Professional Documents
Culture Documents
Scheduled Completion Date for the Project is 1460 days from the Appointed Date.
The Project Milestone to be read as D+(number of days from Appointed Date )
Tentative Start Date 01/11/2022
ay Station of North Central Railway
DATE REMARKS
1/29/2023
2/28/2023
3/30/2023
Major Upgradation of Prayagraj Junction Railway Station of North Cent
COMPLETION PERIOD
S.NO STAGES IN DAYS
e)
2/28/2023
2/28/2023
4/29/2023
4/29/2023
10/31/2023
7/2/2024
10/25/2024
1/23/2025
2/22/2025
8/27/2023
12/30/2023
3/29/2024
6/27/2024
7/27/2024
10/31/2023
1/29/2024
2/28/2024
2/28/2023
6/28/2023
10/26/2023
4/23/2024
8/21/2024
10/20/2024
10/30/2024
6/28/2023
8/27/2023
10/31/2023
11/30/2023
12/30/2023
Major Upgradation of Prayagraj Junction Railway Station of North Cen
COMPLETION PERIOD IN
S.NO STAGES
DAYS
Scheduled Completion Date for Elevated Concourse 1 & 2
1 Submission and approval of Designs and Drawings D+120
2 Shifting of Utilities as per site requirement D+160
3 Demolishing of FOB (F3) D + 210
Foundation: completion of 100 % Foundation work
4 (open foundations/pile foundations including pile D + 390
caps) and testing.
Completion of structural work of Column from
5 flooring to floor level concourse level, lift well, D + 480
stairs, escalator well etc..
6 Structural work placing of Girder, slab casting, D + 720
flooring, roofing.
7 Finishing, Electrical installation, air cooling, D + 810
furnishing and approval from Authorities.
8 Completion, handing over and approval from D + 840
Authorities
Scheduled Completion Date for Through Roof
1 Submission and approval of Designs and Drawings D+120
2 Shifting of Utilities as per Site Requirement D+240
Foundation: completion of 100 % Foundation work
3 (open foundations/pile foundations including pile D + 390
caps) and testing
4 Completion of structural work of Column from D + 720
foundation to Roof level
5 Structural truss for roofing D+900
6 Roofing with sheets including drainage etc. D + 1020
complete
Completion of through roofing including painting, E
7 & M works, false ceiling and complete D + 1200
commissioning
8 Completion, handing over and approval from D + 1230
Authorities
Scheduled Completion Period for 2-Tier (Double Deck) Skywalk connecting Concourse – 1 & Co
connecting Skywalks (Departure Skywalk connecting PF 6 and Station Buildings
1 Submission and approval of designs and drawings D + 120
2 Shifting of Utilities as per site requirement D+ 180
Foundation: On completion of 100 % Foundation D + 300
work
3 Completion of all superstructure, Structural part, D + 540
lift & escalator well etc.
4 Completion of roofing etc D + 600
2/28/2023
4/9/2023
5/29/2023
11/25/2023
10/20/2024
2/28/2023
6/28/2023
10/20/2024
4/23/2024
6/22/2023
10/20/2024
4/23/2024
Major Upgradation of Prayagraj Junction Railway Station of North Cen
COMPLETION PERIOD IN
S.NO STAGES
DAYS
Scheduled Completion Date for Station Building (City Side)
1 Submission and approval of designs and drawings D + 120
2 Shifting of Utilities as per site requirement D+815
Temporary relocation of existing offices to Existing
3 Kumbh Sheds (City Side)/New Station Building (Civil D + 815
Lines Side)
4 Demolition of Existing station building D + 875
Foundation: On completion of 100 % Foundation work
5 (open foundations/pile foundations including pile D + 1025
caps) and testing of substructure.
6 Completion of superstructure of all floors D + 1265
Completion of all the floor finished, wall finishes, door,
7 windows, glazing, partitioning, plumbing, electrical D + 1385
works etc
Completion of HVAC, announcement systems, false
8 ceilings, CCTV, LAN, signages, Lift & Escalators etc. all E D + 1430
& M works complete in all respects.
9 Completion, handing over and approval from D + 1460
Authorities
Scheduled Completion Period for Construction of Arrival skywalk from FOB (F2) to City side statio
1 Submission and approval of designs and drawings D + 120
2 D + 965
Foundation: On completion of 100 % Foundation work
3 Completion of all superstructure, Structural part, lift & D + 1085
escalator well etc.
4 Completion of roofing etc. D + 1145
DATE REMARKS
2/28/2023
DATE REMARKS
2/28/2023
2/28/2023
2/28/2023