Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
CARPENTRY WORKS
MATERIALS ESTIMATED QUANTITIES REQUIRED
MARK CALCULATIONS LUMBER PLYWOOD NAILS
2" x 2" (bd. ft) 1/4" x 4' x 8' 8d 63 mm 2d 25 mm
TOILET & BATH 1
Total Area (m²): 9.504
COMPUTATION
USING 40 x 60 cm SPACING OF 2" x 2" LUMBER
TOTAL AREA x FACTOR = 9.504 x 5.373
CEILING JOIST
= 51.065
; say 52 bd. ft
USING 40 x 60 cm BOARD SIZE
TOTAL AREA 9.504
=
CEILING BOARD EFFECTIVE CEILING PER BOARD 0.24
GROUND FLOOR = 39.6
; say 40 pcs.
FOR CEILING JOIST
TOTAL AREA x FACTOR = 9.504 x 0.055
= 0.523
; say 1 kg
FINISHING NAILS
FOR CEILING BOARD
NO. OF SHEETS x FACTOR = 40 x 0.055
= 2.2
; say 3 kg
MATERIALS ESTIMATED QUANTITIES REQUIRED
MARK CALCULATIONS LUMBER PLYWOOD NAILS
2" x 2" (bd. ft) 1/4" x 4' x 8' 8d 63 mm 2d 25 mm
TOILET & BATH 2
Total Area (m²): 8.659
COMPUTATION
USING 40 x 60 cm SPACING OF 2" x 2" LUMBER
TOTAL AREA x FACTOR = 8.659 x 5.373
CEILING JOIST
= 46.525
; say 47 bd. ft
USING 40 x 60 cm BOARD SIZE
TOTAL AREA 8.659
=
CEILING BOARD EFFECTIVE CEILING PER BOARD 0.24
GROUND FLOOR = 36.079
; say 37 pcs.
FOR CEILING JOIST
TOTAL AREA x FACTOR = 8.659 x 0.055
= 0.476
; say 1 kg
FINISHING NAILS
FOR CEILING BOARD
NO. OF SHEETS x FACTOR = 37 x 0.055
= 2.035
; say 3 kg

Prepared By: Checked By:

COLA, JOHN EDEN ROSS V. ENGR. ARNOLFO ARCIBAL