COMPANY PROFILE

PROJECTS HISTORY- CURRENT AND PAST


Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
1. First Hydrocarbon OGINI  OGINI Flowstation  Detailed Engineering Design and Ongoing
Nigeria Limited, FLOWSTATION Debottlenecking Procurement:
NPDC/FHN Project- PHASE 1 o FEED, DED
o Process Vessels, Equipment
o Produced Water Handling
Facilities
2. First Hydrocarbon OGINI  OGINI Flowstation  Site Installation and Construction Ongoing
Nigeria Limited, FLOWSTATION Debottlenecking o Structural foundations
NPDC/FHN Project- PHASE 2
o Fabrication Works
o Installation
o Commissioning
3. Movido Exploration and Offshore Delta $70m Asset  EPCI- 30,000 BOPD MOPU Ongoing
Production State, OML 88 Development and  Concept Development
Upgrade of the Ekeh  FEED Design
Field, OML 88 for  Detailed Design
Movido Exploration  Procurement & Installation
and Production
 Lease/Own/Operate Arrangement
Limited
with Companies in Partnership.
 Drilling and Completions
4. EPCM INDEPENDENT Delta State 2 x 10,000 BOPD  Concept Development Ongoing
PROJECT Crude Oil Refinery  FEED Design
Projects  Detailed Design
Products: Gasoline,  Procurement & Installation
Associated Gas Oil,

Page 1 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
Aviation Fuel, Naphtha  Lease/Own/Operate Arrangement
and Lubricating Oil. with Cluster Companies in
Partnership.
5. First E & P Offshore OML 83 Concept Selection Flow assurance and sizing of February 2018
and OML 85 Studies for OML upstream raw gas supply pipelines
83&85 Gas Processing  Estimation of required chemicals
Facility and Pipelines quantities to mitigate flow
assurance challenges and
corrosion, especially to allow use of
carbon steel for the pipelines
 Sizing of slug catcher at the plant
inlet and feasibility of installing one
slug catcher for the full plant
capacity (1,050 MMscf/d)
 Estimate of slug catcher weight –
dry and wet
 Prepare and recommend adequate
inlet manifold arrangement that
allows testing of wet gas inlet
streams from different suppliers
 Propose options of custody transfer
requirements to cover 2
possibilities – supplier’s fence and
central gas plant fence
 Recommendation and selection of
preferred options as applicable
6. First E & P Swamp/Onshore ISENI Gas Concept  Gas Technology Options 2017
Development Study Comparison/Analysis (TWISTER,
TURBO EXPANDER, MRU, JT, ETC)
 Preliminary Concept Development

Page 2 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Preliminary FEED
 Options Risk Assessment
 Concept Selection Report
7. Energia/Oando JV OML Kwale, Delta State OSBL (Outside  FEED Completed
56 Nigeria Refinery Battery Limit)  DED
FEED and DED for
Energia’s 10,000  IFC Documentation Development
BOPD Refinery Project  Project Management Services
8. Energia/Oando JV OML Kwale, Delta State Modular 17,500  Process Studies on Current Completed
56 Nigeria Production Unit production profile
complete with  Static and Dynamic Process
Pressure Vessels, Simulation studies
Water treatment,
pumps, metering  Development of Modular Engineering
systems, plus Design for Easy-to-install and
integrated safety integrate modules.
systems to recover  Conduct HAZOP/HAZID/Risk
production and cater Assessments on design
for new wells.
9. OANDO Plc Oshodi, Lagos, Detailed Engineering  Concept Design Development Completed
Nigeria and Construction  Detailed Design
Design, PM and
Commissioning of  Procurement
OANDO Plc’s 10 Specifications/Datasheets
MMSCFD CNG Mother  Construction Project Management
station Facilities  HAZOP Study
 Constructability Reviews
 Risk Analysis

