Professional Documents
Culture Documents
Article
Failure Analysis and Treatments of Tunnel Entrance Collapse
Due to Sustained Rainfall: A Case Study
Long-Long Chen 1 , Zhi-Feng Wang 1,2, * and Ya-Qiong Wang 1,2
Abstract: Rainfall is a crucial issue affecting the entrance slope stability of mountain tunnels, as
it decreases the shearing strength of soil and reduces the stability of tunnel entrance. This paper
presents a case history of the collapse failure of a tunnel entrance in Yunnan Province under rainfall
conditions, in which the failure mechanism and potential factors and treatment measures were
discussed by field investigation, theoretical analysis, and in-situ monitoring. The analysis results
show that the decrease of soil shear strength was mainly attributed to the decline of matric suction
value of soil caused by the increase of soil water content. The decrease of the soil shear strength
reduced the sliding resistance of the entrance slope and then triggered the collapse. Based on the
results, three treatment measures to prevent a secondary tunnel entrance collapse due to rainfall
are adopted, including anti-slide pile, grouting, and slope reinforcement. Combined with the field
monitoring data, the effects of treatment measures were investigated. Lessons in this case study
facilitate prevention and treatment of tunnel entrance constructions under rainfall conditions.
method can be applied to obtain the risk level of tunnel collapse occurrence [16,17]. Based
on the functional mutation theory and related damage criterion, the tunnel damage criterion
and collapse prediction model can be derived [18–20]. In addition, collapse mechanism
studies based on indoor model tests and numerical simulations can study and understand
the tunnel collapse mechanism and evolutionary process [21–23], and then make predictions
for collapse. However, the anomalous features of the surrounding rock or tunnel structure
that appear before the collapse of the tunnel entrance, such as longitudinal cracks in the
initial support, localized collapse of the excavation face, and slope spalling, are aspects that
are easily ignored in collapse prediction studies [24]. Moreover, these anomalous features
from the construction site can directly present the stability state of the tunnel and the
surrounding rock. They are of high value for judging the stability of tunnels and predicting
tunnel collapse [25,26]. So far, there are almost no studies and summaries on the anomalous
characteristics before the occurrence of construction collapse in the tunnel entrance section
under the rainfall action [27].
The mechanism of rainfall−induced tunnel collapse is also very complex. However, a
large number of studies on the analysis of tunnel collapse mechanisms have shown that
low strength of surrounding rock, the softening effect of water, and the synergistic effect
between geological formations are the main causes of tunnel collapse [28–30]. The collapse
of the shallowly buried section of the tunnel entrance is often sudden destabilization
damage caused by accumulated deformation of surrounding rock [31–33]. Therefore,
timely follow−up of the primary support and improvement of the bearing capacity of the
support are very important to circumvent collapse [34,35]. Research shows that the collapse
damage of the tunnel opening section is caused by the combination of the destabilization
of the palm face and the destabilization of the loose rock body in the upper part of the
tunnel [36,37]. The erosion and softening of the surrounding rock by the seepage action of
surface water causes a decrease in the strength and an increase in the self−weight of the
rock, which is the main cause of the instability of the surrounding rock [38,39].
After analyzing the specific causes of tunnel collapse, it is necessary to select a rea-
sonable and effective collapse treatment method to prevent the occurrence of secondary
collapse in a targeted manner [40]. The existing tunnel collapse treatment methods mainly
include: grouting and anchoring method, large pipe shed grouting and advanced support,
and collapse pit grouting method [41–43]. The main mechanism of these methods is to
improve the integrity and strength of loose or weak surrounding rocks and reduce the
deformation of surrounding rocks to prevent collapse, and the treatment effect has been
verified in a large number of engineering applications [44]. In addition, methods such
as changing the excavation method and improving the strength of the initial support are
often used in the treatment of collapse [45,46]. However, the location of the tunnel en-
trance is special, and the treatment of preventing collapse should not only improve the
strength and stability of the slope, but also prevent the seepage erosion of the slope by
continuous precipitation.
In this paper, a tunnel entrance collapse accident was analyzed based on collapse
observation, monitoring, and theoretical analysis, which aims at exploring the mechanism
of collapse under the rainfall condition. Besides, the damage characteristics before large-
scale collapse and treatment measures were summarized and analyzed. This research can
provide a reliable reference for the prevention and control of construction collapse at tunnel
entrance section during continuous rainfall.
2. Project Background
2.1. Tunnel Location
The Fada tunnel in this case study is located in the northeast of Yunnan Province in
China, as shown in Figure 1. The tunnel is a part of the Yibin−Zhaotong highway project
with a design speed of 80 km/h. The construction of this project began on 30 October 2017.
The left bound tunnel is from stake K161 + 739 to K160 + 983, with a total length of 756 m.
It connects the Heping Bridge and the Zhafang Tunnel, and the Haizi River is located
Water 2022, 14, x FOR PEER REVIEW 3 of 18
Figure 2.
Figure 2. Geological conditions.
conditions. (a) Strata at the collapsed site; (b) measured soil parameter profiles.
profiles.
According
According to to the
the geological
geological survey,
survey, thethe silty
silty clay
clay (S1),
(S1), soil
soil aggregate
aggregate (S2),
(S2), and
and mass
mass
rock
Figure and
rock2.and soil (M)
Geological all have
soil (M)conditions. a high rate
(a) Strata
all have a high of water
rate ofatwater content,
the collapsed
content, site;up to
up to(b) 40%. The
measured
40%. porosity of each
soil parameter
The porosity of each profiles.
soil
soil
layerlayer is also
is also high.
high. AsAs thethe sandstone
sandstone atatthis
thislocation
locationisisheavily
heavily weathered,
weathered, the
the uniaxial
uniaxial
compressive
Accordingstrength is less thansurvey,
to the geological 3 MPa. the The silty
mineral
claycomposition of the silty(S2),
(S1), soil aggregate clayand
was mass
rock and soil (M) all have a high rate of water content, up to 40%. The porosity of each soil
layer is also high. As the sandstone at this location is heavily weathered, the uniaxial
Water 2022, 14, x FOR PEER REVIEW 4 of 18
2.3. Precipitation
2.3. Precipitation
The climate
The climate of
of Zhaotong
Zhaotong City, where the
City, where the tunnel
tunnel isis located,
located, isis subtropical
subtropical monsoonal,
monsoonal,
with the southeast monsoon from the Pacific Ocean and the
with the southeast monsoon from the Pacific Ocean and the southwest monsoon southwest monsoon fromfrom the
the
Indian Ocean bringing large amounts of rainfall in summer, with an average
Indian Ocean bringing large amounts of rainfall in summer, with an average annual rainfall annual rain-
fall1110
of of 1110
mm. mm. Rainfall
Rainfall throughout
throughout the yeartheisyear
mainlyis mainly concentrated
concentrated betweenbetween
May andMay and
October,
October, accounting
accounting for 65.6–91.5%
for 65.6–91.5% of annual
of the total the totalrainfall.
