Professional Documents
Culture Documents
Highway Drainage
A means by which surface water is removed from
pavement and ROW
Redirects water into appropriately designed
channels
Eventually discharges into
natural water systems
Introduction to Highway Drainage
Transverse slopes
Removes water from pavement surface
Facilitated by cross-section elements (cross-slope,
shoulder slope)
Longitudinal slopes
Minimum gradient to maintain adequate slope in
longitudinal channels
Longitudinal channels
Ditches along side of road to collect surface water
after run-off
5
Longitudinal slope
Longitudinal
channel
Transverse slope
Introduction to Highway Drainage
6
Trapezoidal
Introduction to Highway Drainage
7
C i Ai
Cw i 1
n
A
i 1
i
Types of Drainage Systems
Design Discharge (Flood) Estimation
Table: Recommended Runoff
Coefficient C for rural
catchment(2013)
Types of Drainage Systems
Design Discharge (Flood) Estimation
The time of concentration(Tc) is defined as the time required for the
surface runoff from the remotest part of the drainage basin to reach the
point where the drainage facility is located.
The time of concentration generally consists of one or more of the
following three components: time for overland flow, time for gutter or
stream sewer flow (urban), or time for channel flow. Travel time(Ti) is
the ratio of flow length to average flow velocity.
n
L
Ti i TC Ti
Vi i 1
Where:
Tc = time of concentration (hours)
Where:
Tc= time of concentration (hours)., Sav = average channel/stream/ slope
(m/m).
L = hydraulic length of catchments measured along flow path from the
catchment boundary to the point where the flood needs to be determined
(km).
H 0.10L =elevation height at 10% of the length of the watercourse (m)
H 0.805L = elevation height at 85% of the length of the watercourse (m)
Types of Drainage Systems
1. Road in cutting
2. Water flowing from hill
3. Water rises through capillary action.
4. Road near drain
Methods of subsurface drainage
1. Lowering of water table.
2. Controlling seepage flow.
3. Controlling capillary water.
Types of Drainage Systems
28
1. Hydrologic design
Objective:
To estimate the maximum quantity of water expected to reach the element
of drainage system under consideration
Q= C i Ad
2. Hydraulic design
Objective:
Design of drain
R 2 / 3 S 1/ 2
Q Av A
n 𝑹 = 𝑨/𝑷
Design of Drainage System
Hydraulics Design
Aim – providing suitable structure size
Economically and efficiently dispose of the expected runoff without detrimental
erosion and sedimentation problem
R 2 / 3 S 1/ 2 Q 2 A3
Q Av A
n g T
Design Procedure
Select n and side slopes of the channel cross-section (based on channel lining
material)
Take the recommended bed slope (S) based on the channel lining type
Solve for b and y using Manning`s formula (or take b=0.5m and calculate for
y)
Check for y > yc >>>> add free board
Check for y < yc >>>> reduce S
Design of Drainage System
Hydraulics Design
• If permissible velocity(v) is taken then the minimum area (A) required for a given
discharge (Q)can be estimated using continuity equation Q=A*v
Design of Drainage System
38
Hydraulics Design
Example 2:
Given the stream data and height of flow (see diagram below), determine
the velocity of flow in the channel, the flow rate and state of flow
(subcritical / critical / supercritical flow).
Bed slope about the site is 0.8%
Elevation of channel bed is 110.60 m
Channel is regular and considered a little rough with a lot of trees and
weeds along the banks thus “n” values ranging between 0.06 and
0.08’.
Design of Drainage System
Hydraulics Design
Example 2:
Solution:
Given the stream data and height of flow (see diagram below),
determine the velocity of flow in the channel, the flow rate and
state of flow (subcritical / critical / supercritical flow).
Bed slope about the site is 0.8%
trees and weeds along the banks thus “n” values ranging
between 0.06 and 0.08’.
