1.

Untuk pondasi = 5,4 kubik


Batu kali = 5,4 x 1,2 = 6,5 kubik
Semen Portland = 202 x 5,4 = 1090 kg = 22 zak (50kg/zak)
Pasir = 0,485 x 5,4 = 2,5 kubik

2. Pekerjaan Sloof
 Beton k175 = 0,65 m3
Semen 0,65 x 1/6 = 0.1 m3
0.1 m3 semen adalah 0.1 / 0.024 = 4 zak
Pasir = 2 x 0.1 = 0.2 m3
Split = 3 x 0.06 = 0. 3 m3

 Besi
Besi utama diameter 10 = 4x 21,5 = 86 m = 86 /12 = 7 btg
Beugel diameter 8 = 144 x 0,6 = 86,4 m = 86,4/12 = 7 btg

3. Pekerjaan kolom
 Beton k175 = 1,08 m3
Semen 1,08 x 1/6 = 0.18 m3
0,18 m3 semen adalah 0,18/ 0.024 = 7,5 zak
Pasir = 2 x 0.18 = 0.35 m3
Split = 3 x 0.18 = 0.54 m3

 Besi
Besi utama diameter 10 = 16 x 3,5 = 56 m = 56 /12 = 5 btg
Besi utama diameter 10 = 44 x 2,5 = 110 m = 110 /12 = 9 btg
Besi utama diameter 10 = 4 x 3,5 = 14 m = 14 /12 = 2 btg
Beugel diameter 8 = 93 x 0,5 = 46,5 m = 46,5/12 = 4 btg
Beugel diameter 8 = 183 x 0,5 = 91,5 m = 91,5/12 = 8 btg
Beugel diameter 8 = 23 x 0,7 = 16 m = 16/12 = 2 btg

4. Pekerjaan balok
 Beton k175 = 1,15 m3
Semen 1,15 x 1/6 = 0.19 m3
0.19 m3 semen adalah 0.19 / 0.024 = 8 zak
Pasir = 2 x 0.19 = 0.4 m3
Split = 3 x 0.19 = 0. 6 m3

 Besi
Besi utama diameter 10 = 4x 38,4 = 153,5m = 153,5 /12 = 13 btg
Beugel diameter 8 = 256 x 0,6 = 153,5 m = 153,5/12 = 13 btg

5. Pekerjaan batu bata = 125 m2


 Batu bata = 125 x 70 = 8750 bh
 Semen = 125 x 11,5 = 1437,5 kg maka 1437,5/50 = 29 zak
 Pasir = 125 x 0,043 = 5,5 kubik
6. Pekerjaan Plester = 250,5 m2
 Semen = 250,5 x 6,24 = 1563/50 = 31 zak
 Pasir = 250,5 x 0,024 = 6 kubik

7. Pekerjaan acian = 250,5 m2


 Semen = 250,5 x 3,25 = 814/50 = 16 zak

8. Pekerjaan plafond = 47,2 m2


 Kebutuhan plafond = 47,2/2,88 = 17 lembar papan plafond gypsum
 Rangka Furing = 50 btg

9. Keramik 50x50 = 41 m2
 Keramik = 41/0,25 = 164 bh keramik
1 dus berisi 4 bh maka 164/4 = 41 kotak/dus

 Semen = 41 x 10 = 410 kg =410/50 = 8 zak


 Pasir = 41 x 0,045 = 2 kubik

10. Keramik 25x25 kamar mandi = 5 m2


 Keramik = 5 /0,0625 = 80 bh keramik
1 dus berisi 16 bh maka 80/16 = 5 kotak/dus

 Semen = 5 x 10 = 50 kg = 50/50 = 1 zak


 Pasir = 5 x 0,045 = 0.25 kubik

11. Keramik 25x40 dinding kamar mandi = 18,16 m2

 Keramik = 18.16 /0,1 = 182 bh keramik


1 dus berisi 10 bh maka 182/10 = 18,5 kotak/dus

 Semen = 18,16 x 10 = 181,6 kg = 181,6/50 = 4 zak


 Pasir = 18,16 x 0,045 = 1 kubik

12. Pekerjaan plumbing


Kloset duduk = 1 bh
Bak fiber = 1 bh
Pipa diameter 4 = 1 btg
Pipa diameter 3 = 3 btg
Pipa diameter ¾ = 3 btg

13. Pekerjaan elektrik


Titik lampu = + 4 bh
Saklar = +5 bh
Stopkontak = +4 bh

14. Pekerjaan bukaan pintu


Kusen = + 1 bh
Daun jendela = + 1 bh

Batu kali 6,5 x 350.000 = Rp 2.275.000


Semen Portland 130 zak x 70.000 = Rp 9.100.000
Pasir 18 kubik x 200.000 = Rp 3.600.000
Batu Split 1,5 kubik x 500.000 = Rp 750.000
Besi dia 10 36 btg x 65.000 = Rp 2.340.000
Besi dia 8 34 btg x 45.000 = Rp 1.530.000
Batu bata 8750 bh x 700 = Rp 6.125.000
Gypsum Plafond 17 lbr x 45.000 = Rp 765.000
Furing 50 btg x 12.000 = Rp 600.000
Keramik 50x50 41 ktk x 100.000 = Rp 4.100.000
Rangka Baja 48 m2 x 210.000 = Rp 10.000.000
Seng 48 m2 x 90.000 = Rp 4.320.000
Keramik 25x25 5 ktk x 65.000 = Rp. 325.000
Keramik 25 x 40 19 ktk x 75.000 = Rp 1.425.000
Roster angin angin 64 bh x 25.000 = Rp 1.600.000
Kloset toto 1 bh x 450.000 = Rp 450.000
Bak fiber 1 bh x 300.000 = Rp 300.000
Pipa dia 4 1 btg x 350.000 = Rp 350.000
Pipa dia 3” 3 btg x 250.000 = Rp 750.000
Pipa dia 3.4” 3 btg x 55.000 = Rp 165.000
Kusen 1 bh x 400.000 = Rp 400.000
Daun pintu 1 bh x 600.000 = Rp 600.000

Total = Rp 51.870.000