annual Therainfall. The seasonal
uneven uneven seasonal dis-
distribution
tribution
of rainfallofresults
rainfall
inresults in frequent
frequent geological geological
hazards such hazards such as landslides
as landslides and debrisandflow
debris
in
flowmountainous
the in the mountainous
areas ofareas of the region
the region in rainy in season.
rainy season.
Figure Figure 3 shows
3 shows the character-
the characteristics
istics
of theofdistribution
the distribution of rainfall
of rainfall in 2018.
in 2018. It can
It can bebe seen
seen fromFigure
from Figure3a 3athat
thatthe
the maximum
maximum
monthly rainfall was 242.5 mm in August, and the rainfall was mainly concentrated from
June to September.
September. The distribution of monthly rainfall from June to September in Yunnan Yunnan
Province where the tunnel is located is shown in Figure 3b. It can be seen from the figure
Yunnan Province
that most areas of Yunnan Province have
have abundant
abundant rainfall
rainfall from
from June
June toto September.
September. In
addition, due to the topographic relief In this region, it is not conducive to the excavation
of the mountain tunnel entrance section section in in summer.
summer.
Figure 3. 3.
Figure Rainfall
Rainfall description
description in 2018: (a) in 2018:rainfall
monthly (a) of monthly rainfall
Zhaotong City of Zhaotong City
(https://www.qweather.com/
(https://www.qweather.com/historical/zhaotong-101291001.html, accessed on
historical/zhaotong-101291001.html, accessed on 5 June 2022); (b) rainfall distribution 5 June 2022); Province
in Yunnan (b) rain-
fall distribution in Yunnan Province (http://www.geodata.cn,
(http://www.geodata.cn, accessed on 5 June 2022). accessed on 5 June 2022).
Figure 4. Photographs of the tunnel: (a) before collapse; (b) after collapse.
Figure 5. Phenomena before collapse: (a) local collapse of tunnel face; (b) lining cracking; (c) shot-
crete spalling.
FigureFigure
5. Phenomena
5. Phenomenabefore collapse:
before collapse: (a)collapse
(a) local local collapse of (b)
of tunnel face; tunnel face; (b)
lining cracking; (c)lining
shotcretecracking;
spalling. (c) sh
crete spalling.
3.2. Collapse Failure Mechanism Analysis
3.2. Collapse Failure Mechanism Analysis
The soil
The soil of
of the
the tunnel
tunnel front
front slope
slope isis mainly
mainly silty
silty clay.
clay. There
There are
are many
many factors
factors that
that
3.2. Collapse
affect Failure
the shear Mechanism
strength of Analysis
silty clay, such as the mineral composition, water content, and
affect the shear strength of silty clay, such as the mineral composition, water content, and
density,
The among
soilamong
density, of the which
tunnel
which the water content
frontcontent
the water slopehas has the most
is mainly obvious
silty clay.
the most obvious effect on
effectTherethe shear
on the are strength
shearmany
th factors
strength
parameters of
parameters of soil.
soil. Moreover,
Moreover, the the shear
shear strength
strength determines
determines thethe stability
stability of
of the
the soil
soil mass.
mass.
affect the shear strength of silty clay, such as the mineral composition, water content, a
Therefore, rainfall is the main cause of the collapse. Through the analysis of the abnormal
density, among which the water content has the most obvious effect on the shear streng
characteristics of the tunnel structure observed on site before the collapse, the main failure
parameters of soil.
mechanism of theMoreover, the shear
accident induced strength
by rainfall can determines the stability
be obtained. Firstly, of the soil ma
the excavation
Water 2022, 14, 2486 6 of 17
of the tunnel caused unloading of the entrance slope, changing the original equilibrium
conditions of the slope. Further, unloading caused slight deformation of the slope, resulting
in cracks in the shotcrete of the tunnel slope protection. During the continuous rainfall, the
surface water continuously scoured the entrance slope, causing the shotcrete cracks of slope
protection to expand. As a result, the water content of slope soil was increasing. As the
water content of soil increased, the cohesion of soil decreased [47]. Thus, the shear strength
of the soil decreased, and the sliding resistance of the slope decreased. At the same time,
due to the infiltration of surface water into the slope, the weight of the slope soil increased
and the sliding force of the slope increased. During the continuous infiltration of surface
water, the shear strength of the clay on the excavation face of the tunnel decreased due
to the continuous increased of water content, and local collapse occurred. The abnormal
phenomena such as longitudinal cracks of lining observed before the large-scale collapse
intuitively show that the stress state of the primary support was changing. Finally, when
the strength of the primary support structure of the tunnel was insufficient, excessive
deformation occurred under the gravity of the upper soil mass, the stress balance was
broken, and the entrance slope of the tunnel also collapse.
Relevant studies show that the mechanism of the decrease of soil shear strength caused
by the increase of water content can be explained by the change of matrix suction between
soil particles. The water content directly affects the matrix suction between soil particles.
The smaller the water content of clay, the greater the matrix suction and cohesion between
soil particles. On the contrary, the greater the water content of clay, the smaller the cohesion.
Therefore, the matrix suction decreases with the increase of soil water content, which is an
important factor leading to the decline of soil shear strength [48,49]. When the soil changes
from unsaturated state to saturated state, the matrix suction between soil particles will
gradually decrease to 0. A large number of landslide accidents were induced by the change
of soil moisture content, so the matrix suction is closely related to the stability of soil [50].