Page 3 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Development of Facility Control
Philosophy Manuals
 Execution Project Management
10. Oando PLC, Nigeria Port-Harcourt OER 10KM x 12” AGI-  Route Selection Risk/Opportunity Completed
BUA Gas Distribution Analysis
Pipeline FEED Project  Detailed Process, Mechanical, E & I
Design and Specifications
 Procurement Datasheets
 IFC documents/drawings
11. Independent Project Kwale/Niger Delta
Development of an  Concept definition Completed
100 MMSCFD  Engineering Design
Condensate
Recover/Gas  Equipment sizing and selection
Processing Plant to  Procurement
Optimize on  Package selection and Integration
oil/condensate
recovery and generate
revenue through LPG
production and
Natural Gas for
Pipeline sales.
12. Energia/Oando JV OML Kwale, Delta State Conceptual/Feasibility  Identification of Alternative Export Completed
56 Nigeria Studies on Alternate Options
Direct Crude Oil Export  Concepts Development
Facilities: 30,000-
50,000 BOPD Export  Network Outlay
Capacity  Options Risk Assessment

Page 4 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Preliminary Route Surveys &
Assessment
 FEED for Pipelines, Jetty and
Associated Facilities
 Project Execution Cost estimates
 Bill of Materials
13. Midwestern Oil & Gas Umusadege, Delta Project Management:  Project Manager Completed
Company Plc State, Nigeria. Construction of Umu-  Project Engineers
East to Central
Processing Facility  Welding Inspection Services
Flowlines/Pipelines  QA/QC- Quality Assurance and Quality
Control
 HSE Inspectors
 Pre-Commissioning and
Commissioning
 As-Built documentat
14. Midwestern Oil & Gas Umusadege, Delta UMU-EAST Flowline  Concept Development Completed
Company Plc State, Nigeria. and Pipeline FEED and  Options Outlay
DETAILED DESIGN
 Options Risk Assessment
 FEED Process, Mechanical, Electrical,
Instrumentation, Structural/Civil
Deliverables
 Detailed Engineering Design: Process,
Mechanical, Electrical,
Instrumentation, Structural/Civil
Deliverables

Page 5 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Detailed Bill of Materials and Cost
Estimates

15. Midwestern Oil & Gas Umusadege, Delta 2 X 40,000 BBLs  Concept Development and Selection Completed
Company Plc State, Nigeria. Storage Tank FEED Studies
and Detailed  Civil/Structural Design and
Engineering Design Specifications
 Mechanical Design and Specifications
in line with API RP 650
 Process Design and Specifications
 E & I Design and Specifications
 Cathodic Protection System
 Export Pumps Sizing and Selection
 Equipment Sizing and Selection
 Process Piping Design
 Materials Selection
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables
 Site Integration Works
16. Midwestern Oil & Gas Umusadege, Delta CPF Debottlenecking  Development of Problem Statement Ongoing
Company Plc. State, Nigeria. Project: Increase  CPF Modelling and Problem
production capacity Resolution
from 20,000 BOPD to
40,000 BOPD.  Flow Assurance and Hydraulic
Calculations
 Mechanical Design

Page 6 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Piping Stress Analysis
 3D Concept Design
 Isometrics and Layout Drawings
 Civil and Foundation Drawing
 Project Costing
 Project Management
 Value Engineering
17. Midwestern Oil & Gas Umusadege, Delta Eriemu Manifold &  Flow Assurance and Hydraulic Completed
Company Plc State, Nigeria. Pipeline Design Calculations
 Mechanical Design
 Piping Stress Analysis
 3D Concept Design
 Isometrics and Layout Drawings
 Civil and Foundation Drawing
 Project Costing
 Project Management
18. Pillar Oil Limited, Delta State, Debottlenecking and  Solution Conception Completed
Umusadege, Delta State, Nigeria. Design/LP Separator  3D Concept Design
Nigeria. EPC and Installation
Project : Increase  3D Plant Layout Drawings
production capacity  3D Installation Drawings
from 2,000 BOPD to  Procurement of LP Separator
7,500 BOPD
 New LP Separator Instrumentation
Hook-up and Fabrication of

