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16386.15
Cost for 15 cum = a+b+c+d+e+f 180247.65
Rate per cum = (a+b+c+d+e+f)/15 12016.51
say 12017.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 32772.30
e) Overhead charges @ 0.2 on (a+b+c+d) 28402.66
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 17041.60
Cost for 15 cum = a+b+c+d+e+f 187457.56
Rate per cum = (a+b+c+d+e+f)/15 12497.17
say 12497.00
14.1E (r) Height above 10m
Case I
(ii)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 109241.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 38234.35
e) Overhead charges @ 0.2 on (a+b+c+d) 29495.07
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 17697.04
Cost for 15 cum = a+b+c+d+e+f 194667.46
Rate per cum = (a+b+c+d+e+f)/15 12977.83
say 12978.00
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7146.39 368753.72 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
Admixture @ 0.4 per cent of cement kg 206.40 179.00 36945.60 M-180
b) Labour
Mate day 0.94 639.10 600.75 L-12
Mason day 3.50 947.10 3314.85 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 775773.00
cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 775773.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 139639.14
e) Overhead charges @ 0.2 on (a+b+c+d) 183082.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 109849.46
Cost for 15 cum = a+b+c+d+e+f 1208344.02
Rate per cum = (a+b+c+d+e+f)/120 10069.53
say 10070.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 178427.79
e) Overhead charges @ 0.2 on (a+b+c+d) 190840.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 114504.09
Cost for 120 cum = a+b+c+d+e+f 1259545.04
Rate per cum = (a+b+c+d+e+f)/120 10496.21
say 10496.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 217216.44
e) Overhead charges @ 0.2 on (a+b+c+d) 198597.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119158.73
Cost for 120 cum = a+b+c+d+e+f 1310746.06
Rate per cum = (a+b+c+d+e+f)/120 10922.88
say 10923.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 178427.79
e) Overhead charges @ 0.2 on (a+b+c+d) 190840.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 114504.09
Cost for 120 cum = a+b+c+d+e+f 1259545.04
Rate per cum = (a+b+c+d+e+f)/120 10496.21
say 10496.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 217216.44
e) Overhead charges @ 0.2 on (a+b+c+d) 198597.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119158.73
Cost for 120 cum = a+b+c+d+e+f 1310746.06
Rate per cum = (a+b+c+d+e+f)/120 10922.88
say 10923.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 256005.09
e) Overhead charges @ 0.2 on (a+b+c+d) 206355.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 123813.37
Cost for 120 cum = a+b+c+d+e+f 1361947.08
Rate per cum = (a+b+c+d+e+f)/120 11349.56
say 11350.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 294793.74
e) Overhead charges @ 0.2 on (a+b+c+d) 214113.35
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 128468.01
Cost for 120 cum = a+b+c+d+e+f 1413148.10
Rate per cum = (a+b+c+d+e+f)/120 11776.23
say 11776.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 372371.04
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.2 on (a+b+c+d) 229628.81
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 137777.28
Cost for 120 cum = a+b+c+d+e+f 1515550.13
Rate per cum = (a+b+c+d+e+f)/120 12629.58
say 12630.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 775773.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 449948.34
e) Overhead charges @ 0.2 on (a+b+c+d) 245144.27
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 147086.56
Cost for 120 cum = a+b+c+d+e+f 1617952.17
Rate per cum = (a+b+c+d+e+f)/120 13482.93
say 13483.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 7146.39 398768.56 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
Admixture @ 0.4 per cent of cement kg 223.20 179.00 39952.80 M-180
b) Labour
Mate day 0.94 639.10 600.75 L-12
Mason day 3.50 947.10 3314.85 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per cent
of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 129407.20
e) Overhead charges @ 0.2 on (a+b+c+d) 187640.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112584.26
Cost for 120 cum = a+b+c+d+e+f 1238426.90
Rate per cum = (a+b+c+d+e+f)/120 10320.22
say 10320.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 169846.95
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.2 on (a+b+c+d) 195728.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117437.03
Cost for 120 cum = a+b+c+d+e+f 1291807.37
Rate per cum = (a+b+c+d+e+f)/120 10765.06
say 10765.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 210286.70
e) Overhead charges @ 0.2 on (a+b+c+d) 203816.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122289.80
Cost for 120 cum = a+b+c+d+e+f 1345187.84
Rate per cum = (a+b+c+d+e+f)/120 11209.90
say 11210.00
14.1F (ii) For T-beam & slab including launching of precast girders by
launching truss upto 40 m span, 21-31 per cent of cost of
concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 169846.95
e) Overhead charges @ 0.2 on (a+b+c+d) 195728.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117437.03
