Professional Documents
Culture Documents
1 5 6
2
7
2
10 8 1
9
SIDE–SHIFT
4 CARRIAGE
CARRIAGE 5. TOP BUSHING
6. TOP BAR
1. LOAD BACKREST EXTENSION 7. BOTTOM BUSHING
2. STANDARD CARRIAGE 8. BOTTOM BAR
3. FORKS 9. SIDE–SHIFT CYLINDER
4. FORK REMOVAL NOTCH 10. CYLINDER MOUNTING BRACKET
1
MAST MOUNTS (See FIGURE 13.)
1. OUTER WELDMENT
2. FIRST INTERMEDIATE WELDMENT
The mast can tilt forward and backward. Tilt cylinders 3. SECOND INTERMEDIATE WELDMENT
are fastened between the frame of the lift truck and the 4. INNER WELDMENT
2 3
outer weldment of the mast to change the angle of the
mast and forks. Pivot pins are installed in the drive axle 4
hangers. The pivot pins rotate in bushings in the hang-
ers. The outer weldment has mounts that fit on the pivot 1
pins. Capscrews hold the mast to the pivot pins.
MAST
Operation
(See FIGURE 3., through FIGURE 6.)
The three hydraulic cylinders are connected by hoses
and tubing as shown in FIGURE 3. To extend the mast,
oil from the main control valve flows to all cylinders at
4 the same time. The free–lift cylinder extends first be-
4 cause it lifts the least amount of weight. The free–lift
cylinder raises the carriage to the top of the inner weld-
5 ment. After the free–lift cylinder reaches the end of its
stroke, the main lift cylinders begin to extend. As the
6 10101 main lift cylinders extend, the first intermediate weld-
1. MAIN LIFT CYLINDER (LEFT–HAND) ment is raised by the lift cylinders. The second inter-
2. FREE–LIFT CYLINDER mediate and inner weldments are raised by the lift
3. MAIN LIFT CYLINDER (RIGHT–HAND)
4. LOWERING CONTROL VALVE (INTERNAL)
chains.
5. LOWERING CONTROL VALVE (EXTERNAL)
6. TO/FROM MAIN CONTROL VALVE The left–hand lift cylinder has a small amount of oil be-
low the piston. The free–lift cylinder has a small amount
FIGURE 3. HYDRAULIC SCHEMATIC of oil above the piston. This oil provides a hydraulic
One set of lift chains is connected to mounts that are near cushion during operation. See FIGURE 5. and
the top of the outer weldment. The lift chains then go FIGURE 6.
over sheaves at the top of the first intermediate weld-
During lowering, the main lift cylinders lower first be-
ment and fasten at the bottom of the second intermediate
cause they have a greater load. After the main lift cylin-
weldment.
ders have retracted, the free–lift cylinder lowers. All oil
Another set of lift chains is connected to mounts that are from the lift cylinders flows through the lowering con-
near the top of the first intermediate weldment. The lift trol valves to the hydraulic tank.
3
2 3
1 4
6
5 11 8
7 5
10
LOWERED
11
9 10 4
10101
9
3
FULLY RAISED
1
FREE–LIFT
FIGURE 4. OPERATION
4
1 As the main lift cylinders retract, hydraulic oil flows out
of the cylinders through the hydraulic port (5). During
the last 20 mm (0.8 in) of the stroke, the hydraulic oil
must flow out through the small orifice (6). This action
2
causes the cylinder rod to move much more slowly at
the end of the stroke. This cushion effect prevents a
sudden stop at the end of the lowering sequence,
3 making a smoother lowering operation.
7
4
6
20 mm (0.8 in) 1. CYLINDER ROD
CUSHION 2. CYLINDER SHELL
3. PISTON
4. INTERNAL CHECK VALVE
5. HYDRAULIC PORT
8 6. ORIFICE
7. PISTON SEAL
8. CUSHION RING
LEFT–HAND LIFT CYLINDER
5
REPAIRS
notch. See FIGURE 7. Lower the carriage further so
WARNING that the top hook of the fork is disengaged from the top
Before working on or near the mast, read SAFETY carriage bar. Move the carriage away from the fork, or
PROCEDURES WHEN WORKING NEAR THE use a lifting device to move the fork away from the car-
MAST. See FIGURE 9. riage.
FORKS
The forks are held on the carriage by hooks. The forks 1. CARRIAGE
are kept in position by latches that fit through the top BARS
fork hooks and into slots in the top carriage bar. The 2. HOOK FORK
3. BLOCKS
forks can be removed from the carriage by aligning the
forks with the fork removal notch. The fork removal 1
notch is in the bottom crossmember of the carriage. Al- 2
ways check that the latches for the forks keep the forks
in position on the carriage. Replace damaged latch parts.
ÉÉ ÉÉ
Removal ÉÉ 3
ÉÉ
WARNING
FIGURE 7. REMOVE A FORK
Do not try to remove a fork without a lifting device.
Each hook fork for these lift trucks can weigh 45 kg Installation
to 115 kg (100 to 250 lb).
Move the fork and carriage so that the top hook on the
A fork can be removed from the carriage for replace- fork can engage the upper carriage bar. Raise the car-
ment of the fork or other maintenance. Slide a hook fork riage to move the lower hook through the fork removal
to the fork removal notch on the carriage. See notch. Slide the fork on the carriage so that both upper
FIGURE 8. Lower the fork onto blocks so that the bot- and lower hooks engage the carriage. Engage the lock
tom hook of the fork moves through the fork removal pin with a notch in the top carriage bar.
