Wing International

UNITED SHUT DOWN- 01MAY-2013-10JUNE-2013


Total Amount =935,000SAR

PROFIT 39,560.00

TOTAL EXPENSES 895440


PLANT TECH- EXPECTED AMOUNT
SCAFF.H.MAT. EXPENSE- NOT YET PAID
CONSUMEBALE+OTHERS 60,000.00

TRAILER +FORK LIFT 20,000.00


EMPLOYEE TRANSPORT 20,000.00
TEA EXPENSES 30,240.00
MATERIAL 20,000.00
7 WEEK EXPENSES 25,200.00
6 WEEK EXPENSES 168,000.00
4-5 WEEK EXPENSES 235,200.00
3 WEEK EXPENSES 201,600.00
2 WEEK EXPENSES 90,000.00
1 WEEK EXPENSES 25,200.00
PROJECT P.O 935,000.00
- 200,000.00 400,000.00 600,000.00 800,000.00 1,000,000.00

Amount in Saudi Riyals


UNITED SHUT DOWN PROJECT
SCAFFOLDING SERVICES SUB CONTRACT BY PLANT TECH
DURATION 40 DAYS
REF # LPO #3312 PLACO/000251-M-1
PROJECT NAME P.O VALUE WING MH.COST H.C.COST SCC.M.COST OTHERS OTHERS
UNITED S/D 935,000.00

- - - -
TOTAL EXPENSED AMOUNT -
TOTAL PROFIT 935,000.00
SIPCHEM-S/D
PROJECT P.O 935,000.00
1 WEEK EXPENSES 25,200.00
2 WEEK EXPENSES 90,000.00
3 WEEK EXPENSES 201,600.00 1 20
4-5 WEEK EXPENSES 235,200.00
6 WEEK EXPENSES 168,000.00
7 WEEK EXPENSES 25,200.00 2 20
MATERIAL 20,000.00
TEA EXPENSES 30,240.00
EMPLOYEE TRANSPORT 20,000.00 3 20
TRAILER +FORK LIFT 20,000.00

CONSUMEBALE+OTHERS 60,000.00 4
SCAFF.H.MAT. EXPENSE- NOT YE 20
PLANT TECH- EXPECTED AMOUN
TOTAL EXPENSES 895440

PROFIT 39,560.00 5 20

115474
P.D 7 DAYS
15 12 3600 25200

P.D 15DAYS
25 12 6000 90000

P.D 21DAYS
35 12 8400 201600

P.D 21DAYS
70 12 16800 235200

P.D 21DAYS
50 12 12000 168000