Major Upgradation of Prayagraj Junction Railway Station of Nor

S.NO STAGES COMPLETION


PERIOD IN DAYS
Scheduled Completion Period for Designing, Planning, Development of Arrangements for Modular Structure and S
Soil Investigation and its report, detailed site digital survey, recording of the
levels, detailed Architectural drawings and Structural Design of foundation &
whole structure, submission & approval of Architectural and Structural
drawings. Submission of detailed drawings of services. All the drawings
should be approved from local bodies/authorities and obtaining permission
to start the work. Site establishment activities like construction of site office,
staff room, conference room, laboratory, labour huts, installation of batching
1 plant, installation of casting yard, approval of design mix, steel yard, cement D+90
godown, shifting of T & P and all the mobilizing activities should be
completed. Work of demolition of existing structure which can be
demolished without disturbing the working of station should be completed
and site should be cleared. Issuance of GFC drawings for work.

Approval of detailed Design Basis Report of development of MODULAR


STRUCTURE for Civil, Architectural and MEPF, Green Building Strategies and
EMP report, Construction methodology, QA, QC and Safety, Health and
2 Environment Manual including sampling, presentations, submission of 3D D+120
model of appropriate scale, vetting from IIT/NIT etc. as required all complete

3 Development of arrangement for Modular structure as per approved D+150


construction methodology, making all arrangements complete

Scheduled Completion Date for the Project is 1460 days from the Appointed Date.
The Project Milestone to be read as D+(number of days from Appointed Date )
Tentative Start Date 01/11/2022
ay Station of North Central Railway
DATE REMARKS

r Modular Structure and Site Establishment

1/29/2023

2/28/2023

3/30/2023
Major Upgradation of Prayagraj Junction Railway Station of North Cent
COMPLETION PERIOD
S.NO STAGES IN DAYS

Scheduled Completion Date for Station Building (Civil Line Side)


1 Vacation of Residential Quarters D + 120
2 Submission and approval of Designs and Drawings D + 120
3 Demolition of residential quarters between 3rd D + 180
Avenue and 7th avenue
4 Shifting of Utilities as per site requirement D + 180
Foundation: On completion of 100 % Foundation
5 work (open foundations/pile foundations including D + 365
pile caps) and testing of substructure
6 Completion of superstructure of all floors D + 605
Completion of all the floor finished, wall finishes,
7 door, windows, glazing, partitioning, plumbing, D + 725
electrical works etc.
Completion of HVAC, announcement systems, false
8 ceilings, CCTV, LAN, signages, Lift & Escalators etc. D + 815
all E & M works complete in all respects.

9 Completion, handing over and approval from D + 845


Authorities
Scheduled Completion Date for Arrival blocks, RMS, Parcel Block (Civil Line Side)
1 Submission and approval of designs and drawings D+120
2 Demolition of residential quarters between 3rd D + 180
Avenue and 7th avenue
3 Shifting of Utilities as per site requirement D + 180
Foundation: On completion of 100 % Foundation
4 work (open foundations/pile foundations including D + 300
pile caps) and testing of substructure.
5 Completion of superstructure of all floors D + 425
Completion of all the floor finished, wall finishes,
6 door, windows, glazing, partitioning, plumbing, D + 515
electrical works etc.
Completion of HVAC, announcement systems, false
7 ceilings, CCTV, LAN, signages, Lift & Escalators etc. D + 605
all E & M works complete in all respects.

8 Completion, handing over and approval from D + 635


Authorities
Scheduled Completion Period for Proposed FOB with Ramps (Civil Line Side)
1 Submission and approval of designs and drawings D + 120
2 Foundation: On completion of 100 % Foundation D + 240
work
3 Completion of superstructure, Structural part, lift & D + 365
escalator well, roofing etc.

