Professional Documents
Culture Documents
Kunzila Design Report W Supply
Kunzila Design Report W Supply
NOVEMBER.2014
BAHIR DAR
Amhara Design & Supervision Works Enterprise VS Amhara Regional State Water Resource Development Bureau
Table of Contents
Table of Contents ...........................................................................................................i
List of Table .................................................................................................................... iii
List of Figures ................................................................................................................. iii
ACRONYMS AND ABBRIVATIONS .............................................................................iv
EXECUTIVE SUMMARY ................................................................................................... v
1. INTRODUCTION ......................................................................................................... 1
1.1 General .............................................................................................................. 1
1.2 Project Objectives ........................................................................................... 2
2. BACK GROUND .......................................................................................................... 3
2.1 Location ............................................................................................................. 3
2.2 Topography ................................................................................................... 4
2.3 Climate............................................................................................................... 5
2.4 Socio Economic Character .................................................................... 5
2.4.1 Economic Activities in Kunzila Town ................................................ 5
2.5 Infrastructure and Social Service............................................................. 6
2.5.1 Power and Communication ..................................................................... 6
2.5.2 Education .................................................................................................... 6
2.5.3 Health and Hygiene.................................................................................. 7
2.6. Existing Sanitation condition ....................................................................... 7
3. EXISTING WATER SUPPLY SYSTEM ........................................................................... 9
3.1 Existing Water Source ..................................................................................... 9
3.2 Rising pipes ........................................................................................................ 9
3.3 Service Reservoir.............................................................................................. 9
3.4 Distribution ......................................................................................................... 9
3.5 Problems Identified for Kunzila Town Water Supply ............................ 10
3.6 Willingness and ability to pay for improved water supply services 10
4. POPULATION AND DEMAND PROJECTION........................................................ 12
4.1 Population ....................................................................................................... 12
4.2 Design Period ................................................................................................. 12
4.3 Population Forecasting ............................................................................... 12
4.3.1 Growth rate ................................................................................................. 13
4.4 Future Water Demand ................................................................................. 13
4.4.1 Domestic water demand (Dwd) ................................................................ 14
4.4.1.1 Growth of Domestic Water Demand .................................................... 14
4.4.1.2 Population distribution by Mode of services ........................................ 14
4.4.2 Climatic Grouping .......................................................................................... 15
4.4.3 Socio-Economic Adjustment Factor.......................................................... 16
4.4.4 Summary of Projected Population and Growth in Domestic Demand 16
4.4.5 Public demand (Pd)....................................................................................... 17
4.4.6 Animal Demand .............................................................................................. 17
4.4.7 Unaccounted water or Water Loss (UL) .................................................... 17
4.4.8 Variation in demand ...................................................................................... 18
4.4.8.1 Maximum daily demand ........................................................................... 19
4.4.8.2 Peak hour demand ..................................................................................... 19
5. PROPOSED SCHEME DESCRIPTION .................................................................... 21
5.1 General ............................................................................................................ 21
List of Table
List of Figures
Figure 2.1 Project Location ............................................................................................................ 3
Figure 2.2 Topography of Kunzila Town ...................................................................................... 4
Figure 5.1 Layout of Proposed Scheme ................................................................................... 21
Annex A ............................................................................................................................................. 44
ANNEX B ............................................................................................................................................. 55
ANNEX C ............................................................................................................................................ 88
EXECUTIVE SUMMARY
The overall objective of this project is to design and implement sustainable water
supply system improving the quantity, quality and level of service of project area
communities.
In Kunzila town, there is one Full cycle Elementary school (1-8) and one High School.
Besides, there is one health center. Eventhough all of them have connected to the
existing system, the limited source capacity affects their working system.
The new project is designed for 15 years design period /2016 to 2030/. The report
comprises the outcomes of study and design of water supply system including the
existing systems.
According to the socioeconomic data, the base population that the project
comprises is 6,773 (2006 E.C). Population projection has been made based on
geometric increase method and is estimated to be 12,516 at the end of the design
period.
Demand projections were also made throughout the design periods. The major
modes and levels of services considered are public fountains/PF/, yard
connections/YC/ and House Connections/HC/. Hence, the maximum day demand
and peak hour demand at the end of design period is calculated to be 8.87 and
13.64 l/s respectively.
The water source for water supply is borehole located at about 2km from the town
in south east direction with estimated yield of 60 l/s. The maximum day demand at
the end of the design period is calculated to be 8.87 l/s, when adjusted for 14 hrs
pumping period the pumping discharge is 15.20 l/s. This signifies that the source is
more than to satisfy the community water supply fully throughout the design
period.
The proposed water supply structures for this project are elevated RCC service
reservoir (100m3), Public fountains (3 new + 7old need maintenance), Road
crossings structures and Generator with operation room. Water from the well is
pumped to the service reservoir and then distribute by gravity to the system.
The rising main (from source to reservoir) has total length of 1,965m PE 100 PN 16
HDPE pipe with OD 160 mm and total length of the distribution line is 12.248km i.e.
PE 100 PN 10 HDPE pipe.
The major positive impacts of the project are, save time and energy in fetching of
drinking water (especially burden of women and child in fetching of water from
other sources can be reduced), improve water supply coverage, improve health,
life standard and productivities of communities, provide better quality and
sustainable water supply for project area communities, easy control of hazards/like
fire outbreaks/, create job opportunities. To operate the system efficiently and
sustainably management organization set up has been structured.
Based on the inventory during study, degree of problem, economic level and
technical point of view, the community can afford this tariff. Therefore, it can be
concluded that if the project is implemented according to the design with good
financial management and close assistance of client, make feasible and
sustainable.
The estimated Costs for various items of works have been also calculated. The
grand total and investment cost of the project to implement the system is about Birr
7,547,064.28.
1. INTRODUCTION
1.1 General
Access to safe drinking water is essential to health, a basic human right and a
component of effective policy for health protection. Hence, Provision of clean water
supply is one of the major factors that greatly contribute to the socioeconomic
transformation of a country by improving the health thereby increasing life standard
and economic of the productive society. However, most of the developing country
like Ethiopia has still low potable water supply and sanitation coverage that resulted in
citizens to be suffered from water born and water related diseases. In the modern
society, it is a must to build sustainable water supply schemes which can provide
potable water. So per the request of the client, Amhara National Regional State Water
Resource Development Bureau (ANRS WRDB), this study and design report is prepared.
