TERM OF REFERENCE
Section 7. Term of Reference
2. As one of the largest slum upgrading projects in the world, the KOTAKU focuses its
strategy in the development of a collaborative platform at all levels (community level, city
level, provincial level, national level, and international level). The collaboration platform is
being established to leverage all resources (organizational and financial) available from
national, provincial and local government programs, alongside donor financing. This project
is designed to support the establishment of such a platform. The platform is delivered through
four main instruments: (1) Integrated settlement improvement planning at city level and
kelurahan level, including safeguards, slum prevention, maintenance, and inclusion of
livelihoods, (2) Institutional Collaboration, horizontally and vertically between relevant
government sectors and stakeholders at all levels, including community level, (3) Web-based
Management Information System (MIS) to monitor slum alleviation, and a (4) Support
System, including planners, architects, engineers and community facilitators.
4. This National Management Consultants (NMC) will support NSUP in the Central and
Eastern Regions supported by the World Bank and AIIB, except for some activities at
national level where NMC is expected to support for overall platform.
- 51 -
Section 7. Term of Reference
A. Project Design
5. Infrastructure investments under this project will focus on 153 cities and 1 province (DKI
Jakarta) in the central and eastern parts of Indonesia. Tertiary infrastructure investments and
institutional capacity building support will be provided in all 154 project cities (153 cities plus
the province of DKI Jakarta)7, while improvement of primary and secondary infrastructure in
the vicinity of slums, and construction of connecting infrastructure will only take place in a
subset of 50 cities (out of 154 cities).
6. City selection. The 50 cities have been selected on the basis of: (a) population
characteristics, including population density and percentage of urban population; (b) size of
the slum area in the city; (c) gaps in access to infrastructure and services8; (d) commitment of
local government to implement NSUP. (See Annex 9 for selected cities). Infrastructure
investments will commence in the first year of the project (2017) in a subset of cities and the
project will subsequently be scaled up to all participating cities (see Project Appraisal
Document for Project Cycle).
B. Project Components
7. The project has five components that together will enable the achievement of the PDO.
Project components are summarized below.
8. Component 1: Institutional and Policy Development (Cost US$7 million, of which IBRD
Loan US$1 million and AIIB loan US$1 million). This component will support institutional
strengthening and capacity building of central government agencies (e.g., BAPPENAS,
MPWH) responsible for the management of the NSUP and will include: (a) institutional
analysis at the national level as well as for a sample of municipal governments to identify the
nature of support needed to facilitate inter-agency coordination during program/project
preparation, implementation and supervision stages; and (b) strategic national upstream policy
level studies to facilitate the development of government policy to support the sustainability
of slum upgrading and prevention efforts.
9. Strategic studies will focus on land administration policy reform, policies towards
informal, and security of land tenure, and synchronization of slum definitions used by MPWH
and BPS. Technical assistance under this component will also be triggered when existing
frameworks are insufficient to resolve specific problems identified at the local level during
project implementation, requiring national policy development.
10. Component 2: Integrated Planning Support and Capacity Building for Local Government
and Communities (Cost US$84 million, of which IBRD Loan US$39 million and AIIB loan
US$39 million). This component will finance the costs of experts and community facilitators
throughout the project cycle to support capacity building (including training, workshops, and
knowledge exchange events between cities as well as urban sub-districts) of local
governments and communities in 154 cities to design and implement slum improvements,
7 In regards to administrative decision making under NSUP the province of DKI Jakarta is considered a city, and will be
referred to as such throughout the rest of the document.
8 Including: roads, clean water, sanitation, electricity, solid waste, drainage, housing space, and housing entitlement. Based
including the development of Slum Improvement Action Plans (SIAPs) at the city level and
Community Settlement Plans (CSPs) at the community level. The activities under this
component will build the capacity of participating local governments to design and implement
slum upgrading. Such capacity building is a necessary precursor for the implementation of
Component 3.
11. Component 3: Urban Infrastructure and Services in Selected Cities (Cost US$1578
million, of which IBRD Loan US$155 million and AIIB loan US$155 million): This
component includes two sub-components as summarized below.
12. Sub-component 3.1: Improvement of Primary and Secondary Infrastructure and Site
Development as well as Construction of Connecting Infrastructure as identified in SIAPs in
50 selected cities. This will include improvements in area-level small-scale roads, sanitation,
water and drainage systems, together with strengthening connectivity of tertiary and
household-level systems with primary and secondary infrastructure through the construction
of connecting infrastructure.
13. Sub-component 3.2: Support for Tertiary Infrastructure Upgrading in the project cohort
of 154 cities based on a CDD approach. This will include, inter alia, small scale water supply,
drainage, sanitation, footpaths, fire safety, site improvements (public spaces and sidewalks)
and modest support for strengthening community-based livelihoods through the construction
of livelihood enabling facilities and services as identified in CSPs. The project will support
improvements to housing of the poorest where deemed necessary within the context of slum
upgrading.
14. Component 4: Implementation Support and Technical Assistance (Cost US$74 million, of
which IBRD Loan US$21.5 million and AIIB loan US$21.5 million). This component will
provide technical support, advisory services and training for Project Management Units
(PMUs) at national level, and for Project Implementation Units (PIUs) at national, provincial
and city levels. Strengthening implementation and project management capacity will involve
support for the monitoring and evaluation system of NSUP and the project9, enhancing
stakeholders’ collaboration at all levels, and training to make substantial use of participatory
techniques at the tertiary level. Costs of National Management Consultants (NMCs),
Technical Management Consultants (TMCs) and Oversight Service Providers (OSPs) will be
financed under this component.
15. Component 5: Contingency for Disaster Response (US$0). Due to a high risk of
catastrophic natural disasters in Indonesia, this provisional component is made available to
finance preparedness and rapid response measures to address disaster, emergency and/or
catastrophic events, as needed, through sub-projects and/or using the project implementation
arrangements.
C. Institutional Arrangement
16. MPWH will be the executing agency for this project and will be responsible for the
procurement and management of all contracts, financial management of loan proceeds, and
implementation of environmental and social safeguards in accordance with Bank policies and
guidelines. A Project Management Unit (PMU) will be established under the Directorate
9
The MPWH has agreed that the project’s M&E system will be that used for the whole program.
- 53 -
Section 7. Term of Reference
17. Local and provincial governments will also be implementing agencies for Components 2
and 3. Local governments are involved in various aspects of the project implementation,
including leading the preparation of SIAPs and execution of several activities defined under
the SIAP. In addition, where local governments have capacity, a local government staff
member will be assigned as the Project Implementation Unit for managing the central
government funds, including procurement. Furthermore, local governments will authorize the
release of funds to communities and manage the tasks of the facilitators (Annex 3 outlines
institutional and implementation arrangements between government agencies).
18. Implementation Arrangement between the World Bank and AIIB. The World Bank
would be the lead co-financier and will undertake all the usual services associated with
project implementation which includes among others Environmental and Social safeguards,
Procurement, Investigative, Financial Management and Disbursement. The World Bank will
also be the GOI’s point of communication for project implementation.
19. A more detailed project description is available in the Project Appraisal Document of the
National Slum Upgrading Project as attached.
20. The objectives of the NMC is to assist the Project Manager/PMU in the implementation
of the NSUP. More specifically National Management Consultants is expected to assist the
Government in achieving the Project Development Objective (PDO) and Key Performance
Indicators (KPI) of NSUP as reflected in the Annex 2 of this TOR within the time frame of
the project.
21. NMC will provide service to PMU in daily overall program management; strengthening
technical and institutional capacities; carrying-out supervision, monitoring, spot-checks, and
evaluation for the overall outputs and outcomes; establishing knowledge management,
advocacy and capacity building materials and activities for communities, kelurahans and local
governments, as well as other relevant stakeholders; strengthening sustainability of the project
outcomes (institutional, financial and technical); facilitating collaboration across stakeholders,
programs and financing, and developing innovative programs and activities to support
achievement of KPIs. NMC will provide various technical experts across disciplines to fulfil
the required services.
22. NMC has a key responsibility for the achievement of the project goals, objectives and
outputs through quality-assured performance of the project activities at the kelurahan, district
provincial and national level.
54 | P a g e
Section 7. Term of Reference
23. The NMC Team or NMC will be furthered referred in this main text as “the Consultant”.
The Consultant should include in the proposal, specific objectives and deliverables of their
services to each component, also description of strategy and action plan to achieve the project
objective and key performance indicators (KPIs) in timely manner.
24. The NMC service will cover central and eastern part of the country in 19 provinces, 154
districts and 6140 about kelurahans that are participated in the overall NSUP as indicated in
Annex 7.
25. NMC will be responsible for the following tasks, but not limited to,:
c. Assisting PMU and Regional SATKERs to implement activities as agreed in the annual
work plan, including to develop implementation strategy and target, ensure PMU has
budget for operation and implementing activities, carry out a quarterly performance
review, and provide technical supports. Included in this task is to collaborate with the
advisory services, PMU, NMC in Western region, and also NMCs from other slum
upgrading programs;
d. Supporting the program planning, i.e to: support the preparation of budget documents and
its revision, set the annual target of KPIs (national, provincial and districts), develop an
annual work plan (AWP), and support coordination meetings and discussions among
PMU and PIUs as well as development partners;
e. Supporting PMU and DGHS in ensuring coordination annual budget preparation for all
sectors involved in the slum upgrading program including, but not limited to, programs
under MPWH (DG Human Settlement and DG Housing Provision) ensuring that they are
supportive to the investment programs proposed in the respective SIAPs and CSPs. NMC
will assist PMU in the preparation of various needs of national budget allocation for all
cities under the program.
f. Ensuring good quality of SIAPs and CSPs and its implementation, including integration
with planning, budgeting and implementation of slum upgrading programs at
kota/kabupaten and kelurahan level.
management and communication; better Governance; and quality assurance. NMC team
should provide capacity building, coaching and backstop for OSPs team, TMCs team,
City Coordinators and Facilitators as part of the above technical supports;
i. Developing, operating and maintaining a robust and reliable web-based and mobile
application-based Integrated Management Information System (MIS) which will provide
basis for all key reporting under the project and serves all key stakeholders. NMC will be
responsible for ensuring the development, reliability and timeliness of MIS for the overall
KOTAKU including the Western Region;
j. Developing, operating and maintaining a robust and reliable web-based and mobile
application-based complaint handling system which is integrated into MIS. Complaint
handling service will include ensuring all complaints are properly recorded, follow up,
monitored and provided support to relevant project operators to resolve the cases;
l. Ensuring compliance of the financial and audit requirements, including to prepare timely
interim financial report (IFR), carry-out regular audit and transaction review of OSPs and
Korkots invoices, undertake spot check and audit of infrastructure investment at city level
and the community block grants, follow up audit reports provided by an independent
auditor (BPKP and BPK), and ensure the functioning of “aplikasi BOP Korkot”
application (completeness, timeliness and validity). NMC should ensure application of
“aplikasi BOP Korkot”, an online invoice verification system, in all process of invoicing.
