Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union

Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

REF NO. CC0007-00/01- WBCR

02 July 2016

Attn:

Mr. Fausto Liriano


Client

RE: QUOTATION – CONSTRUCTION LABOR RATES

Dear Sir,

We are pleased to submit our quotation for the abovementioned subject.

Kindly refer to the attached quotation for your reference and approval.

Thank you.

Best Regards,

MARK ANTHONY P. ACOSTA


Cr3ative Construct
General Manager

1|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

I. PRELIMINARIES PHP 70,000.00

A. MOBILIZATION PHP 25,000.00


- All activities and associated cost for transportation of
equipment & operating supplies into the project site.
- Other miscellaneous items

B. SETTING OUT / SURVEY PEGS PHP 15,000.00


- Setting out by a licensed surveyor

C. DEMOBILIZATION PHP 30,000.00


- All activities and associated cost for transportation of
equipment & operating supplies out from the project
site after the completion of works.
- Other miscellaneous items

II. TECHNICAL STAFF RATES

A. PROJECT MANAGER PHP 40,000.00/month

B. SITE ENGINEER PHP 20,000.00/month


C. QUANTITY SURVEYOR PHP 20,000.00/month

2|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

QUOTATION – CONSTRUCTION LABOR RATES

Item Budget
Description of Works Area Member Rate Unit
No. Code

1 02300 E Excavation Ground Floor Footing 200.00 cu.m.


2 02300 E Excavation Ground Floor Septic Tank 200.00 cu.m.
3 02300 E Excavation Ground Floor Cistern Tank 200.00 cu.m.
4 02300 E Excavation Ground Floor Grade Beam 200.00 cu.m.
5 02300 E Backfill & Compaction Ground Floor Footing 160.00 cu.m.
6 02300 E Backfill & Compaction Ground Floor Septic Tank 160.00 cu.m.
7 02300 E Backfill & Compaction Ground Floor Cistern Tank 160.00 cu.m.
8 02300 E Backfill & Compaction Ground Floor Grade Beam 160.00 cu.m.
9 02300 E Backfill & Compaction Ground Floor Grade Slab 160.00 cu.m.
10 02300 E Grade Preparation Ground Floor Footing 50.00 sq.m
11 02300 E Grade Preparation Ground Floor Grade Slab 50.00 sq.m
12 02800 L Ground Preparation Ground Floor Driveway 50.00 sq.m
13 02800 L Ground Preparation Ground Floor Walkway 50.00 sq.m
14 02800 L Ground Preparation Ground Floor Open Field 50.00 sq.m
15 02800 L Installation of Paver Blocks Ground Floor Driveway 80.00 sq.m
16 02800 L Installation of Paver Blocks Ground Floor Walkway 80.00 sq.m
17 02800 L Installation of Paver Blocks Ground Floor Open Field 80.00 sq.m
18 02800 L Installation of Outdoor Tiles Ground Floor Open Field 200.00 sq.m
19 02900 L Landscaping & Gardening Ground Floor Open Field 80.00 sq.m
20 03100 L Formworks - Fabrication & Installation Foundation Column 150.00 sq.m
21 03100 L Formworks - Fabrication & Installation Ground Floor Column 150.00 sq.m
22 03100 L Formworks - Fabrication & Installation 2nd Floor Column 150.00 sq.m
23 03100 L Formworks - Fabrication & Installation Roof Deck Column 150.00 sq.m
24 03100 L Formworks - Fabrication & Installation Roof Deck Column 150.00 sq.m
25 03100 L Formworks - Fabrication & Installation 2nd Floor Beam 150.00 sq.m
26 03100 L Formworks - Fabrication & Installation Roof Deck Beam 150.00 sq.m
27 03100 L Formworks - Fabrication & Installation 2nd Floor Slab 165.00 sq.m
28 03100 L Formworks - Fabrication & Installation Roof Deck Slab 165.00 sq.m
29 03100 L Formworks - Fabrication & Installation Ground Floor Header 150.00 sq.m
30 03100 L Formworks - Fabrication & Installation 2nd Floor Header 150.00 sq.m
31 03100 L Formworks - Fabrication & Installation Roof Deck Header 150.00 sq.m
32 03100 L Formworks - Removal Foundation Column 50.00 LM
33 03100 L Formworks - Removal Ground Floor Column 50.00 LM
34 03100 L Formworks - Removal 2nd Floor Column 50.00 LM
35 03100 L Formworks - Removal Roof Deck Column 50.00 LM
36 03100 L Formworks - Removal Ground Floor Beam 50.00 LM
37 03100 L Formworks - Removal 2nd Floor Beam 50.00 LM
38 03100 L Formworks - Removal Roof Deck Beam 50.00 LM
39 03100 L Formworks - Removal 2nd Floor Slab 55.00 sq.m