As shown in Figure 6a, before the rainfall, the soil on the entrance slope of the tunnel
was in an unsaturated state with low water content, and all meniscus between soil particles
were independent of each other. At this time, the matrix suction between soil particles
caused the stress Pi (i = 1, 2, 3, . . . , 6) that cannot be transferred between soil particles,
which inhibited the sliding of soil particles. Because the plastic deformation of soil is
interpreted as the sliding between soil particles, the matrix suction resisted the plastic
deformation of soil when the soil water content was low. At this water content, the entrance
slope was in a good state of stability. When the rainfall started, the water content of the
soil mass of the entrance slope gradually increased from the tunnel to the surface [51].
The matrix suction between soil particles also decreased gradually from the tunnel to the
surface. Therefore, the shear strength of soil presented the change law of decreasing from
the tunnel to the surface. At this time, the soil can be roughly divided into saturated soil
and unsaturated soil along the vertical direction. Due to the increasing water content of
the unsaturated soil, the unsaturated state between soil particles changes, as shown in
Figure 6b. The meniscus in the soil pores was gradually connected. The pressure caused by
matrix suction can be transmitted between soil particles, which can cause the compression
of soil and reduce the stability of entrance. When the soil mass in a certain depth below the
surface of the tunnel entrance slope reached the saturated state, the matrix suction of the
soil mass dropped to 0, and this part of the soil mass was prone to sliding.
With the continuous rainfall, the surface water continuously seeped into the entrance
slope, resulting in the continuous increase of the water content of the whole tunnel entrance
slope, including the soil around the tunnel structure. Therefore, the water content of clay
on the tunnel face was also rising, resulting in the decrease of soil shear strength. This
then, resulted in local small−scale collapse on the tunnel face, as shown in Figure 5a. The
stress state of tunnel support structure was also changed due to rainfall and excavation,
which caused abnormal deformation of tunnel primary support, longitudinal cracks. When
the surrounding rock pressure exceeded the bearing capacity of the primary support, the
Water 2022, 14, 2486 7 of 17
Figure The
Figure6. 6. relationships
The between
relationships rate of water
between ratecontent andcontent
of water matric suction of silty clay
and matric [50]. (a)
suction of low
silty clay [
water content; (b) high water content.
low water content; (b) high water content.
3.3. Factors Analysis
Withwere
There the many
continuous rainfall,
factors that led tothe
the surface water continuously
tunnel collapse, seeped
which can be divided into the e
into
intrinsic and extrinsic
slope, resulting in factors. The intrinsic
the continuous factors were
increase poor
of the geological
water conditions
content of theand whole tu
structural defects of the tunnel, while the extrinsic factors were rainfall and
trance slope, including the soil around the tunnel structure. Therefore, the water construction
disturbances. A large number of tunnel construction collapse accidents occur during the
of clay
rainy on the
season, andtunnel facetime,
at the same wastunnels
also rising, resulting
with collapse in theduring
accidents decrease of often
rainfall soil shear s
Thispoor
have then, resulted
geological in local such
conditions, small−scale
as severe collapse
weatheringon of the tunnel face,rock,
the surrounding as shown
loose in Fi
The stress
internal stateand
structure, of tunnel supportofstructure
easy destruction the internalwas also when
structure changed duetotowater.
exposed rainfall and
tion, which caused abnormal deformation of tunnel primary support, longitudina
3.3.1. Rainfall
When the surrounding rock pressure exceeded the bearing capacity of the prima
The collapse area belongs to the subtropical monsoon climate, with heavy and concen-
port, rainfall
trated the tunnel collapsed
in summer. instantaneously.
Continuous rainfall caused At the same
the entrance time,
slope to bethe entrance slope
continuously
its balance
washed and slid.
by surface water, and the water content of the soil rose, leading to hydrogenic
softening, and the shear strength of the soil decreased. At the same time, the weight of the
soil
3.3.increased
Factors due to the increase of water content, which led to the continuous adjustment
Analysis
of the forces acting on the tunnel lining structure, and the stability of the soil decreased
greatly,There
whichwere
was themany
main factors that
reason for the led to collapse.
tunnel the tunnel collapse,
In the whichsection
shallow buried can be divid
intrinsic
of andthe
the tunnel, extrinsic factors.
infiltration Thewater
of surface intrinsic factors
into the werethe
soil made poorwatergeological
content of conditi
the soil near the tunnel lining increase quickly, and the soil reached
structural defects of the tunnel, while the extrinsic factors were rainfall saturation when theand cons
precipitation was large. At this time, the pressure acting on the primary support of the
disturbances. A large number of tunnel construction collapse accidents occur du
tunnel was not only the gravity of the soil, but also the hydrostatic pressure and seepage
rainy resulting
forces, season, inand at the same
a significant time,
increase tunnels
in the load onwith collapse
the primary accidents
support during
compared to rainf
have
that poor
before thegeological conditions,
rainfall. In the such strength
primary support as severe weathering
weak position, theofprimary
the surrounding
support roc
cracking occured, especially the longitudinal cracks were the most harmful
internal structure, and easy destruction of the internal structure when exposed to [52]. As the soil
outside the liner approached saturation, water in the soil leaked into the tunnel along the
liner fissures (Figure 5b) and caused erosion of the shotcrete for the primary support. At
3.3.1. Rainfall
the location of the tunnel face, if the strength of the shotcrete enclosed on the soil surface of
Theface
the tunnel collapse area belongs
was insufficient, to strength
the shear the subtropical monsoonwith
of the soil decreased climate, withofheavy a
the increase
water
centrated rainfall in summer. Continuous rainfall caused the entrancewater
content, which led to a local collapse of the tunnel face (Figure 5a). As surface slope to be
uously washed by surface water, and the water content of the soil rose, leading to
genic softening, and the shear strength of the soil decreased. At the same time, the
of the soil increased due to the increase of water content, which led to the con
adjustment of the forces acting on the tunnel lining structure, and the stability of
Water 2022, 14, 2486 8 of 17
continued to seep underground, the pressure on the lining structures increased, and when
its bearing capacity was exceeded, the tunnel collapsed instantaneously.
Figure 7.
Figure 7. Layout
Layout of
of treatment
treatment measures.
measures. (a)
(a) Vertical
Verticalsection;
section;(b)
(b)vertical
verticalview.
view.
4.1.
