2. Pekerjaan Sloof
Beton k175 = 0,65 m3
Semen 0,65 x 1/6 = 0.1 m3
0.1 m3 semen adalah 0.1 / 0.024 = 4 zak
Pasir = 2 x 0.1 = 0.2 m3
Split = 3 x 0.06 = 0. 3 m3
Besi
Besi utama diameter 10 = 4x 21,5 = 86 m = 86 /12 = 7 btg
Beugel diameter 8 = 144 x 0,6 = 86,4 m = 86,4/12 = 7 btg
3. Pekerjaan kolom
Beton k175 = 1,08 m3
Semen 1,08 x 1/6 = 0.18 m3
0,18 m3 semen adalah 0,18/ 0.024 = 7,5 zak
Pasir = 2 x 0.18 = 0.35 m3
Split = 3 x 0.18 = 0.54 m3
Besi
Besi utama diameter 10 = 16 x 3,5 = 56 m = 56 /12 = 5 btg
Besi utama diameter 10 = 44 x 2,5 = 110 m = 110 /12 = 9 btg
Besi utama diameter 10 = 4 x 3,5 = 14 m = 14 /12 = 2 btg
Beugel diameter 8 = 93 x 0,5 = 46,5 m = 46,5/12 = 4 btg
Beugel diameter 8 = 183 x 0,5 = 91,5 m = 91,5/12 = 8 btg
Beugel diameter 8 = 23 x 0,7 = 16 m = 16/12 = 2 btg
4. Pekerjaan balok
Beton k175 = 1,15 m3
Semen 1,15 x 1/6 = 0.19 m3
0.19 m3 semen adalah 0.19 / 0.024 = 8 zak
Pasir = 2 x 0.19 = 0.4 m3
Split = 3 x 0.19 = 0. 6 m3
Besi
Besi utama diameter 10 = 4x 38,4 = 153,5m = 153,5 /12 = 13 btg
Beugel diameter 8 = 256 x 0,6 = 153,5 m = 153,5/12 = 13 btg
9. Keramik 50x50 = 41 m2
Keramik = 41/0,25 = 164 bh keramik
1 dus berisi 4 bh maka 164/4 = 41 kotak/dus
Total = Rp 51.870.000