GROUP-3

CONSTRUCTION PROJECT EXECUTION, MONITORING AND CONTROL CM-4000

SHIVALIK SHARDA
HARMONY
SITE LAYOUT ANALYSIS-
VISUALIZATION

Guided By: Prepared By:


Prof. Jyoti Trivedi Hetvi Ambasana PCM21135 Aravind Vankadaru PCM21387
Dr. Ganesh Devkar Nisarg Patel PCM21240 Raag Chavda PCM21269
1
• Project Brief
• Site Layout
• Site Layout Model
Content • Quantity Take-off Sheet
• Path of Travel Analysis
• Rendered View of Site

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 2


1

PROJECT BRIEF

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 3


Name of Project: Shivalik Sharda Harmony
Location: University Area, Ahmedabad, Gujarat 380009

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 4


2

SITE LAYOUT

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 5


Site Layout

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 6


Modified Site Execution Layout

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 7


Modified Site Execution Layout
BAR BENDING AT GROUND
FLOOR

REINFORCEMENT STACKING

OFFICE SECURITY CABIN &


STORE
SAFETY TOILETS
OFFICE
CANTEEN

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 8


3

SITE LAYOUT MODEL

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 9


SITE LAYOUT MODEL

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 10


SITE LAYOUT MODEL

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 11


4

QUANTITY TAKE-OFF SHEET

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 12


Summary of blocks planning

1 3 Common Basements, with Driveway Ramps to different levels of basements


Block A Commercial Floors:

Block B Ground Floor to 2nd Floor Level.


II
Block E Residential Floors:

Block F 3rd floor to 13th Floor + Terrace Level


Block C Commercial Floors:

Block D Ground Floor to 2nd Floor Level.


III
Residential Floors:

3rd Floor to 14th Floor + Terrace Level.

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 13


Quantity Take-off Sheet- Slab Concrete Quantity

Shivalik Sharda Harmony Floor Area Quantity Takeoff (Till Date)

Family Type Area Default Thickness Elevation at Top Elevation at Bottom Volume

Slab 3rd Basement Slab 62023 SF 0' - 6" 0' - 0" -0' - 6" 31011.66 CF

Slab 2nd basement slab 62503 SF 0' - 6" 11' - 6" 11' - 0" 31251.26 CF

Slab 1st basement slab 63356 SF 0' - 6" 23' - 0" 22' - 6" 31678.08 CF

Slab Ground Floor Level 62144 SF 0' - 6" 37' - 6" 37' - 0" 31071.81 CF

Slab Plinth Concrete Slab 32808 SF 0' - 6" 40' - 6" 40' - 0" 16403.81 CF

Slab 1st Floor Concrete Slab 35219 SF 0' - 6" 53' - 5" 52' - 11" 17609.61 CF

Slab 2nd Floor Concrete Slab 23075 SF 0' - 6" 66' - 4" 65' - 10" 11537.51 CF

Slab 3rd Floor Concrete Slab 23075 SF 0' - 6" 79' - 3" 78' - 9" 11537.51 CF

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 14


Summary Areas BUILT-UP AREA STATEMENT FOR SHIVALIK SHARDA HARMONY (in sq.ft.)
Floor Type Sq.ft. Sq.ft. Sq.ft.
Basement-3 63660.4
Basement-2 63661.4
Basement-1 63662.4
Total Basement Area 190984.2
Block A+B Block C+D Block E+F
Ground Floor 12246.8 12675.51 11099.46
1st Floor 11940.2 12090.71 11383.85
2nd Floor 11991.4 12090.71 11473.01
3nd Floor 10104.67 11972.04 9901.93
4thFloor 10104.67 11972.04 9901.93
5thFloor 10104.67 11972.04 9901.93
6thFloor 10104.67 11972.04 9901.93
7thFloor 10104.67 11972.04 9901.93
8thFloor 10104.67 11972.04 9901.93
9thFloor 10104.67 11972.04 9901.93
10thFloor 10104.67 11972.04 9901.93
11thFloor 10104.67 11972.04 9901.93
12thFloor 10104.67 11972.04 9901.93
12thFloor 8715.26 11951.15 7280.79
14thFloor 0 9257.45 0
Stair Cabin 991.74 829.25 813.75
146932.1 178615.18 141070.16