4.1. Anti −Slide Pile
Anti−Slide Pile
The
The foundation
foundationunder underthethetunnel
tunnelopening
opening section mainly
section includes
mainly includespelitic siltstone
pelitic and
siltstone
silty mudstone. They were severely weathered, with a large number
and silty mudstone. They were severely weathered, with a large number of fissures, bed- of fissures, bedded
crushing, and low
ded crushing, androck
low strength. In order
rock strength. to prevent
In order the foundation
to prevent from the
the foundation fromtunnel from
the tunnel
sliding underunder
from sliding the rainfall and to
the rainfall andensure the stability
to ensure of theoftunnel
the stability entrance
the tunnel section,
entrance the
section,
foundation of the tunnel was reinforced by anti − slide piles. The anti − slide
the foundation of the tunnel was reinforced by anti−slide piles. The anti−slide piles were piles were set at
the arch foot on both sides of the tunnel entrance, with a pile length of 8 m
set at the arch foot on both sides of the tunnel entrance, with a pile length of 8 m and a and a rectangular
cross −section
rectangular of 2 × 2 m. Pre
cross−section of 2−×excavated pile holes were
2 m. Pre−excavated pile excavated
holes wereon both sides
excavated onatboth
the
arch footing position and the reinforcement cages were placed, then the
sides at the arch footing position and the reinforcement cages were placed, then the piles piles were poured
using C20 concrete,
were poured as shown
using C20 in Figure
concrete, as shown8. Finally, connecting
in Figure 8. Finally,bars were tiedbars
connecting between
were the
tied
Water 2022, 14, x FOR PEER REVIEWtwo anti−slide piles and concrete was poured to form a concrete beam to connect the 10 two
of 18
between the two anti−slide piles and concrete was poured to form a concrete beam to
anti −slide
connect thepiles
twoas a whole and
anti−slide pilesfurther increase
as a whole andthe stability
further of thethe
increase foundation.
stability of the foun-
dation.
Figure 8.
Figure 8. Anti
Anti−slide
−slide pile.
pile.
4.2. Grouting
Grouting reinforcement is divided into two parts: surface grouting and grouting in
tunnel [60]. Surface grouting reinforcement can not only enhance the integrity of the up-
per strata of the tunnel, but also form a curtain for cutting off water to stop the downward
seepage of surface water and fundamentally cure the problem of slope erosion by surface
Figure 8. Anti−slide pile.
Water 2022, 14, 2486 10 of 17
4.2. Grouting
Grouting reinforcement is divided into two parts: surface grouting and grouting in
4.2. Grouting
tunnel [60]. Surface grouting reinforcement can not only enhance the integrity of the up-
Grouting
per strata of the reinforcement
tunnel, but also is divided into twofor
form a curtain parts: surface
cutting off grouting
water to and
stopgrouting in
the downward
tunnel [60]. Surface grouting reinforcement can not only enhance the integrity
seepage of surface water and fundamentally cure the problem of slope erosion by surface of the upper
strata of the tunnel, but also form a curtain for cutting off water to stop the downward
water. The surface reinforcement grouting holes are shown in Figure 9a. The grouting
seepage of surface water and fundamentally cure the problem of slope erosion by surface
pipe is made
water. of steel
The surface pipe with agrouting
reinforcement diameter of are
holes Φ50shown
mm in and pipe9a.
Figure thickness of 5 pipe
The grouting mm. The
front part of
is made of the
steelgrouting
pipe withpipe was drilled
a diameter of Φ50with
mm8andmmpipediameter slurry
thickness of 5 outlets
mm. The with
fronta spac-
ingpart
of 100 mm.
of the Therepipe
grouting waswasno slurry
drilled outlet
with 8 at
mm 500 mm atslurry
diameter the end of the
outlets grouting
with a spacingpipe.
of The
depth of the
100 mm. surface
There was nogrouting hole at
slurry outlet was5005mmm. at
The
theplane
end oflayout of thepipe.
the grouting grouting hole was
The depth
of the surface
arranged accordinggrouting hole
to 1.5 wasm.
× 1.5 5 m.
TheThe planefor
slurry layout of the
surface groutingused
grouting hole ordinary
was arrangedPortland
according to 1.5 × 1.5 m. The slurry for surface grouting used ordinary
cement slurry with a water: cement ratio of 1:1, and the initial grouting pressure ranged Portland cement
slurry
from 0.5 with
to 1.0a MPa
water:andcement ratio of 1:1, and
the termination the initial
pressure grouting
ranged frompressure
1.5 to 2.0ranged
MPa.from
Advance
0.5 to 1.0 MPa and the termination pressure ranged from 1.5 to 2.0 MPa. Advance small
small conduits were used for grouting in the tunnel, with a diameter of 30 mm and a
conduits were used for grouting in the tunnel, with a diameter of 30 mm and a length of
length of 5 m9b).
5 m (Figure (Figure 9b). Thepipes
The grouting grouting pipes were
were spaced 500 mm spaced
along500 mm along
the tunnel the tunnel cir-
circumferential
cumferential
direction withdirection withinsertion
an external an external
angleinsertion angleand
of 15 degrees, of 15
thedegrees, andlap
longitudinal thelength
longitudinal
of
laptwo
length of two adjacent rows of grouting pipes was 1 m. The grouting
adjacent rows of grouting pipes was 1 m. The grouting slurry was ordinary cement slurry was ordi-
nary cement
slurry, and theslurry,
cementandwasthe cement
PO42.5 was cement.
Portland PO42.5WhenPortland cement.
the hole When the
was grouted, theinitial
hole was
pressure
grouted, was
the 0.2 MPa
initial and the
pressure termination
was 0.2 MPa pressure
and the was 0.6 MPa. pressure was 0.6 MPa.
termination
Figure 9. Photographs
Figure 9. Photographsof
ofgrouting. (a) Surface
grouting. (a) Surfacegrouting;
grouting;(b)(b) grouting
grouting in tunnel.
in tunnel.
Figure
Figure 10.
10. Vault settlement before
Vault settlement before collapse:
collapse: (a)
(a) K161
K161 +
+ 746
746 section;
section; (b)
(b) K161
K161 ++ 743
743 section.
section.
Figure
Figure 11.11. Layout
Layout and and photographs
photographs of test elements
of test elements at ZK161 + at ZK161
729. + 729.
(a) (b)
Figure12.
