You are on page 1of 4

CONSTRUCTION & DESIGN FEATURES

OF GAS INSULATED SYSTEM (GIS)


HEMANT KUMAR
M.E SCHOLAR, Department of Electrical and Instrumentation Engineering
Thapar Institute of Engineering & Technology, Patiala (Punjab), India
hkumar_me17@thapar.edu

Abstract - Energy demands are increasing day by day and II. PLANNING AND INSTALLATION
so is the burden on conventional & other non-conventional
sources of energy. Power Sector and associated energy OF GIS
demands in India are growing at an accelerated pace. In a A deliberate and complete installation plan, including
bid to further enhance the transmission capacity, India has
moved towards ULTRA HIGH VOLTAGE (UHV)
the future addition of similar equipment, is essential
transmission level and has adopted 1200kV (UHV) AC so that all aspects of construction can be reviewed.
system to transfer power over a large geographical area. The preassembled sections of the equipment and the
One of today’s major challenges in power transmission is manufacturer’s instructions dictate the assembly
to bring high voltage levels right into the urban area, which sequence and, in most instances, follow a series of
in turn requires switchgear that has small footprint, utmost steps categorized as follows:
reliability, very low noise and electromagnetic emissions. • Preconstruction meeting between user,
Usage of Gas Insulated System (GIS) serves as the most equipment installer, and manufacturer
convenient option having high reliability, availability, high • Site preparation including grading,
degree of safety, compact design, long service life etc.
installation of drainage, foundations, and
I. INTRODUCTION ground grid, access roads, and auxiliary
power
Gas insulated substations (GIS) have become a major • Staging of construction equipment required
component of power networks and have been used during the installation
with considerable success over the past 40 years. GIS • Final alignment and leveling of foundation
are exposed to different over-voltages compared to supports
conventional substations (i.e., lightning, switching • Receiving, unloading, and storing GIS
and temporary over-voltages). In conventional equipment
substations the protection of transformers against • On-site assembly and lay-down area
over-voltages is the most important concern [1]. In • Grounding of GIS equipment to ground grid
GIS, the entire gas insulated assembly (including • Local control cabinet installation
enclosures, circuit breakers, disconnect and • Connection of control wires
grounding switches) must be protected against severe • Evacuation and filling with insulating SF6
over-voltages because the gas insulated system is gas
partially non-self-restoring. Introduction of gas- • Leak testing
insulated switchgear technology during the seventies • Mechanical or operational testing
allowed the end-users, in a first step, to take • Dielectric testing of primary circuits with
advantage of the compactness and the insensitivity to conditioning steps
the environmental conditions of SF6 Gas Insulated • Cleanup in accordance with applicable
Switchgear (GIS). Further reasons based on regulations
geographically difficult areas, pollution and/or • Testing between GIS equipment and balance
environmental issues, visual appearance of a of plant for system integration
substation, but also crime, terrorism and material • Energization
damage are forcing hidden solutions. Underground,
indoor GIS substations have proven their superior The overall installation process for GIS may
reliability in the Middle East and Europe, and thus encompass many months, during which time other
represent the proper answer to the world electrical activities associated with the project should continue.
delivery challenges [2]. World utilities are today also Coordination of activities among the project’s
looking for upgrade, refurbishment and extension of responsible parties is a necessity, especially with
infrastructure with new solutions, predictably higher regard to the interface with the HV power
reliability and long-term availability [3]. transformer and HV cable connections. Time spent in
these coordination processes will help to ensure the III. DESIGN OF 400/220 KV GIS
minimum number of disruptions during the SYSTEM
installation process. Disruptions will nevertheless
occur and a certain degree of flexibility on the part of PART I – BUS SWITCHING SCHEME
all parties is essential. A typical sequence for the PART II – SINGLE LINE DIAGRAM AND
installation of new GIS could be as follows: GENERAL ARRANGEMENT
• The anchoring/support system is installed PART III – SUBSTATION LAYOUT
and leveled to accommodate civil works PART IV – SELECTION OF TECHNICAL
tolerances. PARAMETERS OF MAJOR SUB - STATION
• Complete bays and single- or three-phase EQUIPMENTS
bay components are installed on their
respective supports. PART I –
• Inter-bay connecting elements are installed
and bus-coupled. The various types of well-known
• GIS equipment is grounded to a ground grid. schemes are given below:
• Installation of local control cabinets and a. Single/Sectional Bus –
interconnecting cables. • Simplest and cheapest bus
• Commencement of SF6 gas vacuum-filling bar scheme
process. • Maintenance and
• Gas insulated buses, including SF6 gas-to- extensions of bus bars are
air bushings to outgoing power transformers not possible without
or line positions, are installed. shutdown of the
• Interface components are installed (e.g., GIS substation
to HV cable or power transformers), but bus • Operation of bus bar is
links remain uncoupled. easy
• Site commissioning tests are completed,
including local control cabinets. b. Main and Transfer Bus
• GIS is subjected to the high voltage • Similar to the single bus
withstand tests. scheme except the
• Ancillary GIS devices (e.g., voltage sectionalizing breaker or
transformers and surge arresters) are isolator
installed and bus links to high voltage cables • By keeping the
and/or transformers are coupled. sectionaliser open one
• Means of dust control during installation section can be in service
should be taken into account. and the other can be taken