Page 7 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
Associated Tie-ins to Existing
Oil/Water/Gas Outlets
 Fabrication/Construction and
Delivery of Piping Modifications –
Existing HP Separator PCV Bypass
Piping, Oil/Water Line Tie-in, Flash
Separator Piping Modifications, EPF
Flash Separator PCV Tie-in,
 Material Procurement
 Vessel/Material Delivery to Site
 Site Integration and Hook-up
Activities
19. Energia/Oando JV OML Delta State Nigeria 2 x 30,000 BBLS  Concept Development and Selection Completed
56 in Kwale Crude Oil Storage Tank Studies
FEED Project  Civil/Structural Design and
Specifications
 Mechanical Design and Specifications
in line with API RP 650
 Process Design and Specifications
 E & I Design and Specifications
 Cathodic Protection System
 Export Pumps Sizing and Selection
 Equipment Sizing and Selection
 Process Piping Design
 Materials Selection

Page 8 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables
 Site Integration Works
20. Energia/Oando JV OML Delta State Nigeria 5,000 BOPD Topping  Concept development and Selection Ongoing
56 in Kwale Plant/Refinery Project  FEED Development
– Concept, FEED, ITT
for EPC  3D Drawings
 Mechanical design and specifications
 Process design and specifications
 E & I design and Specifications
 Equipment sizing and selection
 Process Piping Design
 Materials Selection
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables.
21. Midwestern Oil & Gas Delta State, Crude Gathering  Concept development and Selection Completed
Company Plc Nigeria. Project  FEED Development
 3D Drawings
 Mechanical design and specifications
 Process design and specifications
 E & I design and Specifications
 Equipment sizing and selection
 Process Piping Design
 Materials Selection

Page 9 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables.
 Site Integration Works
22. Polar Habour Nigeria 
Lekki-Epe Building Construction  5-Bedroom Duplex + 2-Bedroom BQ –  Completed
Limited Expressway, Projects. External and Internal Tiles Finishing,
Lagos.  Plot D486, Royal Indoor Swimming Pool,
 Lakowe Phase Garden Estate.  8 Units of 3-Bedroom Duplexes + 1-
II, Lekki-Epe Bedroom BQ
 Olokonla, Housing
Expressway
 Victory Estate, Golf  5 Units of 4-Bedroom Twin Semi-
 #4, Tabuko Detached Duplexes
Road.
Gere Close,
Bakare  CO-116 Complex.  Office Complex – Conference
Facilities, Training Facilities, External
Estate,
Tiles Finishing,
Agungi,
Lekki.
23. Energia/Oando JV OML Delta State Nigeria 30,000 BOPD  Develop Basic Concept OPTIONS and Completed
56 Facilities Upgrade perform Concept Selection Analysis
Concept Studies,  Perform Simulation Studies(PIPESIM
Selection & Design Modelling, HYSYS Process Modelling,
Flowline/Pipeline Analysis, Process
Train Capacity Checks, sizing &
Evaluation)
 Concept Selection Matrix/Concept
Selection Workshop
 Base Cost Estimates(Parametric,
Grounds Up, others)

Page 10 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Debottlenecking of existing Facilities
from 10,000 BOPD capacity to 15,000
BOPD Capacity
 Expansion facilities to upgrade to
combined capacity of 30,000 BOPD
 FEED on Adopted Concept
 Detailed Design on Modular
Expansion Modules
 Basis Of Design, PFDs, P&IDs, Gas,
Isometrics, Electrical Line Diagrams,
Structural Drawings
 Procurement Datasheets
 Bill of Materials
 Process Training for company
Engineers
24. Energia/Oando JV Ebendo Debottlenecking and  Design of Flare and Vent Tips Completed
Facilities Flowstation in Design, Procurement  Flare Thermal Radiation Analysis
Delta State Nigeria and Installation of New
LP and HP Flare  Radiation Isopleth plots
Systems  Installation drawings- GAs, Isometrics
 Procurement of Flare LP Knock Out
Drum
 Procurement of LP and HP Flare
 Successfully commissioned.
 Project enabled the company to tie-in
4 new additional wells which had been

Page 11 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
shut-in due to capacity limits on the
Process Plant.