In addition, NMC should ensure that all audit and related monitoring findings will be
settled and published on website;
56 | P a g e
Section 7. Term of Reference
o. Developing the program capacity and strategy for collaboration to support achievement of
0 ha slum by 2020. Included in this tasks is to: facilitate data analysis, carry out series of
workshop and discussion with relevant agencies, develop strategy and plan for
implementation, leverage financing for expansion and maintenance, develop advocacy
materials, and improve monitoring mechanism;
q. Supporting the National Working Group for Housing and Human Settlements (Pokja
PKP) or Steering Committee (SC) to develop advocacy strategy and implementation plan
for achieving zero slum, support data and budget analysis and reports to contribute to the
roadmap to slum alleviation, facilitate discussion among central ministries concerning
recent policies and financing to improve the NSUP implementation, assist the SC to
prepare and follow up collaborative workshop(s) on settlement, and ensure the regular
updates of data and information web-dashboard for the SC in the KOTAKU website;
s. Developing framework and tools for GIS based planning and monitoring. This includes
facilitating the cities to prepare GIS-based SIAPs. The Consultants are also expected to
establish a GIS based monitoring system;
26. Specific services. A task order will be provided in the NMC team for specific assignment
which need specific expertises or at immediate nature in order to achieve the objective of the
program. The Consultant should include in the proposal, list and description of the proposed
task orders. It will be part of the evaluation. However, PMU may modify this task order in the
- 57 -
Section 7. Term of Reference
contract based on needs or recent development. The actual utilization and modification to the
proposed task order will require prior approval from PMU.
27. A detailed Scope of Works for the NMC can be found in Annex 4.
V. NMC STRUCTURE
28. The Consultants will be led by a Team Leader (TL) and will comprise of five sub-teams
as follows:
1. Planning team
2. Implementation team
3. Knowledge management team
4. Operations team
5. Advance team (as required)
29. Each team consists of specialists and sub-specialists according to the field of expertise
with detailed composition required for this assignment is provided in Annex 6. In total, the
assignment requires about 612 for professional staff months of input.
31. The PMU/PIU’s at national level, will conduct periodic evaluations of the NMC
performance. The NMC performance evaluation includes: (1) the substance of the program
(such as progress of KPIs and performance of the scope of works as defined in the TOR); (2)
administrative performance (such as compliance with contract); and (3) experts’ performance.
Considering the importance of the MIS in such large program, the NMC will also be
specifically evaluated based their MIS performance. PMU/PIUs will submit the NMC
performance evaluation reports and relevant recommendations to the executing agency, and
inform each NMC as well as the WB.
32. The Consultants procurement process of The National Slum Upgrading Program (NSUP)
may extend beyond the current assignment period and there may be a need to extend the
NMC contract for an additional period assignment. The Client may request an extension of
the original contract prior its expiration and subject to satisfactory performance and program
needs. Extensions will be based on rates in the original contract with price adjustments as per
the conditions of the contract.
IX. REPORTING
All written reports will be in Bahasa Indonesia with summary in both English and Bahasa
Indonesia. Specifically, for Annual, Mid Term, and Final Report will be written in both
Bahasa Indonesia and English. Scope of the reports of the NMC are mainly based on the
58 | P a g e
Section 7. Term of Reference
ANNEX 1
PROJECT DESCRIPTION
1. Background
The Government of Indonesia (GOI) through The Directorate General of Human Settlement –
Ministry of Public Works and Housing has prepared a National Slum Upgrading Program
(NSUP) in addressing the challenge of slum upgrading. The overarching National Slum
Upgrading Program (NSUP) is set up as a national platform financed by various sources from
Central and Local Governments, private sectors, community, as well as multi-donors such as
the Asian Infrastructure Investment Bank, the Islamic Development Bank, the World Bank,
the Asian Development Bank etc. Each multilateral agency will work in a sub-set of cities
selected jointly with the government. The National Slum Upgrading Program (NSUP) of GOI
directly responds to the RPJMN 2015-2019 and has been designed keeping the principles
highlighted in efforts to empower community and to strengthen local government roles for
acceleration of '100-0-100' movement and slum alleviation in urban area.
10
consist of 153 cities and regencies and 1 province (DKI Jakarta)
11
The project will cover access to the following infrastructure and basic services: (1) building regularity; (2) water; (3)
sanitation; (4) roads; (5) drainage; (6) solid waste; (7) fire safety and public space.
60 | P a g e
Section 7. Term of Reference
Detail project description of NSUP can be found in Project Appraisal Document (PAD)
NSUP Region 2 as attached to this TOR.
- 61 -
ANNEX 2
KEY PERFORMANCE INDICATOR
63
Indicator 3.1. Number of cities which have completed 80% of
primary and secondary infrastructure works and services 0.00 -- -- 20 30 35 40 40
connected to slum areas (Number)
Cumulative Target Values
Indicator Name Baseline YR1 YR2 YR3 YR4 YR5 YR6
End Target
(2016) (2017) (2018) (2019) (2020) (2021)
Indicator 3.2. Number of kelurahans that have completed 90% of
tertiary infrastructure and services implemented in slum areas 0.00 -- 1,400 1,600 2,000 2,200 2,500 2,500
(Number)
Indicator 3.3. Percentage of good quality of infrastructure and
0.00 -- -- 80 90 90 90 90
services (Percentage)
Indicator 3.4. Percentage of infrastructure built that is fully
functioning 0.00 -- -- -- -- -- 70 70
(Percentage)
Component 4: Implementation Support and Technical
Assistance
Indicator 4.1. Percentage of local governments that have a project
monitoring structure and provide regular information on project
0.00 -- 20 30 50 60 70 70
implementation
(Percentage)
Indicator 4.2. Percentage of kelurahans with completed annual
financial audits 0.00 -- 80 80 90 90 90 90
(Percentage)
.
Note: PDO targets for people provided with improved infrastructure under the project represents the total population provided access to at least one of the services under the
core indicators: improved water, roads, solid waste, sanitation and drainage. Achievements for each of these services will be monitored and recorded in the MIS.
ANNEX 3
INSTITUTIONAL ARRANGEMENT
Project Executing Agency. MPWH will be the executing or implementing agency for
this project. A Project Management Unit (PMU), with experienced personnel from
PNPM Urban has been established under the DG of Human Settlements under MPWH.
Under the PMU, the Central Project Implementation Unit (PIU/Satker) will manage the
contracts for consultants and facilitators to assist in capacity building and project
implementation. Likewise, there will also be PIU at the provincial and city level, who
will manage the contracts for consultants and facilitators to assist in capacity building
and project implementation.
a. At National Level
65
1) National Housing and Settlement Taskforce
a. Prepare recommendations, formulation of policy, strategies, and housing and
settlement development programs which effective and consistent with national
development agenda;
b. Prepare coordination measures, synchronization of activities, control, and
strengthening of housing and settlement development implementation;
c. Prepare instruction material in efforts to accelerate achievement of target
"cities without slums"
d. Coordination on integration of program to accelerate the achievement of target
"cities without slums across ministries/institutions associated with slum
alleviation;
e. Report regularly about progress of tasks implementation and results
achievement to the Steering Committee; and
f. Carry out other tasks assigned by the Steering Committee.
4) National Satker
a. Recruitment of consultants;
b. Carry out disbursement and management of funds in accordance with DIPA
designation;
c. Prepare report on the basis of Institution Accounting System (SAI) and E-
Monitoring;
d. Coordination with provincial and regency Satker;
e. Report the results of budget implementation of DIPA in accordance with
regulation.
5) Advisory Team
a. Assist PMU in preparation, concept development and formulation of technical
guidelines; research of KOTAKU development and other programs based on
needs, report and communicate the results of concept research and
development of KOTAKU to the PMU; and capacity building programs,
including finalization of capacity building concepts and documents (such as
training modules, training materials, and training evaluation formats, etc.);
b. Develop various implementation manuals, especially for KOTAKU and other
related programs if necessary;
c. Prepare and formulize a project implementation plan and other related
programs;
d. Assistance to PMU in preparation and development of capacity building.
6) Evaluation Consultant
a. Prepare evaluation/studies, which includes methodology; selection criteria of
sampling location; survey instruments; site survey tools; training for site
survey personnel and data management operators;
b. Recruit data entry operators and data editors; data collection; data management
and processing; database development (basic data); data processiong and
analysis;
c. Prepare site survey report, verification on site data accuracy; reports of
program evaluation.
7) National Management Consultant (see chapter 4 Scope of Works in the main text of
TOR)
b. Province Level
The main protagonist of KOTAKU at province level include Provincial Government,
Provincial Housing and Settlement Taskforce, Provincial PIU and Oversight Service
Provider/Engineering Consultancy Service. Tasks of each party are described below:
67
a. Dissemination of policy recommendations, strategies, and programs of
development of housing and residential areas;
b. Coordination on control, and strengthening the implementation of development
housing and settlement area; coordinate program integration to accelerate the
achievement of "cities without slums";
c. Prepare strategy to accelerate the achievement of the target of "cities without
slums";
d. Advocacy to local government for a more effective housing and settlement
development;
e. Regularly report progress of implementation of tasks and achievement of results
to the National Housing and Settlement Taskforce (Pokja PKP Nasional); and
4) Province PIU
a. Carrying out technical and administrative activities for program implementation;
b. Procuring individual consultants and facilitators; and Making payments of
salaries and BOP individual consultants and facilitators;
c. Distributing and administering BDI funds, particularly SP2D reports and e-
monitoring of BDI disbursement when BDI located in DIPA;
d. Prepare report on the basis of Institution Accounting System (SAI) and the E-
Monitoring; Report entire expenditure of funds according to regulations; and
e. Follow up program relating complaints until legal process / into law
enforcement while promoting amicable settlement; and
f. Report progress and performance of program as well as financial report to Pokja
PKP Provinsi.
c. Regency/City Level
2) Regency/City PIU
69
a. Carry out technical and administrative activities for the implementation of
KOTAKU;
b. Distributing and administering funds BDI, particularly SP2D reports and
BLM disbursement e-monitoring if BDI is located under Regency / City
DIPA;
c. Prepare report on the basis of Institution Accounting System (SAI) and E-
Monitoring; Reporting all expenditures funds according to regulations
accountably; and
d. Following up complaints relating to program until legal process / law
enforcement while maintaining to promote amicable settlement; and
e. Report progress and performance of program as well as its financial report to
Pokja PKP Kabupaten/Kota.
d. Kecamatan Level
Basically, the main actors at kecamatan level include kecamatan apparatus as technical
regional executor led by Camat. Team of facilitators work more at village level, as one
facilitator team covers several kelurahans/villages it involves coordination at kecamatan
level. The tasks of each party are described below:
1) Camat
a. Coordination of KOTAKU implementation in its region;
b. Mentor and control KOTAKU implementation in its region;
c. Mentoring for kelurahan/village government and BKM/LKM.