3|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

40 03100 L Formworks - Removal Roof Deck Slab 55.00 sq.m


41 03100 L Formworks - Removal Ground Floor Header 50.00 LM
42 03100 L Formworks - Removal 2nd Floor Header 50.00 LM
43 03100 L Formworks - Removal Roof Deck Header 50.00 LM
44 03100 L Steel Decking Cutting & Installation 2nd Floor Slab 20.00 LM
45 03100 L Steel Decking Cutting & Installation Roof Deck Slab 20.00 LM
46 03100 L Steel Decking Support Installation 2nd Floor Slab 35.00 sq.m
47 03100 L Steel Decking Support Installation Roof Deck Slab 35.00 sq.m
48 03100 L Steel Decking Support Removal 2nd Floor Slab 35.00 sq.m
49 03100 L Steel Decking Support Removal Roof Deck Slab 35.00 sq.m
50 03200 L Rebar - Cut & Bend Ground Floor Footing 3.50 kgs
51 03200 L Rebar - Cut & Bend Ground Floor Column 3.50 kgs
52 03200 L Rebar - Cut & Bend Ground Floor Grade Beam 3.50 kgs
53 03200 L Rebar - Cut & Bend Ground Floor Beam 3.50 kgs
54 03200 L Rebar - Cut & Bend Ground Floor Grade Slab 3.50 kgs
55 03200 L Rebar - Cut & Bend Ground Floor Stair 3.50 kgs
56 03200 L Rebar - Cut & Bend Ground Floor Header 3.50 kgs
57 03200 L Rebar - Cut & Bend 2nd Floor Column 3.50 kgs
58 03200 L Rebar - Cut & Bend 2nd Floor Beam 3.50 kgs
59 03200 L Rebar - Cut & Bend 2nd Floor Slab 3.50 kgs
60 03200 L Rebar - Cut & Bend 2nd Floor Stair 3.50 kgs
61 03200 L Rebar - Cut & Bend 2nd Floor Header 3.50 kgs
62 03200 L Rebar - Cut & Bend Roof Deck Column 3.50 kgs
63 03200 L Rebar - Cut & Bend Roof Deck Beam 3.50 kgs
64 03200 L Rebar - Cut & Bend Roof Deck Slab 3.50 kgs
65 03200 L Rebar - Cut & Bend Roof Deck Header 3.50 kgs
66 03200 L Rebar - Layout & Fixing Ground Floor Footing 2.50 kgs
67 03200 L Rebar - Layout & Fixing Ground Floor Column 2.50 kgs
68 03200 L Rebar - Layout & Fixing Ground Floor Grade Beam 2.50 kgs
69 03200 L Rebar - Layout & Fixing Ground Floor Beam 2.50 kgs
70 03200 L Rebar - Layout & Fixing Ground Floor Grade Slab 2.50 kgs
71 03200 L Rebar - Layout & Fixing Ground Floor Stair 2.50 kgs
72 03200 L Rebar - Layout & Fixing Ground Floor Header 2.50 kgs
73 03200 L Rebar - Layout & Fixing 2nd Floor Column 2.50 kgs
74 03200 L Rebar - Layout & Fixing 2nd Floor Beam 2.50 kgs
75 03200 L Rebar - Layout & Fixing 2nd Floor Slab 2.50 kgs
76 03200 L Rebar - Layout & Fixing 2nd Floor Stair 2.50 kgs
77 03200 L Rebar - Layout & Fixing 2nd Floor Header 2.50 kgs
78 03200 L Rebar - Layout & Fixing Roof Deck Column 2.50 kgs
79 03200 L Rebar - Layout & Fixing Roof Deck Beam 2.50 kgs
80 03200 L Rebar - Layout & Fixing Roof Deck Slab 2.50 kgs
81 03200 L Rebar - Layout & Fixing Roof Deck Header 2.50 kgs
82 03300 L Concrete Pouring (Pumpcrete) Ground Floor Footing 300.00 cu.m.
83 03300 L Concrete Pouring (Pumpcrete) Ground Floor Column 300.00 cu.m.