This report presents study and design results of water supply and sanitation for Kunzila
Town in North Achefer Woreda, West Gojjam zone, carried out in accordance with the
scope of works agreed up on between the client, Amhara Water Resource
Development Bureau and consultant, Amhara Design and Supervision Works Enterprise
with main objectives of conducting Detail design study on the Water supply system in
order to improve the living conditions of the population in the study area by
enhancing the level of water supply services in terms of quantity, quality and
accessibility.
Thus, in this report detail descriptions of the major works undertaken are:
∗ General background
∗ Infrastructure and social service
∗ Existing water supply system conditions
∗ Population and water demand
∗ Description of the proposed scheme
∗ Cost estimates of the different parts of the system and Tariff Analysis
This report is prepared based on physical field investigation of pipe route surveying,
assessment of existing system, and necessary data collections, from concerned
governmental organizations and dwellers of the community.
2. BACK GROUND
2.1 Location
The project area, Kunzila town is located in North Achefer Woreda, West Gojjam zone
of Amahara National Regional State, at about a distance of 22 km from woreda
capital town, Liben and accessed by 65 km gravel road in the west direction
branched from Bahir Dar to Addis Abeba Asphalt Road, at about a distance of 136 km
from Bahir Dar. There is 24 hour power supply and mobile telecommunication access.
2.2 Topography
The project area is characterized by flat topography the mean altitude of Kunzila
town is about 1,800 a.m.s.l, it actually varies between 1,780 and 1,820 a.m.s.l.
Reservoir
Borehole
Figure 2.2 Topography of Kunzila Town
2.3 Climate
In general, as per to the Ethiopian temperature zoning, Kunzila town belongs to Weyna
Dega Zone. The average yearly temperature records are b/n 25oc and 28oC, and the
average annual rainfall of the area is recorded to be 1,750mm.
The livelihood of the majority of the population in Kunzila Town is based on farming,
small business service, and government employees.
Table 2.1 Commercial Institution in the town
No. Commercial Institute Unit Amount
1 Trade/ Grain No. 96
2 Small retailer No. 20
3 Local Food house No. 5 with a total of 70 beds
4 Bakery No. 2
5 Local Drink House No. 27
6 Flour Mill No. 3
7 Small Shops No. 28
8 Church No. 2
9 Mosques No. 3
10 Municipality No. 1
11 Schools No. 2
12 Health center No. 1
13 Telecommunication No. 1
14 ACSI No. 1
15 Farmers cooperative No. 1
16 Ethiopian seed enterprise No. 1
In the project area the major ethnic groups – Amhara. When religious diversities are
considered, there are mainly two major branches which are Orthodox 65% , Muslim
30% and the rest 5% others.
The total population size of kunzila town is currently about 6,273, of which 3,090 are
males and 3,183 are females. Furthermore, the households in this town are totally 972.
On the other hand, in kunzila zuria there is a village (Got) called mehalge comprises
totally 500 inhabitants of which 400 male and 100 female . so the total of the
population size the project benefit are exactly 6,773 .
According to the survey, 63% of the population are farmers, 35% trader, 1.5% are
employed in governmental offices and 0.5% of the population are daily labourer.
majority of the population are categorized under middle income level.
2.5.2 Education
In Kunzila town, there is one Full cycle primary /1-8/ school and one High school (9-
10). With regard to water supply, the schools have water supply options even though
it’s not enough and hence students and school staffs are faced with lack of water
which in turn affects the teaching and learning process.
Table 2.2 Educational institution in Kunzila town
No. Educational No of students
Name of school level Male Female Sum No of Total
Staffs
Kunzila full cycle
1 primary school 1-8 753 754 1507 36 1543
kindergarten - 131 99 230 2 232
With regard to water supply system of Kunzila health center, there is connection of
water. But now the water source yield is decreasing through time and can’t satisfy the
demand of the institution. According to the information obtained from health center,
the amount to be obtained from the water connection is not sufficient and needs
other options to be connected to the existing distribution system.
The town health center has documented top-ten- diseases which are mostly prevalent
in the town and its vicinity. Water and sanitation (WATSAN) related diseases ranked
first, second, third, fifth, sixth and ninth.
Table 2. 3 top ten diseases in Kunzila town for the year 2006 E.C
S.No Top ten diseases Remark
1 AFI WATSAN related
2 Helmentiasis WATSAN related
3 URTI WATSAN related
4 Pneumonia
5 Malaria WATSAN related
6 Diarrhea WATSAN related
7 Trauma
8 Dyspepsia
9 Dysentery WATSAN related
10 Diseases of MSS
Adequate provision of sanitary facilities such as both private and public toilets,
properly sited, carefully made and managed solid waste disposal facilities will reduce
the spread of contagious diseases and will also make the town clean and attractive.
As observed during study, most of dwellers around 900 households have private pit
latrine in addition to 3 public latrines even though there is no enough water access for
these facilities.
3.4 Distribution
According to the information obtained from the water service committee, the
distribution network of Kunzila town is GI(GS) pipes with sizes ranging from 2'' to 1 1/2''.
However, the committee didn't have documented data for the detail information
about the total layout of the distribution systems i.e the information of the pipe size,
length and even the routes are not documented and found difficult to identify. The
system serves for the previous 19 years and seems old age. The distribution network
doesn’t cover the whole area of the town.
The town has a total of 240 yard tap customers at the time of the field survey (year
2014). There are also 7 public fountains which 4 of them are operational. The rest 3 are
not functional as the limited water pressure couldn't reach. If the faucets of all public
fountains are maintained, the structure of the water points are in good condition and
can be incorporated in the new system.
3.6 Willingness and ability to pay for improved water supply services
Willingness to pay describes the readiness to spend a certain amount of money for a
commodity or service, while ability to pay describes the affordability with regard to the
monetary resources of the household.
With regard to water supply there are several reasons why people would be ready to
pay increased prices:
The recently approved and implemented water tariff in kunzila town is 5.00 birr for all
users except public tap users which is 0.20 cents for one jerican or 20 liters.
Current discussions with the Community Representatives revealed that the majority of
the population considers the present situation of the town water supply service is
unsatisfactory. Most inhabitants of town would be willing and ready to accept a
certain increase in prices for a reliable and good quality water supply.