2) Team of Facilitators
a. Facilitate planning, implementation, operation and maintenance of infrastructure
(O&M) and monitoring of the program by communities and stakeholders at
kelurahan and kecamatan level
b. Facilitate preparation and ensure the quality of community settlement plan
(CSP) to address slums and its linked to the Slums Improvement Action Plan
(SIAP) at city level
c. Facilitate planning and implementation of tertiary infrastructure, ensure its
quality and linked with the primary/secondary infrastructure, and ensure
outcome of the infrastructure to the achievement of the program objectives.
d. Facilitate community meetings, provide technical supports and control to
government of kecamatan and kelurahan and community; and coordinate
regularly with the Kecamatan and kelurahan government related to the
implementation of activities;
e. Provide training to community and KPP through OJT on planning, mapping, etc,
including in order to build motivation (motivation achievement training) and
community critical awareness to maintain infrastructure sustainability in their
area. Provide training to increase community capacity in the implementation of
organizational management, activity management, and financial management;
f. Disseminate the program to public through various media at their working area
in frame of advocacy and education. Dissemination on standards and
requirements of habitable, healthy and harmonious housing and settlement;
g. Encourage active participation and involvement of community, including
women groups and poor people in all stages of program to ensure democratic,
transparent and accountable process of decision making;
h. Facilitate revitalization / strengthening of local community organizations as
trusted BKM / LKM; and facilitate community and target groups in the
preparation of RPLP/RTPLP; training, workshops, knowledge exchange among
communities associated with planning and implementation of slum alleviation,
i. Perform continuous assistance to improve BKM / LKM capacity including
strengthening institutional management, accessibility and channeling to key
resources in the context of sustainability of built infrastructures; and sssist
BKM/LKM in BLM management and bookkeeping and in report verification
before submitted to Satker;
j. Ensure BKM/LKM to strive for O & P (operation and maintenance) fund
allocation for APBD constructed infrastructures mechanism of Musrenbang;
k. Collect data in the logbook to be submitted to Korkot Team for MIS data update;
l. Monitoring on social and environmental impact management together with head
of village /lurah;
71
e. At Kelurahan/ VillageLevel
1) Lurah/Head of Village
a. Build collaboration platform at kelurahan with other stakeholders including
BKM, BUMD, LKM/LPM, etc
b. Provide supports for smooth operation of program implementation in its region
compliance with existing regulation in order to accomplish program objectives
properly
c. Supports to dissemination at kelurahan/ village level; Facilitate meeting of RT /
RW management, community and Korkot / Askot mandiri/Facilitator team, and
settlement volunteers in effort to program information dissemination and
implementation; Facilitate coordination and synchronization of activities related
to program implementation;
The NMC organization structure and coordination with other institutions is shown in
Figure 3.1 and 3.2.
73
Figure 3.2 Organization Structure of NMC
PMU of NSUP
PIU of NSUP & NUSP2
Advisory Team ESC
NMC Team Leader NMC NSUP-
Supporting Staff NMC NUSP-
Knowledge Management
Planning Team Implementation Team Operation Team Advance Team
Team
Sub-prof for institution on Community Sub Prof Training for Sub-Prof for Implementation &
Sub-Prof for Community Planning Sub Prof for Procurement Sub-Prof for SP2D Online
Level Community Control Management
Sub Prof for Social Sub Prof for Sub-Prof for Legal and
Communication Specialist Data Management Specialist
Safeguard Mainstreaming Gender Conflict Resolution
Sub Prof for Media Subprof for Data Processing and Sub Prof for Web
Financial Management and Livelihood Specialist
Management and ICT Reporting Administrator
Under direction of the PMU/PIU, the NMC will conduct scope of works as follows, but not
limited to:
3. Assist PMU and Regional SATKERs to implement activities as agreed in the annual work
plan, including to develop implementation strategy and target, ensure PMU has budget for
operation and implementing activities, carry out a quarterly performance review, and
provide technical supports. Included in this task is to collaborate with the advisory
services and individual consultants in the Steering Committee (SC), PMU, NMC in
Western region, and also NMCs from other slum upgrading programs;
75
• Ensure achievement of the performance indicators specified in the loan agreement and
guidelines
• Coordinate and ensure synergy of OSPs and TMCs through regular coordination
meetings with all OSP and TMC team leaders, etc
• Conduct performance evaluations for consultants and facilitators.
77
should ensure that OSPs and TMCs will carry out and upload the result of spot-check
on website;
e. Assist PMU to fulfill logical framework, KPIs, RPJMN and Sustainable Development
Goals (SDGs) targets;
f. Formulate, disseminate and train all relevant SOPs for project monitoring, data
management and analysis;
g. Prepare and fulfill Master Schedule and Quick Status;
h. Developing framework and tools for GIS based planning and monitoring. This
includes facilitating the cities to prepare GIS-based SIAPs. The Consultants are
also expected to establish a GIS based monitoring system;
i. Developing various innovative programs, creating innovative approach based on
lessons-learned, and adoption new policies. Included in this task is to develop some
mobile-based applications, carry-out disability-inclusive development (DID), develop
affordable technological options, enhance the existing applications such as the user
friendly web and mobile applications. NMC could generate additional resources in the
task order to establish the requested innovative programs as advised by PMU, PIUs
and development partners;
j. Providing regular and timely reporting or other/special reports as requested,
including technical/infrastructure, community and institutional development,
sustainability, financial management, audit and transaction review, procurement
and contact management, and social and environmental safeguards. The reports
should include those reported by OSPs. Included in this task is to ensure timely
submission of OSPs’ reports, timely MIS data upload and reporting, validity
MIS data (including to review its consistency with the actual implementation),
provide monthly and specific data analysis and reports on website (dashboard)
as requested by various stakeholders or other parties as approved by PMU
10. Conduct and manage overall knowledge management activities, including capacity
building, training, socialization, mass communication, and knowledge sharing.
• Ensuring good quality of slum upgrading implementation through, amongst others,
development and continuous updating of project guidelines, manuals, and operation of
an effective flow of information and resources across levels of governments up to
beneficiaries, development and implementation of knowledge management strategy
(including its curriculum, modules, media, etc), vigorous and systematic supervision
and spot checks and provision of evidence based policy proposals;
• Establishing knowledge management, including to manage an ICT-based learning and
knowledge sharing; carry-out expert group meetings, stakeholders’ workshops and
training; establish an effective dissemination of project policies, guidelines and
operating standard, and learning materials. Included in this task is to develop and
deliver learning materials, provide coaching and backstop and follow up the training
and workshop events; and to manage project-related information-sharing through
general social media applications (i.e: facebook, twitter, instagram);
• Ensure and manage effective implementation of knowledge management activities at
all level, including coordination of knowledge management activities related to slum
upgrading among projects and programs ;
• Facilitate, monitor and supervise OSPs, TMCs, and City Coordinator team, and
facilitator team on the implementation of knowledge management activities to meet
the optimal quality;
• Provide regular reports of knowledge management on the website, in timely manner;
• Provide inputs and recommendation to PMU/PIU on issues related to knowledge
management.
11. Conduct and manage overall implementation of Financial Management (FM), and
Sustainable Livelihoods Supports (SLS) including sustainability of Revolving Loan Fund
activities.
79
a. Ensuring compliance of the financial and audit requirements, including to
prepare timely interim financial report (IFR), and ensure the functioning of
“aplikasi BOP Korkot” application (completeness, timeliness and validity). NMC
should ensure application of “aplikasi BOP Korkot”, an online invoice
verification system, in all process of invoicing. In addition, NMC should ensure
that all audit and related monitoring findings will be settled and published on
website;
• Formulate and review grand strategy, implementation manual, technical guidelines,
SOP, training modules, and socialization materials for FM and SLS activities;
• Ensure consistency of guidelines and consolidate data on FM and SLS in the program
website, provided by various development partners (IDB, WB, and others);
• Monitor implementation of FM & SLS activities, develop information system, and
regularly publication of FM and RLF performance in the program website
• Carry out training and technical support for FM & SLS consultants and facilitators to
ensure effective and timely training and technical support provided at
regional/provincial and local level
• Ensuring compliance of the financial and audit requirements, including to monitor
regular audit, undertake spot check and audit of infrastructure investment at city level
and the community block grants, and follow up monitoring and audit reports provided
by the World Bank, Audit Board (BPK, BPKP), Evaluation Consultants (KE), Inter-
Ministries, and coordinate this with the relevant parties. All audit and related
monitoring findings will be settled and published on website.
• Provide regular reports of FM and SLS activities on the website, in timely manner
• Provide inputs and recommendation to PMU/PIU on issues related to FM and SLS
activities
Contract
No List of Professional dan Subprofessional Personnel
# MM Total
Person
I Leadership Team
1 Team Leader 1 42
II Planning Team
2.1 Urban Planning Specialist 1 42
Sub-specialist for City Planning 1 40
Sub-specialist for Community Planning 1 40
2.2 Program Financing and Institutional Collaboration 1 42
Specialist
Sub-specialist for Institution on City Level and Collaboration 1 40
Sub-specialist for Institution on Community Level 1 40
III Implementation Team
3.1 Infrastructure Specialist 1 42
Sub-specialist for Settlement and Housing 1 40
Sub-specialist for Sanitation and Water 1 40
Sub-specialist for Procurement 1 40
3.2 Safeguards Specialist (Environment) 1 42
Sub-specialist for Social Safeguard 1 40
Sub-specialist for Mainstreaming Gender 1 40
Sub-specialist for Mainstreaming DRM 1 40
3.4 Financial Management and Livelihoods Specialist 1 42
Sub-specialist for Financial Management 1 40
Sub-specialist for Livelihood 1 40
IV Knowledge Management Team
4.1 Training Specialist 1 42
Sub-specialist Training for Government 1 40
Sub-specialist Training for Community 1 40
Assistant Training 1 36
4.2 Communication Specialist 1 42
Sub-specialist for Socialization 1 40
Sub-specialist for Media Management and ICT 1 40
Sub-specialist for Graphic Designer and Ilustration 1 40
Assistant for Publication 1 36
Assistant for Social Media dan e-media 1 36
V Operations Team
5.1 Program Monitoring Specialist 1 42
Sub-specialist for Data Analysis and Reporting 1 40
Sub-specialist for Implementation and Control Management 1 40
Assistant for Program Monitoring 1 36
5.2 Data Management Specialist 1 42
Sub-specialist for Data Submission and Validation 1 40
Sub-specialist for Data Processing and Reporting 1 40
5.3 Financial Management Review Specialist 1 42
Sub-specialist for Financial Management Review 1 40
Sub-specialist for SP2D Online 1 40
5.4 Legal and Complaint Handling Specialist 1 42
Sub-specialist for Legal and Conflict Resolution 1 40
5.5 Web Master Specialist 1 42
Sub-specialist for Web Administrator 1 40
Sub-specialist for Web Maintenance 1 40
- 81 -
Contract
No List of Professional dan Subprofessional Personnel
# MM Total
Person
5.6 Human Resources Management Specialist 1 42
Sub-specialist for Human Resources Management Specialist 1 40
VI Advance Team (Task Order)
6.1 Advance Specialist 1 24
Sub-specialist for Advance 1 24
TOTAL 47 1.860 1.860
ANNEX 6
NMC PERSONNEL TASKS
II. Key Personnel
Tasks Assigned • Provide overall program management including program planning, implementation, supervision, monitoring and evaluation as
well as quality assurance NSUP in line with the agreed implementation guidelines. NMC should provide necessary services and
resources as well as guidance to achieve KPIs and PDO, and establish the technical assistances (including individual
consultants, OSPs, TMCs, and facilitators) as a single structure of management and technical support team for the overall
NSUP;
• Assist PMU and Central PIU to implement activities as agreed in the annual work plan, including to develop implementation
strategy and target, ensure PMU has budget for operation and implementing activities, carry out a quarterly performance
review, and provide technical supports. Included in this task is to collaborate with the advisory services and individual
consultants in the Steering Committee (SC), PMU, PIUs, NMC in Western region, and also NMCs from other slum upgrading
programs;
• Establishing quality assurance mechanism to ensure timely and quality implementation, compliance with the project policies
and relevant regulations, rapid response and follow up of issues, fulfil minimum technical standards and targets, effective
guidance and troubleshooting, and improved communications among central, provincial and district teams
• Assist PMU in ensuring consistency of policies and guidelines among various development partners (WB, IDB, ADB, and
83
POSIT ION TEAM LEADER
others).
• Supporting the program planning, i.e to: support the preparation of budget documents and its revision, set the annual target of
KPIs (national, provincial and districts), develop an annual work plan (AWP), and support coordination meetings and
discussions among PMU and PIUs as well as development partners;
• Supporting PMU and DGHS in ensuring coordination annual budget preparation for all sectors involved in the slum upgrading
program including, but not limited to, programs under MPWH (DG Human Settlement and DG Housing Provision) ensuring
that they are supportive to the investment programs proposed in the respective SIAPs and CSPs. Assist PMU in the preparation
of various needs of national budget allocation for all cities under the program
• Ensure development, operation and maintenance a robust and reliable web-based and mobile application-based Integrated
Management Information System (MIS) which will provide basis for all key reporting under the project and serves all key
stakeholders. Lead NMC in development, reliability and timeliness of MIS for the overall KOTAKU including the Western
Region;
• Ensure development, operation and maintenance a robust and reliable web-based and mobile application-based complaint
handling system which is integrated into MIS. Complaint handling service will include ensuring all complaints are properly
recorded, follow up, monitored and provided support to relevant project operators to resolve the cases;
• Developing various innovative programs, creating innovative approach based on lessons-learned, and adoption new policies.
Included in this task is to develop some mobile-based applications, carry-out disability-inclusive development (DID), develop
affordable technological options, enhance the existing applications such as the user friendly web and mobile applications. NMC
could generate additional resources in the task order to establish the requested innovative programs as advised by PMU, PIUs
and development partners;
A. Planning Team
85
POSITION URBAN PLANNING SPECIALIST
including guidelines for the implementation phase.
• Carrying out regular supervision and monitoring, as well as systematic spot-checks to ensure quality and timeliness of the
project implementation and outputs, review the SIAPs and CSPs, and oversee the performance of technical assistance at
provincial and districts levels.
• Developing framework and tools for GIS based planning. This includes facilitating the selected cities to prepare GIS-based
SIAPs and CSPs.
• Monitor, evaluate, and ensure effective implementation of SIAPs and CSPs, including mainstreaming of Disaster Risk
Management (DRM), Climate Change Adaptation (CCA), gender, Disability Inclusive Development (DID), quality control of
the planning process and planning documents, propose improvements as needed, and carry out intensive supervision to review
critical issues and resolve problems in the field.
• Ensure compliance of Environmental and Social Management Framework (ESMF) in planning and implementation and also
compliance of Land Acquisition and Resettlement Policy Framework (LARPF) where needed.
• Manage capacity building and provide technical support related to planning activities, particularly on SIAPs and CSPs, for
provincial, local governments, communities, and consultants to improve their capacity in the preparation and implementation
of SIAPs and CSPs, including mainstreaming of DRM, CCA, DDI, safeguards, and gender.
• Manage and coordinate planning team at all level and ensure quality of their performance, including organizing expert group
meetings (EGMs) regularly.
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• SIAPs and CSPs in targeted location
• Annual work plan for relevant activities
• SIAPs and CSPs quality control system
• Spot check, supervision and monitoring report
•
• Best practices in planning
Accountability • Relevant KPI
• Completion of SIAPs and CSPs that can meet slum alleviation and prevention
• Accurate MIS on planning data
• Good Performance of UP Specialist in OSP, assistant city coordinator and facilitator
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
POSITION PROGRAM FINANCING AND INSTITUTIONAL COLABORATION SPECIALIST
Reporting to CPIU, Team Leader
Duration 42 months
Location Jakarta -based
Experience • Bachelor degree (S1), preferably Master Degree (S2) in any relevant major, preferably in public policy, development studies,
(Min. and social sciences.
Qualification, • Having minimum 10 years working experience in public administration fields of central and local governments (development
Experience) planning, programming, budgeting, fiscal transfers) in any urban or settlement projects in similar type of program scale.
Experience in community empowerment program and community-based or city level infrastructures projects with similar type
of program scale will be an advantage More than 15 years of experience will not be considered to have additional points in the
evaluation.
• Having minimum 5 years working experience in local government facilitation/corporate social responsibility field/marketing.
• Having minimum 5 years working experience with strong leadership roles in relevant project or team management.
• He/she shall have good interpersonal communications and management skills, computer literates, team-work abilities and must
be able to have an extensive field-trip to project areas.
Tasks Assigned • Conduct institutional development and build program financing and institutional collaboration, including program
planning, implementation, supervision, monitoring and evaluation as well as quality assurance, in line with the agreed
implementation guidelines.
• Develop strategy to improve collaboration platform at city level, develop advocacy materials, as well as develop and manage
capacity building activities for local government officials in coordination with Pokja PKP or other relevant agencies; and
improve monitoring mechanisms on the establishment and functioning of local task force;
• Develop strategy and quality control of establishment collaboration platform at kelurahan level, including establishment and
sustainability of community institution (BKM, KSM and other related community institution)
• Formulate implementation manual, technical guidelines, SOP, training modules, and socialization materials for collaboration
of programs and financing among national government, local governments, and communities;
• Support collaboration in planning at central as well as local level, i.e ensure inclusion of relevant activities in SIAPs and CSPs
into regular local planning and budgeting process (RPJMD, RKP, Musrenbang, etc); support the preparation of planning and
budget documents and its revision, set the annual target of KPIs (national, provincial and districts), develop an annual work
plan (AWP), and support coordination meetings and discussions among PMU and PIUs as well as development partners;
• Ensure overall implementation and performances of the programs related program financing and institutional
collaboration
- Conduct data analysis related program financing and institutional collaboration, check data accuracy and ensure timely
87
POSITION PROGRAM FINANCING AND INSTITUTIONAL COLABORATION SPECIALIST
submission of reports in the MIS.
- Conduct spot check regularly according to the spot-check guideline;
• Facilitate, monitor and supervise OSPs on the implementation of institutional and program financing collaboration; manage
and coordinate program financing and institutional collaboration team at all level and ensure quality of their performance,
including organizing expert group meetings (EGMs) regularly.
• Provide regular reports of institutional matters, program planning and budgeting, as well as realization of activities and funding
on the website, in timely manner;
• Provide inputs and recommendation to PMU/PIU on issues related to institutional and program financing collaboration
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• Institution, financing and collaboration in targeted location
• Annual work plan for relevant activities.
• Spot check, supervision and monitoring report
• Best practices in program financing and institutional collaboration
Accountability • Relevant KPI
• Realization of program cost as agreed in PAD
• Accurate MIS on relevant data
• Good Performance of Program Financing and Institutional Collaboration Specialist in OSP, assistant city coordinator and
facilitator
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
B. Implementation Team
89
POSITION INFRASTRUCTURE SPECIALIST
(OM) plan;
- Manage and coordinate all infrastructure specialists and facilitators to comply with the agreed guidelines, manuals and
SOPs;
• Provide guidance and closely monitor selection of infrastructure at city level (connecting infrastructure) and community level
to meet the technical requirements and relevant with the slum upgrading/prevention purposes; Monitor selection of connecting
infrastructure at city level based on SIAPs, and provide recommendations to the local governments as necessary;
• Provide regular reports of infrastructure activities on the website, in timely manner
• Provide inputs and recommendation to PMU/PIU on issues related to infrastructure activities, with synchronization with
financial, procurement and contract management; supervision, monitoring and evaluation; sustainability support (institutional,
financial and technical); advocacy, knowledge management and communication; better governance; and quality assurance.