6
1 6
1
2 7 7
5
5
8
8
9
9
1. LOAD BACKREST
EXTENSION
2. CARRIAGE 6. LEVER
3. FORKS 7. WASHER
4 4. FORK REMOVAL NOTCH 8. SPRING
5. LOCK PIN ASSEMBLY 9. PIN
1. CARRIAGE
2. SNAP RING
3. SHIM
4 LOAD ROLLER
7
1
1
2
3
7 5
THREE–STAGE,
FOUR–STAGE
6 2
4
FIGURE 9. SAFETY PROCEDURES WHEN
WORKING NEAR THE MAST (2 of 2) 8
2
5. CHAIN ANCHOR 3
CARRIAGES 4 2
6. CHAIN PIN
Removal 7. COTTER PIN
8. ANCHOR PIN
STANDARD CARRIAGE
(See FIGURE 8. and FIGURE 10.) FIGURE 10. CARRIAGE
4. Use the lift cylinders to raise the inner weldment. If
1. Put a one–quarter capacity load on the forks. The load
the hydraulic system cannot be used, connect a crane to
must give the carriage stability so that the carriage can-
the top of the inner weldment. Carefully raise the inner
not fall when it is disconnected from the mast.
weldment until it is above the load rollers of the car-
2. Lower the carriage and forks on blocks so that the lift riage.
chains become loose.
5. Move the lift truck away from the carriage. Complete-
ly lower the inner weldment so that it cannot move.
WARNING
When disconnecting the lift chains, keep control of 6. Connect a lifting device to the carriage. Remove the
the ends. Use wire to temporarily connect the ends of load from the forks with another lift truck. Lower the
the lift chains to the mast. This procedure will pre- carriage to the floor so that the load rollers are up.
vent the lift chains from falling from the sheaves and
7. If the forks are removed, use a lifting device to put the
causing an injury or damage.
carriage on the floor so that the load rollers are up.
3. Remove the pin from each chain anchor at the car-
SIDE–SHIFT CARRIAGE (See FIGURE 12.)
riage. Disconnect the lift chains from the carriage. Use
wire to connect the ends of the lift chains to a part of the 1. Lower the carriage completely and remove the forks.
8
2. Connect a lifting device to the lifting eye on the side– 2. Check the clearance of the load rollers. See CHECKS
shift carriage. The side–shift carriage weighs approxi- AND ADJUSTMENTS in this section.
mately 200 kg (400 lb).
3. Connect the lift chains to the chain anchors at the car-
3. Remove the two upper capscrews from the bottom riage. Use new cotter pins in the anchor pins. Adjust the
carriage bar. Slowly loosen the two bottom capscrews, lift chains as described in CHECKS AND ADJUST-
but do not remove them. The slotted holes will allow the MENTS in this section.
bottom carriage bar to move down so that the side–shift
SIDE–SHIFT CARRIAGE (See FIGURE 12.)
carriage can be removed. Carefully lift the side–shift
carriage from the standard carriage. The side–shift cyl- 1. Install the side–shift cylinder in the bracket. Use an
inder mounting bracket and cylinder will stay on the equal number of shims on both sides of the cylinder to
standard carriage. Remove the bushings. limit side–to–side movement within the bracket. Maxi-
mum movement is 0.6 mm (0.024 in). Install the bolts
4. Disconnect the hydraulic lines at the side–shift cylin-
and nuts to hold the cylinder in position. Tighten the nuts
der. Put caps on the open lines. Remove the cylinder
to 26 Nm (19 lbf ft) torque.
mounting bracket from the carriage. If necessary, re-
move the threaded rods and shims to remove the side–
shift cylinder.
4 5
Repairs (See FIGURE 10. and FIGURE 11.) 2 3
1
1. If any of the load rollers must be replaced, make a note
of the location and number of the shims. Install the 7
shims, load rollers and snap rings. See CHECKS AND 6
ADJUSTMENTS for correct adjustment of the load 1
rollers.
NOTE: The carriage has six load rollers. The shims are
installed on the bottom four rollers only.
2. Repair the side–shift cylinder as follows: 2
5 4 3
a. Remove the retainers from the shell. Pull the rod 8
from the shell.
b. Replace seals, O–rings or back–up rings as neces- 1. WIPER 5. O–RING
2. RETAINER 6. PISTON AND ROD
sary. 3. ROD SEAL 7. PISTON SEAL
c. Lubricate all internal parts with clean hydraulic oil. 4. BACK–UP RING 8. SHELL
d. Install the piston and rod in the shell. Apply Loctite FIGURE 11. SIDE–SHIFT CYLINDER
242 to the threads of the retainers. Install the retainers
and tighten them to 27 Nm (20 lbf ft) torque. 2. Install the cylinder mounting bracket on the standard
carriage, making sure it is engaged with the notch in the
Installation top carriage bar. Connect the hydraulic lines to the side–
shift cylinder. Put grease on the ends of the cylinder rod.
