PROJECT: PROPOSED 4-STOREY SCHOOL BUILDING LOCATION:

Tondo, Manila, Philippines


Engineer:
Architect:
Subject:

QTY UNIT Unit Cost TOTAL AMOUNT


Item No. Description MATERIALS AND L
Materials Labor
A. EARTHWORKS
Excavation 2430 cu.m 200 486000
Trimming 1142.12 sq.m 100 114212
Grading 2855.28 sq.m 100 285528
Compaction 2855.28 sq.m 100 285528
Ground Bedding 14.58 cu.m 500 100 8748
Back Fill 2160 cu.m 100 216000
B. STRUCTURAL WORKS
B.1. CONCRETE WORKS
Concrete Pile Cap 188.76 cu.m 3500 250 707850
Isolated Square Footing 270 cu.m 3500 250 1012500
Septic Tank 5.81 cu.m 4000 250 24692.5
Underground Tank 5.81 cu.m 4000 250 24692.5
Ground Floor Slabs (per wing) 28.501 cu.m 4000 250 121129.25
Second Floor Framing Girders (per wing) 30.67 cu.m 4000 250 130347.5
Second Floor Framing Slabs (per wing) 34.835 cu.m 4000 250 148048.75
Third Floor Framing Girders (per wing) 23.9 cu.m 4000 250 101575
Third Floor Framing Slabs (per wing) 34.835 cu.m 4000 250 148048.75
Fourth Floor Framing Girders (per wing) 19.716 cu.m 4000 250 83793
Fourth Floor Framing Slabs (per wing) 34.835 cu.m 4000 250 148048.75
Roof Framing Beam (per wing) 17.924 cu.m 4000 250 76177
Columns (per wing) 139.15 cu.m 4000 250 591387.5
Ground Floor Slabs (M) 71.485 cu.m 4000 250 303811.25
Second Floor Framing Girders (M) 64.518 cu.m 4000 250 274201.5
Second Floor Framing Slabs (M) 87.371 cu.m 4000 250 371326.75
Third Floor Framing Girders (M) 50.274 cu.m 4000 250 213664.5
Third Floor Framing Slabs (M) 87.371 cu.m 4000 250 371326.75
Fourth Floor Framing Girders (M) 41.476 cu.m 4000 250 176273
Fourth Floor Framing Slabs (M) 87.371 cu.m 4000 250 371326.75
Roof Framing Beam (M) 28.575 cu.m 4000 250 121443.75
Columns(M) 236.557 cu.m 4000 250 1005367.25
RC Wall (if any) 76 cu.m 4000 250 323000
Elevator RC Wall (if any) 76 cu.m 4000 250 323000
Concrete Stairs cu.m 4000 250 0
B.2. REINFORCING STEELWORKS
Girders
Second Floor Main Reinforcement Bars 879.098 kg
Third Floor Main Reinforcement Bars 972.375 kg
Fourth Floor Main Reinforcement Bars 1243.43 kg
Second Floor Secondary Reinforcement Bars 39.7348 kg
Third Floor Secondary Reinforcement Bars 52.445 kg
Fourth Floor Secondary Reinforcement Bars 51.4578 kg
Columns
Ground Floor Main Reinforcement Bars 3024.38 kg
Second Floor Main Reinforcement Bars 3024.38 kg
Third Floor Main Reinforcement Bars 3024.38 kg
Fourth Floor Main Reinforcement Bars 3024.38 kg
Ground Floor Secondary Reinforcement Bars 31.6251 kg
Second Floor Secondary Reinforcement Bars 31.6251 kg
Third Floor Secondary Reinforcement Bars 31.6251 kg
Fourth Floor Secondary Reinforcement Bars 31.6251 kg
Slabs
Ground Floor Main Reinforcement Bars 84.2945 kg
Second Floor Main Reinforcement Bars 84.2945 kg
Third Floor Main Reinforcement Bars 84.2945 kg
Fourth Floor Main Reinforcement Bars 84.2945 kg
Ground Floor Secondary Reinforcement Bars 23.9342 kg
Second Floor Secondary Reinforcement Bars 23.9342 kg
Third Floor Secondary Reinforcement Bars 23.9342 kg
Fourth Floor Secondary Reinforcement Bars 23.9342 kg
TOTAL AMOUNT FOR
MATERIALS AND LABOR

486000
114212
285528
285528
8748
216000

707850
1012500
24692.5
24692.5
121129.25
130347.5
148048.75
101575
148048.75
83793
148048.75
76177
591387.5
303811.25
274201.5
371326.75
213664.5
371326.75
176273
371326.75
121443.75
1005367.25
323000
323000
0
Concrete Works Qty Unit
Concrete Square Footings 194.4 m^3
Cistern Tank
Septic Tank
Second Floor Framing Beam
Second Floor Framing Slab
Third Floor Framing Beam
Third Floor Framing Slab
Fourth Floor Framing Beam
Fourth Floor Framing Slab
Roof Framing Beam
Columns