Design of Drainage System
Hydraulics Design
Example 2:
Solution:
Step 1. Calculate the cross sectional area of the flow. Depth, y=1.2m
𝑹 = 𝑨/𝑷 = 𝟒. 𝟒𝟒/𝟓. 𝟖𝟗 = 𝟎. 𝟕𝟓 m
Step 4: Take n= 0.07 as given above and Calculate velocity of flow, V
𝑹𝟐/𝟑 ∗𝑺𝟏/𝟐 𝟎.𝟕𝟓𝟐/𝟑 ∗𝟎.𝟎𝟎𝟖𝟏/𝟐
𝐕= = = 𝟏. 𝟎𝟔 m/s
𝒏 𝟎.𝟎𝟕
Step 5: Using fundamental equation of flow, determine flow rate (Q)
𝑸 = 𝑨𝑽 = 𝟒. 𝟒𝟒 ∗ 𝟏. 𝟎𝟔 = 𝟒. 𝟕𝟏m3/s
Step 6: To determine the ‘state of flow’, we can use any of the two
options
Design of Drainage System
Hydraulics Design
Solution:
Step 6: To determine the ‘state of flow’, we can use any of
𝑽𝟐 𝟏.𝟎𝟔𝟐
(𝒚𝒄 = = =0.057m;
𝟐𝒈 𝟐∗𝟗.𝟖𝟏 𝑩
yc=0.057m<<y=1.2m Fr= 𝑸 ∗ √( )
𝒈𝑨𝟑
𝟒.𝟗
Fr= 𝟒. 𝟕𝟏 ∗ √( )= 0.356
𝟗.𝟖𝟏∗𝟒.𝟒𝟒𝟑
Therefore the flow is subcritical
Fr=0.356<1.0
Therefore the flow is subcritical
Design of Drainage System
43
Example 3:
Design a highway drainage channel in a non-erodible material to carry a discharge of 1.0 cumecs when
the maximum permissible velocity is 0.9 m/s. Assume bed slope = 1 in 4000, side slope = 1:1 and
Manning’s n = 0.020.
Solution:
A = Q/V = 1.0/0.9 = 0.8333 m2
v∗n 3/2 0.9∗0.020 3/2
R= 1 = 1
1 = 0.3326 𝑚
𝑆2 (4000)2
Example 4:
The maximum quantity of water expected in one of the open longitudinal drains on
clayey soil is 0.9 m3/sec. design the cross section and longitudinal slope of trapezoidal
drain assume the bottom width of the trapezoidal section to be 1.0 m and cross slope
to be 1.0 vertical to 1.5 horizontal. The allowable velocity of flow in the drain is 1.2
m/sec and Manning’s roughness coefficient is 0.02.
Solution: −1 ± 12 − 4 ∗ 1.5(−0.75)
𝑏 = 1.0 m (base width) D=
2 ∗ 1.5
𝑄 = 0.9 m3s –1 D =0.45 m
𝑛 = 0.002 m–1/3s
V=1.2 m/sec This is the actual depth, allow a
a) Rectangular Channel free board of 0.15 m, the depth
Discharge:
𝑄 0.9 𝑚3 of the side drain may taken as
𝐴= = = 0.75 𝑚2
𝑉 1.2 𝑚/𝑠𝑒𝑐 0.45+0.15=0.6 m.
Top width of the channel=(1+1.5D+1.5D)=1+3D
Cross section area of the drain=(1+1+3D)*D/2 Slope:
𝐴𝑟𝑒𝑎 = 𝐷 +
3𝐷2
= 0.75 𝑚2 1 2/3 1/2
2 𝑉= 𝑅 𝑆
1.5𝐷 2 + 𝐷 − 0.75 = 0 𝑛
Design of Drainage System
45
Solution:
Slope:
1 2/3 1/2
𝑉= 𝑅 𝑆
𝑛
Assume n=0.02
Wetted perimeter, p
Example 5:
The discharge in a channel with bottom width 3 m is 12 m3s –1 . If Manning’s 𝑛
is 0.013 m–1/3s and the stream wise slope is 1 in 200, find the normal depth if:
a) The channel has vertical sides (i.e. rectangular channel);
b) The channel is trapezoidal with side slopes 2H:1V.
𝑏ℎ5/3 1/2
Solution: Hence, Q = 2ℎ 2/3
𝑆
𝑛(1+ )
𝑏 = 3 m (base width) 𝑏
𝑄 = 12 m3s –1 Reiterate as an iterative formula
𝑛 = 0.013 m–1/3s
𝑆 = 0.005 for h:
a) Rectangular Channel 𝑛𝑄 3/5
Discharge: h= (1 + 2ℎ/𝑏)2/5
Q=VA 𝑏 𝑆
Where, in normal flow Here, with length in meters,
1
𝑉 = 𝑅 2/3 𝑆1/2 A=bh, ℎ = 0.08316(1 + 2ℎ/3)2/5
𝑛
𝑏ℎ ℎ Iteration ( from, e.g., h=0.8316 ) gives
R= =
𝑏 + 2ℎ 1 + 2ℎ/𝑏 h=1.024 m
Answer: normal depth = 1.02 m.