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 15


5

PATH OF TRAVEL ANALYSIS

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 16


Path of Travel Analysis
Shivalik Sharda Harmony Path of Travel Analysis
Mark Speed Time (in seconds) Length
Entry To Office 3.0 mph 29.8 131' - 0 5/32"
University Road Entry To Office 3.0 mph 166 730' - 2 9/32"
Bar Bending Area-1 to B Block 3.0 mph 48.1 211' - 9 25/32"
Bar Bending Area-1 to C Block 3.0 mph 70.8 311' - 6 3/4"
Bar Bending Area-1 to C,d Block 3.0 mph 84.7 372' - 6 21/32"
Bar Bending Area-1 to D Block 3.0 mph 105.7 465' - 0 3/32"
Bar Bending Area-1 to F Block 3.0 mph 159.3 700' - 10 19/32"
Bar Bending Area-1 to E Block 3.0 mph 138.5 609' - 3 13/16"
Bar Bending Area-2 to F Block 3.0 mph 53.8 236' - 10 7/32"
Bar Bending Area-2 to E Block 3.0 mph 31.6 138' - 11 7/8"
Bar Bending Area-2 to D Block – Corner 3.0 mph 25.5 112' - 0 9/32"
Bar Bending Area-2 to D Block 3.0 mph 23.4 102' - 9 9/16"
Bar Bending Area-2 to C Block 3.0 mph 49.6 218' - 5 1/8"
Bar Bending Area-2 to B Block Corner 3.0 mph 51.3 225' - 7 7/16"
Scaffolding to Bar Bending Area-2 3.0 mph 36.1 158' - 11 7/32"
Scaffolding to F Block 3.0 mph 27.2 119' - 8 7/8"
Scaffolding to C Block 3.0 mph 18.4 80' - 10 5/16"
Scaffolding to D Block 3.0 mph 29.9 131' - 8 5/8"
Scaffolding to B Block 3.0 mph 41.9 184' - 3 1/32"
Scaffolding to A Block 3.0 mph 72.5 318' - 11 7/16"

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 18


Path of Travel Analysis
On Site Facilities

Time (in
Mark Speed seconds) Length
Quality Control Office 3.0 mph 135.8 597' - 5 15/32"
Safety Office 3.0 mph 128.3 564' - 8 1/4"
Existing Toilets 3.0 mph 131.4 577' - 11 5/8"
RMC Lift for C Block Casting Slabs 3.0 mph 86.1 378' - 11 21/32"

Proposed Facilities
Time (in
Mark seconds) Length Time Saved
Proposed QC Lab 81.7 359' - 3 1/4" 54.1
Proposed Safety Office 90.1 396' - 4 11/32" 38.2
Proposed Toilets 107.3 471' - 11 5/32" 24.1
Proposed Path for RMC
Entry 51.5 226' - 7 5/32" 34.6

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 19


Path of Travel Analysis
TOILETS TOILETS

RMC UPTO B & C


BLOCK

TOILETS
RMC ENTRY
UPTO GATE-2

QC OFFICE
SAFETY OFFICE
TOILETS

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 20


6

RENDERED VIEWS OF SITE

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 21


A-B Blocks

This block is located on the side


parallel to the Vastrapur Road.
The block is proposed to have 13
floors with 3 level basement
parking facilities. Commercial
Shops will be provided up to 3rd
floor in this block. The basement
work is completed along with
plinth beam and 1st floor slab.
Currently, the reinforcement and
concreting of 2nd floor slab is
going on.

Rendered View of Block A and B from Entrance 1

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 22


C-D Blocks

This block is located on the inside


part and is proposed to have 14
floors with lower floors allotted to
the amenities like gym and clubs.
Currently the works on the 3rd floor
slab is in progress.

Rendered View of Block C and D

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 23


E-F Blocks

This Block is located on the road


parallel to the university road and is
proposed to have 13 floors with 3
level basement parking facilities.
Commercial Shops will be provided
up to the 3rd floor in this block.
Currently the 3rd floor slab work is
completed.

Rendered View of Block E and F

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 24


Labour Colony

Labour Colony is located adjacent to


block A & B and it provide shelter
for around 100-150 Workers.

View of Labour Colony

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 25


QC Lab

Quality office of Chavda Infra are


located near C & D block , Quality
assurance check and Quality control
of material present at site are checked
and observed here.
Cube Casting and Quality testing of
Cube are performed here, this single
curing tank constructed near
boundary wall of C & D.

Quality Control Lab

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 26


Rendered Views of Site

View of Basement View of Block B & C

Stacked Materials Proposed QC Lab and Power Room


CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 27
Rendered Views of Site

Labour Colony Toilets

Labour Colony View of Block E & F


CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 28
Rendered Views of Site

Proposed QC Lab Toilets

View from Entrance -1 Internal Staircase


CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 29
Rendered Views of Site

View of Basement View from Entrance-2

View from Entrance -1 Internal Staircase


CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 30
Rendered Views of Site

Proposed QC Lab Proposed QC Lab

Proposed QC Lab Proposed QC Lab


CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 31
Inference & Summary
• The BIM visualization helps in understanding the construction procedure materials usage of places.
• The Quantity required for the construction
• Future imagination of how the building looks like
• Study of the path of travel helps us to identify the distance of travel of people from one place to other
• So by this we can modify the layout accordingly and save travel time.
• The study of the BIM model we were able to identify Total Built-Area: of 657275 sq. ft.
• Basement for all the blocks were combined and the diaphragm wall was up to basement one and a retaining wall is
being constructed over the diaphragm wall.
• BIM Model helps to identify the problems that might occur in the future it is also helpful in the future to identify the
problem source.
• BIM model helps in understanding the quantity requirement of the future ordering of materials that could be planned
from this exercise.

CPEMC I CM 4000 SHIVALIK SHARDA HARMONY 32