Professional Documents
Culture Documents
Pore Pressure Developmentinthe Coreof Earth Dams During Simultaneous Constructionand Impounding
Pore Pressure Developmentinthe Coreof Earth Dams During Simultaneous Constructionand Impounding
net/publication/294322213
CITATIONS READS
4 1,896
2 authors, including:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Evaluation of elasto-plastic settlement of strip footing on fine gasoil-contaminated soils subjected to cyclic loading View project
Experimental Studies on Footing Depth Effects on Rocking Isolation of Foundation View project
All content following this page was uploaded by Seyed Majdeddin Mir Mohammad Hosseini on 21 December 2018.
R. Ahmadi Fard
M.Sc. in Soil Mech. & Found. Eng., Amirkabir Univ. of Technology
ABSTRACT
In some large and particular water supply projects, the optimum utilization of the resources and
materials often causes the project in some parts goes under service before construction is completed.
This is usually very common in large dams, to start impounding while the construction of the dam is
in progress. Although this will increase the benefit ratio of the project, and make the faster utilization
of the project possible, which is of great importance, however, the adverse effect of such action on
the safety of the project in some cases should not be neglected.
In large earth dams the pore pressure within the clay core will appear in some stages of filling. After
that stage, it starts developing due to increasing the height of the dam. Usually large pore pressure
will develop within the core, when more than half of the dam height is constructed. Due to
consolidation process, it normally takes a long time the developed pore pressure dissipates. If
impounding the dam parallel to the construction process at this stage is done, the excess build up of
the pore pressure within the core may occur due to the head of the water in the reservoir and seeping
the water in the dam. This in some condition may lead to excess pore pressure in the core, resulting
in hydraulic fracturing of the dam.
In this paper, the influence of the impounding of the earth dams on the pore pressure development
within the core, while the construction is under progress, is presented. A special and home developed
computer software (CA2), has been used to model and analyze the earth dam to determine the pore
pressure developing due to both impounding and constructing the dam at the same time. In order to
calibrate the numerical model, the same geometric and geotechnical characteristics of the Karkheh
large embankment dam, recently constructed in Iran, have been taken into account. Since this dam
was subjected to the same condition (simultaneous construction and impounding), the analytical
results, of the present study have been compared with instrumentation data of the dam, and some
important conclusions have been made accordingly.
Keywords: Impounding, Instrumentation, Pore pressure, Construction, Embankment dam, Clay
core, Seepage, Consolidation.
INTRODUCTION
Nowadays, water supply is one of the most important problems in many societies. The limitation of water resources
in the world has caused to implement different methods to get maximum efficiency from the existing and new
water supply projects. Large dams are usually designed and build to control the surface water for different
purposes, mainly water supply. However, it takes a long time to construct and complete all parts of such dams.
The time may be doubled if some financial and construction problems happen during constructing the project.
If utilization of such project in a short period is applicable, it may be of great help. What has to be taken into
account in this extent are:
The possibility of utility from part or parts of the project.
The likely undesirable loading conditions to the project.
The first item can be easily evaluated based on the present level of filling, the induced reservoir volume, the
hydrological system of the upstream region, and the rate of construction operation of the dam. considering these
factors, the impounding can be controlled in a way that always a safe distance between the level of the filling and
reservoir remains. But, the second item needs a special study to be done to investigate the influence of impounding
on the dam behavior while the overburden is continuously increasing due to continuation of the filling of the dam.
In embankment dams the progress of filling, after some stages, will cause induction and development of
considerable pore pressure within the core of the dam. If prior to completing the construction and relative
dissipation of the pore pressure, the impounding starts, the increasing of water level in the reservoir may double
the pore pressure in the core, due to seeping the water within the dam. As a results, it may lead to excess pore
pressure in the core ending to hydraulic fracturing of the dam. In this respect a special study has been carried out
to investigate the effect of simultaneous impounding and construction of an embankment dam, the detail of which
is given in the following sections. Since the same process was applied to Karkheh Embankment Dam, the largest
storage dam recently constructed in the south-western part of Iran, the specification of this dam has been used in
this study. Also the instrumentation records of the Karkheh Dam have been used to verify the results of this study.
In the next section the specifications of the selected embankment dam (Karkheh) are described.
The shells of the dam consist of sand and gravel taken from alluvial deposits and from necessary excavations of
conglomerates. The outer slopes of the dam are made of 1V:2.25H and 1V:2.5H upstream and downstream shells
respectively. The filters act to protect the core from erosion to drain seepage water and to make a transition
between the core and the shell. The core slopes 1V:0.25H both sides with the exception of the left abutment
where it slopes 1V:0.3H between St. 1+025 and 1+145.
Figure 1. A Typical cross-section of the Karkheh Earth Dam with the ground profile and position of
the installed instruments
A plinth of lean concrete is designed to be placed between the core and foundation. The thickness is varying
between 0.3 and 0.5 m. along the dam length. The function of the plinth is to exclude any erosion of fines from
the core into the voids and joints of the foundation. A cut-off wall plastic concrete has been designed to control
seepage in the foundation. The wall intersects the upper layers of conglomerate and penetrates into the one of the
near horizontal mudstone layers. Exception may be at sections where the bottom of the cut-off wall is stepped to
reach the next lower mudstone.
