Professional Documents
Culture Documents
D E T A I L E D C O S T I N G
GROUND FLOOR
Exterior/Interior Wall 230.85 sq.m
Materials
BS Permacoat Flat Latex 6 pail @ ₱ 2,000.00 / pail ₱ 12,000.00
BS Permacoat Gloss Latex 12 pail @ 2,370.00 / pail 28,440.00
BS Acrytex Cast 18 gal. @ 440.00 / gal. 7,920.00
BS Acrytex Reducer 3 gal. @ 385.00 / gal. 1,155.00
Sandpaper #120 50 pcs @ 20.00 / pcs 1,000.00
Roller brush 5 pcs @ 120.00 / pcs 600.00
Paint brush 4" 5 pcs @ 80.00 / pcs 400.00
Paint brush 2" 5 pcs @ 65.00 / pcs 325.00
Miscellaneous 1.00 / lot 3,000.00
Materials Cost = ₱ 54,840.00
Labor
Working area 230.85 sq.m ₱ 150.00 / sq.m ₱ 34,627.50
Labor Cost = ₱ 34,627.50
Labor
Working area 526.97 sq.m ₱ 150.00 / sq.m ₱ 79,045.50
Labor Cost = ₱ 79,045.50
Labor
Working area 368.97 sq.m ₱ 150.00 / sq.m ₱ 55,345.50
Labor Cost = ₱ 55,345.50
Labor
Working area 32.89 sq.m ₱ 150.00 / sq.m ₱ 4,933.50
Labor Cost = ₱ 4,933.50
Parapet wall 66.80 sq.m
Materials
BS Plexibond # 7760 10 gal. @ ₱ 985.00 / gal. ₱ 9,850.00
Portland Cement 3 bgs @ 230.00 / bgs 690.00
BS Wallguard 2 pail @ 3,324.00 / pail 6,648.00
Roller brush 3 pcs @ 120.00 / pcs 360.00
Paint Brush 2" 3 pcs @ 65.00 / pcs 195.00
Materials Cost = ₱ 17,743.00
Labor
Working area 66.80 sq.m ₱ 150.00 / sq.m ₱ 10,020.00
Labor Cost = ₱ 10,020.00
Labor
Working area 282.40 sq.m ₱ 150.00 / sq.m ₱ 42,360.00
Labor Cost = ₱ 42,360.00
Labor
Working area 666.80 l.m ₱ 100.00 / sq.m ₱ 66,680.00
Labor Cost = ₱ 66,680.00
Prepared by :
JULIUS GRAGEDA
Contractor
BILL TO :
Client Name : University of Santo Tomas - legazpi PRICE QUOTE
Adress : Rawis, Legazpi City, Albay
Contact No. :
D E T A I L E D C O S T I N G
GROUND FLOOR
Exterior/Interior Wall 1,764.00 sq.m
Materials
BS Permacoat Flat Latex 25 pail @ ₱ 2,000.00 / pail ₱ 50,000.00
BS Permacoat Gloss Latex 50 pail @ 2,370.00 / pail 118,500.00
BS Acrytex Cast 50 gal. @ 440.00 / gal. 22,000.00
BS Acrytex Reducer 8 gal. @ 385.00 / gal. 3,080.00
Sandpaper #120 100 pcs @ 20.00 / pcs 2,000.00
Roller brush 30 pcs @ 120.00 / pcs 3,600.00
Paint brush 4" 25 pcs @ 80.00 / pcs 2,000.00
Paint brush 2" 25 pcs @ 65.00 / pcs 1,625.00
Miscellaneous 1.00 / lot 3,000.00
Materials Cost = ₱ 205,805.00
Labor
Working area 1,764.00 sq.m ₱ 150.00 / sq.m ₱ 264,600.00
Labor Cost = ₱ 264,600.00
Labor
Working area 364.21 sq.m ₱ 150.00 / sq.m ₱ 54,630.75
Labor Cost = ₱ 54,630.75
586
GI Handrails/Ladder 65.60 l.m
Materials
BS Quick drying enamel 2 gal @ 600.00 / gal 1,200.00
Red Oxide Primer 1 gal @ 375.00 / gal 375.00
Paint Thinner 1 gal @ 550.00 / gal 550.00
Steel brush 5 pcs @ 85.00 / pcs 425.00
Paint Brush 2" 5 pcs @ 65.00 / pcs 325.00
Materials Cost = ₱ 2,875.00
Labor
Working area 65.60 l.m ₱ 100.00 / sq.m ₱ 6,559.60
Labor Cost = ₱ 6,559.60
Prepared by :
JULIUS GRAGEDA
Contractor