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• City and community scale infrastructure in targeted location
• Annual work plan for relevant activities
• Spot check, supervision and monitoring report
• Best practice in infrastructure for tertiary, secondary and primary
Accountability • Relevant KPI
• Good quality detailed engineering design of tertiary, secondary and primary infrastructure in compliance with the ESMF,
gender DID, DRM and CCA principles.
• Good quality tertiary, secondary and primary infrastructure in compliance with the ESMF, gender DID, DRM and CCA
principles.
• Effective procurement process for secondary and primary infrastructure
• Accurate MIS on relevant data
• Good Performance of Infrastructure Specialist in OSP, assistant city coordinator and facilitator
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
91
POSITION TRAINING SPECIALIST
• Facilitate, monitor and supervise OSPs, TMCs, and City Coordinator team, and facilitator team on the implementation of
knowledge management activities to meet the optimal quality;
• Provide regular reports of training, capacity building and knowledge management on the website, in timely manner;
• Provide inputs and recommendation to PMU/PIU on issues related to knowledge management
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• Quality of training activities and capacity for all stakeholder
• Annual work plan for relevant activities.
• New approach and method for training to improve program performance, as needed
• Training materials
• Best practice in training and capacity increased
• Capacity building strategy
• E-learning materials
Accountability • Relevant KPI
• Good quality training activities and its impact
• Accurate MIS on relevant data
• Good Performance of Training Specialist in OSP, assistant city coordinator and facilitator
• Increasing capacity for all stakeholder
• Good and effective training systems and its methods
• Training activities as plan and in timely manner
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
D. Operations Team
93
POSITION DATA MANAGEMENT SPECIALIST
group meetings (EGMs) regularly.
• Manage and analyze data related and conduct spot check regularly according to the spot-check guideline;
• Provide inputs and recommendation to PMU/PIU on issues related to quality and implementation of data management
A. Implementation Team
POSITION SAFEGUARD SPECIALIST (ENVIRONMENT)
Reporting to CPIU, Team Leader
Duration 42 months
Location Jakarta-based
POSITION SAFEGUARD SPECIALIST (ENVIRONMENT)
Experience • Bachelor Degree (S1) in relevant major, preferably in civil engineering or architect or environment engineer
(Min. • Having minimum 10 years working experience with strong technical skills (Specialist) in developing and implementing
Qualification, safeguard environment mechanism for major infrastructure projects with a broad geographic focus and multiple levels of
Experience) project implementation or settlement development. More than 15 years of experience will not be considered to have additional
points in the evaluation.
• Having minimum 5 years working experience with strong leadership roles in relevant project or team management.
• He/she shall have good interpersonal communications and management skills, computer literates for safeguard, team-work
abilities, and must be able to have an extensive field-trip to project areas.
Tasks Assi gned • Provide overall program management in safeguard, including program planning, implementation, supervision, monitoring and
evaluation as well as quality assurance, in line with the agreed implementation guidelines.
• Provide necessary services related to safeguard as well as guidance to achieve KPIs and PDO and establish the technical
assistances.
• Ensure overall implementation and performances of the programs related safeguard (as in point 5 in Annex 5 scope of works).
• Ensure compliance of Environmental and Social Management Framework (ESMF) in planning and implementation and also
compliance of Land Acquisition and Resettlement Policy Framework (LARPF) where needed into planning document.
• Ensure compliance of Environmental and Social Management Framework (ESMF) in implementation of infrastructure
activities.
• Manage and coordinate safeguard team at all level and ensure quality of their performance, including organizing expert group
meetings (EGMs) regularly.
• Manage and analyze data related to safeguard, and ensure data accuracy and timely submission of reports in the MIS.
• Conduct spot check regularly according to the spot-check guideline;
• Provide inputs and recommendation to PMU/PIU on issues related to quality and implementation of planning activities,
including SIAPs and CSPs.
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• Quality of system and data MIS and its reporting
• Annual work plan for relevant activities.
• Spot check, supervision and monitoring report
• New approach and method for safeguard to improve program performance, as needed
• Best practice in safeguard
Accountability • Relevant KPI
95
POSITION SAFEGUARD SPECIALIST (ENVIRONMENT)
• Accurate MIS on relevant data
• Good Performance of Safeguard Specialist in OSP, assistant city coordinator and facilitator
• Compliance of environmental and social safeguard in overall program management
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
97
B. Knowledge Management Team
99
C. Project Management Team
POSITION PROGRAM MONITO RING SPECIALIST
Reporting to CPIU, Team Leader
Duration 42 months
Location Jakarta -based
Experience • Bachelor Degree (S1) and preferably Master Degree (S2) in any relevant major.
(Min. • Having minimum 10 years of experience with strong technical and management skills in project management on program
Qualification, monitoring (develop monitoring mechanism, data analyze, reporting, quality control implementation). Having experience on
Experience) urban/settlement development or community-based development program in similar type of program scale will be an
advantage. More than 15 years of experience will not be considered to have additional points in the evaluation.
• Having minimum 5 years working experience with strong leadership roles in relevant project or team management.
• He/she shall have good interpersonal communications and management skills, computer literates for infrastructure, team-work
abilities, and must be able to have an extensive field-trip to project areas.
Tasks Assigned • Ensuring good quality of slum upgrading implementation through, amongst others, development and continuous updating of
project guidelines, manuals, and operation of an effective flow of information and resources across levels of governments up to
beneficiaries, development and implementation of knowledge management strategy (including its curriculum, modules, media,
etc), vigorous and systematic supervision and spot checks and provision of evidence based policy proposals;
• Establishing training, capacity building, knowledge management, including to manage an ICT-based learning and knowledge
sharing; carry-out expert group meetings, stakeholders’ workshops and training; establish an effective dissemination of project
policies, guidelines and operating standard, and learning materials. Included in this task is to develop and deliver learning
materials, provide coaching and backstop and follow up the training and workshop events; and to manage project-related
information-sharing through general social media applications (i.e: facebook, twitter, instagram)
• Provide overall program management, including program planning, implementation, supervision, monitoring and evaluation as
well as quality assurance, in line with the agreed implementation to achieve KPIs and PDO
• Conduct and manage overall monitoring of the program, Management Information System (MIS) and data management,
program web-site, Complaint Handling (CH), manage and analyze data and ensure data accuracy and timely submission of
reports in the MIS, provide regular reports of program monitoring on the website, in timely manner;
• Develop supervision, monitoring and spot-check strategy and schedule including target and reporting, ensure follow up and
upload of the results on website in timely manner, and update the relevant guidelines and operating standards, conduct spot
check regularly according to the spot-check guideline, ensure that OSPs and TMCs will carry out and upload the result of spot-
check on website
• Facilitate, monitor and supervise OSPs, TMCs, and City Coordinator team, and facilitator team on the implementation of
program monitoring activities to meet the optimal quality; manage and coordinate program monitoring team at all level and
POSITION PROGRAM MONITO RING SPECIALIST
ensure quality of their performance, including organizing expert group meetings (EGMs) regularly.
• Provide inputs and recommendation to PMU/PIU on issues related to program monitoring.
Reporting and • Data analysis and all NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Tools for spot check and monitoring target of KPIs
• Annual work plan for relevant activities.
• New methods and approach for program monitoring as needed
• Best practices in program monitoring
Accountability • Overall program monitoring through web based MIS and android is running well and effective
• SOP, tools for data monitoring, analysis, and reports of monitoring and spot checks
• Timely and effective spot checks conducted by NMC, OSP, and korkot
• Timely and accurate data and analysis of MIS
• Good Performance of monev specialist at OSP, assistant city coordinator and facilitator
• Capability to analyze MIS data and use it for quality assurance
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Inter-ministries, Local Government, OSPs, TMCs
Relationship
101
POSITION FINANCIAL MANAGEMENT REVIEW SPECIALIST
Tasks Assigned • Provide overall program management related financial management review, including program planning, implementation,
supervision, monitoring and evaluation as well as quality assurance, in line with the agreed implementation guidelines.
• Provide necessary services related to financial management review as well as guidance to achieve KPIs and PDO and establish
the technical assistances.
• Ensure accuracy and timely submission of Financial Management Reports (FMR), including: compilation of payment
documents (SPP, SPM and SP2D), preparation of quarterly Interim financial reports from special account reconciliation and
other supporting document on withdrawal applications for the World Bank through the Ministry of Finance; monitor and
analyse status of special account, and follow up issues with related agency; and formulate materials on withdrawal mechanism.
• Manage and coordinate financial sub professional team at OSPs and ensure quality of their performance.
• Manage and analyze data and ensure data accuracy and timely submission of reports in the MIS.
• Conduct spot check regularly according to the spot-check guideline.
• Provide inputs and recommendation to PMU/PIU on issues related to financial management review.
• Provide regular reports of program monitoring on the website, in timely manner;
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• Quality of financial management review activities and capacity for all stakeholder
• Annual work plan for relevant activities.
• Interim Financial Report with accurate financial activities in timely manner
• Follow up audit reports
• Process and report related to loan administration in MoF
• Quarterly Report for Bappenas
Accountability • Relevant KPI
• Good quality training activities and its impact
• Accurate MIS on relevant data
• Good Performance of financial sub professional in OSP
• Good loan management (withdrawal forcasting, time and amount, regular monitoring for client connection, etc)
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs, Ministry of Finance
Relationship
103
POSITION LEGAL AND COMPLAINT HANDLING SPECIALIST
• Complaints distribution to the suitable specialist
• New method and approach for complaint handling as needed
• Best practices in complaing handling
• Legal advice to all stakeholder
Accountability • Relevant KPI
• Good quality complaint handling management and system and its impact
• Accurate MIS on relevant data
• Good Performance of Complaint handler personnel in OSP, assistant city coordinator and facilitator
• Service standard for handling complaint
• Complaint followed up
• Availability of network with law enforcer and law aid
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
POSITION WEB MASTER SPECIALIST
Reporting to CPIU, Team Leader
Duration 42 months
Location Jakarta -based
Experience • Bachelor Degree (S1) and preferably Master Degree (S2) in informatica/computer science.
(Min. • Having minimum 10 years of experience with strong technical skills in web development, maintenance and management
Qualification, (experience in HTML, CSS, XML, Java C++, in new web trend, VB script, FTP, dreamweaver, flash, adobe illustrator or other
Experience) new program design, Having good knowledge in SEO and any other program related to development and management of
web).