Completion of floor finishes, plastering, finishing,


4 cladding, CCTV, announcement systems, signages, D + 455
Lift & escalators E & M services etc complete in all
respects.
5 Completion, handing over and approval from D + 485
Authorities
Scheduled Completion Date for Basement (Civil line side)
1 Submission and approval of designs and drawings D+120
2 Shifting of Utilities as per site requirement D+240
Foundation: On completion of 100 % Foundation
work (open foundations/pile foundations including
3 pile caps/raft) and testing of substructure. D + 360

4 Completion of structural work including Lift, D + 540


escalator etc
5 Completion of all the floor finished, wall finishes, D + 660
door, windows etc.
Completion of announcement systems, false
6 ceilings, CCTV, signages etc. all E & M works D + 720
complete in all respects.
7 Completion, handing over and approval from D + 730
Authorities
Scheduled Completion Date for Substation (Civil Line Side)
Foundation: On completion of 100 % Foundation
1 work (open foundations/pile foundations including D + 240
pile caps) and testing of substructure.
2 Completion of superstructure of all floors D + 300
Completion of all the floor finished, wall finishes,
3 door, windows, glazing, partitioning, plumbing, D + 365
electrical works etc
Completion of HVAC, announcement systems, false
ceilings, CCTV, LAN, signages, Lift & Escalators etc.
4 all E & M works complete in all respects. D + 395

5 Completion, handing over and approval from D + 425


Authorities

Tentative Start Date 01/11/2022


way Station of North Central Railway
DATE REMARKS

e)
2/28/2023
2/28/2023
4/29/2023
4/29/2023

10/31/2023

7/2/2024

10/25/2024

1/23/2025

2/22/2025

ock (Civil Line Side)


2/28/2023
4/29/2023
4/29/2023

8/27/2023

12/30/2023

3/29/2024

6/27/2024

7/27/2024

Civil Line Side)


2/28/2023
6/28/2023

10/31/2023

1/29/2024
2/28/2024

2/28/2023
6/28/2023

10/26/2023

4/23/2024

8/21/2024

10/20/2024

10/30/2024

6/28/2023

8/27/2023

10/31/2023

11/30/2023

12/30/2023
Major Upgradation of Prayagraj Junction Railway Station of North Cen
COMPLETION PERIOD IN
S.NO STAGES
DAYS
Scheduled Completion Date for Elevated Concourse 1 & 2
1 Submission and approval of Designs and Drawings D+120
2 Shifting of Utilities as per site requirement D+160
3 Demolishing of FOB (F3) D + 210
Foundation: completion of 100 % Foundation work
4 (open foundations/pile foundations including pile D + 390
caps) and testing.
Completion of structural work of Column from
5 flooring to floor level concourse level, lift well, D + 480
stairs, escalator well etc..
6 Structural work placing of Girder, slab casting, D + 720
flooring, roofing.
7 Finishing, Electrical installation, air cooling, D + 810
furnishing and approval from Authorities.
8 Completion, handing over and approval from D + 840
Authorities
Scheduled Completion Date for Through Roof
1 Submission and approval of Designs and Drawings D+120
2 Shifting of Utilities as per Site Requirement D+240
Foundation: completion of 100 % Foundation work
3 (open foundations/pile foundations including pile D + 390
caps) and testing
4 Completion of structural work of Column from D + 720
foundation to Roof level
5 Structural truss for roofing D+900
6 Roofing with sheets including drainage etc. D + 1020
complete
Completion of through roofing including painting, E
7 & M works, false ceiling and complete D + 1200
commissioning
8 Completion, handing over and approval from D + 1230
Authorities
Scheduled Completion Period for 2-Tier (Double Deck) Skywalk connecting Concourse – 1 & Co
connecting Skywalks (Departure Skywalk connecting PF 6 and Station Buildings
1 Submission and approval of designs and drawings D + 120
2 Shifting of Utilities as per site requirement D+ 180
Foundation: On completion of 100 % Foundation D + 300
work
3 Completion of all superstructure, Structural part, D + 540
lift & escalator well etc.
4 Completion of roofing etc D + 600

Completion of floor finishes, plastering, finishing,


5 cladding, CCTV, announcement systems, signages, D + 690
Lift & escalators E & M services etc complete in all
respects.
6 Completion, handing over and approval from D + 720
Authorities
Scheduled Completion Period for Construction of Ramps from FOB (F1) to PF and refurbishmen
1 Submission and approval of designs and drawings D+120
2 Shifting of Utilities as per site requirement D+180
3 Dismantling of flooring, roofing etc. D + 180
4 Foundation: On completion of 100 % Foundation D + 270
work of Ramp
5 Completion of superstructure, Structural part of D + 390
ramps, platform, roofing etc.