Cost for 120 cum = a+b+c+d+e+f 1291807.37
Rate per cum = (a+b+c+d+e+f)/120 10765.06
say 10765.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 210286.70
e) Overhead charges @ 0.2 on (a+b+c+d) 203816.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122289.80
Cost for 120 cum = a+b+c+d+e+f 1345187.84
Rate per cum = (a+b+c+d+e+f)/120 11209.90
say 11210.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 250726.45
e) Overhead charges @ 0.2 on (a+b+c+d) 211904.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 127142.57
Cost for 120 cum = a+b+c+d+e+f 1398568.31
Rate per cum = (a+b+c+d+e+f)/120 11654.74
say 11655.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 36 per cent of (a+b+c) 36.00 291166.20
e) Overhead charges @ 0.2 on (a+b+c+d) 219992.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 131995.34
Cost for 120 cum = a+b+c+d+e+f 1451948.78
Rate per cum = (a+b+c+d+e+f)/120 12099.57
say 12100.00
14.1F (q) Height 5m to 10m
(iii)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 46 per cent of (a+b+c) 46.00 372045.70
e) Overhead charges @ 0.2 on (a+b+c+d) 236168.14
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 141700.88
Cost for 120 cum = a+b+c+d+e+f 1558709.72
Rate per cum = (a+b+c+d+e+f)/120 12989.25
say 12989.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 808795.00
120 cum
d) Formwork and staging 56 per cent of (a+b+c) 56.00 452925.20
e) Overhead charges @ 0.2 on (a+b+c+d) 252344.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 151406.42
Cost for 120 cum = a+b+c+d+e+f 1665470.66
Rate per cum = (a+b+c+d+e+f)/120 13878.92
say 13879.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 7146.39 420207.73 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
Admixture @ 0.4 per cent of cement kg 235.20 179.00 42100.80 M-180
b) Labour
Mate day 0.94 639.10 600.75 L-12
Mason day 3.50 947.10 3314.85 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 832382.00
120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 832382.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 291333.70
e) Overhead charges @ 0.2 on (a+b+c+d) 224743.14
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 134845.88
Cost for 120 cum = a+b+c+d+e+f 1483304.72
Rate per cum = (a+b+c+d+e+f)/120 12360.87
say 12361.00
14.1G (q) Height 5m to 10m
(i)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 832382.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 374571.90
e) Overhead charges @ 0.2 on (a+b+c+d) 241390.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 144834.47
Cost for 120 cum = a+b+c+d+e+f 1593179.15
Rate per cum = (a+b+c+d+e+f)/120 13276.49
say 13276.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 832382.00
120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 457810.10
e) Overhead charges @ 0.2 on (a+b+c+d) 258038.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 154823.05
Cost for 120 cum = a+b+c+d+e+f 1703053.57
Rate per cum = (a+b+c+d+e+f)/120 14192.11
say 14192.00
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 7146.39 453795.77 M-081
Coarse sand cum 54.00 1670.49 90206.68 M-004
20 mm Aggregate cum 64.80 1822.49 118097.61 M-053
10 mm Aggregate cum 43.20 1367.49 59075.74 M-051
Admixture @ 0.4 per cent of cement kg 254.00 179.00 45466.00 M-180
b) Labour
Mate day 0.94 639.10 600.75 L-12
Mason day 3.50 947.10 3314.85 L-11
Mazdoor day 20.00 719.40 14388.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 3133.69 18802.15 P&M-002
Generator 100 KVA hour 6.00 1193.51 7161.07 P&M-080
Loader hour 6.00 1379.89 8279.33 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1591.73 23876.02 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.28 23645.69 Lead
=10.82461
0098486
km & P&M-
050
Concrete Pump hour 6.00 437.58 2625.49 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 869336.00
120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 869336.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 304267.60
e) Overhead charges @ 0.2 on (a+b+c+d) 234720.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 140832.43
Cost for 120 cum = a+b+c+d+e+f 1549156.75
Rate per cum = (a+b+c+d+e+f)/120 12909.64
say 12910.00
14.1H (q) Height 5m to 10m
(i)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 869336.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 391201.20
e) Overhead charges @ 0.2 on (a+b+c+d) 252107.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 151264.46
Cost for 120 cum = a+b+c+d+e+f 1663909.10
Rate per cum = (a+b+c+d+e+f)/120 13865.91
say 13866.00
14.1H (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 869336.00
120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 478134.80
e) Overhead charges @ 0.2 on (a+b+c+d) 269494.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 161696.50
Cost for 120 cum = a+b+c+d+e+f 1778661.46
Rate per cum = (a+b+c+d+e+f)/120 14822.18
say 14822.00
Note 1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4 per cent of weight of cement may be added for
achieving desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
separately in the rate analysis.
14.2 1600 Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 52222.68 54833.81 M-082