Figure 12.Displacement
Displacementmonitoring
monitoringcurve
curve
ofof primary
primary (a)(a)
lining.
lining. variation
variation curve
curve of vault
of vault settle-
settlement;
ment;
(b) (b) variation
variation curve of convergence
curve of convergence deformation.deformation.
The
Thedisplacement
displacementofofsoil
soilmass
massinside
insidethe
theentrance
entranceslope
slopecancanbebeobtained
obtainedbybyusing usingthe
the
inclinometer,
inclinometer,andandthen
thenthe
thepossible
possiblesliding
slidingsurface
surfaceand
anddisplacement
displacementofofthe theslope
slopecancanbebe
judged.
judged.Figure
Figure1313shows
showsthethedistribution
distributionofofdisplacement
displacementsize sizeofofthe
thesoil
soillayer
layeratatthe
thefour
four
inclinometer tubes locations when the monitoring data were stable. At this
inclinometer tubes locations when the monitoring data were stable. At this time, the tun-time, the tunnel
was
nelexcavated to ZK161
was excavated + 712 +position.
to ZK161 The displacement
712 position. valuesvalues
The displacement of the of
soil
thelayer
soilat the at
layer four
the
monitoring locations were all within 4.46 mm, and the soil layer of the entrance
four monitoring locations were all within 4.46 mm, and the soil layer of the entrance slope slope did
not
didproduce too much
not produce displacement.
too much displacement.The monitoring resultsresults
The monitoring show show
that the
thatreinforcement
the reinforce-
measures are effective
ment measures for the tunnel
are effective for the entrance collapse.
tunnel entrance collapse.
Figure 14 shows the distribution of steel arch stress and surrounding rock pressure
at the basic stability of the location of the monitoring section ZK161 + 729. Because the
thickness of the upper soil layer of the tunnel at this location was only about 15 m, the steel
arch stress and the surrounding rock pressure were not very large. The maximum value
(a) (b)
Figure 12. Displacement monitoring curve of primary lining. (a) variation curve of vault
Water 2022, 14, 2486 ment; (b) variation curve of convergence deformation. 13 of 17
The displacement of soil mass inside the entrance slope can be obtained by us
of the surrounding rock pressure was 22.3 kPa at the vault, and it shows the distribution
inclinometer, and then the possible sliding surface and displacement of the slope
feature of “large at the top and small at the bottom”. In general, the pressure on the right
judged. Figure
side of the tunnel13wasshows
slightlythe distribution
higher ofthe
than that on displacement sizearch
left side. The steel of the
wassoil
underlayer at t
inclinometer tubes
pressure at the five locations
monitoring when with
positions, the monitoring
a maximum stressdataofwere
5.954 stable.
kN, andAtthethis
size time, t
distribution characteristics were similar to those of the surrounding rock
nel was excavated to ZK161 + 712 position. The displacement values of the soil layepressure. The
steel arch stress and the surrounding rock pressure were within reasonable limits and no
four monitoring locations were all within 4.46 mm, and the soil layer of the entranc
abnormalities occurred, which reflected that the tunnel was in a stable state at this location,
did notdemonstrating
further produce toothat much displacement.were
the countermeasures Theeffective
monitoring results
in improving theshow that
stability of the rei
ment measures are effective for the tunnel entrance collapse.
the tunnel structure and entrance slope of the secondary excavation.
and the size distribution characteristics were similar to those of the surrounding rock pres-
sure. The steel arch stress and the surrounding rock pressure were within reasonable lim-
its and no abnormalities occurred, which reflected that the tunnel was in a stable state at
this location, further demonstrating that the countermeasures were effective in improving
13.Variation
Figure 13.
Figure
the stabilityVariationcurve of horizontal
curve
of the tunnel
displacement
of horizontal
structure
at various at
anddisplacement
entrance slope
depths.
various
of depths. excavation.
the secondary
Figure 14 shows the distribution of steel arch stress and surrounding rock p
at the basic stability of the location of the monitoring section ZK161 + 729. Beca
thickness of the upper soil layer of the tunnel at this location was only about 15
steel arch stress and the surrounding rock pressure were not very large. The ma
value of the surrounding rock pressure was 22.3 kPa at the vault, and it shows the
bution feature of “large at the top and small at the bottom”. In general, the press
the right side of the tunnel was slightly higher than that on the left side. The ste
was under pressure at the five monitoring positions, with a maximum stress of 5.9
There are many other tunnel construction sites in southwest China with geological and
There are many other tunnel construction sites in southwest China with geological
climatic conditions similar to those of the tunnel site in this study. These projects have many
and climatic conditions similar to those of the tunnel site in this study. These projects have
commonalities, such as geological conditions, precipitation, and construction methods.
many commonalities,
Therefore, such as geological
it is of good application conditions,the
value to summarize precipitation,
experience ofand construction
tunnel entrance meth-
ods. Therefore,
section collapse init is of area
this good application
and to achievevalue to prevention
collapse summarizeand theeffective
experience of tunnel en-
treatment
trance
for similar projects by engineering analogy method. After the study of this accident, an treat-
section collapse in this area and to achieve collapse prevention and effective
ment for similar
excavation collapseprojects by engineering
prevention analogy
and treatment processmethod. After
applicable the study
to areas of this
with high accident,
and
concentrated
an excavation seasonal rainfall
collapse and complex
prevention andgeological
treatmentconditions
process in the tunnel to
applicable inlet section
areas with high
is summarized,
and concentrated as shown in Figure
seasonal 15. and complex geological conditions in the tunnel inlet
rainfall
section is summarized, as shown in Figure 15.
many commonalities, such as geological conditions, precipitation, and construction meth-
ods. Therefore, it is of good application value to summarize the experience of tunnel en-
trance section collapse in this area and to achieve collapse prevention and effective treat-
ment for similar projects by engineering analogy method. After the study of this accident,
an excavation collapse prevention and treatment process applicable to areas with high
Water 2022, 14, 2486 14 of 17
and concentrated seasonal rainfall and complex geological conditions in the tunnel inlet
section is summarized, as shown in Figure 15.
Figure15.
Figure 15. Prevention
Prevention and
and treatment
treatmentprocess
processof
oftunnel
tunnelentrance
entrancecollapse
collapseunder
underrainfall
rainfallcondition.
condition.
5.