Completion of floor finishes, plastering, finishing,


6 cladding, CCTV, announcement systems, signages, D + 510
Lift & escalators E & M services etc complete in all
respects.
7 Completion, handing over and approval from D + 540
Authorities

Tentative Start Date 01/11/2022


way Station of North Central Railway
DATE REMARKS

2/28/2023
4/9/2023
5/29/2023

11/25/2023

10/20/2024

2/28/2023
6/28/2023

10/20/2024

connecting Concourse – 1 & Concourse – 2. & all


tation Buildings
2/28/2023
4/29/2023
8/27/2023

4/23/2024

6/22/2023
10/20/2024

FOB (F1) to PF and refurbishment of FOB (F1, F2)


2/28/2023
4/29/2023
4/29/2023

4/23/2024
Major Upgradation of Prayagraj Junction Railway Station of North Cen
COMPLETION PERIOD IN
S.NO STAGES
DAYS
Scheduled Completion Date for Station Building (City Side)
1 Submission and approval of designs and drawings D + 120
2 Shifting of Utilities as per site requirement D+815
Temporary relocation of existing offices to Existing
3 Kumbh Sheds (City Side)/New Station Building (Civil D + 815
Lines Side)
4 Demolition of Existing station building D + 875
Foundation: On completion of 100 % Foundation work
5 (open foundations/pile foundations including pile D + 1025
caps) and testing of substructure.
6 Completion of superstructure of all floors D + 1265
Completion of all the floor finished, wall finishes, door,
7 windows, glazing, partitioning, plumbing, electrical D + 1385
works etc
Completion of HVAC, announcement systems, false
8 ceilings, CCTV, LAN, signages, Lift & Escalators etc. all E D + 1430
& M works complete in all respects.
9 Completion, handing over and approval from D + 1460
Authorities
Scheduled Completion Period for Construction of Arrival skywalk from FOB (F2) to City side statio
1 Submission and approval of designs and drawings D + 120
2 D + 965
Foundation: On completion of 100 % Foundation work
3 Completion of all superstructure, Structural part, lift & D + 1085
escalator well etc.
4 Completion of roofing etc. D + 1145

