Question: 1 Correct

Based on the following diagram, what is the total duration of


the project?

https://www.pm-tricks.com/QuizHistory/review/4581 1/37
7/23/2019 PM-Tricks | Dashboard

https://www.pm-tricks.com/QuizHistory/review/4581 2/37
7/23/2019 PM-Tricks | Dashboard

17

15

22

21

Explanation
The critical path is Start-A-D-E-G-H-End, and the duration of the critical path with the data given is
17.

Question: 2 Correct

Rekha is a project manager on a large construction project.


Rekha had originally planned to use both of the company's
tower crane simultaneously for a project but has just learned
that one of them will be unavailable. Rekha adjusts the
schedule so that the components are created sequentially
using the one remaining tower crane. Unfortunately, this action
affects the critical path and delays the planned finish date of
the project. Which of the following techniques has been used
by Rekha in this situation?

Resource leveling

Fast tracking

Reserve analysis

Critical path method

https://www.pm-tricks.com/QuizHistory/review/4581 3/37
7/23/2019 PM-Tricks | Dashboard

Explanation
Resource leveling is a resource optimization technique in which start and finish dates are adjusted
based on resource constraints with the goal of balancing the demand for the resources with the
available supply. Resource leveling can often cause the original critical path to change which is
what happened in the scenario described. Adjusting the schedule to accommodate the loss of one
of the tower crane is an example of resource leveling. [PMBOK 6th edition, Page 211]

Question: 3 Incorrect

You and your team have compiled your project’s activity list,
determined how the activities should be performed and
analyzed the schedule. You are preparing information for the
project sponsor to highlight the identified activities that may
create a delay in the overall project schedule. Which of the
following would be most useful in this situation?

Project schedule network diagrams

Activity attributes

Duration estimates

Project calendars

Explanation
In this question, project network diagrams would best serve to provide information concerning
activities that would possibly create schedule delays. A project network diagram is one of three
suggested project schedule models. At a minimum, a project schedule should include planned
start dates and planned finished dates for each activity. Network diagrams which include activity
date information and critical path activities, display how those activities logically relate to other
activities and the overall project timeline. A detailed network diagram that includes critical path
activities, durations, milestones, and resources could be useful in this situation to highlight the
activities that may create a delay in the overall project schedule. [PMBOK 6th edition, Page 164]

Question: 4 Correct

https://www.pm-tricks.com/QuizHistory/review/4581 4/37
7/23/2019 PM-Tricks | Dashboard

A detailed milestone list is created as an output of what


process?

Define Activities

Sequence Activities

Develop Project Charter

Develop Schedule

Explanation
A detailed milestone list is created as an output of the Define Activities process and includes
information on whether the milestone is mandatory or optional. Note that the project charter also
contains milestone information but at a higher level. [PMBOK 6th edition, Page 186]

Question: 5 Correct

Your project Production rates changed over the last 3 months.


Therefore, you’re currently doing the performance reviews of
the project, doing a comparative graphical analysis, comparing
the future performance goals to the current performance of the
project to determine future performance. An appropriate tool
which you can use is:

Trend analysis

Control chart

Statistical sampling

Scatter diagram

https://www.pm-tricks.com/QuizHistory/review/4581 5/37
7/23/2019 PM-Tricks | Dashboard

Explanation
Trend analysis examines project performance over time to determine whether performance is
improving or deteriorating. Graphical analysis techniques are valuable for understanding
performance to date and for comparing to future performance goals in the form of completion
dates. [PMBOK 6th edition, Page 227]

Question: 6 Incorrect

A project manager is working with the project team to estimate


durations for the identified project activities. The team is
looking to achieve the most accurate estimate possible. What
estimating technique can they use to generate the desired
result?

Three-point estimating

Top-down estimating

Parametric estimating

Analogous estimating

Explanation
Three-point estimating, it uses three estimates (most likely, optimistic, and pessimistic) to
calculate the average value of activity duration. It reduces the bias, risks, and uncertainties from
the duration calculation. It is more accurate than the analogous technique and Parametric
estimating. Analogous estimating is also referred to as top-down estimating.