Design of Drainage System
47
Hence,
Example 5: 2
2ℎ 3
Solution: 1 2 1+ 1 2ℎ
Q= ℎ3 𝑏 𝑆 2 ℎ𝑏(1 + )
𝑏 = 3 m (base width) 𝑛 1 + 2 5ℎ/𝑏 𝑏
𝑄 = 12 m3s –1 5/3
2ℎ
𝑛 = 0.013 m–1/3s nQ 5 1+
𝑏
𝑆 = 0.005 ⋙ = ℎ3 2
a) Trapezoidal Channel 𝑏 𝑆 3
1 + 2 5ℎ/𝑏
Base width b, surface width 𝑏 + 2 × (2ℎ) and 2
two sloping side lengths (ℎ2 + (2ℎ)2 = ℎ√5. 3/5 5
nQ 1 + 2 5ℎ/𝑏
Area and wetted perimeter: ⋙ℎ=
1 𝑏 𝑆 2ℎ
𝐴 = 𝑏 + 𝑏 + 4ℎ h=h(𝑏 + 2h) 1+
2 𝑏
A = ℎ𝑏(1 + 2ℎ/𝑏) Here, with lengths in meters,
𝑃 = 𝑏 + 2ℎ√5 2
1 + 2 5ℎ/𝑏 5
Hydraulic radius:
A ℎ(1 + 2ℎ/𝑏) ℎ = 0.8316
R= =
2ℎ
𝑃
1+ 3
1 + 2√5h/b
Discharge: Iteration ( from, e.g., h=0.8316 ) gives
1
Q=VA= 𝑅 2/3 𝑆1/2 𝐴 h=0.7487 m
𝑛
Answer: normal depth = 0.749 m.
Design of Drainage System
Hydraulics Design
Design of Cross-Drainage structures
Drifts:
Most of the time concrete slab is used (when the bed
of the river is not able to carry vehicles.
Are always over flooded if there is rainfall
Vented Fords:
Have vents or pipes to handle low level of flood but
subjected to flooding at high rainfall period
Design of Drainage System
Hydraulics Design
Drifts
Design of Drainage System
Hydraulics Design
Vented fords
Hydraulics Design
Design of Cross-Drainage structures
Culverts:
convey water below the road
span of 6 m or less
sometimes designed to flow full and does not form part of the roadway
located at bottom of depressions, point where natural streams intersect the roadway and
points required for passing surface drainage in side ditches
Highway bridges:
to carry the roadbed over an established waterways
span of more than 6 m
designed to pass floating debris or vessels
form part of the travelled roadway
Design of Drainage System
Hydraulics Design
Hydraulic Design of Culverts. involves the following
general procedure:
obtain all site data and plot a roadway cross section at the culvert site,
including a profile of the stream channel.
establish the culvert invert elevations at the inlet and outlet and determine
the culvert length and slope
determine the allowable depth of headwater and tail water
select a type and size of culvert that will accommodate the design flow under
the established conditions.
provide protective devices to prevent destructive channel erosion.
Hydraulics Design
Culvert types and
materials
Types of culverts of
different sizes:
Circular
Box
• Selection of the type depends on
Elliptical
Arch • Hydraulic requirements
• Strength required to sustain the weight of a fill
Materials or moving wheel loads economics
Reinforced concrete
Corrugated metal
Stone masonry, etc
Design of Drainage System
Hydraulics Design
Highway bridges
Design principle involves
Location
Alignment
Foundation
Traffic safety, operating conditions, and fulfilment of the purposes of the road
Constriction of flow
Velocity of flow
Scouring
Flooding
Economics
Design of Drainage System
Hydraulics Design
Bridge best site
Source: ERA(2013)
Low volume road
design manual
Design of Drainage System
56
Drainage channels
Drainage channels should:
Have adequate capacity for the design runoff,
Minimize damage to the highway caused by
unusual storm water,
Minimize risk for motorists,
Be resistant to the high speed water flows where
expected,
Prevent sedimentation of the particles carried by
water.
Design of Drainage System
57
Collection and transport of water across the road so as to not cause damage to
the road bank or the stream bed by scouring.
To provide sufficient waterway to prevent heading up of water above the road
surface.
Design of Drainage System
58
Box Culvert
Suitable for large flow where the boulder movement may occur.
Constructed where the nature of the soil below the foundation is not
suitable for individual footing under piers and abutments.
These culverts have larger life spans, greater hydraulic efficiency,
superior durability for worst environmental conditions and greater
resistance to damage due to debris.
Design of Drainage System
59
Reflection Questions
1. Explain the process involved in design surface
drainage systems such as ditches
2. What are cross-drainage structures?
3. What factors are taken into considerations in
the selection of cross-drainage structures?
4. What are the possible solutions to subsurface
drainage problem?
References
1) ERA(2013) Drainage Design manual
2) Huang J.(2004), Pavement Analysis and Design
3) ERA(2013) Low volume road design manual
The End.
Thank You