25. Midwestern Oil & Gas Delta State, 12”x 53km UACL  Pre-Start-up Inspection Completed
Company Plc, Nigeria Crude Oil Pipeline  Verification
Certification:
Commissioning and  Certification and Calibration
Start-Up  Accelerated Pump/piping modification
to meet First Oil Targets
 Piping Isometrics
 Bill of Materials
26. General Public – Bakare Estate, FEDP Career  Program started in 2009 as 2-week Completed
Engineering and Science Agungi, Lekki, Development Program workshops.
Graduates Lagos. for Engineers and  Program upgraded to 4-month
Science graduates Intensive FEDP-111 format which
Commenced February 3, 2014.
 Current Class commenced June 2,
2014
 Next Class starts September 2, 2014.
 Programs all ADVERTIZED in THE
GUARDIAN NEWSPAPER
27. NAVGAS Limited Apapa, Lagos LPG Blending Facilities  Final detailed design specifications for Completed
Detailed Blender, Pumps and Piping systems
 Equipment Procurement Datasheets
 Line Pipe Procurement Datasheets
 General Equipment Plot plans
 Piping General Arrangement Drawings

Page 12 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Piping Isometrics
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables.
28. NAVGAS Limited Apapa, Lagos LPG Blending Facilities  Concept selection studies Completed
FEED  Equipment sizing and selection
 Process Piping Design
 Materials Selection
 Pump Sizing and Selection
 Process, Mechanical, Electrical,
Safety, Civil/Structural Deliverables.
29. Oando Reservoir And Eket, Akwa-Ibom, FEED & FEED Update,  Flow lines Design Completed
Production Nigeria EPF/Central Crude Oil  Pipeline Design
Services/Network E & P Processing Facilities
 Geotechnical Surveys
 Heavy Oil and Light Oil Blending
 Surface Production, Storage and
Export Facilities
 Produced Water System packages
 Process, Mechanical, Electrical,
Civil/Structural Engineering
deliverables.
30. PAN OCEAN Oil Flare Thermal  Flare back-pressure analysis Completed
Corporation Radiation Analysis.  Flare Thermal Radiation analysis
 Thermal radiation plots
 HAZID

Page 13 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Quantitative Risk Analysis

31. OANDO Plc Concept Development  Concept Development and FEED Completed
Studies for OANDO’s  Pre-Construction Risk Analysis
Akepo Offshore and
Onshore Crude Oil
Production Facilities.
32. OANDO Plc HAZOP Studies and  HAZOP & RA Report Completed
Risk Assessment  Action Tracking Register
workshop for Detailed
Design of Akepo  Risk Bubble Plots
Wellhead and Pipeline
Facilities
33. ENERGIA/OANDO JV Technical and  Feasibility Study Reports Completed
Economic Feasibility  Trucking Procedure Manuals
Study for Road Tanker
Crude Oil Sales.

34. ENERGIA/OANDO JV HAZOP Study  Data gathering/Document Collation Completed


facilitation for (PFD, P&IDs, Cause and Effect Matrix)
OANDO/ENERGIA JV  Study Workshop Facilitation
NGL Gas Processing
plant  Issue Final Study Report

Page 14 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
35. East Horizon Gas Calabar, Cross Design, Procurement  Design Completed
Company (EHGC) River State and Construction of  Procurement
Access Platforms for
EHGC PRMS Facilities  Construction/Commissioning
at City Gate and
UNICEM locations
36. East Horizon Gas Calabar, Cross Design, Procurement  Design Completed
Company (EHGC) River State and Construction of 2 x  Procurement
44000 Firewater
Storage Tank for EHGC  Construction
City Gate PRMS  Commissioning
Facilities
37. East Horizon Gas Calabar, Cross Design, Construction  Installation Design Completed
Company (EHGC) River State and Installation works  Start-Up/Operations Procedures and
on 2 x 100% Capacity manuals
Weishaupt/Vitoplex
200 Boiler/Burner  Troubleshooting
units  Commissioning
38. East Horizon Gas Calabar, Cross Fire Consequence and  Fire Protection System guidelines Completed
Company (EHGC) River State QRA Studies for  Phased Installation Plan
OANDO/EHGC PRMS
Facilities in Cross River
State
39. East Horizon Gas Calabar, Cross Pre-Commissioning  Pre-Commissioning Punch list Completed
Company (EHGC) River State and Commissioning development and stewardship to
Engineering closure
Consultants for 18” x  Commissioning Procedure Manuals
128Km EHGC Natural
Gas Pipeline Facilities  Nitrogen Purging Procedures
 Start-Up Procedures and Plans