Question: 7 Correct

As per the Below Table, what is the Critical Path?

https://www.pm-tricks.com/QuizHistory/review/4581 6/37
7/23/2019 PM-Tricks | Dashboard

A-B-C-E & A-B-D-E

A-B-C-E & A-D-E

A-C-E

https://www.pm-tricks.com/QuizHistory/review/4581 7/37
7/23/2019 PM-Tricks | Dashboard

A-B-D-C

Explanation
There are 3 paths in this network diagram are as follows: ABCDE, ABDE, ADE. Since paths
ABCDE, ABDE is the longest paths with zero float for all of the activities, it represents the critical
path.

Question: 8 Incorrect

You are a project manager in a big construction project. A


strike by local workers occurs due to the lateness workers'
payments. That leads to delays in a major component delivery.
What is the process the project manager could have been done
differently to prevent this type of situation?

Develop Schedule

Monitor Risk

Identify Stakeholder

Control Scope

Explanation
To prevent this type of situation, we must go to planning. So choice B & D are wrong and C not
related. when developing Schedule, we identify milestones which payments related to milestone
and progress. Develop Schedule Process include What-if scenario analysis as a tool. What-if
scenario analysis is the process of evaluating scenarios in order to predict their effect, positive or
negative, on project objectives. A schedule network analysis is performed using the schedule to
compute the different scenarios, such as delaying a major component delivery, such as a strike.
[PMBOK 6th edition, Page 213] . The above question very important and you will counter like this
idea in the real exam.

Question: 9 Correct

https://www.pm-tricks.com/QuizHistory/review/4581 8/37
7/23/2019 PM-Tricks | Dashboard

A project manager is estimating activity durations for a project.


Which of the following is the best to help the project manager
to estimate duration?

Subject matter expert (SME)

Project sponsor

All Stakeholders

HR manger

Explanation
SME is a part of EXPERT JUDGMENT and Expert Judgment Tools and Techniques in the Estimate
Activity Duration Process. [PMBOK 6th edition, Page 200]

Question: 10 Correct

As a Project Manager, you are estimating the duration of your


project activities using Using a triangular distribution formula.
For a particular project activity, your Optimistic estimate is 14
days, Pessimistic estimate is 49 days, and Most Likely estimate
is 27 days. What should be the expected duration of this
activity?

30

50

25

32

https://www.pm-tricks.com/QuizHistory/review/4581 9/37
7/23/2019 PM-Tricks | Dashboard

Explanation
triangular distribution allows the estimator to include three estimates: optimistic, pessimistic, and
most likely. The expected duration is calculated using the equation: Expected Duration = [P + ML +
O]/3, where P is the pessimistic estimate, ML is the most likely estimate, and O is the optimistic
estimate. Using this method, the correct answer 14+49+27/3=30 days.

Question: 11 Correct

You are a project manager in the XYZ project for your


organization. Due to the lateness of workers' payments, the
workers made a strike, causing delays in an important
component delivery. What could have been done differently to
prevent this type of situation?

What-If Scenario Analysis

Fast-Tracking

Crashing

Change management plan

Explanation
Keyword ( strike ) What-if scenario analysis is the process of evaluating scenarios to predict their
effect, positive or negative, on project objectives. A schedule network analysis is performed using
the schedule to compute the different scenarios, such as delaying a major component delivery,
extending specific engineering durations, or introducing external factors, such as a strike or a
change in the permit process. The outcome of the what-if scenario analysis can be used to assess
the feasibility of the project schedule under different conditions, and in preparing schedule
reserves and response plans to address the impact of unexpected situations. [PMBOK 6th edition,
Page 213]

Question: 12 Correct

https://www.pm-tricks.com/QuizHistory/review/4581 10/37
7/23/2019 PM-Tricks | Dashboard

You are leading your team in the preparation of your project


schedule and are currently sequencing the activities and
determining which type of precedence relationship exists
between them. Which of the following is the most commonly
used type of precedence relationship that you will use?

Finish-to-start

Finish-to-finish

Start-to-finish

Start-to-start

Explanation
In PDM, FS is the most commonly used type of precedence relationship. The SF relationship is
very rarely. [PMBOK 6th edition, Page 190]

Question: 13 Correct

You are in the planning process of an R1b project. You realize


that your schedule requires more resources in certain months
of the project than what are available to you. Your senior
management has clearly instructed that you will not be able to
obtain additional resources for the project. So, you instruct
your planner to adjust the schedule to accommodate these
constraints. What are you instructing the planner to do?