4|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

84 03300 L Concrete Pouring (Pumpcrete) Ground Floor Grade Slab 300.00 cu.m.
85 03300 L Concrete Pouring (Pumpcrete) Ground Floor Grade Beam 300.00 cu.m.
86 03300 L Concrete Pouring (Pumpcrete) Ground Floor Beam 300.00 cu.m.
87 03300 L Concrete Pouring (Pumpcrete) 2nd Floor Column 300.00 cu.m.
88 03300 L Concrete Pouring (Pumpcrete) 2nd Floor Beam 300.00 cu.m.
89 03300 L Concrete Pouring (Pumpcrete) 2nd Floor Slab 300.00 cu.m.
90 03300 L Concrete Pouring (Pumpcrete) Roof Deck Column 300.00 cu.m.
91 03300 L Concrete Pouring (Pumpcrete) Roof Deck Beam 300.00 cu.m.
92 03300 L Concrete Pouring (Pumpcrete) Roof Deck Slab 300.00 cu.m.
93 03300 L Concrete Pouring (Pumpcrete) Roof Deck Slab 300.00 cu.m.
94 03300 L Concrete Pouring (Manual) Ground Floor Column 500.00 cu.m.
95 03300 L Concrete Pouring (Manual) Ground Floor Grade Slab 500.00 cu.m.
96 03300 L Concrete Pouring (Manual) Ground Floor Grade Beam 500.00 cu.m.
97 03300 L Concrete Pouring (Manual) Ground Floor Beam 500.00 cu.m.
98 03300 L Concrete Pouring (Manual) Ground Floor Header 500.00 cu.m.
99 03300 L Concrete Pouring (Manual) 2nd Floor Column 600.00 cu.m.
100 03300 L Concrete Pouring (Manual) 2nd Floor Beam 600.00 cu.m.
101 03300 L Concrete Pouring (Manual) 2nd Floor Slab 600.00 cu.m.
102 03300 L Concrete Pouring (Manual) 2nd Floor Header 600.00 cu.m.
103 03300 L Concrete Pouring (Manual) Roof Deck Column 700.00 cu.m.
104 03300 L Concrete Pouring (Manual) Roof Deck Beam 700.00 cu.m.
105 03300 L Concrete Pouring (Manual) Roof Deck Slab 700.00 cu.m.
106 03300 L Concrete Pouring (Manual) Roof Deck Header 700.00 cu.m.
107 04060 L Masonry - Plastering Ground Floor Interior 60.00 sq.m
108 04060 L Masonry - Plastering Ground Floor Extrior 60.00 sq.m
109 04060 L Masonry - Plastering 2nd Floor Interior 60.00 sq.m
110 04060 L Masonry - Plastering 2nd Floor Extrior 65.00 sq.m
111 04060 L Masonry - Plastering Roof Deck Interior 60.00 sq.m
112 04060 L Masonry - Plastering Roof Deck Extrior 70.00 sq.m
113 04060 L Masonry - Plastering Soffit Stair 75.00 sq.m
114 04060 L Masonry - Plastering Soffit Slab 75.00 sq.m
115 04060 L Masonry - Plastering Top Roof Slab 75.00 sq.m
116 04060 L Masonry - Plastering (Corner) Corner Extrior 75.00 LM
117 04060 L Masonry - Plastering (Corner) Corner Interior 75.00 LM
118 04060 L Masonry - Moulding Perimeter Window 75.00 LM
119 04060 L Masonry - Moulding Perimeter Door 75.00 LM
120 04200 L CHB Laying Ground Floor 6" CHB 70.00 sq.m
121 04200 L CHB Laying 2nd Floor 6" CHB 80.00 sq.m
122 04200 L CHB Laying Roof Deck 6" CHB 90.00 sq.m
123 04200 L CHB Laying Ground Floor 4" CHB 65.00 sq.m
124 04200 L CHB Laying 2nd Floor 4" CHB 75.00 sq.m
125 04200 L CHB Laying Roof Deck 4" CHB 85.00 sq.m
126 04400 L Stone Cladding Wall Extrior 60.00 sq.m
127 04400 L Stone Cladding Wall Interior 60.00 sq.m

