Ajdan Tower VRF INSTALLATION WORK

1) FCU unit installation


Description QTY Unit Rate
Basement Floor 1 FCU`s 30.00 250.00
GF FCU`s 21.00 250.00
1ST Floor FCU`s 43.00 250.00
2 nd floor FCU`s 45.00 250.00
3 rd Floor FCU`s 25.00 250.00
4 th Floor FCU`s 41.00 250.00
5 th Floor FCU`s 43.00 250.00
6 th Floor FCU`s 43.00 250.00
7 th Floor FCU`s 43.00 250.00
8 th Floor FCU`s 43.00 250.00
9 th Floor FCU`s 40.00 250.00
10 th Floor FCU`s 37.00 250.00
11 th Floor FCU`s 34.00 250.00
12 th Floor FCU`s 16.00 250.00
13 th Floor FCU`s 16.00 250.00
14 th Floor FCU`s 20.00 250.00
15 th Floor FCU`s 19.00 250.00
16 th Floor FCU`s 20.00 250.00
17 th Floor FCU`s 19.00 250.00
18 th Floor FCU`s 20.00 250.00
19 th Floor FCU`s 19.00 250.00
20 th Floor FCU`s 0.00 250.00
21 th Floor FCU`s 19.00 250.00
22 th Floor FCU`s 20.00 250.00
23 th Floor FCU`s 19.00 250.00
24 th Floor FCU`s 20.00 250.00
25 th Floor FCU`s 19.00 250.00
26 th Floor FCU`s 20.00 250.00
27 th Floor FCU`s 19.00 250.00
28 th Floor FCU`s 20.00 250.00
29 th Floor FCU`s 19.00 250.00
30 th Floor FCU`s 20.00 250.00
31 th Floor FCU`s 19.00 250.00
32 th Floor FCU`s 19.00 250.00
33 th Floor FCU`s 19.00 250.00
34 th Floor FCU`s 18.00 250.00
35 th Floor FCU`s 18.00 250.00
36 th Floor FCU`s 9.00 250.00
TOTAL 934.000
2) Copper pipe installation each floor
Description QTY Unit Rate
Basement Floor Cooper pipe Suction discharge 783 45
GF Cooper pipe Suction discharge 652 45
1 ST Floor Cooper pipe Suction discharge 608 45
2 ST Floor Cooper pipe Suction discharge 704 45
3 ST Floor Cooper pipe Suction discharge 583 45
4 ST Floor Cooper pipe Suction discharge 666 45
5 ST Floor Cooper pipe Suction discharge 895 45
6 ST Floor Cooper pipe Suction discharge 858 45
7 ST Floor Cooper pipe Suction discharge 895 45
8 ST Floor Cooper pipe Suction discharge 858 45
9 ST Floor Cooper pipe Suction discharge 880 45
10 ST Floor Cooper pipe Suction discharge 703 45
11 ST Floor Cooper pipe Suction discharge 620 45
12 ST Floor Cooper pipe Suction discharge 369 45
13 ST Floor Cooper pipe Suction discharge 318 45
14 ST Floor Cooper pipe Suction discharge 340 45
15 ST Floor Cooper pipe Suction discharge 360 45
16 ST Floor Cooper pipe Suction discharge 340 45
17 ST Floor Cooper pipe Suction discharge 360 45
18 ST Floor Cooper pipe Suction discharge 340 45
19 ST Floor Cooper pipe Suction discharge 360 45
20 ST Floor Cooper pipe Suction discharge 0 45
21 ST Floor Cooper pipe Suction discharge 445 45
22 ST Floor Cooper pipe Suction discharge 340 45
23 ST Floor Cooper pipe Suction discharge 360 45
24 ST Floor Cooper pipe Suction discharge 340 45
25 ST Floor Cooper pipe Suction discharge 360 45
26 ST Floor Cooper pipe Suction discharge 340 45
27 ST Floor Cooper pipe Suction discharge 360 45
28 ST Floor Cooper pipe Suction discharge 340 45
29 ST Floor Cooper pipe Suction discharge 360 45
30 ST Floor Cooper pipe Suction discharge 340 45
31 ST Floor Cooper pipe Suction discharge 360 45
32 ST Floor Cooper pipe Suction discharge 360 45
33 ST Floor Cooper pipe Suction discharge 360 45
34 ST Floor Cooper pipe Suction discharge 343 45
35 ST Floor Cooper pipe Suction discharge 305 45
36 ST Floor Cooper pipe Suction discharge 120 45
TOTAL 17925.000
3) FAHU Installation
Description QTY Unit Rate
FAHU 2nd floor 1 1000
FAHU 3rd Floor 7 1000
TOTAL 8.000
4) Testing for complete system
Description QTY Unit Rate
Pressure test for complete suystem LOT 35000
TOTAL LOT
4) VRF Outdoor installations
Description QTY Unit Rate
GF Outdoor units 7 750
1ST Floor OUTDOOR UNITS 2 750
2nd Floor OUTDOOR UNITS 1 750
3RDTH Floor OUTDOOR UNITS 4 750
12th Floor OUTDOOR UNITS 30 750
13th Floor OUTDOOR UNITS 48 750
14th Floor OUTDOOR UNITS 72 750
Rooftop Floor OUTDOOR UNITS 76 750
TOTAL 240.000
SUMMARY :
No. Item QTY
1 FCU unit installation 934.00
2 Copper pipe installation each floor 17925.00
3 FAHU Installation LOT
4 Testing for complete system LOT
5 VRF Outdoor installations 240.00
TOTAL AMOUNT IN SAR
Total Price
7500.00
5250.00
10750.00
11250.00
6250.00
10250.00
10750.00
10750.00
10750.00
10750.00
10000.00
9250.00
8500.00
4000.00
4000.00
5000.00
4750.00
5000.00
4750.00
5000.00
4750.00
0.00
4750.00
5000.00
4750.00
5000.00
4750.00
5000.00
4750.00
5000.00
4750.00
5000.00
4750.00
4750.00
4750.00
4500.00
4500.00
2250.00
233500.000
floor
Total Price
35235.00
29340.00
27360.00
31680.00
26235.00
29970.00
40275.00
38610.00
40275.00
38610.00
39600.00
31635.00
27900.00
16605.00
14310.00
15300.00
16200.00
15300.00
16200.00
15300.00
16200.00
0.00
20025.00
15300.00
16200.00
15300.00
16200.00
15300.00
16200.00
15300.00
16200.00
15300.00
16200.00
16200.00
16200.00
15435.00
13725.00
5400.00
806625.000

Total Price
1000.00
7000.00
8000.000
m
Total Price
35000.00
35000.000

Total Price
5250.00
1500.00
750.00
3000.00
22500.00
36000.00
54000.00
57000.00
180000.000

Price (SAR)
233500.00
806625.00
8000.00
35000.00
180000.00
1263125.000

You might also like