Resource leveling

Crashing

Fast tracking

https://www.pm-tricks.com/QuizHistory/review/4581 11/37
7/23/2019 PM-Tricks | Dashboard

Evaluation and Review Technique

Explanation
Resource leveling. A technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing the demand for resources with the available supply.
[PMBOK 6th edition, Page 211]

Question: 14 Correct

You are Creating a network diagram for your project. Activity A


(5 days ) can start immediately. Activity B ( 3 days ) can start
after Activity A is complete. Activity C ( 2 days ) can start after
Activity B is complete. Activity D (4 days ) can start after
Activity A and B are complete. Activity E ( 3 days ) can start
after Activity C and D are complete. While having all Activities
as FS relation, what is the Float of Activity D?

0 Day

2 Day

1 Day

3 Day

Explanation
After drawing the network, you will determine that Activity D on the Critical Path. So the float =
zero

Question: 15 Correct

https://www.pm-tricks.com/QuizHistory/review/4581 12/37
7/23/2019 PM-Tricks | Dashboard

The flexibility or total float in a schedule is measured by


subtracting the early dates from the late dates. Which one of
the following will help you identify the flexibility in your
schedule?

Critical Path Method

Leads and lags

Checklist

What-if Scenario Analysis

Explanation
The critical path of a project is the series of activities that have the least amount of float - usually
zero (flexibility). [PMBOK 6th edition, Page 210]

Question: 16 Correct

You are running one week behind on a project due to late


delivery by a vendor. You are forced to compress your project
schedule due to a government-mandated end date that
constrains your project. After meeting with your team, you
found a method to compress the project without adding more
resources or increase the project cost. This is an example of
which of the following?

Fast Tracking

Crashing

Risk mitigation

https://www.pm-tricks.com/QuizHistory/review/4581 13/37
7/23/2019 PM-Tricks | Dashboard

Resource leveling.

Explanation
Fast tracking. A schedule compression technique in which activities or phases are normally done
in the sequence is performed in parallel for at least a portion of their duration without adding more
resources or increase the project cost. [PMBOK 6th edition, Page 215]

Question: 17 Correct

You are using a methodology that calculates the amount of


float on various paths in the network diagram to determine the
minimum project duration. What tool or technique are you
using?

Critical path method

Critical chain method

Parametric estimating

Three-point estimating

Explanation
The critical path method is used to estimate the minimum project duration and determine the
amount of schedule flexibility on the logical network paths within the schedule model. A critical
path is normally characterized by zero total floats on the critical path. [PMBOK 6th edition, Page
210]

Question: 18 Correct

What is the correct sequence for these tools and techniques


used in Project Schedule Management?

https://www.pm-tricks.com/QuizHistory/review/4581 14/37
7/23/2019 PM-Tricks | Dashboard

Decomposition work packages into activities, Three-Point Estimates


and Schedule Task

Dependency determination, Decomposition, Bottom up estimating,


and Resource leveling

Variance analysis, Three point estimates, Dependency determination,


and Decomposition

Decomposition, Alternatives analysis, Variance analysis, and Three


point estimates

Explanation
Decomposition work packages into activities = Define activity & Three-point estimates= estimate
activity Duration & schedule task = Develop schedule.

Question: 19 Incorrect

A senior project manager is working on monitoring the


progress of the schedule. To determine whether performance is
getting better or worse, he analyzes project performance over
time. What technique is the project manager using?

Trend Analysis

Variance analysis

Inspection

Performance reviews

Explanation
Trend analysis examines project performance over time to determine whether performance is
improving or deteriorating. Graphical analysis techniques are valuable for understanding

https://www.pm-tricks.com/QuizHistory/review/4581 15/37
7/23/2019 PM-Tricks | Dashboard

performance to date and for comparing to future performance goals in the form of completion
dates.[PMBOK 6th edition, Page 227]

Question: 20 Correct

Using a triangular distribution formula, calculate the expected


activity duration based on the following three-point estimates:
Optimistic =18 days, Most Likely = 22days, Pessimistic =
27days.