STANDARD CARRIAGE
3. Install the top bushing on the mounting bracket. Lu-
1. Use the hydraulic system of the lift truck or a crane to
bricate the outer surface of the bushing with multi–pur-
raise the inner weldment. If the hydraulic system cannot
pose grease.
be used, connect a crane to the top of the inner weld-
ment. Carefully raise the inner weldment until it is 4. Connect the top and bottom carriage bars by installing
above the load rollers of the carriage. Move the lift truck the two bottom capscrews. Do not tighten the cap-
toward the carriage until the inner weldment is aligned screws. Lubricate the outer surface of the bottom bush-
with the carriage rollers. Carefully lower the inner weld- ing with multi–purpose grease. Install the bottom bush-
ment until it engages all of the load rollers. ing in the bottom carriage bar.
9
2
1
3
5 1. TOP BUSHING
4 2. CYLINDER MOUNTING
BRACKET
3. SHIM
4. SIDE–SHIFT CYLINDER
5. LIFTING EYE
6. BOTTOM CARRIAGE
10 BAR
7. BOTTOM BUSHING
9 8. TOP CARRIAGE BAR
9. GREASE FITTING
6 10. BOLT
8
5. Make sure the standard carriage is completely low- weldments are fastened together. Make sure the chains
ered. Connect a lifting device to the lifting eye. Install will not damage the sheaves, tubing, or other parts of the
the side–shift carriage on the standard carriage. Put mast. Make sure the crane has a capacity of at least 1600
blocks under the bottom bar of the side–shift carriage so kg (3500 lb).
that the bottom bushing moves tight against the standard
3. Put a drain pan under the area of the hydraulic fittings.
carriage.
Disconnect the hydraulic line at the external lowering
6. Install the two top capscrews into the side–shift car- control valve on the outer weldment.
riage. On the E2.00–2.75XM (E45–55XM) units, tight-
en all of the capscrews to 435 Nm (320 lbf ft) torque. On WARNING
E3.00–3.20XM (E60–65XM) units, tighten all of the Use a driver, not your fingers, to push the anchor
capscrews to 755 Nm (557 lbf ft) torque. Remove the pins from the rod ends on the tilt cylinders. The cyl-
lifting device. Lubricate the top bushing at the grease fit- inder or mast can move and cause serious injury.
tings. 4. Remove the cotter pins and anchor pins at the tilt cyl-
inder mounts on the mast.
MAST
5. Remove the capscrews that hold the mast to the pivot
Removal (See FIGURE 13.)
pins at the mounts.
NOTE: If the mast must be disassembled, remove the
6. Use the crane to lift the mast assembly from the lift
forks and carriage as described in the procedures for the
truck. Put the mast on the floor so that the back of the
CARRIAGES. If only the lift cylinders need to be re-
mast is toward the floor.
moved, see the procedures for the LIFT CYLINDERS.
Disassembly
1. Before removing the mast, check the length of the lift (See FIGURE 16. and FIGURE 17.)
chains. See the procedures in Cleaning and Inspection.
NOTE: If only the lift cylinders need to be removed and
2. Fully lower all of the mast weldments and the car- repaired, see the procedures for the LIFT CYLINDERS.
riage. Tilt the mast fully forward. Use chains and con- When the mast has header hoses, see the procedures for
nect a crane to the top of the mast. Make sure all the the HEADER HOSES.
10
the inner weldment from the second intermediate weld-
4 ment.
5. Disconnect the lift chains at the bottom of the second
intermediate weldment and the top of the outer weld-
3 ment. Remove the lift chains. Push the second inter-
mediate weldment toward the bottom of the mast assem-
bly until the bottom load rollers are seen.
6. Remove the strip bearings and spacers at the top of the
first intermediate weldment. Remove the load rollers at
the bottom of the second intermediate weldment. Re-
move the load rollers at the top of the first intermediate
weldment. Make a note of each shim arrangement and
2 load roller location. The shim arrangements will be ap-
proximately the same during assembly.
7. Slide the second intermediate weldment half–way out
of the top of the first intermediate weldment. Connect a
1 crane to the center of the second intermediate weldment.
See FIGURE 14. Slide the second intermediate weld-
ment out until the stub shafts are in the notches of the
1. PIVOT PIN first intermediate weldment. Remove the second inter-
2. DRIVE AXLE mediate weldment.
HANGER
(MAST MOUNT)
3. TILT CYLINDER
4. OUTER WELDMENT 12791
WARNING
Cleaning solvents can be flammable and toxic, and
can cause severe skin irritation. When using clean- 12174
ing solvents, always follow the solvent manufactur-
1. CHAIN WEAR SCALE
er’s recommended safety precautions.
NOTE: The instructions for measuring chain
2. Clean the lift chains with solvent. Remove all dirt and wear are shown on the Chain Wear Scale.
grease. Inspect the lift chains for wear or damage. The FIGURE 15. CHECK THE LIFT CHAINS
lift chains must be installed on the mast before they can
be checked for length. A lift chain becomes longer when
it is worn. If a chain is 3% longer than a new lift chain, a
new set of lift chains must be installed. If a chain scale is WARNING
available, check the lift chain as shown in FIGURE 15. Be careful when cleaning with steam. Steam can
If a chain scale is not available, measure 20 links of the cause serious burns. Wear protective clothing and
lift chain. Compare the measurement with the lengths gloves. Never expose your skin to steam.
given in FIGURE 15. Lubricate the chains with SAE 30
engine oil. The best procedure is to soak the lift chains in 4. Clean the mast weldments with steam or solvent.
engine oil.