In general, GIS is essentially immune to many of the for maintenance or
degradation mechanisms that affect air insulated extension
equipment. The following is a partial list of some of
the major degradation mechanisms -: c. Sectionalized Main and Transfer
• Frequent operation above thermal limits Bus
• Frequent high electrical stresses due to • Individual CB can be
surges taken out for maintenance
• Particles in the high voltage encapsulation on-load at a time
from production and/or installation • The transfer bus coupler
• Excessive moisture in the SF6 gas acts as the breaker for the
• Impurities in the SF6 gas circuit under bypass
• Contaminants entering flanges and affecting
O-rings d. Double Main with bypass Isolator
• Mechanical wear/aging • This bus arrangement
provides the facilities of a
• Poor assembly techniques
double bus arrangement
• Poor management of decomposition
& a main and transfer bus
products due to switching or interruption of
arrangement
currents
• The bus to which the
transfer bus isolator is
connected can be used as PART II –
a transfer bus also • Bay Allocation:- The identification of
• During the time a circuit various feeders in any substation is
is under bypass, the bus done keeping following points in view
coupler will act as the • Minimum Line Crossings
breaker for the bypassed • Compactness and Flexibility of
circuit S/S expansion
• Sub Station Layout:- For 400/200 KV
e. Double Main and Transfer Bus substation low level or rigid bus bar
• In this bus scheme, in layout is been used due to following
addition to the main buses advantages
there will be a separate • Each feeder of D/C lines/Auto
transfer bus also transformers can be directly
• Since separate transfer connected to separate buses
bus is available there will • Less structures and associated
be no need of transferring Civil Works
the load from one bus to • Better aesthetic appearances of
other bus unlike in a substation
double main cum transfer • ROAD AND RAIL TRACKS:- Road
bus arrangement and rail track layout is an important
aspect from operation and maintenance
f. Ring Bus point of view
• This arrangement is very • The road and rail layout is
popular judiciously chosen keeping in
• Extension of mesh station view higher cost of rail track,
is almost impossible rolling/shifting of heavy
• No bus bar protection equipment's in substation
required without causing shutdown of
heavy equipment's.
g. One and Half Breaker • For 400/220 KV S/S, Roads
• In this layout, two circuits have been provided near main
have three breakers; the and tie equipment’s and along
middle breaker ties the the inside boundary of
two circuits and hence is substation.
called the tie breaker. • LOCATION OF CONTROL ROOM
• The combination of three AND OTHER AUXILIARY
breakers is called a BUILDINGS:-The location of control
diameter. room and other auxiliary buildings play
• One great advantage of a major role for economic design of S/S
this scheme is that even • Easy access to control
both the buses are out of room with minimum
service, power can be routing through S/S area
transferred from feeder to • Clear view of substation,
another control room is referred to
be in center considering
h. Double Bus and Double Breaker future bays requirements
• This arrangement is very also.
expensive one and hence PART III –
followed in very • There can be several combinations in
important circuit only which the equipment's, bus-bars,
• In this arrangement structures etc. can be arranged to
breaker maintenance for achieve a particular switching scheme.
each circuit is possible • The first objective of sub-station
scheme is to translate the selected
scheme into a layout so as to physically
achieve the feeder switching
requirements, maintaining safety • Shunt reactors shall have ONAN
clearances and clearances required for cooling so that failure of cooling
ease in erection and maintenance. system does not necessitate tripping
• For 400/220 KV sub-station, Breaker of line or shunt reactor
and Half scheme for 400 KV s/s and • CIRCUIT BREAKER:- SF6 type of Circuit
Double main with transfer bus scheme breakers are of state of art design and are
for 220 KV s/s have been considered. reasonably maintenance free
Factors Influencing the Choice:- • SF6 circuit breakers are capable of
• Reliability breaking a number of full short
• Electrical and safety clearance circuit currents before needing to
• Ease of construction and extension replace/repair their main/arcing
• Ease of operation and maintenance contacts
• Safety of operating personnel • SF6 circuit breakers complying to
• Safety of equipment and latest IEC 56/ IS 2516 standard are
installation specified
• Economy • ISOLATORS:- Isolator of Double break
PART IV – type conforming to IEC 129/IS 9921
• AUTO TRANSFORMER: - For standard are most commonly used and have
interconnection between two systems at very a reasonably good reliability level
high voltage for bulk power transfer, use of • Isolators are provided with earth
auto transformers are recommended as a switches where required as per
single transportable limit. layout requirements for ease
• Keeping in view of the transport, maintenance of adjoining
manufacturing & testing limitation equipment
in Indian condition 315 MVA, 3-
phase capacity has been REFERENCES
standardized as the largest unit [1] S. Okabe, J. Takami, "Occurrence probability of
• For 400/220 KV substation 315 lightning failure rates at substations in consideration
MVA, 3-phase capacity has been of lightning stroke current waveforms," IEEE Trans.
used Dielectrics and Insulation, Vol. 18, No. 1, pp. 221-
• 420 KV SHUNT REACTORS & 231, Jan. 2011
NEUTRAL GROUNDING REACTOR:-
Shunt reactors are meant for shunt [2] G.F. Montillet, E. Mikes et al. "Underground
connection in a system to compensate transmission and distribution GIS solutions"
capacitive current and switching operation IEEE/PES T&D Exposition and Conference, Dallas
• As 400 KV lines are practically USA, 2003.
compensated type, reactors of
capacities ranging from 50 to 100 [3] E. Mikes, Ch. Tschannen, et al. "GIS substation
MVAR shall be required extensions and upgrades" CEPSI Paper T1-068,
2000, Manila, Philippines.

You might also like