Bongawan Bridge - Estimated Qty Steel Bar

RC bar, tonne
Concreted
Boring Not Length of
Pile Total Length, Boring to Not Exceeding Exceeding Total Length, m Cut Off Pile,
Item Location Date through Exceeding Temporary
Dia., m m earth, m 20mm 20mm Tonnage, t (Pile Length nr
Rock, m 20mm Casing, m
(main bar) (main bar) Basis)
(Helical)
1 Abutment A, Pile No. 1 20.08.2019 0.90 26.80 20.80 6.00 0.00 2.81 0.70 3.51 26.80 16.00

2 Abutment B, Pile No. 1 14.09.2019 0.90 25.00 19.00 6.00 0.00 2.67 0.66 3.33 25.00 12.50

A Total Remeasurement Qty 51.80 39.80 12.00 0.00 5.48 1.36 6.84 51.80 0 28.50