4.1 Population
Even though, the central statistics Authority (CSA) is recognized body in Ethiopia to
determine the official population figures and growth rates that should be taken for
any development activity throughout the country, Town Administrator and
concerned woreda professionals also count population periodically. The data
obtained from Woreda Water Resource development office is tabulated in the
following table.
Generally the design period of water supply system is determined by considering the
following facts: -
∗ The trend of water demand
∗ The Prospect of securing water resources
∗ Funds available for the construction of the project
∗ The serviceability of facilities/Economic life of facilities
∗ Rate of interest on the loans taken to complete the project
∗ Anticipated Rate of the population
Kunzila is a developing town and based on the aforementioned controlling factors,
15 years design period is considered.
After the design period has been fixed, the population of the study area in various
periods has to be determined.
For the purpose of this design, rural growth rates for Amhara region as determined by
CSA are used for population projection. For such developing towns, population
geometric progress method is used to forecast the population at the end of 15 years.
Where:
Pn= population at the target year
Pp = present population (6,773)
r = Annual growth rate in%
n = design period, in year (15 yr)
Source: The 1994 population and housing census of Ethiopia, Result at country level,
Volume II Analytical Report, June 1999
There for the projected population at the end of the design year (2030) is 12,516.
The major types of water consumptions, modes and levels of services for Kunzila Town
Water Supply system, are estimated based on MoWR design guide lines. The results of
analysis made to project water consumption modes and percapita water
consumptions considered for Kunzila Town water supply system design purpose are
discussed below.
assumed water demand to grow at growth rates of 1% per annum for public fountains
/PF/ and 2% per annum for yard and House connection users.
Table 4. 4 Projected Average Per Capita domestic Water demand
Year
Demand Category 2016 2020 2025 2030
HTU 50 54.12 59.75 65.97
YTU 30 32.47 35.85 39.58
PTU 20 20.81 21.87 22.99
The mean altitude of Kunzila town is about 1,800 a.m.s.l, it actually varies between
1,780 and 1,820 a.m.s.l. Therefore an adjustment factor of 1.0 to refine the average per
capita domestic water demand is considered.
Losses as % of Production
water losses, considered for 2016, 2020, 2025 and 2030 are 40%, 35%, 30% and 27.5%
respectively.
Therefore, Maximum day factor of 1.3 and Peak hour factor of 2 are adopted for
economical design of this water supply system.
Table 4.13 Summery of water demand projection
Year 2014 2016 2020 2025 2030
Population 6,773 7,368 8,620 10,387 12,516
Domestic Demand (m3/d) 162 201 275 379
Public Demand (m3/d) 35.7 44.2 60.4 83.4
Average Day Demand (m3/d) 197.8 245.1 335.1 462.2
Losses in the system 79.1 85.8 100.5 127.1
Total Average Day Demand
m3/d 276.9 330.9 435.6 589.3
l/s 3.20 3.83 5.04 6.82
Maximum day demand
Max day Coefficient 1.30 1.30 1.30 1.30
m3/d 359.92 430.21 566.34 766.15
l/s 4.17 4.98 6.55 8.87
5.1 General
A design period of 15 years in one phase is considered for the design of the proposed
scheme as it is small town water supply system. The proposed water supply structures
for kunzila town are pipe line installation, service reservoir and public fountains. Water
from the borehole is pumped to the 100m3 elevated service reservoir and distribute by
gravity to public fountains and water taps. These structures are to be constructed at
selected sites and fenced properly.
The source of water supply system for this project is a borehole which is situated at
around 2km from center of the town at UTM location of E-286145.568, N-1311834.143
and Elevation of 1805.865m a.m.s.l.
Head loss
Friction losses
The size of the rising main is calculated by using the empirical formula developed for
fixing an economical pipe diameter, as shown below.
D= 0.97√Q to 1.22 √Q
Where Q = 0.0152 m3/sec
As per the analysis from the hydraulic calculation summary, the maximum pressure at
minimum demand is 35.9 mH2o. Therefore, due to the suitability of the soil and
topographic nature PE 100 PN 10 HDPE pipe in the distribution network is proposed.
Table 5. 2 Summary of Pipe Diameter and Length
Diameter Diameter Pipe type
/OD/ /Internal/
S/N (mm) (mm) Length (m)
1 125 110.2 266
2 110 96.8 1,151
3 75 66 980 PE 100
4 63 55.4 891 PN 10
5 50 44 6,796 HDPE Pipe
6 40 32.6 1,936
7 32 26 229
Total 12,248
The hourly variation coefficients stated in the design criteria has been used in
determining the capacity of the reservoir. Capacity of reservoir is determined using
simplified empirical method commonly practiced in many water supply projects for no
previously recorded hourly variation data. This is simply one third of the maximum day
demand at the end of design period.
Capacity of Reservoir = 1/3*maximum day demand at the end of design period.
= 1/3*766 m3/d
= 255m3
Accordingly, in addition to the 45m3 existing reservoir, construction of 200m3 capacity
new reservoir needs to meet the design period demand. However, the ground
topography of the reservoir site is not enough to give good water pressure for all the
project areas. As such, 13m elevated 100m3 RCC circular reservoir above the normal
ground level is proposed at the UTM location of E- 285847.84, N- 1313768.889 and
elevation of 1812.577m. The new reservoir is located besides to the existing reservoir
and the overflow of the new will be connected to the inlet of the existing. The outlets
of the two reservoir will be connected with Tee and then to the HDPE distribution line.
The storage capacity of the two reservoir will be145m3. An additional 100m3 elevated
reservoir is proposed to construct in phase II (2025).
5. 7 Pumps
The primary function of a pump is to add hydraulic energy to certain values of fluid. A
pump serves to transfer energy from a power source to a fluid, thereby creating flow
or simply creating greater pressures on the fluid.
Many types and sizes of pumps are available ranging a power from fraction of horse
power to several thousand horse power.
In the selection of particular type of pump, the capacity, reliability, cost, power,
maintenance and efficiency factors are taken to account.
In this case Water from the BH directly lifted by the submersible pump to 100m3
elevated service reservoir. The pumps are designed for the end of the design period
(2030) to work 14 hrs each in one day in an average of 15.20 l/s with a head of 131
mH2O. The Pumping station is located near to the BH, i.e. 4m next to the BH in the
direction of Rising main.