5. Inspect the sliding surfaces for wear or damage. In-
WARNING spect the load roller contact surfaces for wear or da-
mage. Inspect all welds for cracks.
Never replace just the worn section of a chain. Install
the complete chain. Never replace just one chain of a
chain pair. Install new chains in pairs. WARNING
Incorrect welding procedures can cause damage to
3. Inspect the chain anchors and pins. Install new parts the structure of the mast. Get information from your
for old parts that are worn or damaged. Hyster lift truck dealer before welding on the mast.
12
3
1. OUTER WELDMENT
2. O–RING 1
2
3. SHIM(S)
4
4. STRIP BEARING 13
5. LIFT CHAIN
6. SPACER 5
7. ANCHOR PIN 7
8. COTTER PIN 6
17
8
16
9
13
10
11
12
13
14
9. CHAIN ANCHOR
10. WASHER 15
11. NUT
12. FIRST INTERMEDIATE
WELDMENT
13. SNAP RING
14. SHIMS
15. LOAD ROLLER
16. BEARING
17. CHAIN SHEAVE
1. SNAP RING
2. BEARING
3. CHAIN SHEAVE
4. SECOND INTERMEDIATE
WELDMENT
5. O–RING
6. SHIM(S)
7. STRIP BEARING
8. INNER WELDMENT
9. LOAD ROLLER
16 8
11
15
14
13 10
1
12 9
11
10. SHIMS
11. COTTER PIN
12. NUT
13. WASHER
14. CHAIN ANCHOR
15. ANCHOR PIN
16. LIFT CHAIN
14
Assembly (See FIGURE 16. and FIGURE 17.) at the top of the left–hand cylinder rod until both cylin-
ders are even. Install the keeper at the top of the right–
NOTE: The shims for the load rollers keep the weld-
hand cylinder. Install the snap ring and washer at the top
ments parallel and give correct clearance. During as-
of the lift cylinders. Install the nuts, bolts and spacers at
sembly, the shim arrangement will be approximately the
the lift cylinder mounts on the outer weldment. Tighten
same as before disassembly. Check the clearance and
the nuts to 53 Nm (39 lbf ft) torque.
adjust the shims for wear or for changes caused by re-
pairs. The strip bearings are also adjusted by using 5. Install the housing for the lowering control valve on
shims. See CHECKS AND ADJUSTMENTS in this the outer weldment. Tighten the nuts for the lowering
section for the adjustment procedures. control valve to 18 Nm (13 lbf ft) torque. Install the low-
ering control valve in the housing. Connect the hydrau-
NOTE: When the mast has header hoses, see the proce-
lic lines and fittings between the lowering control valve
dures for the HEADER HOSES.
and the main lift cylinders.
15
13. Install the free–lift cylinder in the mounts on the in-
ner weldment. Install the brackets for the cylinder and
tighten the nuts and bolts. LOWER LOAD 2
ROLLERS
14. Install the hose sheave for the free–lift cylinder. 1
2
Install the hydraulic hose and tubing that connect the
free–lift cylinder to the right–hand lift cylinder. Install
the balance line between the two main lift cylinders. 2
1. Lubricate the pivot pins and install them into the 1. LUBRICATE STRIP BEARINGS SURFACES
2. LUBRICATE LOAD ROLLER SURFACES
mounts at the drive axle hanger. 3. LOAD ROLLER
2. Connect a crane to the top of the mast using chains. FIGURE 19. LUBRICATE THE MAST
Make sure all the weldments are fastened together.
Make sure the chains will not damage the sheaves, tub- LIFT CYLINDERS
ing or other parts of the mast. Make sure the crane has a
capacity of at least 1600 kg (3500 lb).
WARNING
Before working on or near the mast, see SAFETY
3. Use the crane to install the mast assembly on the pivot PROCEDURES WHEN WORKING NEAR THE
pins. Install the capscrews that hold the mast to the pivot MAST. See FIGURE 9.
pins. Tighten the capscrews to 90 Nm (66 lbf ft) torque.
Removal
4. Connect the tilt cylinders to the mast. Install the an- MAIN LIFT CYLINDERS
chor pin and cotter pin. (See FIGURE 16. And FIGURE 22.)
NOTE: The following procedures are for the removal
5. Connect the hydraulic line to the lowering control
of the lift cylinders with the mast installed on the lift
valve.
truck.
6. Install the carriage as described in the procedures for 1. Remove the carriage as described in the procedures
the CARRIAGE. for the CARRIAGE.
7. Check the tilt cylinder adjustment as described in 2. Raise the mast until it is almost fully extended. Use a
CHECKS AND ADJUSTMENTS. Operate the mast safety chain to connect the middle crossmember of the
and check for leaks and correct operation. Check the lift first intermediate weldment to the top crossmember on
chains as described in CHECKS AND ADJUST- the outer weldment. Lower the mast so that the safety
MENTS. chain holds the weight of the weldments.
3. On the left–hand lift cylinder, remove the snap ring
8. Lubricate the sliding surfaces and the load roller sur- from the top of the cylinder rod. On the right–hand lift
faces along the full length of the channels as shown in cylinder, remove the spacer and retainer from the cylin-
FIGURE 19. Apply lubricant only to the surfaces indi- der rod.
cated.