5. Conclusions
Conclusions
This
This paper
paper analyzed
analyzed the
the failure
failure mechanisms
mechanisms and
and treatment
treatment measures
measures ofof entrance
entrance col-
col-
lapse due to sustained rainfall in a highway tunnel as a case study. Also, the characteristics
lapse due to sustained rainfall in a highway tunnel as a case study. Also, the characteristics
of tunnel before collapse was summed up by field investigation, and the main factors of the
collapse were analyzed. Based on the analysis results, treatment measures for tunnel en-
trance collapse were adopted. Further, the effectiveness of the collapse treatment measures
was verified by field monitoring. The main conclusions can be summarized as follows:
(1) In the process of construction at tunnel entrance, rainfall should be emphasized. It
reduces the shearing strength of the soil and damages the structure of tunnel, which
often causes collapse failures. Other factors including unacceptable construction,
topography, and geology also contribute to tunnel entrance collapse. Particularly,
improving the quality of slope protection is highly recommended.
(2) The basic causes of the collapse were the infiltration of surface water and the increase
of water content of silty clay. The matrix suction decreased with the increase of soil
water content, which led to the decline of soil shear strength.
(3) Field investigation showed that abnormal phenomena appeared before large−scale
tunnel collapse, such as local collapse of tunnel face, primary support cracking, and
shotcrete spalling of slope protection. Timely discovery of abnormal phenomena is of
great significance for the prevention of large−scale tunnel collapse accidents. When
these phenomena occur on the construction site, it is strongly recommended that the
construction personnel evacuate the tunnel immediately.
(4) To prevent a secondary collapse in construction, targeted treatment measures were
implemented at this tunnel, such as anti−slide pipe, grouting, and slope reinforce-
ment. Grouting can prevent the seepage of water in soil and improve the stability of
surrounding rock. After the collapse treatment was completed, the vault settlement of
the monitoring section was only about 24 mm. The countermeasures are effective for
collapse at tunnel entrance under rainfall conditions based on the monitoring results
and can be applied to similar tunnel entrance slope. Lessons learned from this case
provide a reference for the reinforcement of tunnel entrance slope.
Water 2022, 14, 2486 15 of 17
Author Contributions: Writing—manuscript, L.-L.C. and Z.-F.W.; methodology, L.-L.C. and Y.-Q.W.,
data collection, L.-L.C., Y.-Q.W., and Z.-F.W.; case analysis, L.-L.C.; project management, Y.-Q.W. and
Z.-F.W.; funding, Z.-F.W. and Y.-Q.W. All authors have read and agreed to the published version of
the manuscript.
Funding: The authors gratefully acknowledge the financial support by the National Key R&D
Program of China (No. 2021YFB2600404, 2021YFF0501101, 2021YFA0716901 & 2021YFB2601402) and
the National Natural Science Foundation of China (No. 51978059 & 52178310).
Institutional Review Board Statement: Not applicable.
Informed Consent Statement: Not applicable.
Data Availability Statement: The data used to support the findings of this study are available from
the corresponding author upon request.
Conflicts of Interest: The authors declare no conflict of interest.
References
1. Lai, J.; Wang, X.; Qiu, J.; Chen, J.; Hu, Z.; Wang, H. Extreme deformation characteristics and countermeasures for a tunnel in
difficult grounds in southern Shaanxi. Environ. Earth Sci. 2018, 77, 706. [CrossRef]
2. Aberle, J.; Henry, P.Y.; Kleischmann, F.; Navaratnam, C.U.; Vold, M.; Eikenberg, R.; Olsen, N.R.B. Experimental and Numerical
Determination of the Head Loss of a Pressure Driven Flow through an Unlined Rock-Blasted Tunnel. Water 2021, 12, 3492.
[CrossRef]
3. Lai, J.; He, S.; Qiu, J.; Chen, J.; Shi, S.; Wang, L.; Wang, K.; Wang, J. Cause analysis of soft and hard rock tunnel collapse and
information management. Environ. Earth Sci. 2018, 76, 94. [CrossRef]
4. Soga, K.; Laver, R.G.; Li, Z.L. Long-term tunnel behaviour and ground movements after tunnelling in clayey soils. Undergr. Space
2018, 2, 149–167. [CrossRef]
5. Zhang, N.; Zheng, Q.; Elbaz, K.; Xu, Y. Water Inrush Hazards in the Chaoyang Tunnel, Guizhou, China: A Preliminary
Investigation. Water 2020, 12, 1083. [CrossRef]
6. Kim, J.; Kim, C.; Kim, G.; Kim, I.; Abbas, Q.; Lee, J. Probabilistic tunnel collapse risk evaluation model using analytical hierarchy
process (AHP) and Delphi survey technique. Tunn. Undergr. Space Technol. 2022, 120, 104262. [CrossRef]
7. Zheng, X.; Zhang, L.; Wu, S.; Song, K. Study on the Shape of the Aerator of High-Head Discharge Tunnel with Mild Bottom Slope.
Water 2021, 13, 2128. [CrossRef]
8. Farghaly, A.A.; Kontoni, D.P.N. Train induced dynamic response of a pedestrian tunnel under a four-track surface railway for
different soil water contents. Geomech. Eng. 2019, 16, 341–353. [CrossRef]
9. Gattinoni, P.; Consonni, M.; Francani, V.; Leonelli, G.; Lorenzo, C. Tunnelling in landslide areas connected to deep seated
gravitational deformations: An example in Central Alps (northern Italy). Tunn. Undergr. Space Technol. 2019, 93, 103100.
[CrossRef]
10. Xue, Y.; Zhang, S.; Zhou, M.; Zhu, H. Novel SfM-DLT method for metro tunnel 3D reconstruction and visualization. Undergr.
Space 2021, 6, 134–141. [CrossRef]
11. Guo, C.; Guo, Q.; Zhang, T.; Li, W.; Zhu, H.; Yan, Z. Study on real-time heat release rate inversion for dynamic reconstruction and
visualization of tunnel fire scenarios. Tunn. Undergr. Space Technol. 2022, 122, 104333. [CrossRef]
12. Fraldi, M.; Guarracino, F. Analytical solutions for collapse mechanisms in tunnels with arbitrary cross sections. Int. J. Solids Struct.
2010, 47, 216–223. [CrossRef]
13. Sun, W.; Liang, Q.; Qin, S.; Yuan, Y.; Zhang, T. Evaluation of groundwater effects on tunnel engineering in loess. Bull. Eng. Geol.