Completion of floor finishes, plastering, finishing,


5 cladding, CCTV, announcement systems, signages, Lift D + 1235
& escalators E & M services etc complete in all
respects.
6 Completion, handing over and approval from D + 1265
Authorities
Scheduled Completion Date for Construction of office block and parcel block at City side.
1 Submission and approval of designs and drawings D+120
2 Shifting of Utilities as per site requirement D+845
Foundation: On completion of 100 % Foundation work
3 (open foundations/pile foundations including pile D + 935
caps) and testing of substructure.
4 Completion of superstructure of all floors D + 995
Completion of all the floor finished, wall finishes, door,
5 windows, glazing, partitioning, plumbing, electrical D + 1055
works etc.
Completion of HVAC, announcement systems, false
6 ceilings, CCTV, LAN, signages, Lift & Escalators etc. all E D + 1115
& M works complete in all respects.
7 Completion, handing over and approval from D + 1145
Authorities
Scheduled Completion Date for Basement (City side)
1 Submission and approval of designs and drawings D+120
2 Shifting of Utilities as per site requirement D+845
Foundation: On completion of 100 % Foundation work
3 (open foundations/pile foundations including pile D + 1090
caps/raft) and testing of substructure.
4 Completion of structural work including Lift, escalator D + 1270
etc.
5 Completion of all the floor finished, wall finishes, door, D + 1390
windows etc.
Completion of announcement systems, false ceilings,
6 CCTV, signages etc. all E & M works complete in all D + 1450
respects.
7 Completion, handing over and approval from D + 1460
Authorities
Scheduled Completion Date for Substation (City side)
Foundation: On completion of 100 % Foundation work
1 (open foundations/pile foundations including pile D + 965
caps) and testing of substructure
2 Completion of superstructure of all floors D + 1025
Completion of all the floor finished, wall finishes, door,
3 windows, glazing, partitioning, plumbing, electrical D + 1090
works etc.
Completion of HVAC, announcement systems, false
4 ceilings, CCTV, LAN, signages, Lift & Escalators etc. all E D + 1120
& M works complete in all respects.
5 Completion, handing over and approval from D + 1150
Authorities
Scheduled Completion Date for Residential Quarter Tower (G+7)
1 Submission and approval of designs and drawings D+120
2 Shifting of Utilities as per site requirement D+180
Foundation: On completion of 100 % Foundation work
3 (open foundations/pile foundations including pile D + 240
caps) and testing of substructure
4 Completion of superstructure of all floors D + 405
Completion of all the floor finished, wall finishes, door,
5 windows, glazing, partitioning, plumbing, electrical D + 555
works etc.
6 Completion of CCTV, etc. complete in all respects. D + 600
7 Completion, handing over and approval from D + 615
Authorities
Scheduled Completion Period for refurbishment of Platform Resurfacing & Covering
1 Submission and approval of designs and drawings D+120
D+760
Foundation: On completion of 100 % Foundation work
2 (civil lines side Platform no 4,5,7,8,9 & 10) Foundation:
On completion of 100 % Foundation work (City Side
Platform no 1,2,3)
D + 1100
Completion of superstructure etc. (civil lines side
Platform no 4,5,7,8,9 & 10) D + 800
3
Completion of superstructure etc (City Side Platform
no 1,2,3) D + 1280

Completion of floor finishes, plastering, finishing,


HVAC,announcement systems, signages etc complete D + 880
in all respects. (Civil
4 lines side Platform no 4,5,7,8,9 & 10)
Completion of floor finishes, plastering, finishing,
HVAC, announcement systems, signages etc complete D + 1400
in all respects (City Side Platform no 1,2,3)
Completion, handing over and approval from
Authorities (civil lines side Platform no 4,5,7,8,9 & 10) D+900
5
Completion, handing over and approval from D + 1430
Authorities (City Side Platform no 1,2,3)
Scheduled Completion Period for Refurbishment of FOB(F4)
1 Submission and approval of designs and drawings D + 120
2 Dismantling of existing floor, roofing, cladding etc. D + 1100
3 Completion of roofing, cladding etc. D + 1280
Completion of floor finishes, plastering, finishing,
4 announcement systems, signages etc complete in all D + 1400
respects.
5 Completion, handing over and approval from D + 1430
Authorities

Tentative Start Date 01/11/2022


way Station of North Central Railway

DATE REMARKS

2/28/2023

om FOB (F2) to City side station block


2/28/2023

rcel block at City side.