5|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

128 07100 L Waterproofing Works (Cementitious) Roof Deck Slab 120.00 sq.m
129 07100 L Waterproofing Works (Cementitious) Roof Deck Toilet 120.00 sq.m
130 07100 L Waterproofing Works (Cementitious) 2nd Floor Balcony 120.00 sq.m
131 07100 L Waterproofing Works (Cementitious) 2nd Floor Toilet 120.00 sq.m
132 09300 L Cutting of Porcelain Tiles 60cm x 60cm Toilet 20.00 pc
133 09300 L Cutting of Porcelain Tiles 30cm x 60cm Toilet 10.00 pc
Installation of Ceramic Tiles (30cm x
134 09300 L 30cm) Ground Floor Wall 120.00 sq.m
Installation of Ceramic Tiles (30cm x
135 09300 L 30cm) Ground Floor Floor 100.00 sq.m
Installation of Ceramic Tiles (30cm x
136 09300 L 30cm) 2nd Floor Wall 120.00 sq.m
Installation of Ceramic Tiles (30cm x
137 09300 L 30cm) 2nd Floor Floor 100.00 sq.m
Installation of Ceramic Tiles (30cm x
138 09300 L 30cm) Roof Deck Wall 120.00 sq.m
Installation of Ceramic Tiles (30cm x
139 09300 L 30cm) Roof Deck Floor 100.00 sq.m
Installation of Porcelain Tiles (30cm x
140 09300 L 30cm) Ground Floor Wall 140.00 sq.m
Installation of Porcelain Tiles (30cm x
141 09300 L 30cm) Ground Floor Floor 120.00 sq.m
Installation of Porcelain Tiles (30cm x
142 09300 L 30cm) 2nd Floor Wall 140.00 sq.m
Installation of Porcelain Tiles (30cm x
143 09300 L 30cm) 2nd Floor Floor 120.00 sq.m
Installation of Porcelain Tiles (30cm x
144 09300 L 30cm) Roof Deck Wall 140.00 sq.m
Installation of Porcelain Tiles (30cm x
145 09300 L 30cm) Roof Deck Floor 120.00 sq.m
Installation of Laminated Wood Tiles
146 09300 L (15cm x 60cm) Ground Floor Floor 180.00 sq.m
Installation of Laminated Wood Tiles
147 09300 L (15cm x 60cm) 2nd Floor Floor 180.00 sq.m
Installation of Laminated Wood Tiles
148 09300 L (15cm x 90cm) Ground Floor Floor 160.00 sq.m
Installation of Laminated Wood Tiles
149 09300 L (15cm x 90cm) 2nd Floor Floor 160.00 sq.m
150 09300 L Instalation of Mossaic Tiles Ground Floor Wall 180.00 sq.m
151 09300 L Instalation of Mossaic Tiles 2nd Floor Wall 180.00 sq.m
Installation of Marble Polished Tiles
152 09300 L (60cm x 60cm) - 20mm Thk Ground Floor Floor 350.00 sq.m
Installation of Marble Polished Tiles
153 09300 L (60cm x 60cm) - 20mm Thk 2nd Floor Floor 350.00 sq.m
Installation of Granite Polished Tiles
154 09300 L (60cm x 60cm) - 1/2" Thk Ground Floor Floor 200.00 sq.m
Installation of Granite Polished Tiles
155 09300 L (60cm x 60cm) - 1/2" Thk 2nd Floor Floor 200.00 sq.m
156 09500 L Installation of Metal Furring Ground Floor Ceiling 75.00 sq.m