NB. The Particular Technical Specification for Submersible Pumps are attached in
the ANNEX.
For institutions such as Mosque, Gedam, Church, Health centre, and Agricultural
Bureau, eight single water taps are proposed for each.
The locations of the new public fountains are decided together with the presence of
town's water committee and dwellers.
The public fountains are designed in such a way that users of various water fetching
types like Jerican, and barrel could easily be served.
5.16 Disinfection
All water supplies should be disinfected in order to protect public health. Disinfections
inactivates any remaining bacteria in the water after previous treatment steps and
provides a residual disinfectants to inactivate bacteria introduced by any
subsequent entrance of contaminated water during storage or distribution. Hence all
water supplied through distribution system should be disinfected to provide a residual
disinfectant, which provides ongoing protection from bacterial growth and survival.
At present, the principal disinfectant used worldwide is chlorine. Chlorine in its various
forms is invariably and almost universally used for disinfecting public water supplies. It
is cheap, reliable, easy to handle, easily measurable, and above all, it is capable of
providing residual disinfecting effects for long periods, thus affording complete
protection against future recontamination of water in the distribution system. Its only
disadvantage is that when used in greater amounts, it imparts bitter and bad taste to
the water, which may not be liked by certain consumers.
Generally chlorine gas and chlorine compounds are used to disinfect water before
distribution. Chlorine gas needs more expensive feeding equipment, difficult to
operate & maintain, and requires skilled supervisor so, use of chlorine compounds is
preferred to chlorine gas. Among the chlorine compounds, calcium hypochlorite is
selected to sodium hypochlorite, as the available chlorine in calcium hypochlorite is
greater.
The calcium hypochlorite solution will be prepared in a tank provided with motor
driven paddles to thoroughly mix the chemical. The solution will then be directed to a
constant head regulator to keep constant head then will be dosed in to the clean
water reservoir through plastic tube fitted with flow regulating tap. Two solution tanks
with mixers will be employed to ensure uninterrupted operation while one tank is
being filled for solution preparation.
This chlorine dosing facilities will be installed at the top of the clean water reservoir.
The equipment will be provided with simple shade to protect it from the attack of
direct sunlight and rain.
6.1 Introduction
Environment is a system which consists of Hydrological, Biophysical, Atmospherically,
Cultural and Social condition. EIA provides the answer for impact during construction
and after construction. It is used as an instrument for sustainable development by
minimizing the adverse effects and maximizing the benefits that is obtained as result
of the project. In addition to these it identifies the problems which exist in the
environment and select alternatives that mitigate the impact.
Water supply service is a mechanism that delivers adequate, clean and safe water
to a community according to their present and forecasted demand. Presently this is
one of the characteristics of this water supply project. The abundant quantity with
high storing capacity as build from locally found materials to supply adequate safe
and clean water at proximal delivery distance to the user with cost effective and
efficient operation mechanism are some of the principles in the water supply.
Environmental study shall respect these principles to conceive a mitigation measure
and devise a monitoring plan.
The main mission of the initial environmental impact examination and evaluation in
this study is needed to assess the existing condition. Furthermore, to observe
preliminary cases and predicted effects that can be noticed due to the project on
natural and physical resources and human-environment of the proposed water
supply sites. The observed results will be used in improving the design, decision-
making and community participation to ensure sustainable and environmentally
sound water supply to this town.
Thus, the study will thoroughly focus on existing situations that have impacts on the
project and other likelihood effects or impacts that may arise due to the project on
the immediate sites and on the subsequent water delivering mechanisms to the
beneficiaries. The finding will further enhance the positive impacts and provide
protective devices and mitigation measures for negative impacts. It further assists to
formulate the monitoring and the follow-up procedures for some immediate and
long term adverse effects.
♦ Save time and energy saving in fetching of drinking water. Especially the
burden of women and child in fetching of water from other sources can
be reduced.
♦ Improve the Water Supply and Sanitation coverage
♦ Improve health, life standard and productivity of the communities
♦ Provide better quality and sustainable water supply for project area
communities.
♦ Easy control of hazards (like fire).
♦ Create job opportunities
There is no as such considerable negative impact in this rural piped water supply and
sanitation project. But some of expected impacts are:
♦ Disturbance of a small amount of agricultural land and vegetations during
laying of pipelines.
♦ land Loss of farmers for construction of public fountain
Most of the negative impacts caused by the project are accomplished in the
construction period of pipe laying .This can be reduced by proper planning of the
7.1 INTRODUCTION
Most water supply schemes in our region suffer from sustainability due poor
Managemental system right from the beginning till the final operation stage. To
alleviate the problem the Federal and Regional Governments issued Policies and
regulations to upgrade and improve the institutional and technical capacity of those
major actors in the sector. This section of the document is intended to prepare
Management Models and Organizational structure for Kunzla town water supply
system to operate efficiently and sustainably.
Town Water
Board
Manager
Secretarial
typist
Generator
Accountant Casher Plumber Tap attendant Guard
operator
Water sellers
As can be seen in the above diagram, a person titled manger is accountable to the
TWB and subordinated by other hired people with different experience and
assignments.
The TWB shall follow and monitor the overall performance of the scheme instead of
taking over other routine activities.
The purpose of the proposed organizational structure is to create the appropriate
institutional framework for effective management and cost recovery as well as close
relation with the community and other stakeholders.
The major organizational units are the following:
♦ Head, Water Service
♦ Customer Relations Service
♦ Audit Service
♦ Administration Service
Functional Responsibilities
The functional responsibilities of the organizational units of the water service are
explained as follows.
The TWB will hold a meeting every month to look at matters and present financial and
other administrative reports to the community. The report consists of all works executed
throughout the reporting period and encountered problems, it can be prepared by
the scheme manger. All community members shall involve solutions to ensure
ownership of the scheme.
7.4. Training
A special initiative is needed to develop the capacity of the TWB, Subordinate staffs
and communities for effective and sustainable management of the town piped water
supply scheme. The approach to capacity building and create awareness on the all
over duties and responsibilities of the communities included in the project will be
during and after implementation and operation.
The esteemed cost doesn't consider the construction cost of the elevated reservoir to
be constructed in phase II.