acing & Covering
Major Upgradation of Prayagraj Junction Railway Station of North C
COMPLETION PERIOD IN
S.NO STAGES DAYS
Scheduled Completion Period for OHE Modification & TRD Works
1 Submission and approval of designs and drawings D+120
2 OHE Modification & TRD Works (civil lines side Platform no D + 760
4,5,7,8,9 & 10)
3 OHE Modification & TRD Works (City Side Platform no 1,2,3) D + 1400
4 Completion, handing over and approval from Authorities D + 1430
Scheduled Completion Period for ART Works at Various Locations
1 Submission and approval of designs and drawings D+120
Art work at various buildings, Concourse and other locations D + 830
2 as per approved drawings (civil lines side)
3 Art work at various buildings, Concourse and other locations D + 1400
as per approved drawings (City Side)
Completion, handing over and approval from Authorities (civil D + 845
lines side)
4
Completion, handing over and approval from Authorities (City D + 1430
Side)
Scheduled Completion Period for Electrical & Mechanical Supply & Installation Works, IncludingS
Sets, Ups, Solar Photo Voltaic, Façade Lighting, Professional Display System, Interactive Display, I
Information System, Integrated PassengerInformation System, Ticket Dispenser, Ticket Dispenser
1 Submission and approval of designs and drawings D + 120
Sub-station installation & commissioning (Civil Lines side) D + 815
2
Sub-station installation & commissioning (City Side) D + 1430
Diesel generating sets (Civil Lines side) D + 815
3
Diesel generating sets (City Side) D + 1430
Uninterrupted power supply (Civil Lines side) D + 815
4
Uninterrupted power supply (City Side) D + 1430
VRV/VRF AC system (Civil Lines side) D + 815
5
VRV/VRF AC system (City Side) D + 1430
Solar photo voltaic power generation system (Civil Lines side) D + 815
6
Solar photo voltaic power generation system (City Side) D + 1430
Solar water heating system (Civil Lines side) D + 815
7
Solar water heating system (City Side) D + 1430
Cctv system (external portion- Civil Lines side) D + 815
8
Cctv system (external portion- City Side) D + 1430
Street lighting with led (Civil Lines side) D + 815
9
Street lighting with led (City Side) D + 1430
Stp/etp plant (Civil Lines side) D + 815
10
Stp/etp plant (City Side) D + 1430
Emergency light & illuminated signages (Civil Lines side) D + 815
11
Emergency light & illuminated signages (City Side) D + 1430
Professional display panel integrated passenger information,
digital clock, ticket dispenser etc. (Civil Lines side) D + 815
12
Professional display panel integrated passenger information, D + 1430
digital clock, ticket dispenser etc. (City Side)
Baggage scanner (Civil Lines side) D + 815
13
Baggage scanner (City Side) D + 1430
Facade lighting (Civil Lines side) D + 815
14
Facade lighting (City Side) D + 1430
Door frame metal detector (Civil Lines side) D + 815
15
Door frame metal detector (City Side) D + 1430
Completion, handing over and approval from authorities (Civil D + 845
Lines side)
16
Completion, handing over and approval from authorities (City D + 1460
Side)
Scheduled Completion Date for Site Development (Roads & Paths, External Plumbing, Drainage, R
Landscaping Etc.) & Public Plaza
1 Submission and approval of designs and drawings D+120
Development of public plaza at civil lines. D+815
2
Development of public plaza at city side D + 1400
Completion of civil work, road construction work, cc work and
testing of substructure. (Civil lines Side) D+815
3
Completion of civil work, road construction work, cc work and
testing of substructure. (City Side) D + 1430
Completion of Horticulture work, Drainage Work, Water
Supply & Sewerage (civil lines Side) D+815
4
Completion of Horticulture work, Drainage Work, Water
Supply & Sewerage (City Side) D + 1430
Completion of electrical work, IT systems, signages complete
in all respects. (Civil lines Side) D+815
5
Completion of electrical work, IT systems, signages complete
in all respects. (City Side) D + 1430
Completion, finishing & furnishing handing over and approval
from Authorities. (Civil lines Side) D + 845
6
Completion, finishing & furnishing handing over and approval
from Authorities. (City Side) D + 1460
Scheduled Completion Date for integrated testing & commissioning:
Successful Completion of Integrated testing and
1 commissioning along with submission of completion drawings D + 1460
and maintenance manual.

Tentative Start Date 01/11/2022


ay Station of North Central Railway

DATE REMARKS

2/28/2023

2/28/2023

allation Works, IncludingSub Station, STP, Generator


tem, Interactive Display, Integrated Passenger
spenser, Ticket Dispenser, etc.
2/28/2023
rnal Plumbing, Drainage, RWH Services with

2/28/2023