• Having minimum 5 years working experience with strong leadership roles in relevant project or team management.
• He/she shall have good interpersonal communications and management skills, computer literates for infrastructure, team-work
abilities, and must be able to have an extensive field-trip to project areas.
Tasks Assigned • Provide overall program management in program web site, including program planning, implementation, supervision,
monitoring and evaluation as well as quality assurance, in line with the agreed implementation guidelines.
• Provide necessary services related to program web site as well as guidance to achieve KPIs and PDO and establish the
technical assistances.
• Conduct and manage overall program web-site.
• Ensure overall implementation and performances of the programs related program web site (as in point 5 in Annex 5 scope of
works).
• Manage and coordinate team that related with program web site at all level and ensure quality of their performance.
• Manage and analyze data related to program web site, and ensure data accuracy and timely submission of reports in the MIS.
• Provide inputs and recommendation to PMU/PIU on issues related to program website.
Reporting and • All NMC reports relevant activities
Deliverables • Guidelines and SOPs relevant activities
• Strategy, Implementation Plan, and Target for relevant KPIs and outputs
• Quality of program website
• Annual work plan for relevant activities.
Accountability • Relevant KPI
• Good quality program website
• …
105
POSITION WEB MASTER SPECIALIST
Critical Executing Agency (DGHS and Bappenas), PMU, PIUs, Interministries, Local Government, OSPs, TMCs
Relationship
107
IV. Sub-professional Personel
Subprofessional will be support professional staff in task assigned and providing reporting and
deliverables. Accountability of subprofessional related to professional personnel.
Subprofessional and its qualification as follow:
109
No Proposed Position Qualification
alleviation/settlement development program.
13 Sub-Proff Training • Bachelor Degree (S1) in any relevant major.
for Government • Having experience with technical skills in training. Experience in
community empowerment program will be an advantage.
• He/she shall have good interpersonal communications and management
skills, computer literates, team-work abilities, and must be able to have an
extensive field-trip to project areas.with the same scale.
14 Sub-Proff Training • Bachelor Degree (S1) in any relevant major.
for Community • Having experience with technical skills in training. Experience in
community empowerment program will be an advantage.
• He/she shall have good interpersonal communications and management
skills, computer literates, team-work abilities, and must be able to have an
extensive field-trip to project areas.with the same scale.
16 Sub-Proff for • Bachelor Degree (S1) in communication,
Socialization • Having experience with technical skills in communication. Experience in
community empowerment program will be an advantage.
• He/she shall have good interpersonal communications and management
skills, computer literates, team-work abilities, and must be able to have an
extensive field-trip to project areas.with the same scale.
111
No Proposed Position Qualification
• He/she shall have good interpersonal communications and management
skills, computer literates, team-work abilities, and must be able to have an
extensive field-trip to project areas.with the same scale.program
30 Sub-Proff for To be determined by PMU/CPIU
Additional Advanced
Program
31 Assistant for • Educational background from all major
Training • He/she shall have good interpersonal communications, computer literates,
team-work abilities, and must be able to have an extensive field-trip to
project areas.with the same scale.program
32 Assistant for • Educational background from communication/design graphic/design
Publication/Illustrator communication visual/art
• Having experience in making publication product/illustration
• He/she shall have good interpersonal communications, computer literates,
team-work abilities, and must be able to have an extensive field-trip to
project areas.with the same scale.program
33 Assistant for Social • Educational background from all major
Media and e-media • Having experience in managing content of social media and e-media
• He/she shall have good interpersonal communications, computer literates,
team-work abilities, and must be able to have an extensive field-trip to
project areas.with the same scale.program
22 Assistant for Program • Educational background from all major
Monitoring • Having experience in community empowerment program, local
government facilitation, and other program focused on capacity building
with the same scale
• He/she shall have good interpersonal communications, computer literates,
team-work abilities, and must be able to have an extensive field-trip to
project areas.with the same scale.program
ANNEX 7
COVERAGE AREAS (LOCATION)
1
KOTA SALATIGA 4 23 19 4 -
KOTA SEMARANG 16 177 115 62 415.930
KOTA TEGAL 4 27 16 11 191.130
KUDUS 6 86 66 20 -
PATI 4 101 83 18 107.392
PEKALONGAN 8 119 85 34 671.844
PEMALANG 4 79 66 13 137.300
REMBANG 2 54 46 8 59.527
SEMARANG 3 30 24 6 193.540
TEGAL 7 116 114 2 -
WONOSOBO 1 20 15 5 70.829
TEMANGGUNG 2 41 35 6 8.340
20 84 1,201 950 251 2,787
113
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
WONOGIRI 2 26 21 5 24.470
BANJARNEGARA 1 13 4 9 58.215
BANYUMAS 8 85 75 10 69.578
BOYOLALI 5 61 60 1 0.358
CILACAP 3 15 9 6 20.840
KARANGANYAR 5 51 30 21 68.277
KLATEN 15 212 201 11 145.530
KOTA MAGELANG 3 17 10 7 -
KEBUMEN 3 54 41 13 69.574
2
MAGELANG 2 27 21 6 69.910
PURBALINGGA 3 44 39 5 32.390
PURWOREJO 1 27 22 5 109.275
SRAGEN 2 16 14 2 2.330
SUKOHARJO 6 83 76 7 35.276
KOTA SURAKARTA 5 51 - 51 467.610
15 64 782 623 159 1,174
35 148 1,983 1,573 410 3,960
2 DI YOGYAKARTA BANTUL 12 50 37 13 27.290
KOTA YOGYAKARTA 14 45 12 33 271.070
KULON PROGO 1 8 6 2 8.730
SLEMAN 15 75 58 17 41.410
4 42 178 113 65 349
19 106 960 736 224 1,522
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
3 JAWA TIMUR BANGKALAN 1 13 12 1 -
BOJONEGORO 1 18 12 6 -
GRESIK 5 103 63 40 102.790
JOMBANG 7 113 112 1 12.070
KOTA MOJOKERTO 2 18 11 7 -
KOTA SURABAYA 31 154 142 12 239.533
KOTA MADIUN 3 27 21 6 -
3
LAMONGAN 2 37 30 7 18.220
MADIUN 1 14 14 - -
MAGETAN 3 42 41 1 -
MOJOKERTO 6 100 96 4 -
NGANJUK 3 50 43 7 -
PACITAN 1 25 20 5 12.200
PAMEKASAN 1 18 11 7 -
PONOROGO 2 37 30 7 30.070
SIDOARJO 15 289 288 1 18.150
SUMENEP 2 23 13 10 -
TUBAN 1 17 10 7 -
18 87 1,098 969 129 433
115
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
TULUNGAGUNG 5 81 71 10 150.050
BANYUWANGI 5 45 42 3 -
BLITAR 3 37 32 5 -
BONDOWOSO 1 11 8 3 59.640
JEMBER 5 37 34 3 -
KEDIRI 4 46 43 3 -
KOTA BATU 3 24 24 - -
4
KOTA BLITAR 3 21 20 1 -
KOTA KEDIRI 3 46 42 4 -
KOTA PASURUAN 3 34 23 11 58.870
KOTA PROBOLINGGO 5 29 6 23 197.970
KOTA MALANG 5 57 28 29 555.590
LUMAJANG 1 12 8 4 15.761
MALANG 7 98 98 - -
PASURUAN 6 91 80 11 -
PROBOLINGGO 3 47 46 1 -
SITUBONDO 4 30 29 1 -
TRENGGALEK 1 13 10 3 69.940
18 67 759 644 115 1,108
36 154 1,857 1,613 244 1,541
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
4 BALI BADUNG 2 11 11 - -
BULELENG 1 29 23 6 35.180
GIANYAR 2 17 10 7 6.970
KLUNGKUNG 2 30 25 5 37.000
KOTA DENPASAR 4 43 37 6 15.010
5 11 130 106 24 94.160
5 NUSA TENGGARA BARAT KOTA BIMA 5 38 21 17 59.480
KOTA MATARAM 6 50 25 25 303.570
LOMBOK BARAT 2 22 16 6 -
5
LOMBOK TENGAH 2 26 20 6 59.030
LOMBOK TIMUR 6 67 51 16 177.830
SUMBAWA 2 16 12 4 -
6 23 219 145 74 599.910
6 NUSA TENGGARA TIMUR BELU 1 4 1 3 7.950
ENDE 1 5 4 1 -
KOTA KUPANG 6 51 40 11 39.100
MANGGARAI 1 11 8 3 2.710
NGADA 1 20 16 4 -
SIKKA 1 7 5 2 4.890
SUMBA BARAT 1 12 9 3 -
SUMBA TIMUR 1 7 4 3 63.080
TIMOR TENGAH SELATAN 1 13 11 2 -
9 14 130 98 32 117.730
20 48 479 349 130 812
7 KALIMANTAN TENGAH KOTA PALANGKA RAYA 5 30 27 3 50.000
KOTAWARINGIN TIMUR 1 11 7 4 34.160
2 6 41 34 7 84.160
8 KALIMANTAN SELATAN BANJAR 1 26 20 6 151.550
BARITO KUALA 1 10 9 1 -
6
HULU SUNGAI SELATAN 1 18 17 1 7.226
HULU SUNGAI TENGAH 1 18 12 6 61.070
HULU SUNGAI UTARA 1 29 19 10 125.480
KOTA BANJAR BARU 5 20 19 1 349.120
KOTA BANJARMASIN 5 52 - 52 709.700
KOTABARU 1 21 18 3 149.600
TABALONG 2 25 22 3 -
TANAH LAUT 1 20 17 3 -
10 19 239 153 86 1,553.746
12 25 280 187 93 1,638
117
9 KALIMANTAN TIMUR BERAU 1 6 3 3 -
7
KOTA BALIKPAPAN 6 34 22 12 282.200
KOTA BONTANG 3 15 7 8 91.600
KOTA SAMARINDA 10 53 41 12 387.493
KUTAI KARTANEGARA 2 21 19 2 -
PASER 1 16 13 3 -
6 23 145 105 40 761
10 SULAWESI UTARA KEPULAUAN SANGIHE 3 22 11 11 34.090
KOTA BITUNG 8 69 64 5 34.560
KOTA MANADO 9 87 77 10 124.000
KOTA KOTAMOBAGU 4 33 26 7 36.070
KOTA TOMOHON 5 44 36 8 -
8
MINAHASA 5 43 31 12 12.150
MINAHASA UTARA 1 9 9 - -
7 35 307 254 53 240.870
14 GORONTALO GORONTALO 2 23 18 5 12.750
KOTA GORONTALO 9 50 44 6 159.300
2 11 73 62 11 172.050
17 MALUKU UTARA KOTA TERNATE 7 77 65 12 20.390
KOTA TIDORE KEPULAUAN 8 75 71 4 -
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
11 SULAWESI TENGAH KOTA PALU 8 45 31 14 85.160
POSO 1 4 3 1 -
TOLI-TOLI 1 9 4 5 -
3 10 58 38 20 85.160
12 SULAWESI SELATAN BANTAENG 1 9 5 4 -
BONE 1 8 1 7 68.720
BULUKUMBA 1 9 3 6 23.000
GOWA 1 14 - 14 196.150
KOTA MAKASSAR 14 143 40 103 740.020
9
KOTA PALOPO 9 48 39 9 89.334
KOTA PARE-PARE 4 22 4 18 274.000
MAROS 1 7 5 2 4.210
PINRANG 1 6 4 2 -
SELAYAR 1 3 - 3 11.050
SIDENRENG RAPPANG 1 12 9 3 11.000
SINJAI 1 6 2 4 67.085
TORAJA UTARA 2 18 16 2 24.390
WAJO 1 16 1 15 36.358
14 39 321 129 192 1,545.317
15 SULAWESI BARAT MAJENE 1 8 3 5 21.490
POLEWALI MANDAR 1 9 5 4 7.440
2 2 17 8 9 28.930
19 51 396 175 221 1,659
119
OVERSIGHT SERVICE JUMLAH JUMLAH JML LOKASI JML LOKASI
NO PROVINSI KABUPATEN/KOTA JML LUAS KUMUH (Ha)
PROVIDER KECAMATAN KELURAHAN/DESA PENCEGAHAN KUMUH
10
13 SULAWESI TENGGARA KOLAKA 2 14 - 14 105.230
KOTA BAU-BAU 7 43 39 4 21.660
KOTA KENDARI 10 64 11 53 397.700
MUNA 1 8 2 6 94.980
4 20 129 52 77 620
16 MALUKU KOTA AMBON 5 50 35 15 102.626
KOTA TUAL 4 29 18 11 63.390
11
MALUKU TENGAH 1 5 2 3 5.820
3 10 84 55 29 171.836
18 PAPUA BARAT KOTA SORONG 6 31 14 17 51.700
MANOKWARI 1 10 7 3 43.510
2 7 41 21 20 95.210
19 PAPUA KOTA JAYAPURA 5 39 28 11 101.740
1 5 39 28 11 101.740
153 594 6,143 4,723 1,420 12,141.669
WILAYAH 2 (WB LOAN) 153 594 6,143 4,723 1,420 12,141.669
ANNEX 8
CITY COORDINATOR AND FACILITATOR TEAM
08. Ask
10.