6|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

157 09500 L Installation of Metal Furring 2nd Floor Ceiling 75.00 sq.m
158 09500 L Installation of Gypsum Board Ground Floor Ceiling 55.00 sq.m
159 09500 L Installation of Gypsum Board 2nd Floor Ceiling 55.00 sq.m
160 09500 L Painting of Ceiling Ground Floor Ceiling 120.00 sq.m
161 09500 L Painting of Ceiling 2nd Floor Ceiling 120.00 sq.m
162 09700 L Interior Paint Ground Floor Wall 70.00 sq.m
163 09700 L Interior Paint 2nd Floor Wall 70.00 sq.m
164 09700 L Interior Paint Roof Deck Wall 70.00 sq.m
165 09700 L Interior Paint Soffit Stair 90.00 sq.m
166 09700 L Interior Paint Soffit Slab 90.00 sq.m
163 09700 L Exterior Paint Ground Floor Wall 80.00 sq.m
164 09700 L Exterior Paint 2nd Floor Wall 85.00 sq.m
165 09700 L Exterior Paint Roof Deck Wall 90.00 sq.m
166 02600 L RCP Laying Ground Floor RCP 60.00 pc
167 04000 L Installation of Balluster Balcony Balluster
Utility Services 3 dia Conduit Pipe
168 02500 L Laying Duct Bank Pipe 40.00 LM
Utility Services 1.5 dia Conduit Pipe
169 02500 L Laying Duct Bank Pipe 10.00 LM
170 03300 L Concrete Pouring (Direct Pouring) Ground Floor Grade Beam 500.00 cu.m.
171 02300 E Trimming of Excavation Ground Floor Footing 50.00 sq.m
172 02800 L Subgrade Preparation Ground Floor grade slab 50.00 sq.m
173 07100 L Water Proofing Ground Floor 120.00 sq.m.
174 03200 L Steel Matting - Cutting Ground Floor Second Floor 3.50 kgs
175 03200 L Steel Matting - Layout & Fixing Ground Floor Second Floor 2.50 kgs
Utility Services 8 dia Conduit Pipe
176 02500 L Laying Ground Floor Second Floor 50.00 lm
177 04060 L Soffit of Stair Ground Floor Stair 75.00 sq.m.
178 04200 L Demolition of Wall Ground Floor wall 60.00 sq.m.
179 02300 L gravel bedding Ground Floor Slab 75.00 sq.m.
180 02500 L conduit pipe wrapping Ground Floor retaining wall 20.00 lm
181 02500 L conduit pipe drilling Ground Floor 10.00 lm
182 03300 L Concrete Pouring (Direct Pouring) Ground Floor 500.00
183 02300 E Excavation with Back Hoe Ground Floor 50.00 sq.m.
Backfill & Compaction w/ heavy
184 02300 E equipment Ground Floor 80.00 cu.m.
Stone Arrangement for Gabion
185 02370 L Baskets Ground Floor 500.00 cu.m.

7|P a g e
Main Office: BLK 12 LOT 2 Mustard Seed Street, Manna Residences, Pagdaraon, San Fernando La Union
Email cr3ative.construct@gmail.com • Contact No.: +63 916 279 5602

Note:

- Rates applies to and only to the specified scope of works listed


- Technical staffs shall only be provided as per the main contractor’s request.
- Consumable materials and heavy equipment such as excavators/backhoe, dump
trucks, 1 bagger concrete mixer et al shall be provided by the main contractor unless
requested to be supplied by cr3ative construct. Rates for heavy equipment will still
be applied as stipulated in the rates provided in the list.
- In the event that there is a delay of materials or absence of materials on site, our
manpower shall stop all activities and will resume as soon as the materials are
available.
- Temporary facilities such as site office, material storage & fabrication areas shall be
provided by the main contractor.
- Worker’s permit & benefits such as SSS shall be processed and paid by cr3ative
construct. Proof of payments for the said benefits shall be provided as per the main
contractor’s request.
- Duration of the project shall be in line with the main contractor’s project schedule.
- Connection of temporary power & water shall be provided by the main contractor.
Cost for water & electricity consumption shall be borne by the main contractor.
- This quotation shall be notarized and shall be a referred to as the “contract” between
the client and Cr3ative Construct.

Mode of Payment

Mobilization cost to be release upon signing and approval of the quotation

Surveying works / setting out shall be paid per visit.

Weekly progress billing

SUBMITTED BY: CONFORME & APPROVED BY:

ENGR. MARK ANTHONY P. ACOSTA MR. FAUSTO LIRIANO


GENERAL MANAGER CLIENT/OWNER
CR3ATIVE CONSTRUCT WAVES BEACH CLUB & RES.