Table 8. 1 Summary of investment cost
Bill Amount
No Description Unit Quantity (birr)
1 General Items LS 1 538,626.95
Pipes Electro
Electro and mechanic
Civil Pipes and mechani Civil Work fittings al
Year Work fittings cal Total (0.5%) (.2%) (2%) Total
2838.5
2016 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2017 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2018 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2019 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2020 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2021 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2022 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2023 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2024 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2025 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2026 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2027 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2028 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2029 201,038 116,700 80,000 397,737 1005 233 1600 9
2838.5
2030 201,038 116,700 80,000 397,737 1005 233 1600 9
Amount of water
Total Cost Amount of water Water tariff Water tariff
Year produced
(Birr/year) produced m3/day birr/m3 cents/20lit
m3/year
Generally, the inhabitants of kunzila showed a very positive attitude towards the
improvement of water supply facilities. As such most inhabitants of town would be
willing and ready to accept a certain increase in prices for a reliable and good quality
water supply. After considering the willingness to pay options given and their implications the
Consultant has recommended FULL TARIFF. The recommended tariff for Kunzila Town at this
scenario, therefore, is presented below.
Amount of water
Total Cost Amount of water Water tariff Water tariff
Year produced
(Birr/year) produced m3/day birr/m3 cents/20lit
m3/year
• The existing drinking water supply systems of all the villages incorporated in the
project are not satisfactory and sustainable with respect to quality, quantity and
distribution.
• `The Proposed Water Supply Project is therefore, at right time and is expected to
bring an improvement in the public health status, economical productivity,
sanitation conditions and time & energy savings, particularly for women and
children.
• In order to optimize benefits and minimize the negative impacts of the proposed
water supply project, the following measures are recommended:
Annex A
Pressure
Label Easting (m) Northing (m) Elevation (m)
(m H2O)
255 285,111.22 1,313,707.92 1,798.95 26.578
Health Center 285,443.53 1,313,690.23 1,798.95 26.578
Mesjid 3 285,495.06 1,313,693.16 1,798.95 26.576
J-226 285,440.97 1,313,696.39 1,798.95 26.576
168 285,333.77 1,313,692.47 1,798.98 26.545
J-225 285,470.44 1,313,705.27 1,799.01 26.516
J6 285,653.52 1,313,822.72 1,799.13 26.399
J3 285,752.27 1,313,587.49 1,799.13 26.399
227 284,945.55 1,313,618.97 1,799.23 26.297
J10 285,533.77 1,313,579.85 1,799.32 26.211
J9 285,661.07 1,313,690.82 1,799.37 26.16
176 285,262.49 1,313,676.97 1,799.38 26.149
99 285,662.15 1,313,725.88 1,799.38 26.149
94 285,553.04 1,313,571.92 1,799.39 26.133
CROSS T2 285,683.61 1,313,754.24 1,799.43 26.095
J23 285,665.73 1,313,751.77 1,799.45 26.079
189 284,978.94 1,313,613.83 1,799.47 26.06
397 285,711.74 1,313,865.95 1,799.51 26.019
13 285,682.60 1,313,722.12 1,799.57 25.955
413 284,818.19 1,314,083.19 1,799.79 25.738
J2 285,711.71 1,313,844.14 1,799.97 25.559
CROSS T1 285,710.64 1,313,751.38 1,799.98 25.553
Menaheriya new WPT 285,728.65 1,313,845.09 1,800.11 25.417
J18 285,615.28 1,313,239.82 1,800.36 25.168
443 285,875.91 1,312,806.79 1,800.61 24.922
371 285,507.06 1,313,363.71 1,800.69 24.845
190 284,936.92 1,313,599.53 1,800.77 24.759
457 286,447.13 1,312,253.12 1,800.79 24.74
452 286,382.95 1,312,315.18 1,800.90 24.631
EWPT 2 285,157.17 1,313,566.32 1,800.97 24.561
445 286,007.34 1,312,678.51 1,801.08 24.453
191 284,971.70 1,313,592.16 1,801.10 24.436
138 285,412.08 1,313,397.33 1,801.14 24.396
144 285,430.68 1,313,383.62 1,801.20 24.33
450 286,276.74 1,312,416.49 1,801.23 24.299
EWPT 8 285,570.35 1,313,208.95 1,801.25 24.281
Pressure
Label Easting (m) Northing (m) Elevation (m)
(m H2O)
449 286,205.31 1,312,484.33 1,801.30 24.235
460 286,562.84 1,312,109.48 1,801.47 24.061
J11 285,138.30 1,313,500.30 1,801.49 24.037
J12 285,149.51 1,313,518.18 1,801.55 23.98
Mirt Zer Faucet 285,710.27 1,312,901.83 1,801.81 23.724
281 285,272.75 1,313,386.68 1,801.84 23.692
215 285,358.11 1,313,343.30 1,801.88 23.653
Road Crossing 1 285,288.89 1,313,404.03 1,801.97 23.558
447 286,098.03 1,312,589.76 1,802.04 23.494
462 286,625.22 1,311,974.54 1,802.07 23.466
256 285,292.32 1,313,349.93 1,802.08 23.456
J17 285,715.92 1,312,862.22 1,802.10 23.438
J15 285,359.81 1,313,310.39 1,802.11 23.419
293 285,506.37 1,313,141.24 1,802.12 23.418
294 285,497.12 1,313,128.64 1,802.12 23.409