Page 15 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
from Akwa Ibom to  Fire And Gas Protection System
Cross River State design, execution and Operating
Manual
 Isolation Procedures
 Blow-down Philosophy/Procedures
 Vent Dispersion Studies
 Boiler Commissioning Procedures
 Vitoplex 200 Boiler Operating
Procedures and Manuals
40. ENERGIA/OANDO JV Design of 6” Crude  Detailed Process, Mechanical, E & I Completed
Delivery Pipeline Design and Specifications
 Procurement Datasheets
 IFC documents/drawings
41. ENERGIA/OANDO JV Early Production  Data gathering/Document Collation Completed
Facility Concept Risk (PFD, P&IDs, Cause and Effect Matrix)
Assessment.  Consequence Modelling Analysis
 Risk Assessment Workshop
 Issue Final Study Report (Risk
assessment Report and Action
Tracking Register)
42. ENERGIA/OANDO JV OANDO/ENERGIA EPF  Data gathering/Document Collation Completed
Detailed Design (PFD, P&IDs, Cause and Effect Matrix)
HAZOP Study  Study Workshop Facilitation
 Issue Final Study Report

Page 16 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
43. ENERGIA/OANDO JV Kwale, Delta State 2 x 10, 000 Barrels  Civil/Structural design and Completed
Crude Storage Tank specifications
FEED, Detailed  Mechanical design and specifications
Engineering Design in line with API RP 650
and Project
Management  Process design and specifications
 E & I design and Specifications
 Cathodic Protection System
 Crude oil Inter-Tank Transfer and
Export pumps
 Tank Operating System Manuals
 Start-Up and Commissioning
Procedures
 Facility Interconnection/Procedure
Manuals
 Construction Project Management
and Execution Procedures & Manuals
44. ENERGIA/OANDO JV FEED and Detailed  Flow-station Perimeter Fence Completed
design  Procurement and Installation of Mini
Separator
 Design & Const of 4'' In-let manifold to
accommodate well 4 & 5
 Design & Const of 2 x 4'' x 400m Flow
line from well 4 to Inlet manifold
 Design Fabrication/Installation of a
gas scrubber.
 Design and Construction of MCC

Page 17 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Design of Mini Warehouse for the
flow-station.
 Design and Construction of Produced
water Treatment Facility
 Procurement and installation of
500KVA Transformer.
 Procurement and Installation of
500KVA gas fired generators
 Design of gas metering system at the
flowstation
45. ENERGIA/OANDO JV Detailed Design of  Civil, Mechanical, Process, E & I Completed
Produced Water Design specifications
System  Equipment Datasheets
 Demolition Plan
 Construction Procedures
 Operating Procedures
 Maintenance Procedures/Plan
 Bill of Materials
 Cost Estimates/Budget
46. ENERGIA/OANDO JV Detailed design of  Civil Design specifications Completed
Energia’s New  Demolition Plan
Administration and
Accommodation  Construction Procedures
Complex  Bill of Materials
 Cost Estimates/Budget

Page 18 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
47. ENERGIA/OANDO JV Development of  Site Inspection /Visitation Completed
Energia Facility As-  Facility Survey/Data gathering
Built 2D/3D Layout
drawings & Operations  Review Construction MOC
Data  Develop 2D/3D Layout Drawing