Environ. 2021, 80, 1947–1962. [CrossRef]
14. Wang, J.; Lin, G.; Xu, G.; Wei, Y.; Li, S.; Tang, X.; He, C. Face stability of EPB shield tunnels in multilayered ground with soft
sand lying on hard rock considering dynamic excavation process: A DEM study. Tunn. Undergr. Space Technol. 2022, 120, 104268.
[CrossRef]
15. Prendes-Gero, M.B.; Lopez-Gayarre, F.; Menendez-Fernandez, C.; Llardent, M.R.A. Forensic analysis of the failure of the
foundations of a tunnel built to channel the course of a river. Eng. Fail. Anal. 2013, 32, 152–166. [CrossRef]
16. Xu, Z.; Cai, N.; Li, X.; Xian, M.; Dong, T. Risk assessment of loess tunnel collapse during construction based on an attribute
recognition model. Bull. Eng. Geol. Environ. 2021, 80, 6205–6220. [CrossRef]
17. Wu, B.; Qiu, W.; Huang, W.; Meng, G.; Huang, J.; Xu, S. Dynamic risk evaluation method for collapse disasters of drill-and-blast
tunnels: A case study. Math. Biosci. Eng. 2021, 19, 309–330. [CrossRef]
18. Han, K.; Ju, J.W.W.; Kong, H.; Wang, M. Functional catastrophe analysis of progressive failures for deep tunnel roof considering
variable dilatancy angle and detaching velocity. Rock Mech. Rock Eng. 2019, 52, 3987–3997. [CrossRef]
19. Zhang, C.; Han, K. Collapsed shape of shallow unlined tunnels based on functional catastrophe theory. Math. Probl. Eng. 2015,
2015, 681257. [CrossRef]
Water 2022, 14, 2486 16 of 17
20. Ma, E.; Lai, J.; Xu, S.; Shi, S.; Zhang, J.; Zhong, Y. Failure analysis and treatments of a loess tunnel being constructed in ground
fissure area. Eng. Fail. Anal. 2022, 134, 106034. [CrossRef]
21. Xu, S.; Lei, H.; Li, C.; Liu, H.; Lai, J.; Liu, T. Model test on mechanical characteristics of shallow tunnel excavation failure in gully
topography. Eng. Fail. Anal. 2020, 119, 104978. [CrossRef]
22. Yu, L.; Zhang, D.; Fang, Q.; Cao, L.; Zhang, Y.; Xu, T. Face stability of shallow tunnelling in sandy soil considering unsupported
length. Tunn. Undergr. Space Technol. 2020, 102, 103445. [CrossRef]
23. Hu, X.; Fu, W.; Wu, S.; Fang, Y.; Wang, J.; He, C. Numerical study on the tunnel stability in granular soil using DEM virtual air
bag model. Acta Geotech. 2021, 16, 3285–3300. [CrossRef]
24. Wu, Y.; Wang, K.; Zhang, L.; Peng, S. Sand-layer collapse treatment: An engineering example from Qingdao Metro subway tunnel.
J. Clean Prod. 2018, 197, 19–24. [CrossRef]
25. Xu, H.; Shao, Z.; Chen, C.; Wang, Z.; Cai, L.; Li, Z.; Huang, C. Characteristics and evolution of tunnel collapse in fully-weathered
coastal red sandstone strata. J. Coast. Res. 2022, 38, 289–301. [CrossRef]
26. Xu, H.; Wang, Z.; Chen, C.; Cai, L.; Li, Z.; Deng, Y.; Xia, Y. Model tests on characteristics and evolution of tunnel collapse in
soil-sand interbedded strata. Chin. J. Geotech. Eng. 2021, 43, 1050–1058. (In Chinese)
27. Wang, Z.; Xie, Y.; Lai, J.; Xie, Y.; Su, X.; Shi, Y.; Guo, C. Designing an innovative support system in loess tunnel. Geomech. Eng.
2021, 24, 253–266. [CrossRef]
28. Senent, S.; Jimenez, R. A tunnel face failure mechanism for layered ground, considering the possibility of partial collapse. Tunn.
Undergr. Space Technol. 2015, 47, 182–192. [CrossRef]
29. Wang, B.; Li, T.; HE, C.; Zhou, Y. Analysis of failure properties and formatting mechanism of soft rock tunnel in meizoseismal
areas. Chin. J. Rock Mech. Eng. 2012, 31, 928–936. (In Chinese)
30. Toulkeridis, T.; Rodriguez, F.; Jimenez, N.A.; Baile, D.S.; Martinez, R.S.; Addison, A.; Freyre, D.C.; Mato, F.; Perez, C.D. Causes
and consequences of the sinkhole at El Trebol of Quito, Ecuador-implications for economic damage and risk assessment. Nat.
Hazards Earth Syst. Sci. 2016, 16, 2031–2041. [CrossRef]
31. Liu, X.; Liu, F.; Song, K. Mechanism analysis of tunnel collapse in a soft-hard interbedded surrounding rock mass: A case study of
the Yangshan Tunnel in China. Eng. Fail. Anal. 2022, 138, 106304. [CrossRef]
32. Wang, Y. Collapse mechanism and preventive measures of mountain tunnel. Chin. J. Rock Mech. Eng. 2012, 30, 2376. (In Chinese)
33. Wang, Z.; Shen, S.; Modoni, G.; Zhou, A. Excess pore water pressure caused by the installation of jet grouting columns in clay.
Comput. Geotech. 2020, 125, 103667. [CrossRef]
34. Jiang, Z.; Duan, S.; Zhao, X. Manipulation of tunnelling in a quantum dot array. J. Phys.-Condes. Matter 2005, 17, 4207–4222.
[CrossRef]
35. Niu, J.; Sun, Y.; Wang, B.; Zhang, K.; Huang, Y.; Huang, S.; Yu, J.; Qiu, L. Grouting Treatment of Water and Mud Inrush in Fully
Weathered Granite Tunnel: A Case Study. Disaster Adv. 2020, 2020, 8838769. [CrossRef]
36. Zhang, T.; Taylor, R.N.; Zheng, G.; Sun, J.; Fan, Q.; Diao, Y.; Zhou, H. Modelling ground movements near a pressurised tunnel
heading in drained granular soil. Comput. Geotech. 2018, 104, 152–166. [CrossRef]
37. Wu, D.; Deng, T.; Zhao, R.; Wang, Y. THM modeling of ground subsidence induced by excavation of subway tunnel. Comput.
Geotech. 2018, 94, 1–11. [CrossRef]
38. Wang, Z.; Cheng, W. Predicting jet-grout column diameter to mitigate the environmental impact using an artificial intelligence
algorithm. Undergr. Space. 2021, 6, 267–280. [CrossRef]
39. Yang, Z.; Wu, S.; Gao, Y.; Jin, A.; Cong, Z. Time and technique of rehabilitation for large deformation of tunnels in jointed rock
masses based on FDM and DEM numerical modeling. Tunn. Undergr. Space Technol. 2018, 81, 669–681. [CrossRef]
40. Yuan, J.; Chen, W.; Tan, X.; Yang, D.; Wang, S. Countermeasures of water and mud inrush disaster in completely weathered
granite tunnels: A case study. Environ. Earth Sci. 2019, 78, 576. [CrossRef]
41. Zhang, N.; Shen, J.; Lin, C.; Arulrajah, A.; Chai, J. Investigation of a large ground collapse and countermeasures during mountain
tunnelling in Hangzhou: A case study. Bull. Eng. Geol. Environ. 2019, 78, 991–1003. [CrossRef]
42. Zheng, G.; Cui, T.; Cheng, X.; Diao, Y.; Zhang, T.; Sun, J.; Ge, L. Study of the collapse mechanism of shield tunnels due to the
failure of segments in sandy ground. Eng. Fail. Anal. 2017, 79, 464–490. [CrossRef]
43. Zheng, H.; Li, P.; Ma, G.; Zhang, Q. Experimental investigation of mechanical characteristics for linings of twins tunnels with
asymmetric cross-section. Tunn. Undergr. Space Technol. 2021, 119, 104209. [CrossRef]
44. Qiu, J.; Wang, X.; Lai, J.; Zhang, Q.; Wang, J. Response characteristics and preventions for seismic subsidence of loess in Northwest
China. Nat. Hazards 2018, 98, 1909–1935. [CrossRef]
45. Wang, Z.; Shen, S.; Modoni, G. Enhancing discharge of spoil to mitigate disturbance induced by horizontal jet grouting in clayey
soil: Theoretical model and application. Comput. Geotech. 2019, 111, 222–228. [CrossRef]
46. Koyama, T.; Nishiyama, S.; Yang, M.; Ohnishi, Y. Modeling the interaction between fluid flow and particle movement with
discontinuous deformation analysis (DDA) method. Int. J. Numer. Anal. Methods Geomech. 2011, 35, 1–20. [CrossRef]
47. Yang, Q.; He, J.; Luan, M. Comparative study on shear strength of unsaturated red clay and expansive soils. Rock Soil Mech. 2003,
24, 13–16. (In Chinese)
48. Shiau, J.; Al-Asadi, F. Revisiting circular tunnel stability using Broms and Bennermarks’ original stability number. Int. J. Geomech.
2021, 21, 06021009. [CrossRef]
Water 2022, 14, 2486 17 of 17
49. Cho, S.E. Stability analysis of unsaturated soil slopes considering water-air flow caused by rainfall infiltration. Eng. Geol. 2016,
211, 184–197. [CrossRef]
50. Lin, H.; Li, G.; Yu, Y.; Lu, H. Influence of matric suction on shear strength behavior of unsaturated soils. Rock Soil Mech. 2007, 28,
1931–1936. (In Chinese)
51. Mahmood, K.; Kim, J.M.; Khan, H.; Safdar, M.; Khan, U. The probabilistic stability analysis of saturated-unsaturated MH and CL
soil slope with rainfall infiltration. KSCE J. Civ. Eng. 2018, 22, 1742–1749. [CrossRef]
52. Lan, W.; Deng, X.; Sutton, M.A. Investigation of crack tunneling in ductile materials. Eng. Fract. Mech. 2010, 77, 2800–2812.
[CrossRef]
53. Stark, T.D.; Jafari, N.H.; Zhindon, J.S.L.; Baghdady, A. Unsaturated and Transient Seepage Analysis of San Luis Dam. J. Geotech.
Geoenviron. Eng. 2017, 14, 04016093. [CrossRef]
54. Zhang, Y.; Pu, S.; Li, R.T.Y.M.; Zhang, J. Microscopic and mechanical properties of undistributed and remoulded red clay from
Guiyang, China. Sci. Rep. 2021, 10, 18003. [CrossRef] [PubMed]
55. Lu, C.; Qin, W.; Zhao, G.; Zhang, Y.; Wang, W. Better-Fitted Probability of Hydraulic Conductivity for a Silty Clay Site and Its
Effects on Solute Transport. Water 2017, 9, 466. [CrossRef]
56. John, D.; Jaye, C.; Robert, L.; Kemp, G.P. Sediment Deposition at the Caernarvon Crevasse during the Great Mississippi Flood of
1927: Implications for Coastal Restoration. Water 2016, 8, 38. [CrossRef]
57. Zhang, W.; Cai, F.; Zhou, J.; Hua, Y. Experimental Investigation on Air-Water Interaction in a Hydropower Station Combining a
Diversion Tunnel with a Tailrace Tunnel. Water. Stud. 2019, 9, 274. [CrossRef]
58. Xue, Y.; Li, X.; Li, G.; Qiu, D.; Gong, H.; Kong, F. An analytical model for assessing soft rock tunnel collapse risk and its
engineering application. Geomech. Eng. 2020, 23, 441–454. [CrossRef]
59. Huang, F.; Zhao, L.; Ling, T.; Yang, X. Rock mass collapse mechanism of concealed karst cave beneath deep tunnel. Int. J. Rock
Mech. Min. Sci. 2017, 91, 133–138. [CrossRef]
60. Niu, F.; Cai, Y.; Liao, H.; Li, J.; Tang, K.; Wang, Q.; Wang, Z.; Liu, D.; Liu, T.; Liu, C. Unfavorable Geology and Mitigation Measures
for Water Inrush Hazard during Subsea Tunnel Construction: A Global Review. Water 2022, 14, 1592. [CrossRef]