06. Ask Kelembag 09. 16.
01. 02. Askot 03. Ask 04. Ask 05. Ask 07. Askot Jumlah
NO OVERSIGHT SERVICE PROVIDER PROVINSI KABUPATEN/KOTA Urban aan & Jumlah 11. SF 12. F.Tek 13. F.UP 14. F.Sos 15. F.Ek Jumlah 17. TOTAL
Korkot Mandiri Infra Ekonomi Mandat Safeguard Tim
Planner Kolaboras Korkot Tim Faskel
Korkot
i
1 JAWA TENGAH GROBOGAN 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
BLORA 0 1 0 0 0 0 0 0 0 1 5 8 2 5 5 25 26
REMBANG 0 1 0 0 0 0 0 0 0 1 6 10 2 6 6 30 31
PATI 0 1 0 0 0 0 0 0 0 1 9 15 3 9 9 45 46
KUDUS 0 1 0 0 0 0 0 0 0 1 8 13 3 8 8 40 41
JEPARA 0 1 0 0 0 0 0 0 0 1 7 13 1 7 7 35 36
DEMAK 1 0 1 1 1 1 1 1 1 7 2 3 1 2 2 10 17
SEMARANG 1 0 1 1 1 1 1 1 1 7 3 5 1 3 3 15 22
1
TEMANGGUNG 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
KENDAL 1 0 1 1 1 1 1 1 1 7 6 10 2 6 6 30 37
BATANG 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
PEKALONGAN 1 0 1 1 1 1 1 1 1 7 14 21 7 14 14 70 77
PEMALANG 1 0 1 1 1 1 1 1 1 7 8 13 3 8 8 40 47
TEGAL 0 1 0 0 0 0 0 0 0 1 9 18 0 9 9 45 46
BREBES 0 1 0 0 0 0 0 0 0 1 4 6 2 4 4 20 21
KOTA SALATIGA 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTA SEMARANG 1 0 1 1 1 1 1 1 1 7 21 30 12 21 21 105 112
KOTA PEKALONGAN 1 0 1 1 1 1 1 1 1 7 4 5 3 4 4 20 27
KOTA TEGAL 1 0 1 1 1 1 1 1 1 7 3 4 2 3 3 15 22
WONOSOBO 1 0 1 1 1 1 1 1 1 7 2 3 1 2 2 10 17
20 9 11 9 9 9 9 9 9 9 74 122 195 49 122 122 610 684
121
CILACAP 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
BANYUMAS 1 0 1 1 1 1 0 1 1 6 8 14 2 8 8 40 46
PURBALINGGA 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
BANJARNEGARA 0 1 0 0 0 0 0 0 0 1 3 3 2 2 3 13 14
KEBUMEN 0 1 0 0 0 0 0 0 0 1 5 8 2 5 5 25 26
PURWOREJO 1 0 1 1 1 1 1 1 1 7 3 5 1 3 3 15 22
MAGELANG 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
BOYOLALI 0 1 0 0 0 0 0 0 0 1 5 10 0 5 5 25 26
KLATEN 0 1 0 0 0 0 0 0 0 1 17 32 2 17 17 85 86
2
SUKOHARJO 0 1 0 0 0 0 0 0 0 1 7 13 1 7 7 35 36
WONOGIRI 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
KARANGANYAR 0 1 0 0 0 0 0 0 0 1 6 8 4 6 6 30 31
SRAGEN 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
KOTA SURAKARTA 1 0 1 1 1 1 1 1 1 7 10 10 10 10 10 50 57
KOTA MAGELANG 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
15 3 12 3 3 3 3 2 3 3 32 79 128 29 78 79 393 425
35 12 23 12 12 12 12 11 12 12 106 201 323 78 200 201 1003 1109
2 DI YOGYAKARTA KULON PROGO 0 1 0 0 0 0 0 0 0 1 1 1 0 0 1 3 4
BANTUL 0 1 0 0 0 0 0 0 0 1 5 8 2 5 5 25 26
SLEMAN 0 1 0 0 0 0 0 0 0 1 7 11 3 7 7 35 36
KOTA YOGYAKARTA 1 0 1 1 1 1 1 1 1 7 8 9 7 8 8 40 47
4 1 3 1 1 1 1 1 1 1 10 21 29 12 20 21 103 113
19 4 15 4 4 4 4 3 4 4 42 100 157 41 98 100 496 538
3 JAWA TIMUR PACITAN 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
PONOROGO 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
SIDOARJO 1 0 1 1 1 1 1 1 1 7 22 44 0 22 22 110 117
MOJOKERTO 0 1 0 0 0 0 0 0 0 1 8 15 1 8 8 40 41
JOMBANG 0 1 0 0 0 0 0 0 0 1 9 18 0 9 9 45 46
NGANJUK 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
MADIUN 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
3
MAGETAN 0 1 0 0 0 0 0 0 0 1 3 6 0 3 3 15 16
BOJONEGORO 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
TUBAN 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
LAMONGAN 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
GRESIK 1 0 1 1 1 1 1 1 1 7 13 18 8 13 13 65 72
BANGKALAN 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
PAMEKASAN 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
SUMENEP 0 1 0 0 0 0 0 0 0 1 3 4 2 3 3 15 16
KOTA MOJOKERTO 0 1 0 0 0 0 1 1 1 7 2 3 1 2 2 10 17
KOTA MADIUN 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
KOTA SURABAYA 1 0 1 1 1 1 1 1 1 7 13 24 2 13 13 65 72
18 3 15 3 3 3 3 4 4 4 42 97 172 22 97 97 485 527
KOTA BATU 0 1 0 0 0 0 0 0 0 1 2 4 0 2 2 10 11
TRENGGALEK 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
TULUNGAGUNG 1 0 1 1 1 1 1 1 1 7 7 12 2 7 7 35 42
BLITAR 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
KEDIRI 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
MALANG 0 1 0 0 0 0 0 0 0 1 8 16 0 8 8 40 41
LUMAJANG 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
4
JEMBER 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
BANYUWANGI 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
BONDOWOSO 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
SITUBONDO 0 1 0 0 0 0 0 0 0 1 2 4 0 2 2 10 11
PROBOLINGGO 0 1 0 0 0 0 0 0 0 1 4 8 0 4 4 20 21
PASURUAN 0 1 0 0 0 0 0 0 0 1 8 14 2 8 8 40 41
KOTA KEDIRI 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
KOTA BLITAR 0 1 0 0 0 0 0 0 0 1 2 4 0 2 2 10 11
KOTA MALANG 1 0 1 1 1 1 1 1 1 7 8 10 6 8 8 40 47
KOTA PROBOLINGGO 1 0 1 1 1 1 1 1 1 7 6 6 5 5 6 28 35
KOTA PASURUAN 0 1 0 0 0 0 0 0 0 1 4 6 2 4 4 20 21
18 3 15 3 3 3 3 3 3 3 36 76 126 25 75 76 378 414
36 6 30 6 6 6 6 7 7 7 78 173 298 47 172 173 863 941
4 BALI BADUNG 1 0 1 1 1 1 1 1 1 7 1 2 0 1 1 5 12
GIANYAR 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KLUNGKUNG 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
BULELENG 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
KOTA DENPASAR 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
5 1 4 1 1 1 1 1 1 1 11 13 22 4 13 13 65 76
5 NUSA TENGGARA BARAT LOMBOK BARAT 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
LOMBOK TENGAH 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
LOMBOK TIMUR 1 0 1 1 1 1 1 1 1 7 7 11 3 7 7 35 42
SUMBAWA 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
5
KOTA MATARAM 1 0 1 1 1 1 1 1 1 7 7 9 5 7 7 35 42
KOTA BIMA 1 0 1 1 1 1 1 1 1 7 5 7 3 5 5 25 32
6 3 3 3 3 3 3 3 3 3 24 26 38 14 26 26 130 154
6 NUSA TENGGARA TIMUR SUMBA BARAT 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
SUMBA TIMUR 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
TIMOR TENGAH SELATAN 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
BELU 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
SIKKA 0 1 0 0 0 0 0 0 0 1 1 1 0 0 1 3 4
ENDE 1 0 1 1 1 1 0 1 1 6 1 1 0 0 1 3 9
NGADA 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
MANGGARAI 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTA KUPANG 1 0 1 1 1 1 1 1 1 7 5 8 2 5 5 25 32
9 2 7 2 2 2 2 1 2 2 20 18 25 7 14 18 82 102
20 6 14 6 6 6 6 5 6 6 55 57 85 25 53 57 277 332
7 KALIMANTAN TENGAH KOTAWARINGIN TIMUR 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTA PALANGKA RAYA 1 0 1 1 1 1 1 1 1 7 3 5 1 3 3 15 22
2 1 1 1 1 1 1 1 1 1 8 5 8 2 5 5 25 33
8 KALIMANTAN SELATAN TANAH LAUT 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTABARU 1 0 1 1 1 1 1 1 1 7 2 3 1 2 2 10 17
6
BANJAR 1 0 1 1 1 1 1 1 1 7 3 5 1 3 3 15 22
BARITO KUALA 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
HULU SUNGAI SELATAN 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
HULU SUNGAI TENGAH 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
HULU SUNGAI UTARA 0 1 0 0 0 0 0 0 0 1 3 4 2 3 3 15 16
TABALONG 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