J-249 286,639.04 1,311,854.10 1,802.15 23.379
464 286,640.46 1,311,837.77 1,802.18 23.358
441 285,711.35 1,312,825.54 1,802.24 23.294
428 285,726.56 1,312,829.08 1,802.24 23.292
424 285,657.79 1,312,941.04 1,802.27 23.262
Mehalge NWPT 3 286,623.09 1,311,852.50 1,802.32 23.212
Road Crossing 2 285,343.89 1,313,301.04 1,802.34 23.198
425 285,668.14 1,312,956.30 1,802.34 23.198
426 285,687.41 1,312,886.17 1,802.39 23.147
260 285,288.58 1,313,304.87 1,802.41 23.12
J16 285,697.48 1,312,901.19 1,802.51 23.019
418 284,643.77 1,314,152.08 1,803.08 22.455
EWPT 6 285,279.80 1,313,250.55 1,803.16 22.376
J13 285,275.73 1,313,255.84 1,803.29 22.245
264 285,259.37 1,313,268.67 1,803.68 21.857
414 284,691.14 1,314,131.14 1,805.53 20.01
Mesjid 2 285,836.43 1,313,969.52 1,806.00 19.541
H. School NWPT 1 284,799.65 1,313,284.00 1,807.65 17.898
276 284,969.52 1,313,050.43 1,808.10 17.449
275 284,984.21 1,313,032.95 1,808.42 17.125
ANNEX B
BILL OF QUANTITY
FOR
KUNZILA TOWN WATER
SUPPLY PROJECT
Table 1. Cost Summary for Kunzila Town Water supply Project Supply and Installation
Sub Total
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
Subtotal
2.2 FITTINGS
PE 100 PN 10 HDPE CROSS Tee (mm x mm x mm
2.2.1
x mm)
2.2.1.1 OD 50 x 50 x 50 X 50 1
2.2.1.2 OD 125 x 125 x 125 X 125 2
Subtotal
PE 100 PN 10 HDPE Reducer Tee (mm x mm x
2.2.2
mm)
2.2.2.1 OD 110 x 75 x 110 No. 3
2.2.2.2 OD 75 x 50 x 75 No. 3
2.2.2.3 OD 75 x 63 x 63 No. 1
2.2.2.4 OD 63 x 50 x 63 No. 2
2.2.2.5 OD 50 x 40 x 50 No. 4
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
2.2.2.6 OD 110 x 50 x 110 No. 1
2.2.2.7 OD 50 x 32 x 50 No. 2
2.2.2.7 OD 75 x 40 x 75 No. 1
2.2.2.7 OD 75 x 32 x 75 No. 1
2.2.2.7 OD 63 x 40 x 63 No. 2
Subtotal
2.2.3.2 OD 40 x 40 x 40 No. 1
2.2.3.3 OD 50 x 50 x 50 No. 4
2.2.3.4 OD 75 x 75 x 75 No. 2
Subtotal
2.2.3 PN 10 PVC Ball gate Valve
2.2.3.1 4" x 4" No. 2
2.2.3.2 2 1/2" x 2 1/2" No. 5
2.2.3.3 2" x 2" No. 3
2.2.3.4 1 1/2" x 1 1/2" No. 1
Subtotal
2.2.4 PE 100 PN 10 HDPE End Cap
2.2.4.1 OD 50 mm No. 10
2.2.4.2 OD 40 mm No. 5
Subtotal
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
2.2.5.5 Reducing Nipple 1 1/2" x 1" No. 10
2.2.5.6 Reducing Nipple 2" x 1" No. 10
2.2.5.7 Reducing Nipple 2" x 1 1/2" No. 10
Subtotal
Subtotal
2.2.7.3 75 x 75 mm No. 20
2.2.7.4 63 x 63 mm No. 9
2.2.7.5 50 x 50 mm No. 68
2.2.7.6 40 x 40 mm No. 19
2.2.7.7 32 x 32 mm No. 2
Subtotal
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
2.2.8.5 75 x 40 mm No. 1
2.2.8.6 63 x 40 mm No. 1
2.2.8.8 63 x 50 mm No. 2
2.2.8.9 75 x 63 mm No. 1
2.2.8.10 75 x 50 mm No. 3
2.2.8.12 50 x 40 mm No. 5
2.2.8.13 40 x 32 mm No. 1
Subtotal
2.2 0.45x0.45 RCC columns Grade C-25 for elevated concrete m3 15.19
reservoir
2.3 Bottom, intermediate and top beams Grade C-25 m3 12.29
2.4 Bottom slab for reservoir RCC 20cm thick with Grade C-30 m3 8.14
2.6 15 cm thick RCC cover slab for reservoir with Grade C-25 m3 6.1
3 Form work
3.1 Base & top Slab m2 72
3.2 Wall m2 146
3.3 Columns m2 159.3
3.4 beams m2 91
3.5 Footings m2 24
4 Reinforcement bars according to the drawing
5.6 Provide and install water stopper made of synthetic pvc m2 22.3
Sub total
6 Provide and install the following pipes and fittings
6.1 Inlet Pipe
6.1.1 DN 150 flanged DCI pipe m 16
6.1.2 DCI DN 150mm flanged elbow No. 2
6.1.3 Butt Weld Stub flange with back ring size 160 PN 10 No 1
6.1.4 Pipe Clamp to the wall/column of the reservoir No 3
Sub total
6.2 Over Flow & drain pipe
6.2.1 GI, DN 4” pipe m 24
6.2.2 GI Gate valve, DN 4” no. 1
6.2.3 GI , DN 4” elbow No 4
6.2.4 Normal tee, DN 4” No. 1
6.2.5 GI DN 4”, union No. 2
6.2.6 Pipe Clamp to the wall/column of the reservoir No 3
Sub Total
Sub Total
7.1.6 Caraway the excavated materials not more than 50m m³ 11.42
7.2.1 masonry work with 1:5 cement/sand mortar below ground m³ 7.08
7.3.5 Formwork
7.3.6 Formwork columns, beams and lintels m² 13.04
7.3.7 Reinforcement bars
a. Diameter 10 mm deformed bar kg 179.1
b. Diameter 6mm deformed bar kg 41.6
7.4 Roofing
Supply and install light fittings type Philips TMS012 1X36 watt
7.8.3 No 2
or equivalent complete with 36 watt fluorescent lamp
1 Excavation
Amou
Item Unit
Description Unit Qty nt
No. Rat
(Birr)
e
5.3 ø 10 mm Kg 227.04
5.4 ø 12 mm Kg 56.02
5.5 ø 14 mm Kg 63.82
5.6 ø 16 mm Kg 236.17
6 Roofing
8 Painting
Amou
Item Unit
Description Unit Qty nt
No. Rat
(Birr)
e
Metal door size 900x2100mm, SEIKO profile, frame,
9.3 glazing and complete with all accessories as per the no 2
drawing(D2 type)
Metal louvered window size 800x1000mm Seiko profile
9.4 no 3
with frame and screen grilled as per the drawing
Metal window size 1200x1200mm Seiko profile frame,
9.5 no 1
glazing and accessories
Light points fed through 2x1.5 mm² insulated wires in
thermoplastic conduits of Ø13.5 mm diameter including
9.6 no 2
flush mounted switches, wall boxes, insulating cups all
completely wired and ready for use.