4. Put a drain pan under the area of the hydraulic fittings.
NOTE: The load rollers and sheaves have sealed bear- Disconnect the hydraulic lines at the cylinder. Retract
ings and do not need additional lubrication. the rod into the lift cylinder.
16
5. Remove the nut, bolt and spacer at the mounts. Assembly (See FIGURE 20. and FIGURE 21.)
6. Use a lifting device as necessary to remove the lift cyl- NOTE: Assembly of the main lift cylinders and the
inder from the mast. Keep the shims from the top of the free–lift cylinder is similar. All of the lift cylinders are
left–hand cylinder with the cylinder. assembled from the rod end of the cylinder shell.
FREE–LIFT CYLINDER (See FIGURE 16.) 1. Lubricate all internal parts of the lift cylinder with
1. Remove the carriage as described in the procedures clean hydraulic oil or packing lubricant, Hyster Part No.
for the CARRIAGE. Lower the mast completely. 186061. Use new O–rings, seals and wear rings.
2. Put a drain pan under the area of the hydraulic fittings. 2. On the main lift cylinders, do the following:
Disconnect the hydraulic line at the cylinder. a. Install the rod wiper and rod seal in the retainer.
3. Move the chains from the chain sheaves. Remove the Install the O–ring on the outside of the retainer. Install
clamp and bracket for the free–lift cylinder. Remove the the retainer on the rod.
free–lift cylinder. b. Install the O–ring and back–up ring on the piston
for the right–hand cylinder. If a spacer is used, install it
4. See FIGURE 23. Remove the crosshead from the cyl-
on the rod. Install the piston in the rod. Tighten the pis-
inder rod. Disassemble the crosshead as necessary.
ton to 170 to 200 Nm (125 to 150 lbf ft) torque.
Disassembly 3. Install the check valve and O–ring in the base of the
(See FIGURE 20. and FIGURE 21.)
piston of the free–lift cylinder and left–hand lift cylin-
CAUTION der. Make sure the arrow on the check valve is towards
Carefully disassemble the lift cylinders so that the the base of the piston. Install the washer and snap ring
piston rods and sliding surfaces are not damaged. for the check valve.
2
4 5
14
5 15
3
6
5
4
7
5
8
1 6
8
9
7
10
9 12
11 10
1. ROD
2. WIPER 9. PISTON SEAL 11
3. ROD SEAL 10. WEAR RING
4. RETAINER 11. SEAL RING
5. O–RING 12. SHELL
6. SPACER 13. CHECK VALVE
7. BACK–UP RING 14. WASHER
8. PISTON 15. SNAP RING
FIGURE 20. MAIN LIFT CYLINDERS
9. Install the lowering control valve in the port at the Installation
base of the left–hand, main lift cylinder. See
FIGURE 22. Make sure the special washer and the MAIN LIFT CYLINDERS
spring are installed correctly. The special washer is next (See FIGURE 16. and FIGURE 22.)
to the cylinder shell. A wrong installation can cause the
load to lower too fast. 1. Use a lifting device to raise the mast until it is almost
fully extended. See FIGURE 9. Use safety chains to
10. Install the fitting at the base of the free–lift cylinder. connect the bottom crossmember of the first intermedi-
This is a special fitting that limits flow of the hydraulic ate weldment to a crossmember on the outer weldment.
oil. Use safety chains between the other weldments so that
18
they cannot move. Lower the mast so that the safety
chains hold the weight of the weldments. 1
6
6. Connect the main lift chains as necessary and adjust
them as specified in CHECKS AND ADJUSTMENTS.
3. Connect the hydraulic line at the cylinder. FIGURE 21. FREE–LIFT CYLINDER
10
5
12
4
8
11 6
7. HOUSING
8. HOSE
9. LOWERING CONTROL VALVE
10
9 10. MAIN LIFT CYLINDER, RIGHT–HAND
11. SPACER
12. RETAINER
HEADER HOSE ARRANGEMENTS NOTE: This procedure is for the four function option.
The three function option will have hoses “A” and “B”
Some lift trucks are equipped with auxiliary hydraulic
only.
functions that are fastened to the carriage. Examples of
these auxiliary functions are a side–shift carriage or a
roll clamp. These auxiliary functions require header NOTE: The carriage height must be correct before the
hoses for their operation. header hoses can be adjusted. See ADJUST THE LIFT
CHAINS for the carriage adjustment procedure.
NOTE: Before installing the header hoses, make sure
you know the lift height of the mast. The tension on the NOTE: If the header hoses were removed, use this pro-
header hoses is adjusted according to lift height. The lift cedure to install the Type “A” or Type “B” header hoses.
height is on the nameplate of the lift truck and on the See TABLE 1. If the mast components have not been as-
right–hand side of the outer weldment. sembled, assemble the mast as described in the previous
procedure.
Installation, Header Hoses (See FIGURE 24.
through FIGURE 26. and TABLE 1.)
1. Raise the carriage so that the free–lift chains are not
WARNING tight. Raise the inner channel so that the main–lift chains
Before working on or near the mast, see SAFETY are not tight. Install chains to prevent the inner channel
PROCEDURES WHEN WORKING NEAR THE and carriage from moving. The chains must not be in the
MAST. See FIGURE 9. path of the header hose.