22.33

21.33

22.11

23.20

Explanation
uses a triangular distribution is as follows: (Optimistic + Pessimistic + Most Likely) ÷ 3. Plug in the
values provided to calculate the following: (18 + 22 + 22) ÷ 3 = 22.33 days

Question: 21 Correct

During a presentation to management, you want to display the


project schedule with only the key deliverables displayed. What
is the correct tool for this purpose?

Milestone chart

Control chart

Critical path method


https://www.pm-tricks.com/QuizHistory/review/4581 16/37
7/23/2019 PM-Tricks | Dashboard

Critical chain diagram

Explanation
Milestone chart using with senior management. A milestone chart displays only the key
deliverables and is simple and easy to understand. [PMBOK 6th edition, Page 218]

Question: 22 Correct

Which of the following estimating technique that uses a


statistical relationship between historical data and project
parameters to calculate the activity duration?

Parametric estimating

Three-Point estimating

Bottom-up estimating

Top-down estimating

Explanation
Parametric estimating is an estimating technique in which an algorithm is used to calculate cost or
duration based on historical data and project parameters. Parametric estimating uses a statistical
relationship between historical data and other variables (e.g., square footage in construction) to
calculate an estimate for activity parameters, such as cost, budget, and duration. [PMBOK 6th
edition, Page 200]

Question: 23 Correct

You are a Project Manager. In the process of sequencing


activities for your project, you create a schedule network
diagram that uses boxes called nodes to represent activities

https://www.pm-tricks.com/QuizHistory/review/4581 17/37
7/23/2019 PM-Tricks | Dashboard

and connects them with arrows to represent logical


relationships between them. What is this popular scheduling
diagram known as?

Precedence Diagramming Method (PDM)

Arrow Diagramming Method (ADM)

Program Evaluation and Review technique (PERT)

Graphical Evaluation and Review Technique (GERT)

Explanation
The Precedence Diagram Method, also known as Activity-On-Node, is a tool for scheduling
activities in a project plan and constructing a project schedule network diagram that uses boxes,
referred to as nodes, to represent activities and connects them with arrows that show the
dependencies.

Question: 24 Correct

The critical activities of the project have been estimated for


their durations but risks associated with them have not been
factored yet. The risks listed in the risk register are then
reviewed and additional durations are factored for activities
which could be prone to those risks. What type of reserve has
been applied?

Contingency reserve

Management reserve

Alternative reserve

Estimation bucket

https://www.pm-tricks.com/QuizHistory/review/4581 18/37
7/23/2019 PM-Tricks | Dashboard

Explanation
Explanation: Additional duration factored due to possible risks are known as contingency
reserves. These may be applied to cost estimates also. Management reserve is for unknown risks.
Alternative reserve and estimation bucket are not valid terminologies.

Question: 25 Correct

A project consists of 5 activities, A, B, C, D and E. B & C can't


start until A has finished, D can't start until C has finished, and
E can't start until B and D have finished. The duration of A is 5,
B is 8, C is 10, D is 19 and E is 15. How many days can activity
B be delayed, without delaying the whole project?

21

37

29

38

Explanation
Explanation: Answer = 21 ; to answer the question you need to build the CPM network. . The two
paths are ACDE of length 49 and ABE with length 28. The float of B will be 49-28=21.

Question: 26 Correct

Your current project phase has 8 activities, A to H. A and E can


start at the same time. A must finish before B starts. B must
finish before C and F start. C must finish before D starts. E
must finish before F and G start. F and G must finish before H
starts. C and H must finish before D starts. Duration of: A = 5, B
= 8, C = 15, D = 10, E = 6, F = 9, G = 19, H = 5. What is the critical
path?
https://www.pm-tricks.com/QuizHistory/review/4581 19/37
7/23/2019 PM-Tricks | Dashboard

EGHD

ABCD

ABFHD

EFHD

Explanation
Explanation: Answer = EGHD because EGHD is the longest path with 40 days and therefore all
activities have zero float

Question: 27 Correct

A project manager and his team have finished creating the


Work Breakdown Structure (WBS) and the Work Breakdown
Structure dictionary. The project manager then prepares a
detailed and itemized documentation of all the schedule
activities that are part of a particular project. What should the
Project Manager do NEXT?