Socket points fed through 2x2.5 mm² insulated wired in
thermoplastic conduits of Ø 16 mm diameter including
9.7 no 2
wall boxes, insulating cups and other fixing accessories
all completely wired and ready for use.
Supply and install light fittings type Philips TMS012 1X36
9.8 watt or equivalent complete with 36 watt fluorescent no 3
lamp
0.5m wide semi dressed stone pavement around the
9.9 M2 36
Generator house
Supply and construction of 300mm dia. half ditch
9.10 M 24
concrete around the Generator house
Sub Total
-
10.1.6 Caraway the excavated materials not more than 50m m³ 11.42
10.3.5 Formwork
10.3.6 Formwork columns, beams and lintels m² 13.04
10.3.7 Reinforcement bars
a. Diameter 10 mm deformed bar kg 179.1
b. Diameter 6mm deformed bar kg 41.6
10.4 Roofing
Eucalyptus truss complete as shown on the drawings,
span approx. 3600mm including 70 x 50 ZIGBA purling,
10.4.1 no 4
200 x 25mm fascia board, fittings and fastenings: 1.2 m
c/c
Sub Total
Unit
No. Descriptions Unit Quantity Amount
Rates
1 Earth Work
Clearing and removal of top soil to an
1.1 m2 42.2
average depth of 20cm
Bulk excavation for foundation to a depth
1.2 m3 20
not exceeding 500mm
Cart away surplus excavated material to a
1.3 m3 20
distance not exceeding 1000m
Supply and place 250mm thick trachytic
1.4 m2 10
hardcore blinded with crushed aggregate
Supply and install half concrete pipes DN
1.5 300mm for surface drainage around water m 23.2
point stand
Sub Total
2 CONCRETE WORK
Unit
No. Descriptions Unit Quantity Amount
Rates
Hard trachytic or equivalent stone masonry
5.1 water point wall grouted and filled with 1:3 m3 2.85
mortar
400mm thick trachytic stone or equivalent
5.2 m3 0.58
manhole walls grouted in 1:3 mortar
Sub Total
6 FINISHING WORK
Three coats of plastering to internal walls of
6.1 m2 2.52
manhole, using 1:3 mortar
Pointing stone masonry wall of water point
6.2 m2 8.04
with rich mortar
6.3 30mm thick sand and cement floor screed m2 22.5
Sub Total
7 PIPES AND ACCESSORIES
7.1 G.S pipe 1'' of class 'B' Type M 12
7.2 G.S pipe 1 1/2'' of class 'B' Type M 12
7.2 Elbow 90 deg. dia. 1” pcs 5
7.3 Reducer dia. 1"x3/4" pcs 4
7.4 Tee dia. 1” pcs 3
7.5 Coupling (socket) dia. 1” pcs 4
7.6 Faucet dia. ¾” pcs 4
7.7 Water Meter dia. 1” pcs 1
7.8 Gate Valve dia. 1” pcs 1
7.9 Nipples dia 1 ½” pcs 3
7.1 Nipples dia 1” pcs 4
7.11 Union dia 1 ½” pcs 1
7.12 Union dia 1” pcs 2
7.13 Male Adator 1 ½” pcs 1
7.14 Female Adator 1 ½” pcs 1
subtotal
8 FENCE WORK
Barbed wires fencing consist of 2.5 mm
thickness wire horizontal and diagonal
member fixed to 2100 mm long angle iron
8.1 m 26
50mm*50mm with 5mm thickness anchored
with concrete posts spaced every 2000mm,
including lock and all necessary material as
Unit
No. Descriptions Unit Quantity Amount
Rates
per the drawing.
8.2 Supply and construct RHS framed type II gate
as per the drawing including lock with its all
accessory No. 1
Sub Total
9 masonry Valve chamber construction as
shown in the drawing including metal sheet
for manhole cover with thickness 4mm with
all accessory including lock. No 1
Sub Total
Total Sum
Total for 3 new Water Points
10 Maintenance Public Fountain
Unit
No. Descriptions Unit Quantity Amount
Rates
10.1 Earth Work
Supply and install half concrete pipes DN
10.1.1 300mm for surface drainage around water m 23.2
point stand
Sub Total
10.2 PIPES AND ACCESSORIES
10.2.1 G.S pipe 1 1/2'' of class 'B' Type M 12
10.2.2 Coupling (socket) dia. 1 1/2” pcs 4
10.2.3 Faucet dia. ¾” pcs 4
10.2.4 Water Meter dia. 1 1/2” pcs 1
10.2.5 Gate Valve dia. 1 1/2” pcs 1
10.2.6 Nipples dia 1 ½” pcs 3
10.2.7 Nipples dia 1 1/2” pcs 4
10.2.8 Union dia 1 ½” pcs 1
10.2.9 Union dia 1 1/2” pcs 2
10.2.10 Male Adaptor 1 ½” pcs 1
Unit
No. Descriptions Unit Quantity Amount
Rates
Barbed wires fencing consist of 2.5 mm
thickness wire horizontal and diagonal
member fixed to 2100 mm long angle iron
10.3.1 50mm*50mm with 5mm thickness anchored m 26
with concrete posts spaced every 2000mm,
including lock and all necessary material as
per the drawing.
10.3.2 Supply and construct RHS framed type II gate
as per the drawing including lock with its all
accessory No. 1
Sub Total
10.4 Valve chamber
10.4.1 masonry Valve chamber construction as
shown in the drawing including metal sheet
for manhole cover with thickness 4mm with
all accessory including lock.