Binding wire Kg 8.00 50.30 402.40 M-072


b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 639.10 281.20 L-12
Blacksmith day 3.00 729.30 2187.90 L-02
Mazdoor day 8.00 719.40 5755.20 L-13
Basic Cost of Labour & Material (a+b) 63461.00
c) Overhead charges @ 0.2 on (a+b) 12692.10
d) Contractor's profit @ 0.1 on (a+b+c) 7615.26
Rate per MT = a+b+c+d 83767.88
say 83768.00
14.9 2705 Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 41.20 164.80 M-
wastage 087/1000
GI pipe 100mm dia metre 6.00 47.10 282.60 M-056
GI bolt 10 mm Dia each 6.00 7.00 42.00 M-110
Galvanised MS flat clamp each 2.00 37.00 74.00 M-101
b) Labour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
For fabrication
Mate day 0.02 639.10 12.78 L-12
Skilled (Blacksmith, welder etc.) day 0.02 729.30 14.59 L-02
Mazdoor day 0.02 719.40 14.39 L-13
For fixing in position
Mate day 0.01 639.10 6.39 L-12
Mason day 0.01 947.10 9.47 L-11
Mazdoor day 0.20 719.40 143.88 L-13
Add @ 5 per cent of cost of material and labour for 38.24
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
c) Overhead charges @ 0.2 on (a+b) 160.63
d) Contractor's profit @ 0.1 on (a+b+c) 96.38
Rate per metre (a+b+c+d) 1060
say 2163.00
Note 1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from
the drainage spout on the structure.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 7450.00 7450.00 Item 12.8
formworks (A)
Rate per cum say 7450.00
14.11 1500,16
00,1700
& 2704
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 5974.00 5974.00 Item 12.8
concrete in item 12.8(G)by using batching plant, (G)
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) 119.48
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 63459.00 3172.95 Item 14.2 A
14.2(Excluding OH & CP)
b) Overhead charges @ 0.2 on (a) 1853.29
c) Contractor's profit @ 0.1 on(a+b) 1111.97
Rate per cum (a+b+c) 12232
say 12232.00
Note The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.

14.16 800 Painting on concrete surface


Providing and applying 2 coats of water based cement paint
to unplastered concrete surface after cleaning the surface of
dirt, dust, oil, grease, efflorescence and applying paint @ of
1 litre for 2 sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.01 639.10 6.39 L-12
Painter day 0.25 756.80 189.20 L-18
Mazdoor (Skilled) day 0.25 698.50 174.63 L-15
b) Material
Water based paint of approved quality for cement Litres 5.00 250.00 1250.00 M-190
concrete surface
c) Overhead charges @ 0.2 on (a+b) 324.04
d) Contractor's profit @ 0.1 on (a+b+c) 194.43
Cost for 10 sqm (a+b+c+d) 2138.69
Rate per sqm (a+b+c+d)/10 213.87
say 214.00
14.18 (ii) Providing & fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 639.10 5.11 L-12
Mazdoor day 0.10 719.40 71.94 L-13
Mazdoor (Skilled) day 0.10 698.50 69.85 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 sqm 3.00 550.00 1650.00 M-084
cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 0.2 on (a+b) 359.38
d) Contractor's profit @ 0.1 on (a+b+c) 215.63
Cost for 12 m = (a+b+c+d) 2371.91
Rate per m = (a+b+c+d)/12 197.66
say 198.00
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.4 2504 Providing and laying Pitching on slopes laid over prepared
filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 745.49 745.49 M-003
Stone spalls of minimum 25 mm size cum 0.20 614.56 122.91 M-008
b) Labour
Mate day 0.04 639.10 25.56 L-12
Mason day 0.35 947.10 331.49 L-11
Mazdoor day 0.75 719.40 539.55 L-13
c) Overhead charges @ 0.2 on (a+b) 353.00
d) Contractor's profit @ 0.1 on (a+b+c) 211.80
Rate per cum = (a+b+c+d) 2329.81
say 2330.00
15.5 2504 Providing and laying Filter material underneath pitching in
slopes complete as per drawing and Technical specification

Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 1082.49 1298.99 M-012
b) Labour
Mate day 0.05 639.10 31.96 L-12
Mazdoor (Skilled) day 0.25 698.50 174.63 L-15
Mazdoor * day 1.00 719.40 719.40 L-13
c) Overhead charges @ 0.2 on (a+b) 444.99
d) Contractor's profit @ 0.1 on (a+b+c) 267.00
Rate per cum = (a+b+c+d) 2936.96
say 2937.00
Includes Mazdoor required for trimming of slope to proper
profile and preparation of bed.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than
40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 745.49 745.49 M-003
Stone Spalls cum 0.20 614.56 122.91 M-008
b) Labour
Mate day 0.05 639.10 31.96 L-12
Mason day 0.25 947.10 236.78 L-11
Mazdoor day 1.00 719.40 719.40 L-13
Add 1 per cent of cost of (a+b) for trimming and 18.57
preparation of bed.
c) Overhead charges @ 0.2 on (a+b) 375.02
d) Contractor's profit @ 0.1 on (a+b+c) 225.01
Rate per cum = (a+b+c+d) 2475.13
say 2475.00
Preparation of Detailed Project Report for Rehabilitation and Upgradation DDPR
to 4 lane with paved shoulder configuration of National Highway 227 Volume 6: Rate Analysis
in the state of Tamil Nadu. Annexures

CHAPTER-16
REPAIR AND REHABILITATION
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.18 Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.20 639.10 127.82 L-12
Mazdoor day 5.00 719.40 3597.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 620.49 620.49 P&M-053
c) Overhead charges @ 0.2 on (a+b) 869.06
d) Contractor's profit @ 0.1 on (a+b+c) 521.44
Cost for 10 m = a+b+c+d 5735.81
Rate per metre = (a+b+c+d)/10 573.58
say 574.00
Note The rate for the provision of new railing may be adopted
from the chapter on superstructure.

Aarvee Associates In Association With


Vax Consultants Pvt. Ltd., 1 of 277
Rate Analysis done as per adjacent site approved by NHAI PIU, Kanchipuram
Single Arm Lighting for Main Carriageway with Minimum
11 Lux(Pole to Pole spacing 30 mtrs) Unit Qty. Rate Amount

Earth Work in Excavation of foundation of structure as


per drawing and technical specification,including setting
out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of sides
and bottom, backfilling the excavation earth to the extent
required and utilizing the remaining earth locally for road
11.1 work. Excavation for single Arm in Cum 21 67 1407
11.2 Providing of RCC M20 for poles: Cum 21 7507 157647
9 mtr Length Bracket Pole with Base Plate
(300x300x6mm) of relevent specifications as 114.3 mm
OD x 5.40mm thick 88.9mm OD x 4.85mm
Thick x 2000mm Length 76.10mm
11.3 OD x 3.25mm thick x 2000mm Length Nos. 14 13390 187460
11.4 LED Outdoor fittings 150W Nos. 14 17010 238140
Installation Charges including labor, transport &
11.5 machinery for fixing of new Poles Nos. 14 10000 140000
11.6 Installation of new EB meter panels with all fittings Nos. 1 15000 15000
11.7 Installation of new feeder pillars with all fittings Nos. 1 65000 65000
Laying of electrical cables 31/2 core 35 Sq.mm PVC
armoured UG Cable-EB Transformer to meter panels &
11.8 feeder Pillars RM 150 227.9 34185
Laying of electrical cables 31/2 core 35 Sq.mm PVC
11.9 armoured UG Cable- feeder Pillars to DA Pole RM 30 227.9 6837
12 4 core 16 sqmm. PVC Armoured UG Cable- DA Pole RM 420 160.1 67242
12.1 36/0.3 (2.5 sq.mm)- Pole wiring RM 210 20.8 4368
12.2 Providing electrical fixures & cable in electricle poles: Nos. 14 571 7994
Electrical consumption charges for lightning purposes (4
years) 5765.8 4 23063
925280
This is for Single Arm inclusive of 4 years maintenance
cost 66091.43
This is for Double Arm inclusive of 4 years maintenance
cost 83101

You might also like