V1 V1 INDUSTRIAL(HK) LIMITED
QUOTATION For Modification CM115
Quotation No: V1-20211209VR
To:Llenamex
Contact person:Peter Edition No: A
From:Sidney
Tel:(86)769-8228 8061 Page: 1-1
9/Dec/21
Item Tool Number Part picture ECR content ECR days ECR Price Remark
1. Design
Only implement ECR 1
2. CNC
1 3.EDM 9 days $1,200
(Hella’s request to remove material
4.Polishing
in part)
5.Trial
CM115
1. Design
Implement ECR 1+ECR 2
2. CNC
2 3.EDM 16 days $1,950
(Hella’s request to remove material
4.Polishing
in part AND optimize hinge area)
5.Trial
Remarks
1. The quotation is for mold ECR.
4.. The quotation is only valid for 15 days from date of this.