20
2 3 4 5
1
8 9
18 8
10
9
7
5 11
12
13
1. HOSE
2. HOSE SHEAVE
3. STUB SHAFT WELDMENT
4. WASHER
5. CAPSCREW
6. CHAIN GUARD
7. SPACER 14
8. CHAIN SHEAVE
9. SNAP RING
10. PIN
11. CROSSHEAD
12. ALIGNMENT PIN
13. FREE–LIFT CYLINDER
14. STRAP 15
15. TUBE SPACER
16. BRACKET
17. LOWERING CONTROL
VALVE FITTING
18. BEARING
17 16
21
header hoses are straight on a flat surface. Mark header FIGURE 25.:
hose at points ”E” and “G” (mm) as shown in TABLE 1. a. Put a coating of multi–purpose grease on the stub
Measure from the end of the hose with the small fitting. shafts before assembly.
4. Loosely assemble the hose sheaves as shown in
2
1 3 5
4
DC B A
3
DC B A
6
5
DC BA
1 4
2 8
DC B A
A B C D = HOSES
1372390 2/3 R7
DC BA
1. CARRIAGE
6
1 2. MAST ASSEMBLY
7 3. CHAIN AND HOSE SHEAVES
DC B A AT FREE–LIFT CYLINDER
4. REAR HOSE SHEAVES
5. FRONT HOSE SHEAVES
2 6. MIDDLE HOSE SHEAVES
D A 7. MIDDLE HOSE CLAMP
8. CABLE MOUNT BLOCKS
CB 9. BOTTOM HOSE CLAMP
DC BA ASSEMBLIES
9 8
8
22
TABLE 1. STANDARD FOUR–STAGE HOSE DIMENSIONS
Channel
Lift Height Length Dimension “E” Dimension “G”
(Reference)
mm in mm mm in mm in
4839 190.5 1735 1351 53.2 4750 187.0
5143 202.5 1811 1426 56.1 4971 195.7
5450 214.6 1888 1501 59.1 5192 204.4
5754 226.5 1964 1576 62.1 5414 213.1
6058 238.5 2040 1651 65.0 5635 221.9
6364 250.6 2141 1751 68.9 5930 233.5
6670 262.6 2243 1851 72.9 6225 245.1
6977 274.7 2345 1951 76.8 6520 256.7
7274 286.4 2446 2051 80.8 6815 268.3
7583 298.5 2548 2151 84.7 7110 279.9
7886 310.5 2649 2251 88.6 7405 291.6
8192 322.5 2751 2351 92.6 7701 303.2
8496 334.5 2853 2452 96.5 7996 314.8
8799 346.4 2954 2552 100.5 8291 326.4
9108 358.6 3056 2652 104.4 8586 338.0
Dimension “G”
Dimension “E”
TYPE A
Dimension “G”
Dimension “E”
“E” = (0.985 x channel length in mm) –358.2 “G” = (2.905 x channel length in mm) –291.0
b. The nuts for the sheave capscrew (axle) must be brackets so that the hoses can slip to equalize the pres-
on the inside of each assembly. sure. Tighten the capscrews and nuts of the bracket to 18
c. Do NOT tighten any of the nuts or capscrews. Nm (13 lbf ft) torque. Do NOT tighten the capscrews
They must be loose to allow installation of the and nuts for the strap clamps at this time.
hoses on the hose sheave. 7. If the crosshead of the free –lift cylinder does not have
5. Install the plate at the middle hose clamp and tighten hose guides, remove the chain guard brackets, chains
the capscrews to 8 Nm (6 lbf ft) torque. and chain sheaves. Install hose guides (flare towards
outside) and snap rings to the chain sheaves. Install the
6. Install the bottom hose clamps as shown in free–lift sheaves, chains and chain guard brackets as
FIGURE 24. Put some grease on the bottom of the shown in FIGURE 24. and FIGURE 26.
23
17 16
14
1. CARRIAGE CLAMP
2 15 2. WASHER
29 15 3. HOSE SHEAVE
4. STUB SHAFT
3 5. STUB SHAFT
27 WELDMENT
4 6. SNAP RING
18 7. HOSE GUIDE
8. CLAMP, C–D
3 14
29 9. PLATE
10. CLAMP, A–B
11. HOSE BRACKET
24 12. GUIDE BRACKET
13. STRAP
26 5 14. HOSE GUARD
15. STUB SHAFT
2 16. TUBE
14 15 17. ROLLER
3 18. CABLE ROLLER
18 16 6 19. CABLE ASSEMBLY
17 20. NUT
7
25 21. BLOCK
14 22. PIN
15 9
14 23. COTTER PIN
17 8
24. HEADER HOSE
25. HOSE MOUNT
16
26. HOSE CLAMP
27. CLAMP, C–D
19 28. SPRING
6
18 29. SPACER
28 2 2
26 23
20 28
10
20
22 19
2
25
21 2
24
11 11
1
12
13
24
D C B A
8 9
C B
D A 10
D 4
25
8. Install hoses over the free–lift cylinder with marks ers, and cotter pins to fasten the cable loops. See
“E“ aligned with the top edge of the clamp of the middle FIGURE 25. If necessary, install the mount blocks on
hose clamp assemblies. Tighten the capscrews and nuts the bottom crossmember of the intermediate channel us-
of the clamps to 8 Nm (6 lbf ft) torque. ing the capscrews and washers. Tighten the capscrews
to 18 Nm (13 lbf ft) torque.