Create a network diagram for the project

Determine quality standards, processes, and metrics

Determine high-level project assumptions and constraints

Conduct a project progress meeting

Explanation
The project manager has created a WBS, a WBS dictionary, and an activity list in the planning
stage. The next step would be to create a network diagram for the project.

https://www.pm-tricks.com/QuizHistory/review/4581 20/37
7/23/2019 PM-Tricks | Dashboard

Question: 28 Correct

A project manager is in the process of analyzing activity


sequences, durations, resource requirements, and schedule
constraints to create an approved project schedule. What
should the project manager do NEXT?

Use the approved schedule duration as a baseline and start tracking


the project

Create a network diagram of the project using one of the


diagramming methods

Use techniques like Critical Path method and What-if Analysis to


calculate optimum duration of the project

Determine resource requirement for each activity in the project

Explanation
The project manager is in the "develop schedule" process and has already derived an approved
project schedule. Other options are already completed as part of the processes estimate activity
resources, develop schedule, and sequence activities. The next step would be to treat this
estimate as a schedule baseline and start tracking the project as part of the control schedule
process.

Question: 29 Correct

Which of the following statements is INCORRECT about the


critical path method?

It considers resource limitations to derive a more realistic schedule

It helps a project manager determine where it is best to focus his


project management efforts

https://www.pm-tricks.com/QuizHistory/review/4581 21/37
7/23/2019 PM-Tricks | Dashboard

It helps to determine which activities have float and can be delayed


without delaying the project

It calculates and determines the shortest time to complete the project

Explanation
The critical path method calculates theoretical early start and finish dates along with late start and
finish dates for all activities without regard to any resource limitations. In fact, the critical path
method is a schedule network analysis technique which modifies the project schedule to account
for limited resources.

Question: 30 Correct

You are creating a network diagram for your project. Activity A


(6 days) and Activity B (4 days) can start immediately. Activity C
(5 days) can start after Activity B is complete. Activity D (4
days) and Activity F (2 days) can start after Activity A is
complete. Activity E (4 days) can start after Activity C and
Activity D are complete. Activity G (5 days) can start after
Activity D and Activity F are complete. When Activity E and
Activity G are completed, the project is done. What is the slack
of Activity E?

One day

Four days

Zero

Two days

Explanation
There are four possible paths on this network diagram. ADG (duration of 15 days) is the critical
path with the longest duration. The other three are AFG (duration of 13 days), ADE (duration of 14

https://www.pm-tricks.com/QuizHistory/review/4581 22/37
7/23/2019 PM-Tricks | Dashboard

days), and BCE (duration of 13 days). Subtracting the length of ADE from the critical path (15-14)
shows a difference of one day. This is the slack of Activity E.

Question: 31 Correct

You are a Project Manager who manages a large software


project. It has a month-long design phase in which the team
would be preparing the design documents for independent
project modules. The activity review for these modules can
begin 15 days after starting the design phase. The 15 days'
difference between the start of the design phase and the start
of the review activity shows _____ between the two activities.

Lag

Lead

External dependency

Mandatory dependency

Explanation
There is a lag of 15 days between the activities. If the second activity starts, when the first activity
is running, this situation is called Lead. After the first activity completes, if there is a delay or wait
period before the second activity starts, it is called a lag.

Question: 32 Correct

You are managing a project to build a multi-storey complex in


your city. You are waiting for the clearance to start construction
of the building. Which kind of dependency is this an example
of?

https://www.pm-tricks.com/QuizHistory/review/4581 23/37
7/23/2019 PM-Tricks | Dashboard

External Dependency

Mandatory Dependency

Discretionary Dependency

Internal Dependency

Explanation
This is an example of external dependency that involves the relationship between the project and
non-project activities which are outside the control of the project manager. For example,
government clearance before the construction activity can start at a site.[PMBOK 6th edition, Page
192]

Question: 33 Correct

A major stakeholder in a project wants to know his role and


responsibility in the scheduling process of the project. He also
wants to understand how the schedule baseline is established
and which scheduling methodologies are used. Which of the
following best provides the information?