An inspection gallery is incorporated in the design between St.0+950 and 2+160 (the valley section of the dam).
It is located some 7.5 m. downstream of the cut-off wall and has three accesses, at its ends and St.1+425. The
gallery is dewatered by two pumping stations and via the middle access. It covers the diversion culvert below
this structure. The inner clearance of the gallery is 3 m. in height and 2.2 m. in width. Such dimensions are
sufficient to work inside with drill rigs in case of necessity. A typical cross-section of the Karkheh dam with the
positions of installed instruments and mudstone layers in the dam foundation is shown in figure(1).
The types of different instruments used in the Karkheh dam are as follows:
Rock Piezometers (RP): for electrical monitoring of the pore pressures in the dam foundation.
Electrical Piezometers (EP): for electrical monitoring of the pore pressures in the dam body.
Stand Pipe Piezometers (SP): for manual monitoring of the pore pressures in the dam foundation and
body (often as the double check devices).
Pressure Cells (PC): for electrical monitoring of the total earth pressures in the dam body.
Inclinometers (I): for electrical monitoring of the lateral displacements in tow horizontal directions.
Settlement Recorder Plates: for measuring the vertical displacement of the dam body at different levels.
There are totally some 929 different instruments used in the Karkheh dam, the distributions of which are as
follows:
The distribution of the above instruments in dam different cross-sections are given in Table 1.
Total no. Total no. Total no. Total no. Total no.
1-1 1 20 8 2 6
2-2 1 20 10 7 8
3-3 1 30 11 6 10
4-4 3 75 10 4 21
5-5 4 75 10 5 27
6-6 4 40 11 5 27
7-7 4 65 8 2 25
8-8 3 30 10 4 19
9-9 3 65 11 5 19
10-10 2 30 11 4 15
11-11 0 20 6 0 4
12-12 0 10 4 0 2
13-13 0 20 8 2 6
14-14 0 10 6 2 2
15-15 0 0 2 2 0
16-16 0 0 2 4 0
17-17 0 0 0 4 0
18-18 0 0 0 2 0
19-19 0 0 0 2 0
20-20 0 0 0 2 0
21-21 0 0 0 2 0
22-22 0 0 2 2 0
23-23 0 0 2 0 0
A home-developed computer package (CA2) has been used to analyze the dam, as well as the
field data collected from the largest embankment dam (Karkheh) recently built in
southwestern region of Iran. According to the obtained results, the simultaneous impounding
and construction does not have any effect on the pore pressure developed at the central zone
of the core due to overburden, and it will only increase the pore pressure in the upstream side
of the core, where the pore pressure is always small due to influence of the transition filter
zone. The amount of increment is not such a value to cause any problem for the core and is
always less than the piezometric level in the dam reservoir.
REFERENCES
1. Mirghasemi, A.A., Tarkeshdooz, N., & Dadgostania, S. “Pore pressure monitoring within foundation and
impervious zone of Karkheh Dam during construction”, Proc. of 20th Int. Conf. on Large Dams, ICOLD,
Volume 3, PP.259-274, Sept.2000, Beijing-China
2. Institute of water conservancy & hydraulic power research., “Static and dynamic property of sandy gravel
and mudstone material for Karkheh project”, Technical report, Earthquake Dept.,. August 1994, Beijing-
China.
3. IIEES of Iran ,“Results of cyclic triaxial and resonant column tests on core material and mudstone of
Karkheh Dam”, Technical report, Oct.1995, Tehran-Iran.
4. The Housing & Building research center of Iran (HBRC) ,“Performing Dynamic tests on the soil materials
of Karkheh Dam”, Final report, Oct. 1996, Tehran-Iran.
5. Mahab Ghods Consulting Eng ,“Evaluation of instrumentation records of the dam body and foundation
of Karkheh (after impounding), June 2000, Tehran-Iran.
6. Mahab Ghods Consulting Eng. ,“The report of instrumentation performance of Karkheh Dam during
years of 1998 to 2001, Technical report, Oct.2001, Tehran-Iran.
7. Mir Mohammad Hosseini, S.M., & Tarkeshdooz, N.,”A Comparison between predicted and instrumented
deformations of Karkheh Embankment Dam”, Proc. of 20th Int. Conf. on Large Dams, ICOLD, Volume
3, PP.275-288, Sept.2000, China-China.
8. Niroomand, H.,” The evaluation of Karkheh behavior during construction according to instrumentation
records”, MSc. thesis submitted in the Technical Faculty of Tehran University, Jan.2000.
9. Ahmadifard, R.,” Pore pressure evaluation during simultaneous construction and impounding of earth
dam and estimation of critical impounding rate”, MSc. thesis submitted in the Department of Civil
Engineering , Amirkabir University of Technology , Jan.2002.
© 2002 ejge