9. Pass the hoses under the lower hose clamps and install
the strap clamps on the hoses. Align marks “G“ to the 13. Make sure the cables are in the grooves of the idler
bottoms of the lower hose clamps. Tighten the caps- wheels and under the formed feature of the hose guards
crews and nuts of the strap clamps to 18 Nm (13 lbf ft) of the floating sheaves. Install the ends of the cables in
torque. the brackets so that there is spring tension on the cables.
Make sure the axle capscrews and nuts of the sheaves
10. Install the hoses on hose sheaves (items 5 & 4 of are tightened to 53 Nm (39 lbf ft) torque.
FIGURE 24.) with loops long enough to install on the
floating hose sheaves. Tighten the axle capscrews and 14. Slowly operate the hydraulic system so that the lift
nuts of sheaves 4 & 5 to 53 Nm (39 lbf ft) torque. chains are tight. Remove the chains that fasten the car-
riage and channel weldment. Slowly raise the carriage
11. Partially assemble the floating sheaves (6) as shown using the hydraulic system. Make sure the hoses move
in FIGURE 24. and FIGURE 25. Install the loops of the through all the sheaves correctly.
hoses under the sheaves (6). Then install the roller guide
assemblies over the hoses and between the hose guards. 15. Slowly operate the mast through a few cycles to
See FIGURE 24. and FIGURE 26. Tighten the roller make sure the hoses track correctly. Tighten the strap
guide capscrews and nuts to 8 Nm (6 lbf ft) torque. clamps at the bottom hose clamps to 18 Nm (13 lbf ft)
torque. Fasten the hose assemblies to the main cylinders
12. Fasten the looped ends of the cables of the floating using hose clamps and screw clamps as shown in
sheaves to the cable mount blocks. Use the pins, wash- FIGURE 24. and FIGURE 25.
CHECK FOR LEAKS IN THE LIFT AND 2. Raise the carriage and load one meter (3 ft). If the car-
TILT SYSTEM riage slowly lowers when the control valve is in the Neu-
tral position, there are leaks in the hydraulic system. The
WARNING maximum speed that the carriage is allowed to lower is
During the test procedures for the hydraulic system, 50 mm (2 in) per 10 minutes when the hydraulic oil is
use chains to fasten the load to the carriage to pre- 30°C (90°F). If the oil temperature is 70°C (160°F), the
vent it from falling. Keep all people away from the maximum speed that the carriage can lower is 150 mm
lift truck during the tests. (6 in) per 10 minutes.
Do not try to find hydraulic leaks by putting your 3. Check the lift cylinders for internal leaks. Remove the
hand on hydraulic components under pressure. Hy- load from the forks. Install a gate valve in the supply line
draulic oil can be injected into the body by the pres- between the main control valve and the mast. Put a ca-
sure. pacity load on the forks again. Raise the carriage one
meter (3 ft). Close the gate valve. If the carriage or mast
Check The Lift Cylinders For Leaks weldments lower slowly, the seals in the lift cylinders
have leaks.
1. Operate the hydraulic system. Put a capacity load on
the forks. Use a safety chain to hold the load to the car- 4. If the carriage does not move, open the gate valve and
riage. Raise and lower the load several times. Lower the check the movement again. If the carriage lowers when
load and tilt the mast forward and backward several the gate valve is open, check for leaks in the hydraulic
times. Check for leaks. lines and fittings. If no leaks are found, the main control
26
valve can be worn or damaged. Remove the load from b. Slowly tilt the mast backward until one rod end just
the forks. contacts the spacer. Add shims to fill the gap at the op-
posite rod end until both rod ends contact the spacers
Check The Tilt Cylinders For Leaks within 0.5 mm (0.02 in).
1. Put a capacity load on the forks. Use a safety chain to c. After the adjustments are complete, tighten the
hold the load to the carriage. Raise the load approxi- capscrews on the rod ends.
mately 2.5 m (8 ft). Put the mast in a vertical position. d. Tilt the mast fully backward and measure the tilt
angle. (See Nameplate for tilt angles.) If necessary,
2. Measure the distance that the rod for the tilt cylinder
add an equal number of shims to both rods for the cor-
extends from the shell. Check the distance the rod
rect angle.
moves in five or ten minutes. The maximum tilt rate
with the oil at 20°C (68°F) is 1.0 mm/min (0.04 in/min).
The maximum tilt rate with the oil at 60°C (140°F) is 6.8 1
mm/min (0.30 in/min). 2 3
4
3. If the tilt rate is greater than the specifications, lower
5
the mast and remove the load from the forks. Install a
valve between the port at the front of the tilt cylinder and
the hydraulic line. Put the load on the forks again. Close
the valve. Tilt the mast forward just past the vertical
position. If the mast continues to tilt slowly forward, the
seals on the piston are leaking. 2
4. If the mast does not move, open the gate valve and
check the movement again. If the mast moves forward
when the gate valve is open, check for leaks in the hy-
draulic lines and fittings. If no leaks are found, the main
control valve can be worn or damaged. Remove the load
from the forks when the checks are complete.