Schedule Management Plan

Stakeholder Register

Project Schedule Baseline

Project Management Plan

Explanation
The schedule management plan could be a subsidiary of the project management plan or an
independent document that establishes how to schedule management will be carried out in the
project. It serves as guidance for the scheduling process and defines the roles and
responsibilities of stakeholders in the process, along with scheduling methodologies and
schedule and change control procedures.

https://www.pm-tricks.com/QuizHistory/review/4581 24/37
7/23/2019 PM-Tricks | Dashboard

Question: 34 Incorrect

Rolling wave planning is a form of progressive elaboration


planning where the work to be accomplished in the near term is
planned in detail, and future work is planned at a higher level of
the WBS. Which process uses rolling wave planning as a tool
and technique?

Define Activities

Sequence Activities

Estimate Activity Resources

Develop Schedule

Explanation
The define activities process uses rolling wave planning as a tool and technique.[PMBOK 6th
edition, Page 185]

Question: 35 Correct

You are managing a project in which your team members are


uncertain as to how much time will be needed for each activity.
Which of the following techniques is considered the most
useful in this case?

Project Evaluation and Review Technique (PERT)

Critical Path Method (CPM)

Arrow Diagramming Method (ADM)

https://www.pm-tricks.com/QuizHistory/review/4581 25/37
7/23/2019 PM-Tricks | Dashboard

Precedence Diagramming Method (PDM)

Explanation
Project Evaluation and Review Technique (PERT) ( Beta )is the technique used for time
measurement in case of uncertainties. Optimistic, pessimistic, and most likely are taken into
consideration.

Question: 36 Correct

You are running a research project. Your team has developed a


project schedule and calculated theoretical early start, early
finish, late start and late finish dates for all activities using the
Critical Path Method (CPM). In this context, which of the
following statements is correct?

On any network path the schedule flexibility is measured by the


amount of total float

The critical chain method should be performed immediately after


performing the critical path method

Resource limitations are already taken into account when using the
critical path method

This schedule becomes the final schedule since the critical path
method was used to develop it

Explanation
The schedule flexibility on any network path is measured by the total float. The critical path has
zero total float.

Question: 37 Correct

https://www.pm-tricks.com/QuizHistory/review/4581 26/37
7/23/2019 PM-Tricks | Dashboard

You are monitoring the status of a project to update the project


progress and manage changes to the schedule baseline. You
have some resources assigned to more than one activity
simultaneously, making them overallocated during those days.
You want to reduce this overallocation and keep resource
usage at a constant level. What technique should you use to
achieve this goal?

Resource Leveling

Schedule Compression

Resource Compression

Resource DeAllocation

Explanation
Resource leveling is used to reduce overallocation and to keep resource usage at a constant level.
This technique can be used in both the Develop Schedule process and the Control Schedule
process.

Question: 38 Incorrect

Which of the following methods in the Control Schedule


process is used to compute different scenarios to get the
project realigned with the Project Management Plan?

Whatif Scenario analysis

Corrective Action

Delphi Technique

Pareto Chart
https://www.pm-tricks.com/QuizHistory/review/4581 27/37
7/23/2019 PM-Tricks | Dashboard

Explanation
What if scenario analysis is a type of modeling technique, which can be used along with risk
monitoring to review various scenarios and bring the schedule into alignment with the Project
Management Plan.

Question: 39 Incorrect

Which of the following terms is used to describe the amount of


time that a schedule activity can be delayed or extended from
its early start date without delaying the project finish date or
violating a schedule constraint?

Total Float

Activity Float

Project Float

Free Float

Explanation
Total Float is the amount of time that a schedule activity can be delayed or extended from its early
start date without delaying the project finish date or violating a schedule constraint. Free Float is
the amount of time that a schedule activity can be delayed without delaying the early start date of
any successor or violating a schedule constraint.

Question: 40 Correct

You are managing a pharmaceutical research project. Your


research officer tells you that you need to plan his research
activity so that it finishes before the documentation begins.

https://www.pm-tricks.com/QuizHistory/review/4581 28/37
7/23/2019 PM-Tricks | Dashboard

Other than that he says it can start as late in the project as


necessary. What is the relationship between the research
activity and the documentation activity?

Finish-to-Start

Finish-to-Finish

Start-to-Finish

Start-to-Start

Explanation
The question contains a twist: "the activity can start as late as necessary." If you don't focus on
this distraction, you will notice that it's a simple finish to start a relationship. Read the question
again; even if you schedule the activity as late as possible it doesn't change the relationship.