48. ENERGIA/OANDO JV Energia Flowstation  Test Separator design & Completed


Process Capacity Specifications
Upgrade to  HP Separator Control System upgrade
10,000BOPD.
 LP Separator Control System upgrade
 Flare System Capacity upgrade
 Setting Tank/Surge vessel upgrade
 Process Piping upgrade re-design
49. PAN OCEAN OIL 200 MMSCFD Gas  Concept Development Completed
CORPORATION processing facility  Front End Engineering Design
Front End Engineering
design (FEED).  ITT Package
50. PAN OCEAN OIL Mini LPG Plant  Concept Development Completed
CORPORATION Facilities Design and  Front End Engineering Design
Evacuation Pipeline
(FEED)
51. PAN OCEAN OIL Flare Thermal  Data gathering and gap analysis Completed
CORPORATION Radiation Study/Fire  Site Inspection
Consequence Analysis
 Study Workshop Facilitation
 Issue Final Study Report

Page 19 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
52. PAN OCEAN OIL Gas Processing Plant  Statement of Fitness Completed
CORPORATION HSE Case  Review of Operating Philosophy and
Upgrades
 Development of Asset Integrity
Procedures
 Development of
Operating/Maintenance Procedures
 Failure Modes and Effects Analysis
(FMEA) and Reporting
 Fire Consequence Analysis
 Risk Assessments and Report
 HSE Case structure Development
 HSE/Safety Management System
 Hazard/Risk Register Development
53. PAN OCEAN OIL Production Flowstation  Statement of Fitness Completed
CORPORATION HSE Case  Review of Operating Philosophy and
Upgrades
 Development of Asset Integrity
Procedures
 Development of
Operating/Maintenance Procedures
 Failure Modes and Effects Analysis
(FMEA) and Reporting
 Fire Consequence Analysis
 Risk Assessments and Report

Page 20 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 HSE Case structure Development
 HSE/Safety Management System
 Hazard/Risk Register Development
54. PAN OCEAN OIL Conducted Safety  Data gathering Completed
CORPORATION Integrity Level (SIL)  Study Workshop Facilitation
Assessment for PAN
OCEAN  Issue Final Study Report
CORPORATION’s 65
MMSCFD Gas
Processing Plant
55. FRONTIER OIL LIMITED Uquo Field Early Production &  Feasibility Study Completed
Production, Eket. Crude Trucking Sales  Frequency Modelling
Planning, Risk
Assessment and  Consequence Modelling analysis
Journey Management  Risk Assessment
for Frontier Oil Limited  Issue final Report
(FOL).
56. Frontier, Universal & Eket, Akwa Ibom. FUN-MPN QIT-Facilities  Construction Contractor Bid Analysis Completed
Network (FUN) Design, Construction and Selection
Project Management &  Procurement RFQ Bid Analysis, MPN
Commissioning Requirements
Project. reconciliation/alignment, Contractor
Clarifications/response
 MPN-FUN Interface Project
Management- 3 Months
 Development of 36# Operations and
Maintenance Manuals

Page 21 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.


COMPANY PROFILE
Brief Project Execution
S/No Client Project Location Scope of Work Performed
Description Date/Duration
 Development of Construction Work
Packs and Procedures for Civil,
Mechanical, Electrical and
Instrumentation Work Scopes.
 Modification design of Civil/Structural
Foundation for Construction Phase +
Re-design of buried pipeline to
Surface pipeline.
57. LINETRALE GAS Apapa, Lagos. Detailed Design  Data gathering Completed
LIMITED HAZOP Studies for  Study Workshop Facilitation
Linetrale Gas Ltd 240
Tons LPG Storage &  Issue Final Study Report
Distribution Terminal.
58. LINETRALE GAS Apapa, Lagos. Development of  Document collation gathering and Completed
LIMITED Detailed HSE gap analysis.
Management  Issue Final HSE MS Document
System Manuals for
Linetrale Gas
Limited’s LPG Plant
and Distribution
Facilities

Page 22 of 22 www.epcmengineers.com, info@epcmengineers.com, CO-116 Complex, Bakare Estate, Agungi, Lekki.