3. Adjust the lift chains at the outer weldment so that the FIGURE 28. ADJUST THE LIFT CHAINS
top of the second intermediate weldment is even with During assembly, the shim arrangement will be approxi-
the top of the outer weldment within 1.5 mm (0.06 in). mately the same as before disassembly. Check the clear-
ance and adjust for wear or change because of repairs.
4. Adjust the lift chains at the first intermediate weld-
ment so that the top of the inner weldment is even with 1. The load rollers control the alignment of the weld-
the top of the outer weldment within 1.5 mm (0.06 in). ments. The alignment conditions are given on a list be-
low with the most important condition first. See
5. When the chain adjustments are complete, make sure FIGURE 29.
that the threads on the nuts of the chain anchors are com- a. The weldments must be parallel to each other.
pletely engaged. Make sure that all of the adjustment is
b. Use shims to adjust the load rollers so that there is
not removed from the chain anchors. The chain anchors
zero clearance between the load roller and the channel
must be able to move in their sockets.
at the point of tightest fit.
6. Check the clearance of the carriage when the mast is c. The number of shims under a load roller must be
fully extended. The carriage stops must not touch the approximately the same as the stub shaft in the oppo-
stop on the top crossmember of the inner weldment. The site side of the weldment. The weldments will be ap-
chains are too tight if the carriage touches the proximately in the center.
crossmember.
2. Do the following steps to adjust the mast load rollers:
7. Lower the mast completely and put a capacity load on a. Use a crowbar to move the weldments from side
the forks. Tilt the mast fully backward and do Step 2 to side to measure the movement. Measure the
again. movement in a minimum of three different posi-
tions of the weldments.
MAST ADJUSTMENTS (See FIGURE 29.)
b. Separate the mast weldments and change the
NOTE: Shims are installed on both sides of the load shim arrangements as required. Assemble the
rollers. Do not add or remove shims from the stub shafts. weldments. Slide the weldment all the way to the
To change the position of the roller on the stub shaft, top and bottom to find the tightest fit.
28
c. Repeat Steps a and b until there is zero clearance there is less than 0.8 mm (0.030 in) at the tightest fit. See
at the point of the tightest fit. FIGURE 29.
d. Measure the distance between the channels of the CARRIAGE ADJUSTMENTS
weldments on the top and bottom. Change shims (See FIGURE 29.)
to keep the distance equal between the top and 1. Install the six load rollers on the carriage. Install the
bottom so that the mast weldments are parallel. shims for the rollers in the same sequence on the stub
Also make sure that the weldments are parallel shaft before disassembly.
within 1.5 mm (0.060 in).
2. Use a lifting device to raise the carriage up the inner
3. Adjust the strip bearings. See FIGURE 30. Insert channel. Find the point of tightest fit between the load
shims under the strip bearing. Adjust the clearance until rollers and the inner channels.
6
1
7
2
9
10
3
11
4 5
5 8
8
29
3. Remove the carriage from the mast. Adjust the shim within +1.5 mm (0.060 in.
arrangement for each roller for clearance between the
5. After adjustment, lubricate the channels with a thin
roller and the inner channel. Repeat Steps 1 and 2 until
layer of grease. Adjust the hydraulic hoses and make
there is zero clearance at the point of tightest fit.
sure the connections are correct if the carriage is
equipped with hydraulic attachments.
4. Keep the shim arrangement on each side of the car-
riage approximately equal. Also keep the shim arrange- CAUTION
ment on each side of the carriage approximately equal. Too much grease will cause the rollers to slide and
The carriage must run parallel with the inner weldment wear flat areas on the rollers.
3
2
3
2
1.STRIP BEARING
2. LOAD ROLLER
3. WELDMENT
4. SHIMS
5. O–RING 1
4
1
4
3
3 3 10106
5
30
TROUBLESHOOTING
PROBLEM POSSIBLE CAUSE PROCEDURE OR ACTION
Slow or no movement of lift Air is in the hydraulic system. Remove air from hydraulic system.
or tilt cylinders. The hydraulic pump is worn or dam- Repair or replace hydraulic pump.
aged.
Restriction in the hydraulic lines. Repair hydraulic lines.
Cylinder seals are damaged. Repair cylinders.
Load is greater than capacity. Reduce load.
Linkage is disconnected or damaged. Repair and adjust linkage for control
levers.
Pressure relief valve(s) is not adjusted Repair or adjust relief valve(s).
correctly or is damaged.
Large leaks between spool and bore. Replace valve section.
Spool is not fully extended or re- Adjust linkage to spool.
tracted.
Rough movement of the mast Air is in the hydraulic system. Remove air from hydraulic system.
assembly. Lift cylinder(s) is damaged. Repair cylinder(s).
Mast weldments are damaged or not Repair or adjust mast weldments.
aligned.
Mast weldments are not lubricated Lubricate mast correctly.
correctly.
Lift or tilt cylinders retract Check valve for the lift spool is dam- Replace check valve.
when the spool is in the NEU- aged.
TRAL position. Cylinder seals have leaks. Repair lift cylinders.
Hydraulic lines have leaks. Repair or tighten lines or fittings.
Leaks between the lift spool and the Replace valve section.
bore.
Tilt cylinders extend when the Cylinder seal have leaks. Repair tilt cylinders.
tilt spool is in the NEUTRAL Oil leaks between control valve spool Replace valve section.
position. and bore.
Hydraulic lines have leaks. Repair or tighten lines or fittings.
31