KOTA BANJARMASIN 1 0 1 1 1 1 1 1 1 7 10 10 10 10 10 50 57
KOTA BANJAR BARU 1 0 1 1 1 1 1 1 1 7 1 2 0 1 1 5 12
10 4 6 4 4 4 4 4 4 4 34 28 39 17 28 28 140 174
12 5 7 5 5 5 5 5 5 5 42 33 47 19 33 33 165 207
9 KALIMANTAN TIMUR PASER 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
7
KUTAI KARTANEGARA 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
BERAU 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
KOTA BALIKPAPAN 1 0 1 1 1 1 1 1 1 7 4 6 2 4 4 20 27
KOTA SAMARINDA 1 0 1 1 1 1 1 1 1 7 5 8 2 5 5 25 32
KOTA BONTANG 1 0 1 1 1 1 1 1 1 7 2 3 1 2 2 10 17
6 3 3 3 3 3 3 3 3 3 24 16 24 7 15 16 78 102
10 SULAWESI UTARA MINAHASA 1 0 1 1 1 1 1 0 1 6 4 6 2 4 4 20 26
KEPULAUAN SANGIHE 0 1 0 0 0 0 0 0 0 1 3 4 2 3 3 15 16
MINAHASA UTARA 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
KOTA MANADO 1 0 1 1 1 1 1 1 1 7 8 14 2 8 8 40 47
KOTA BITUNG 0 1 0 0 0 0 0 0 0 1 6 11 1 6 6 30 31
8
KOTA TOMOHON 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
KOTA KOTAMOBAGU 0 1 0 0 0 0 0 0 0 1 3 5 1 3 3 15 16
7 2 5 2 2 2 2 2 1 2 18 29 49 9 29 29 145 163
11 GORONTALO GORONTALO 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTA GORONTALO 1 0 1 1 1 1 1 1 1 7 4 7 1 4 4 20 27
2 1 1 1 1 1 1 1 1 1 8 6 10 2 6 6 30 38
12 MALUKU UTARA KOTA TERNATE 1 0 1 1 1 1 1 1 1 7 7 12 2 7 7 35 42
KOTA TIDORE KEPULAUAN 0 1 0 0 0 0 0 0 0 1 6 11 1 6 6 30 31
2 1 1 1 1 1 1 1 1 1 8 13 23 3 13 13 65 73
11 4 7 4 4 4 4 4 3 4 34 48 82 14 48 48 240 274
123
13 SULAWESI TENGAH POSO 0 1 0 0 0 0 0 0 0 1 1 1 0 0 1 3 4
TOLI-TOLI 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
KOTA PALU 1 0 1 1 1 1 1 1 1 7 5 7 3 5 5 25 32
3 1 2 1 1 1 1 1 1 1 9 8 10 4 6 8 36 45
14 SULAWESI SELATAN SELAYAR 0 1 0 0 0 0 0 0 0 1 1 1 1 1 1 5 6
BULUKUMBA 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
BANTAENG 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
GOWA 1 0 1 1 1 1 1 1 1 7 3 3 3 3 3 15 22
SINJAI 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
9
MAROS 0 1 0 0 0 0 0 0 0 1 1 1 0 0 1 3 4
BONE 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
WAJO 0 1 0 0 0 0 0 0 0 1 4 4 3 3 4 18 19
SIDENRENG RAPPANG 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
PINRANG 0 1 0 0 0 0 0 0 0 1 1 1 0 0 1 3 4
TORAJA UTARA 0 1 0 0 0 0 0 0 0 1 1 2 0 1 1 5 6
KOTA MAKASSAR 1 0 1 1 1 1 1 1 1 7 24 27 21 24 24 120 127
KOTA PARE-PARE 1 0 1 1 1 1 1 1 1 7 5 5 4 4 5 23 30
KOTA PALOPO 1 0 1 1 1 1 1 1 1 7 5 8 2 5 5 25 32
14 4 10 4 4 4 4 4 4 4 38 55 63 39 47 55 259 297
15 SULAWESI BARAT MAJENE 1 0 1 1 1 1 1 1 1 7 2 2 1 1 2 8 15
POLEWALI MANDAR 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
2 1 1 1 1 1 1 1 1 1 8 4 4 2 2 4 16 24
19 6 13 6 6 6 6 6 6 6 55 67 77 45 55 67 311 366
10
16 SULAWESI TENGGARA MUNA 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
KOLAKA 1 0 1 1 1 1 1 1 1 7 2 2 2 2 2 10 17
KOTA KENDARI 1 0 1 1 1 1 1 1 1 7 12 13 11 12 12 60 67
KOTA BAU-BAU 0 1 0 0 0 0 0 0 0 1 4 7 1 4 4 20 21
4 2 2 2 2 2 2 2 2 2 16 20 24 15 19 20 98 114
17 MALUKU MALUKU TENGAH 0 1 0 0 0 0 0 0 0 1 2 2 1 1 2 8 9
KOTA AMBON 1 0 1 1 1 1 1 1 1 7 6 9 3 6 6 30 37
KOTA TUAL 1 0 1 1 1 1 1 1 1 7 3 4 2 3 3 15 22
11
3 2 1 2 2 2 2 2 2 2 15 11 15 6 10 11 53 68
18 PAPUA KOTA JAYAPURA 1 0 1 1 1 1 1 1 1 7 4 6 2 4 4 20 27
1 1 0 1 1 1 1 1 1 1 7 4 6 2 4 4 20 27
19 PAPUA BARAT MANOKWARI 0 1 0 0 0 0 0 0 0 1 2 3 1 2 2 10 11
KOTA SORONG 1 0 1 1 1 1 1 1 1 7 4 5 3 4 4 20 27
2 1 1 1 1 1 1 1 1 1 8 6 8 4 6 6 30 38
6 4 2 4 4 4 4 4 4 4 30 21 29 12 20 21 103 133
153 49 104 49 49 49 49 48 49 50 450 657 1,018 274 635 657 3,241 3,691
6. Slums location is defined as: (1) Have Mayor/Regent Decree of Slum area locations, with the
slum profil; (2) Urban District; (3) Slum area Profil based on community mapping and
planning; (4) Local Goverment commitment to support slum alleviation.
7. Prevention location is defined as: (1) NSUP Locations; (2) 100-0-100 Profil based on
community mapping and planning; and (3) Local Goverment commitment to support 100-0-
100 Movement.
8. For NSUP, as has been identified as in Surat Edaran Direktur Jenderal Cipta Karya number
110/KPTS/DC/2016 about Penetapan Lokasi Program KOTAKU
(http://kotaku.pu.go.id/pustakadetil.asp?mid=455&catid=3&), City scale location has been
selected 44 from 65 long list plus DKI Jakarta. The selection criteria are population
characteristic, size of slum area, gaps in access to infrastructure and services, local
government commitment to implement NSUP, location 30 priority for slum alleviation set by
Minister of PWH, and here are the location:
125
Figure 7.2 Location for City Scale Infrastructure
9. NMC should visit minimum 4 kelurahan in each targeted spot check city/regency.
a. Monthly Report
Monthly report should be submitted according to executive summary format, which covers NMC
administrative activities, progress of work to date, and planning for next month. The monthly report
does not need to be submitted at time of quarterly report submission.
b. Quarterly Report
Quarterly report contains implementation progress, outstanding activities, problems encountered and
planned solutions. The report should be submitted in 15 copies and NMC should also make a
presentation to project steering committee on behalf of Project /PMU.
c. Annual Report
This report contains annual progress on implementation result and outcomes. The report must
be submitted in both English and Bahasa Indonesia not later than January 31` each year and
published in KOTAKU website. The report must be presented to the PMU.
d. Final Report
This report contains a comprehensive review on project implementation results and outcomes,
lessons-learned, experiences, and conclusions as well as recommendations for future improvements.
The report must be submitted not later than 20 days after completion of services and provided in 15
copies. The draft final report must be presented to the project steering committee. The Final report
must be available in English with acceptable quality. Advisory/R & D Team will assess this draft and
final report and provide recommendations to PMU in relation to revise or finalize.
e. Special Reports
Special reports anticipated including:
• performance evaluations of special city coordinator teams
• training activity reports
• complaint resolution follow-up reports
• workshop findings and results
• coordination meeting results
127
g. Project Data
All project data generated in the process of undertaking this assignment is the property of the
Government of Indonesia, and NMC is responsible for the proper and accurate preparation,
utilization, maintenance and storage in the project MIS database. NMC must ensure that all data and
information will be handed over to the project/PMU after completion of services.
All reports will use, and must be consistent with, data from the website published MIS data
(http://kotatanpakumuh.pu.go.id).