Professional Documents
Culture Documents
ITEM – I EARTHWORKS
A. Backfill & Compaction
10 cu.m. @ 100.00 cu.m. = 1,000.00
B. Gravel Base:
3 cu.m. @ 500.00 cu.m. = 1,500.00
C. EARTH FILL
22 cu.m. @ 500.00 cu.m. = 11,000.00
Equipment Rental:
1 Unit Concrete Mixer for 20 days @ 350.00 / day = 7,000.00
ITEM – 9 DOORS
Materials:
1 Pieces Main Door @ 4,200.00 / piece = 4,200.00
2 Pieces Bedroom Door @ 3,500.00 / piece = 7,000.00
1 Pieces Kitchen Door @ 3,500.00 / piece = 3,500.00
ITEM – 12 TILES
Materials:
100 Pieces 0.60m X 0.60m Ceramic Tiles @ 100.00 / piece = 10,000.00
110 Pieces 0.20m X 0.40m Tiles @ 100.00 / piece = 11,000.00
22 Pieces 0.30m X 0.30m Tiles @ 100.00 / piece = 2,200.00
10 Box Laminated Wood Plank @ 3,500.00 / bag = 35,000.00
5 Bags Tiles Grout @ 70.00 / bag = 350.00
Labor Cost = 20,000.00
ITEM COST = 78,550.00
ITEM – 13 CABINETS
Materials:
2 Sets Bedroom Cabinet @ 15,000.00 / sets = 12,000.00
1 Sets Kitchen Cabinet @ 10,000.00 / sets = 8,000.00
A. Sanitary Pipes
8 Pieces 100mm dia. X 3.00m @ 750.00 / piece = 6,000.00
10 Pieces 75mm dia. X 3.00m @ 649.00 / piece = 6,490.00
3 Pieces 50mm dia. X 3.00m @ 484.00 / piece = 1,452.00
2 Pieces Elbow, 90 deg. - 100mm dia. @ 70.00 / piece = 140.00
16 Pieces Elbow, 90 deg. - 75mm dia. @ 60.00 / piece = 960.00
5 Pieces Elbow, 90 deg. – 50mm dia. @ 40.00 / piece = 200.00
3 Pieces Elbow, 45 deg. – 100mm dia. @ 70.00 / piece = 210.00
2 Pieces Elbow, 45 deg. – 50mm dia. @ 40.00 / piece = 80.00
8 Pieces 75mm dia. Coupling @ 12.00 / piece = 96.00
3 Pieces Sanitary WYE – 100mm dia. @ 250.00 / piece = 750.00
4 Pieces Reducer WYE – @ 150.00 / piece = 600.00
100mm dia. X 50mm dia.
1 Pieces Floor Drain Trap @ 350.00 / piece = 350.00
2 Pieces Clean – Out w/ Plug – 50mm dia. @ 120.00 / piece = 240.00
3 Pieces Clean – Out w/ Plug – 100mm dia. @ 180.00 / piece = 540.00
2 Pieces 16 oz. PVC Clear Solvent Cement @ 200.00 / = 400.00
B. Water Pipes
Materials:
1 Pieces Water Meter @ 230.00 / piece = 230.00
1 Pieces Gate Valve @ 170.00 / piece = 170.00
24 Pieces Elbow 90 deg. @ 18.00 / piece = 432.00
6 Pieces 20mm dia. Pipe @ 400.00 / piece = 2,400.00
5 Pieces Reducer Tee @ 45.00 / piece = 225.00
3 Pieces Nipple Reducer @ 35.00 / piece = 105.00
2 Pieces Coupling @ 15.00 / piece = 30.00
5 Pieces Teflon Tape @ 15.00 / piece = 75.00
ITEM – 16 ELECTRICAL
Materials:
1 Piece Panel Board (12 Branches) @ 2500.00 / pcs. = 2,500.00
1 Piece Main Circuit (60 A) @ 560.00 / pcs. = 560.00
3 Piece Circuit Breaker (15 A) @ 300.00 / pcs. = 900.00
8 Piece Circuit Breaker (20 A) @ 325.00 / pcs. = 2,600.00
33 Piece 3 Gang Lighting Outlet w/ switch @ 365.00 / pcs. = 3,650.00
12 Piece 3 Gang Convenience Outlet @ 380.00 / pcs. = 4,560.00
1 Piece Refrigerator Outlet @ 385.00 / pcs. = 385.00
1 Piece Ranger Outlet @ 385.00 / pcs. = 385.00
1 Piece Washing Machine Outlet @ 385.00 / pcs. = 385.00
2 Piece #14 THHN Wire (BOX) @ 2,580.00 / pcs. = 5,160.00
2 Piece #12 THHN Wire (BOX) @ 3,845.00 / pcs. = 7,690.00
1 Piece #10 THHN Wire (BOX) @ 3,890.00 / pcs. = 3,890.00
2 Piece #14 THHN Wire (BOX) @ 2,580.00 / pcs. = 5,160.00
1 Piece #8 THHN Wire (10m) @ 69.00 / pcs. = 690.00
1 Piece #6 THHN Wire (10m) @ 115.00 / pcs. = 1,150.00
20 Piece 20mm dia. PVC Pipe @ 95.00 / pcs. = 1,900.00
1/4 Quartz PVC CIELANT @ 145.00 / pcs. = 145.00
1 Piece @1/2 RSC Conduit Pipe @ 380.00 / pcs. = 380.00
1 Piece @2 RSC Conduit Pipe @ 980.00 / pcs. = 980.00
1 Piece PVC Connector (BOX) @ 205.00 / pcs. = 205.00
1 Piece PVC U Clamp @ 285.00 / pcs. = 285.00
10 Piece Flush Wall Switch @ 220.00 / pcs. = 2,200.00
1 Piece Ceiling Light W/ Fan @ 2,250.00 / pcs. = 380.00
5 Piece T5 Fluorescent Lamp @ 380.00 / pcs. = 1,900.00
SUMMARY
ITEM – I EARTHWORKS = 18,500.0 0
ITEM – 2 FORMS and SCAFFOLDS = 26,925.00
ITEM – 3 REINFORCEMENT BARS = 85,090.00
ITEM – 4 CONCRETE WORKS (SLAB & COLUMN & BEAM) = 61,360.00
ITEM – 5 MASONRY WORKS = 55,885.00
ITEM – 6 ROOF FRAMING = 85,440.00
ITEM – 7 ROOFING WORKS WITH GUTTER and FLUSHING = 26,320.00
ITEM – 8 CEILING WORKS = 26,320.00
ITEM – 9 DOORS = 17,300.00
ITEM – 10 WINDOWS = 36,000.00
ITEM – 12 TILES = 78,550.00
ITEM – 13 CABINETS = 20,000.00
ITEM – 14 PAINTING = 70,140.00
ITEM – 15 PLUMBING PIPES and FITTING = 45,320.00
ITEM – 16 ELECTRICAL = 70,350.00
5% CONTENGENCY = 34,859.00
CONTRUCTORS PROFIT = 73,203.00
PREPARED BY: