VRF ACU PM Accomplishment Report Summary

1st Quarter (March/April/May 2018)

Total Completed Total Completed


Schedule Total Percent
Tenant Indoor Units Outdoor Units
Accomplishment
Plan Actual Units Quantity Percentage Units Quantity Percentage

Trax Main March 10 - March 24 March 10 - April 7 27 22 81.48% 5 5 100.00% 84.38%

JRB & C March 24 - March 31 March 17 14 14 100.00% 3 3 100.00% 100.00%

i2 Serviced Offices April 7 - April 14 May 6 - May 12 17 16 94.12% 2 2 100.00% 94.74%

APN April 1 March 17 6 6 100.00% 1 1 100.00% 100.00%

17 SO April 14 - April 29 April 7 - April 15 35 26 74.29% 4 0.00% 66.67%

1&1 16th Floor May 5 -May 6 April 29 11 10 90.91% 4 0.00% 66.67%

1&1 15th Floor May 6 - May 13 April 15 - April 28 13 13 100.00% 4 0.00% 76.47%

Remarks :

- Percentage accomplishment were based on the service report of Easylink.


- Units that do not have service report :
i2 Serviced Offices -

Prepared By : Noted by: Approved By:

Christian Argoncillo Alta Crystal Fernandez Israel P. Batas


i2/i3 Building Engineer i2/i3 BuildingAdministartor Section-In-Charge
PPC MITSUBISHI VRF AIR CONDITIONING UNITS
1st QUARTER OF 2021 PREVENTIVE MAINTENANCE

Quantities (Indoor/Outdoor)
VRF @ i2 Bldg VRF @ i3 Bldg Additional Units
Date Day Week
Trax Main Suite Works i2SO APN 17SO 1&1, 16F 1&1, 15F i2 Admin EHSS Office i3 Office i2 Lobby i3 Lobby 1&1, 15F
Office 3F Basement
25-Jan-21 Mon 4
26-Jan-21 Tue 4
27-Jan-21 Wed 4
WK4
28-Jan-21 Thu 4
29-Jan-21 Fri 4
30-Jan-21 Sat
31-Jan-21 Sun
1-Feb-21 Mon 4
2-Feb-21 Tue 4
3-Feb-21 Wed WK5 4
4-Feb-21 Thu 4
5-Feb-21 Fri 4
6-Feb-21 Sat
7-Feb-21 Sun
8-Feb-21 Mon 4
9-Feb-21 Tue 4
10-Feb-21 Wed WK6 1 3
11-Feb-21 Thu 4
12-Feb-21 Fri 4
13-Feb-21 Sat
14-Feb-21 Sun
15-Feb-21 Mon 4
16-Feb-21 Tue 4
17-Feb-21 Wed WK7 4
18-Feb-21 Thu 3 1
19-Feb-21 Fri 4
20-Feb-21 Sat
21-Feb-21 Sun
22-Feb-21 Mon 4
23-Feb-21 Tue 4
24-Feb-21 Wed WK8 4
25-Feb-21 Thu 4
26-Feb-21 Fri 4
27-Feb-21 Sat
28-Feb-21 Sun
1-Mar-21 Mon 4
2-Mar-21 Tue 4
3-Mar-21 Wed WK9 4
4-Mar-21 Thu 2 2
5-Mar-21 Fri 4
6-Mar-21 Sat
7-Mar-21 Sun
8-Mar-21 Mon 4
9-Mar-21 Tue 4
10-Mar-21 Wed WK10 1 3
11-Mar-21 Thu 4
12-Mar-21 Fri 4
13-Mar-21 Sat
14-Mar-21 Sun
15-Mar-21 Mon 4
16-Mar-21 Tue 2
17-Mar-21 Wed WK11 2 2
18-Mar-21 Thu 2 2
19-Mar-21 Fri 2 2
20-Mar-21 Sat
21-Mar-21 Sun
22-Mar-21 Mon 4
23-Mar-21 Tue 2
24-Mar-21 Wed WK12
25-Mar-21 Thu
26-Mar-21 Fri
27-Mar-21 Sat
28-Mar-21 Sun
29-Mar-21 Mon
WK13
30-Mar-21 Tue
31-Mar-21 Wed
32 17 19 7 39 15 17 2 2 2 2 2 8
TOTAL units per Tenant 32 (27 17 19 7 (6 39 (35 15 17 2 2 2 2 2 8
indoor/ 5 (14 indoor/ (17 indoor/ 2 indoor/ 1 indoor/ 4 (11 indoor/ 4 (13 indoor/ 4 (1 indoor/ (1 indoor/ (1 indoor/ (4 indoor/ (4 indoor/ (4 indoor/
outdoor) 3 outdoor) outdoor) outdoor) outdoor) outdoor) outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 4 outdoor) 4 outdoor) 4 outdoor)

Prepared By: Noted by: Approved by:

Mark Joseph C. Yagonia Nerland R. Bulac Raph Jayward N. Sagayno


Building Engineer Building Administrator PMD Cluster-In-Charge
PPC MITSUBISHI VRF AIR CONDITIONING UNITS
1st QUARTER OF 2021 PREVENTIVE MAINTENANCE

Quantities (Indoor/Outdoor)
VRF @ i2 Bldg VRF @ i3 Bldg Additional Units
Date Day Week
Trax Main Trax Expansion Suite Works i2SO APN 17SO 1&1, 16F 1&1, 15F i2 Admin EHSS Office i3 Office i2 Lobby i3 Lobby 1&1, 15F
Office 3F Basement
1-Jul-21 Thu 4
2-Jul-21 Fri WK27 4
3-Jul-21 Sat 4
4-Jul-21 Sun 4
5-Jul-21 Mon 4
6-Jul-21 Tue
7-Jul-21 Wed WK28
8-Jul-21 Thu
9-Jul-21 Fri 4
10-Jul-21 Sat 4
11-Jul-21 Sun 4
12-Jul-21 Mon
13-Jul-21 Tue
14-Jul-21 Wed WK29
15-Jul-21 Thu 4
16-Jul-21 Fri 4
17-Jul-21 Sat 4
18-Jul-21 Sun 4
19-Jul-21 Mon 3
20-Jul-21 Tue
21-Jul-21 Wed WK30
22-Jul-21 Thu
23-Jul-21 Fri 4
24-Jul-21 Sat 4
25-Jul-21 Sun 4
26-Jul-21 Mon
27-Jul-21 Tue
28-Jul-21 Wed WK31
29-Jul-21 Thu 4
30-Jul-21 Fri 3
31-Jul-21 Sat 4
1-Aug-21 Sun 4
2-Aug-21 Mon 4
3-Aug-21 Tue
4-Aug-21 Wed WK32
5-Aug-21 Thu
6-Aug-21 Fri 3
7-Aug-21 Sat 4
8-Aug-21 Sun 4
9-Aug-21 Mon 4
10-Aug-21 Tue
11-Aug-21 Wed WK33
12-Aug-21 Thu 4
13-Aug-21 Fri 3
14-Aug-21 Sat 4
15-Aug-21 Sun 4
16-Aug-21 Mon 4
17-Aug-21 Tue
18-Aug-21 Wed WK34
19-Aug-21 Thu
20-Aug-21 Fri 4
21-Aug-21 Sat 4
22-Aug-21 Sun 4
23-Aug-21 Mon
24-Aug-21 Tue
25-Aug-21 Wed WK35
26-Aug-21 Thu
27-Aug-21 Fri 2
28-Aug-21 Sat 4
29-Aug-21 Sun 1
30-Aug-21 Mon 4
31-Aug-21 Tue
1-Sep-21 Wed WK36
2-Sep-21 Thu 3
3-Sep-21 Fri
4-Sep-21 Sat 4
5-Sep-21 Sun 4
6-Sep-21 Mon 4
7-Sep-21 Tue
8-Sep-21 Wed WK37 2
9-Sep-21 Thu
10-Sep-21 Fri
11-Sep-21 Sat 2
12-Sep-21 Sun 2
13-Sep-21 Mon
14-Sep-21 Tue
15-Sep-21 Wed WK38
16-Sep-21 Thu
17-Sep-21 Fri
18-Sep-21 Sat 2
19-Sep-21 Sun 2
20-Sep-21 Mon
21-Sep-21 Tue
22-Sep-21 Wed WK39
23-Sep-21 Thu 2
24-Sep-21 Fri
25-Sep-21 Sat 2
26-Sep-21 Sun 2
27-Sep-21 Mon
28-Sep-21 Tue WK40
29-Sep-21 Wed
30-Sep-21 Thu
32 12 19 19 7 35 17 18 2 2 2 2 2 4
TOTAL units per Tenant 32 (27 12 19 19 7 (6 39 (35 17 (13 18 2 2 2 2 2 4
indoor/ 5 (6 indoor/ 6 (16 indoor/ (17 indoor/ 2 indoor/ 1 indoor/ 4 indoor/ 4 (14 indoor/ 4 (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (2 indoor/
outdoor) outdoor) 3 outdoor) outdoor) outdoor) outdoor) outdoor) outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 2 outdoor)

Prepared By: Noted by: Approved by:

Mark Joseph C. Yagonia Nerland R. Bulac Raph Jayward N. Sagayno


Building Engineer Building Administrator PMD Cluster-In-Charge
PPC MITSUBISHI VRF AIR CONDITIONING UNITS
1st QUARTER OF 2021 PREVENTIVE MAINTENANCE

Quantities (Indoor/Outdoor)
VRF @ i2 Bldg VRF @ i3 Bldg Additional Units
Date Day Week
Trax Main Trax Expansion Suite Works i2SO APN 17SO 1&1, 16F 1&1, 15F i2 Admin EHSS Office i3 Office i2 Lobby i3 Lobby 1&1, 15F
Office 3F Basement
1-Oct-21 Fri 4
WK40
2-Oct-21 Sat 4
3-Oct-21 Sun 4
4-Oct-21 Mon 4
5-Oct-21 Tue 4
6-Oct-21 Wed WK41
7-Oct-21 Thu
8-Oct-21 Fri
9-Oct-21 Sat 4
10-Oct-21 Sun 4
11-Oct-21 Mon 4
12-Oct-21 Tue
13-Oct-21 Wed WK42
14-Oct-21 Thu
15-Oct-21 Fri 4
16-Oct-21 Sat 4
17-Oct-21 Sun 4
18-Oct-21 Mon 4
19-Oct-21 Tue 3
20-Oct-21 Wed WK42
21-Oct-21 Thu
22-Oct-21 Fri
23-Oct-21 Sat 4
24-Oct-21 Sun 4
25-Oct-21 Mon 4
26-Oct-21 Tue
27-Oct-21 Wed WK43
28-Oct-21 Thu
29-Oct-21 Fri 4
30-Oct-21 Sat 3
31-Oct-21 Sun 4
1-Nov-21 Mon 4
2-Nov-21 Tue 4
3-Nov-21 Wed WK44
4-Nov-21 Thu
5-Nov-21 Fri
6-Nov-21 Sat 3
7-Nov-21 Sun 4
8-Nov-21 Mon 4
9-Nov-21 Tue 4
10-Nov-21 Wed WK45
11-Nov-21 Thu
12-Nov-21 Fri 4
13-Nov-21 Sat 3
14-Nov-21 Sun 4
15-Nov-21 Mon 4
16-Nov-21 Tue 4
17-Nov-21 Wed WK46
18-Nov-21 Thu
19-Nov-21 Fri
20-Nov-21 Sat 4
21-Nov-21 Sun 4
22-Nov-21 Mon 4
23-Nov-21 Tue
24-Nov-21 Wed WK47
25-Nov-21 Thu
26-Nov-21 Fri
27-Nov-21 Sat 2
28-Nov-21 Sun 4
29-Nov-21 Mon 1
30-Nov-21 Tue 4
1-Dec-21 Wed WK48
2-Dec-21 Thu
3-Dec-21 Fri 3
4-Dec-21 Sat
5-Dec-21 Sun 4
6-Dec-21 Mon 4
7-Dec-21 Tue 4
8-Dec-21 Wed WK49
9-Dec-21 Thu 2
10-Dec-21 Fri
11-Dec-21 Sat
12-Dec-21 Sun 2
13-Dec-21 Mon 2
14-Dec-21 Tue
15-Dec-21 Wed WK50
16-Dec-21 Thu
17-Dec-21 Fri
18-Dec-21 Sat
19-Dec-21 Sun 2
20-Dec-21 Mon 2
21-Dec-21 Tue
22-Dec-21 Wed WK51
23-Dec-21 Thu
24-Dec-21 Fri 2
25-Dec-21 Sat
26-Dec-21 Sun 2
27-Dec-21 Mon 2
28-Dec-21 Tue
WK52
29-Dec-21 Wed
30-Dec-21 Thu
31-Dec-21 Fri
32 12 19 19 7 35 17 18 2 2 2 2 2 4
TOTAL units per Tenant 32 (27 12 19 19 7 (6 39 (35 17 (13 18 2 2 2 2 2 4
indoor/ 5 (6 indoor/ 6 (16 indoor/ (17 indoor/ 2 indoor/ 1 indoor/ 4 indoor/ 4 (14 indoor/ 4 (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (2 indoor/
outdoor) outdoor) 3 outdoor) outdoor) outdoor) outdoor) outdoor) outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 2 outdoor)

Prepared By: Noted by: Approved by:

Mark Joseph C. Yagonia Nerland R. Bulac Raph Jayward N. Sagayno


Building Engineer Building Administrator PMD Cluster-In-Charge
PPC MITSUBISHI VRF AIR CONDITIONING UNITS
1st QUARTER OF 2022 PREVENTIVE MAINTENANCE

Quantities (Indoor/Outdoor)
VRF @ i2 Bldg VRF @ i3 Bldg Additional Units
Date Day Week
Trax Main Trax Expansion Suite Works i2SO APN 17SO 1&1, 16F 1&1, 15F i2 Admin EHSS Office i3 Office i2 Lobby i3 Lobby 1&1, 15F
Office 3F Basement
1-Jan-22 Sat 4
WK1
2-Jan-22 Sun 4
3-Jan-22 Mon 4
4-Jan-22 Tue 4
5-Jan-22 Wed 4
6-Jan-22 Thu WK2
7-Jan-22 Fri
8-Jan-22 Sat
9-Jan-22 Sun 4
10-Jan-22 Mon 4
11-Jan-22 Tue 4
12-Jan-22 Wed
13-Jan-22 Thu WK3
14-Jan-22 Fri
15-Jan-22 Sat 4
16-Jan-22 Sun 4
17-Jan-22 Mon 4
18-Jan-22 Tue 4
19-Jan-22 Wed 3
20-Jan-22 Thu WK4
21-Jan-22 Fri
22-Jan-22 Sat 4
23-Jan-22 Sun 4 5
24-Jan-22 Mon 4
25-Jan-22 Tue 4
26-Jan-22 Wed
27-Jan-22 Thu WK43
28-Jan-22 Fri
29-Jan-22 Sat 4 5
30-Jan-22 Sun 3 5
31-Jan-22 Mon 4
1-Feb-22 Tue 4
2-Feb-22 Wed 4
3-Feb-22 Thu WK44
4-Feb-22 Fri
5-Feb-22 Sat 6
6-Feb-22 Sun 3 2
7-Feb-22 Mon 4
8-Feb-22 Tue 4
9-Feb-22 Wed 4
10-Feb-22 Thu WK45
11-Feb-22 Fri
12-Feb-22 Sat 4
13-Feb-22 Sun 3
14-Feb-22 Mon 4
15-Feb-22 Tue 4
16-Feb-22 Wed 4
17-Feb-22 Thu WK46
18-Feb-22 Fri
19-Feb-22 Sat
20-Feb-22 Sun 4
21-Feb-22 Mon 4
22-Feb-22 Tue
23-Feb-22 Wed
24-Feb-22 Thu WK47
25-Feb-22 Fri
26-Feb-22 Sat
27-Feb-22 Sun
28-Feb-22 Mon
1-Mar-22 Tue
2-Mar-22 Wed
3-Mar-22 Thu WK48
4-Mar-22 Fri
5-Mar-22 Sat
6-Mar-22 Sun
7-Mar-22 Mon
8-Mar-22 Tue
9-Mar-22 Wed
10-Mar-22 Thu WK49
11-Mar-22 Fri
12-Mar-22 Sat
13-Mar-22 Sun
14-Mar-22 Mon 2
15-Mar-22 Tue 2
16-Mar-22 Wed
17-Mar-22 Thu WK50
18-Mar-22 Fri
19-Mar-22 Sat
20-Mar-22 Sun
21-Mar-22 Mon 2
22-Mar-22 Tue 2
23-Mar-22 Wed
24-Mar-22 Thu WK51
25-Mar-22 Fri
26-Mar-22 Sat 2
27-Mar-22 Sun
28-Mar-22 Mon 2
29-Mar-22 Tue
WK52
30-Mar-22 Wed
31-Mar-22 Thu
32 12 19 19 7 35 17 18 2 2 2 2 2 2
TOTAL units per Tenant 32 (27 12 19 19 7 (6 39 (35 17 (13 18 2 2 2 2 2 4
indoor/ 5 (6 indoor/ 6 (16 indoor/ (17 indoor/ 2 indoor/ 1 indoor/ 4 indoor/ 4 (14 indoor/ 4 (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (2 indoor/
outdoor) outdoor) 3 outdoor) outdoor) outdoor) outdoor) outdoor) outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 2 outdoor)

Prepared By: Noted by: Approved by:

Mark Joseph C. Yagonia Nerland R. Bulac Raph Jayward N. Sagayno


Building Engineer Building Administrator PMD Cluster-In-Charge
PPC MITSUBISHI VRF AIR CONDITIONING UNITS
3rd QUARTER OF 2022 PREVENTIVE MAINTENANCE

Quantities (Indoor/Outdoor)
VRF @ i2 Bldg VRF @ i3 Bldg Additional Units
Date Day Week
Trax Main Trax Expansion Suite Works i2SO APN 17SO 1&1, 16F 1&1, 15F i2 Admin EHSS Office i3 Office i2 Lobby i3 Lobby 1&1, 16F 1&1, 15F
Office 3F Basement
1-Jul-22 Fri
2-Jul-22 Sat Wk 27
3-Jul-22 Sun
4-Jul-22 Mon
5-Jul-22 Tue
6-Jul-22 Wed
7-Jul-22 Thu Wk 28
8-Jul-22 Fri
9-Jul-22 Sat
10-Jul-22 Sun
11-Jul-22 Mon
12-Jul-22 Tue
13-Jul-22 Wed
14-Jul-22 Thu Wk 29
15-Jul-22 Fri
16-Jul-22 Sat
17-Jul-22 Sun
18-Jul-22 Mon
19-Jul-22 Tue
20-Jul-22 Wed
21-Jul-22 Thu Wk 30
22-Jul-22 Fri
23-Jul-22 Sat
24-Jul-22 Sun
25-Jul-22 Mon
26-Jul-22 Tue
27-Jul-22 Wed
28-Jul-22 Thu Wk 31
29-Jul-22 Fri
30-Jul-22 Sat
31-Jul-22 Sun
1-Aug-22 Mon
2-Aug-22 Tue
3-Aug-22 Wed
4-Aug-22 Thu Wk 32
5-Aug-22 Fri 2
6-Aug-22 Sat 4
7-Aug-22 Sun 4
8-Aug-22 Mon 2
9-Aug-22 Tue
10-Aug-22 Wed
11-Aug-22 Thu Wk 33
12-Aug-22 Fri
13-Aug-22 Sat 4
14-Aug-22 Sun 3
15-Aug-22 Mon 2
16-Aug-22 Tue 2
17-Aug-22 Wed 2
Wk 34
18-Aug-22 Thu Wk 34 2
19-Aug-22 Fri 2
20-Aug-22 Sat 4
21-Aug-22 Sun 4
22-Aug-22 Mon 2
23-Aug-22 Tue 2
24-Aug-22 Wed
25-Aug-22 Thu Wk 35 2
26-Aug-22 Fri 2
27-Aug-22 Sat 4
28-Aug-22 Sun 4
29-Aug-22 Mon 1
30-Aug-22 Tue 2
31-Aug-22 Wed 2
1-Sep-22 Thu Wk 36
2-Sep-22 Fri
3-Sep-22 Sat 4 4
4-Sep-22 Sun 2
New Units
5-Sep-22 Mon
6-Sep-22 Tue 2
7-Sep-22 Wed 2
8-Sep-22 Thu Wk 37 2
9-Sep-22 Fri 2
10-Sep-22 Sat 4
11-Sep-22 Sun 4
12-Sep-22 Mon 2
13-Sep-22 Tue 2
14-Sep-22 Wed 2
15-Sep-22 Thu Wk 38 2
16-Sep-22 Fri 2
17-Sep-22 Sat 4
18-Sep-22 Sun 4
19-Sep-22 Mon 2
20-Sep-22 Tue 2
21-Sep-22 Wed 2
22-Sep-22 Thu Wk 39 2
23-Sep-22 Fri 2
24-Sep-22 Sat 1 2
25-Sep-22 Sun 4
26-Sep-22 Mon 2
27-Sep-22 Tue 2
28-Sep-22 Wed 2
29-Sep-22 Thu Wk 40 2
30-Sep-22 Fri 2
1-Oct-22 Sat 4
2-Oct-22 Sun 4
3-Oct-22 Mon 2 1
4-Oct-22 Tue 2
5-Oct-22 Wed 2
6-Oct-22 Thu Wk 41 1
7-Oct-22 Fri
8-Oct-22 Sat 4
9-Oct-22 Sun 4
0 12 19 19 7 39 17 22 2 2 2 2 2 4 4
TOTAL units per Tenant 32 (27 12 19 19 7 (6 39 (35 17 (13 18 2 2 2 2 2 4 4
indoor/ 5 (6 indoor/ 6 (16 indoor/ (17 indoor/ 2 indoor/ 1 indoor/ 4 indoor/ 4 (14 indoor/ 4 (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (1 indoor/ (2 indoor/ (2 indoor/
outdoor) outdoor) 3 outdoor) outdoor) outdoor) outdoor) outdoor) outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 1 outdoor) 2 outdoor) 2 outdoor)

Prepared By: Noted by: Approved by:


Mark Gil Abella Nerland R. Bulac Raph Jayward N. Sagayno
Building Engineer Building Administrator PMD Cluster-In-Charge