No 1
Sub Total
Total Sum
Total for 7 Water Points
11 Single Faucet Water Taps for Public Institutions
Unit
No. Descriptions Unit Quantity Amount
Rates
11.1 PIPES AND ACCESSORIES
11.1.1 G.S pipe 1'' of class 'B' Type M 2
11.1.2 Elbow 90 deg. dia. 1” pcs 2
11.1.3 Reducer dia. 1"x3/4" pcs 1
11.1.4 Coupling (socket) dia. 1” pcs 1
11.1.5 Faucet dia. ¾” pcs 1
11.1.6 Water Meter dia. 1” pcs 1
11.1.7 Gate Valve dia. 1” pcs 1
11.1.8 Nipples dia 1” pcs 1
11.1.9 Union dia 1” pcs 2
subtotal
Unit
No. Descriptions Unit Quantity Amount
Rates
Total of 8 Single Water Taps
Total Sum
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
1 Earth work
1.1 Excavation for pipe trench 0.9m*0.6m m3 6613.92
Subtotal
Subtotal
2.2 FITTINGS
PE 100 PN 10 HDPE CROSS Tee (mm x mm x mm
2.2.1
x mm)
2.2.1.1 OD 50 x 50 x 50 X 50 1
2.2.1.2 OD 125 x 125 x 125 X 125 2
Subtotal
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
PE 100 PN 10 HDPE Reducer Tee (mm x mm x
2.2.2
mm)
2.2.2.1 OD 110 x 75 x 110 No. 3
2.2.2.2 OD 75 x 50 x 75 No. 3
2.2.2.3 OD 75 x 63 x 63 No. 1
2.2.2.4 OD 63 x 50 x 63 No. 2
2.2.2.5 OD 50 x 40 x 50 No. 4
2.2.2.7 OD 50 x 32 x 50 No. 2
2.2.2.7 OD 75 x 40 x 75 No. 1
2.2.2.7 OD 75 x 32 x 75 No. 1
2.2.2.7 OD 63 x 40 x 63 No. 2
Subtotal
2.2.3.2 OD 40 x 40 x 40 No. 1
2.2.3.3 OD 50 x 50 x 50 No. 4
2.2.3.4 OD 75 x 75 x 75 No. 2
Subtotal
2.2.3 PN 10 PVC Ball gate Valve
2.2.3.1 4" x 4" No. 2
2.2.3.2 2 1/2" x 2 1/2" No. 5
2.2.3.3 2" x 2" No. 3
2.2.3.4 1 1/2" x 1 1/2" No. 1
Subtotal
2.2.4 PE 100 PN 10 HDPE End Cap
2.2.4.1 OD 50 mm No. 10
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
2.2.4.2 OD 40 mm No. 5
Subtotal
Subtotal
2.2.7.3 75 x 75 mm No. 20
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
2.2.7.4 63 x 63 mm No. 9
2.2.7.5 50 x 50 mm No. 68
2.2.7.6 40 x 40 mm No. 19
2.2.7.7 32 x 32 mm No. 2
Subtotal
2.2.8.5 75 x 40 mm No. 1
2.2.8.6 63 x 40 mm No. 1
2.2.8.8 63 x 50 mm No. 2
2.2.8.9 75 x 63 mm No. 1
2.2.8.10 75 x 50 mm No. 3
2.2.8.12 50 x 40 mm No. 5
2.2.8.13 40 x 32 mm No. 1
Total
Unit
It.No Description Unit Qty Amount
Price
(Eth.Birr)
Subtotal
SUB TOTAL
3.5 Cable tray, cable trunking, cable supports & cable Set 1
lage etc. as required within of the borehole
compound
SUB TOTAL,
TOTAL
ANNEX C
SURVEYING DATA
1 General
o Submersible pump directly coupled to wet submersible motor for pumping ground
water from deep wells.
o Working temperature maximum above30 0 C (degree centigrade)
o Min permissible sand content of 25mg/l
o Max. external diameter of pump including motor over the cable should be less than
the diameter of the well casing at least by 2’’
2 Motor
o Submersible wet type motor adequate power
o Voltage three phases, 380/400v 50HZ
o Designed as to facilitate rewinding infield work shop
o Over load margin over rated HP by about 1.1% times
o Three phase induction motor
o Squirrel cage rotor
o RPM-2900
o Starting can be direct on line for motors less than 7.5kw, for pumps having the
capacity up to 50kw Auto Transformer and above 50KW Star-Delta type of starting.
o Motor shaft body should be made of stainless steel.
3 Pump
o Multistage, centrifugal radial type or centrifugal mixed flow type
o Impellers, diffusers, shaft and pump body should be made of stainless steel
o Stainless steel impellers statically and dynamically balanced
o Non return valve at the out let.
o Stainless steel strainer at pump suction
o Screwed connection for riser pipes up to four inch and flange connection for riser
pipes above four inches.
o Motor cable protection on the pump body
o The pump size in diameter includes the pump, cable and cable guard.
4 Clamp
• The clamps should have at least 2’’ extra length from the permanent surface
casing diameter on both sides accordingly
For wells with 12’’ production casing permanent surface casing is 14’’
For wells with 10’’ production casing permanent surface casing is 12’’
For wells with 8’’ production casing permanent surface casing is 10’’
• The thickness & strength of the clamp should be designed to carry the load/ weight
of the pump & the riser pipe column full of water
o One or two, according to a number of cable core, jointing kit with quick drying
epoxy resin compound.
8 Technical Information
o The technical information should include but not limited to
o Pump discharge and total head.
o Complete pump performance at duty point and at different heads and discharge.
o Pump HP or KW
o Pump efficiency at 0.7 power factor (lagging)
o Number of stages and total length of pump and motor
o Pump over cable and motor diameter
o Pump out let connection diameter
o Type of impeller
o Impeller pump shaft, motor and pump casing material
o Size of submersible cable
o Make and type of starter
o Control panel box full details (wiring diagram and spare list)
o Impeller vane thickness, number of vane, vane angle at inlet and outlet of typical
stage.
o Other relevant information.
2. Generator
This specification shall be taken as standard, for an internal combustion engine as
prime mover diesel generating sets
2.1 Engine (Fundamental)
The engine shall be capable of operating at its rated speed loaded to its rated
capacity on hazardous working environment up to altitudes of 2300 meter, at ambient
air temperature and relative air humidity variations specified in art.1-2 without
evidence of ever loading the capacity of the engine.
2.2 Horse Power
The required minimum Brake Horse BHP, as per ISO standard power specified for the
respective equipment in sec. 2 shall be delivered by the engine at the flywheel at its
rated speed at standard reference at condition with all required accessories.
The rating of the engine bid upon should be specified in accessories with ISO standard
power. If other standards are taken the following points should be specified clearly.
The engine shall be provided with a complete electrical charging, starting, electrical
switch, preheating switch, preheating switch and at least two keys.
The engine shall start satisfactorily at temperatures as low as 00c. The generator or
alternator shall be the manufacturer’s standard production model and shall be
adequate to provide service under normal operation conditions.
3.6 Tests on Completion
On delivery to Site, the Plant will be visually inspected, and any Plant with obvious
defects will be rejected.