This means, basic prices for the supply of material are inclusive of wastage
caused by the Bidder/Contractor.
Therefore, the Unit Rate Breakdown Analysis should consider only the exact
quantity of material required for the corresponding item without adding wastage
in percent.
Reviewer: Alexander O.
Review No.: 01
Signature: __________
Date: October 21, 2022