Question: 41 Correct

While running a mobile phone project, Cindy hires some


consultants for her project who will be working only on a short
term basis. She will likely perform Resource Leveling to keep
the consultants' usage at a constant level during project
execution. In this scenario, which of the following statements
about Resource Leveling is true?

Resource Leveling can often cause the critical path to change

Critical Path Method is applied after Resource Leveling is performed

Resource Leveling is used as a tool for the Define Activities process

Resource Leveling does not change the critical path

https://www.pm-tricks.com/QuizHistory/review/4581 29/37
7/23/2019 PM-Tricks | Dashboard

Explanation
Resource Leveling is a technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing the demand for resources with the available supply.
Resource Leveling is performed when resources are over-allocated to keep the resources at a
constant level and it often alters the original critical path.

Question: 42 Correct

A key stakeholder on Diana's project requests information


about the planned finish date and milestone dates. Which of the
following documents will provide Diana with the most accurate
information about the planned finish date and milestone dates
for her project?

Project Schedule

Project Scope Statement

Activity List

Project Charter

Explanation
The Project Charter contains initial project finish dates and summary milestones, which are both
created during the initiation phase, when very little is known about the project. The Project
Schedule contains more detailed information about the schedule start dates, end dates, and
milestone dates, based upon a further understanding of the project after the Project Charter was
developed, and is, therefore, the "best" document in this scenario to provide Diana with the
information that the stakeholder requires.

Question: 43 Correct

After creating a project schedule, the project manager could


use the Control Schedule process for all of the following
activities except?

https://www.pm-tricks.com/QuizHistory/review/4581 30/37
7/23/2019 PM-Tricks | Dashboard

Determining planned start and finish dates for project activities

Managing actual schedule changes as they occur

Influencing the factors that create schedule changes

Determining that the project schedule has changed

Explanation
Development of planned start and finish dates is an activity performed in the Develop Schedule
process. All other options indicate activities that are performed in the Control Schedule process.

Question: 44 Correct

You and your team have just created a schedule network


diagram. You have come up with the estimates and have
defined the durations and subsequently have identified the
Critical Path. You now decide to do a "Backward Pass" through
the Schedule Network Diagram. What would you be
calculating?

The Late Start and Late Finish for each activity

The duration of paths other than the critical path

The duration of the critical path

The Early Start and Early Finish for each activity

Explanation
Options ( The duration of paths other than the critical path ) and ( The duration of the critical path )
are incorrect as the Backward Pass is not used to calculate the duration. In fact, the critical path is
calculated based on duration. Option ( The Early Start and Early Finish for each activity ) talks
about Early Start and Early Finish, which are calculated using "Forward Pass." Using "Backward
Pass," we calculate the Late Start and Late Finish of all the activities in the network diagram.

https://www.pm-tricks.com/QuizHistory/review/4581 31/37
7/23/2019 PM-Tricks | Dashboard

Question: 45 Correct

You are in charge of constructing a high-rise residential


building. After creating a Network diagram, you have identified
the Critical Path. Work has started, but suddenly due to
inclement weather, plinth work has got delayed. This plinth
work activity was on the critical path. As a manager driving this
project, would you be worried and why?

Yes - Any delay of activities on the critical path would lead to a delay
of the entire project

Yes - you will now have to relay this bad news to the client

No - Activities on the critical path do not impact the schedule

No - It will not matter if the Plinth work is delayed.

Explanation
If activities on the critical path are delayed, it can lead to a delay in the entire Project.

Question: 46 Correct

You are the project manager of a software project. You have


just analyzed activity sequences, durations, resource
requirements, and schedule constraints and created project
schedule. To which process does the above tasks belong?

Develop Schedule

Control Schedule

https://www.pm-tricks.com/QuizHistory/review/4581 32/37
7/23/2019 PM-Tricks | Dashboard

Sequence Activities

Define Activities

Explanation
Analyzing activity sequences, durations, resource requirements, and schedule constraints and
creating project schedule belong to Develop Schedule process.

Question: 47 Correct

Your company has won a prestigious project that deals with


building software to be used on spaceships landing on the
moon. After building the schedule network diagram, you
identify the critical path and also a number of near-critical
paths. What does this mean with respect to Risks related to
Project Schedule?

The project is at high risk of meeting its schedule, considering


additional near-critical paths

The project has no risks of meeting its schedule, considering


additional near-critical paths

Near-critical path will have no impact on the schedule; hence, no


risks at all

The near-critical path activities have a lot of Float, so there is no fear


of not meeting the project completion

Explanation
Greater the number of near-critical paths, greater the risk of the project not meeting its scheduled
completion dates. This is because the near-critical path activities will have a very little float, so
thereby hardly any flexibility. Any slippages in these tasks, in addition to tasks on the Critical Path,
can lead to schedule slippage.

https://www.pm-tricks.com/QuizHistory/review/4581 33/37
7/23/2019 PM-Tricks | Dashboard

Question: 48 Correct

A software development project has been awarded to one of


the many vendors. Your company and the vendor have agreed
to build this project using the Waterfall Methodology. You
decide to check with the progress regarding when development
will start. The vendor informs you that the actual development
can only start after the completion of the design. Which type of
relationship best describes the dependency between design
and actual development?

Finish-to-Start

Finish-to-Finish

Start-to-Start

Start-to-Finish

Explanation
Finish-to-Start means that the Successor Activity cannot start without the Predecessor activity
being completed. In this case, the Design is the Predecessor activity and Development is the
Successor Activity. So, here Development (Successor Activity) cannot start without completion of
Design (Predecessor Activity).

Question: 49 Correct

You and your team have compiled your project’s activity list,
determined how the activities should be performed and
analyzed the schedule. You are preparing information for the
project sponsor to highlight the identified activities that may
create a delay in the overall project schedule. Which of the
following would be most useful in this situation?

https://www.pm-tricks.com/QuizHistory/review/4581 34/37
7/23/2019 PM-Tricks | Dashboard

Project network diagrams

Activity attributes

Duration estimates

Project calendars

Explanation
In this question, project network diagrams would best serve to provide information concerning
activities that would possibly create schedule delays. A project network diagram is one of three
suggested project schedule models. At a minimum, a project schedule should include planned
start dates and planned finished dates for each activity. Network diagrams which include activity
date information and critical path activities, display how those activities logically relate to other
activities and the overall project time line. A detailed network diagram that includes critical path
activities, durations, milestones, and resources could be useful in this situation to highlight the
activities that may create a delay in the overall project schedule.

Question: 50 Correct

The ES of an activity is 2 days, and the duration of the activity


is 5 days. The LF for the activity is 8 days. What is the total float
for this activity?

1 day

5 days

3 days

6 days

Explanation
We can calculate float using the formula EF=ES+D=2+5=7 and LS=LF-D=8-5=3. The formula for
Total float is LS-ES or LF-EF. The answer is 1 day.

https://www.pm-tricks.com/QuizHistory/review/4581 35/37
7/23/2019 PM-Tricks | Dashboard

Question: 51 Correct

Which of the following is a soft logic dependency in a


precedence network?

To opt for laying out the electrical cables and plumbing at the same
time in a completed floor of the building though they may be laid
separately

Waiting for internal approval before proceeding to the next activity

Waiting for materials to arrive from a supplier before the product can
be made

To develop software only after the required systems are installed

Explanation
The electrical and plumbing need not be done in parallel, therefore, a discretionary or soft logic of
preferential dependency. All other choices are either mandatory, internal or external dependencies.

Question: 52 Incorrect

While deriving the schedule for an agile project you ask your
team member to provide their acceptance for a schedule
related decision. Some of them show a closed fist and the
others show only two fingers. An insignificant number of
people show all five fingers. What is your conclusion about
their response?

Most team members do not support the decision

It is not possible to say anything from the information provided

https://www.pm-tricks.com/QuizHistory/review/4581 36/37
7/23/2019 PM-Tricks | Dashboard

The closed fist indicates frustration of some of the team members


with the project

Most team members support the decision

Explanation
( fist to five). In this technique, the project manager asks the team to show their level of support
for a decision by holding up a closed fist (indicating no support) up to five fingers (indicating full
support). If a team member holds up fewer than three fingers, the team member is given the
opportunity to discuss any objections with the team. The project manager continues the fist-of-
five process until the team achieves consensus (everyone holds up three or more fingers) or
agrees to move on to the next decision.

https://www.pm-tricks.com/QuizHistory/review/4581 37/37