Professional Documents
Culture Documents
Training on
Given Data:
• Location of Project-X:
• Projection : UTM;
• Zone : 36
• Datum : Adindan
• MFL/Mark at a proposed weir = 1211.671 & Deepest RBL =1208.973 m a.s.l.
• Cross Sections at, u/s & d/s of Weir Axis: As attached
• Geo-technique study has shown that river banks are loose but bed is of sound
bedrock at 2m depth.
Question - 1: Estimate Qd from this observed Flood Mark at a proposed weir axis.
Question - 2: Estimate TWD corresponding to selected Q50 at the proposed weir axis;
River
Flow
Command
Hav2
Hav1 Hav3
He Hd
D2 D3
h
d1
B C
C
A B m
A
Submerged/Drowned Weir
1
Where, B = bottom width of the weir, m; P = h = weir height above u/s apron level; He =
overflow depth including approaching velocity head
But take practical value and check for its stability to obtain final dimension.
4.9 Choice of Stilling Basin Type
Criterion for deciding which type of stilling basin to use depends on the maximum
velocity of water (v1) entering the stilling basin, which can be obtained from equation:
V1 = Qm/(Lcxd1); If V < 15 m/sec then use Type I & If V > 15 m/sec then use Type II. Where,
V1 = velocity of approach to stilling basin (m/sec); Q m = Max flood discharge (m3/s); Lc =
Length of crest of diversion weir (m); d1 = Initial depth of jump (m)
GIRDC 31 September 2015
Weir Hydraulic Design(ctd…)
Basin Type 1: Plain horizontal basin. Jump occurs on the floor with no chute
blocks, baffle piers or end sill provided. Usually not
recommended because of excessive length
Basin Type 2: This basin is for use with high spillways, large canal structures,
etc., for Froude numbers above 4.5.
Basin Type 3: This basin is for use on small spillways, outlet works & small canal
structures where velocity at u/s end of a basin does not exceed 15
to 18m/s
Basin Type 4: This basin is for use with jumps with Froude numbers between 2.5 and
4.5. This basin reduces excessive waves created by imperfect jumps.
4.10 Bed level of Stilling basin (apron)
Fixed by applying energy equation on u/s & d/s of weir for assumed floor level
of the d/s apron by trial & error or by goal seek (Note: If (D3-D2) lies b/n 0.2 to
0.4 acceptable but if greater adjust it. i.e. RBL + h + Hd + Hav = Z + D1 + Hav1 =
D1+q2/D12/2g after substituting Hav1=V12/(2g) & V1=q/D1s basin level should be
depressed by some level)
GIRDC 32 September 2015
Weir Hydraulic Design(ctd…)
Causes of Failure of Weir/Barrage on Permeable Foundation
(i) Failure due to subsurface flow:
a) Piping - result in failure by undermining
b) Uplift Pressure - result in failure by rapture
(ii) Failure by Surface Flow:
a) Hydraulic Jump – result in failure by rapture
b) Scouring During Floods - result in failure by shearing
Remedies for Failure of Weir: Main remedies against failure are:
i. Path of percolation or creep length of seepage water should be increased
either by providing sheet piles at upstream, downstream or at intermediate
point to reduce the hydraulic gradient or increase length of the impervious
layer itself.
ii. Floor thickness should be increased to increase its self-weight to
counterbalance the uplift force.
iii. Energy dissipater blocks like friction blocks, impact blocks, shall be provided.
iv. Inverted filter should be provided with concrete blocks on the top so that the
percolating water does not wash out the soil particles.
v.
GIRDC
Deep foundation like well foundation33 should be provided for barrageSeptember
piers 2015
Weir Hydraulic Design(ctd…)
Failed Failed
Hazemb Side
ara weir intake
due to on
poor Bilate
analysis River
of due to
foundat poor
ion analysis
seepage of earth
quake
forces
Failed Failed
Goche aqueduct
weir on Lenda
due to Project
poor due to
design poor
of design of
impervi Scouring
ous and
GIRDC perviou 34 September 2015
s aprons
Weir Hydraulic Design(ctd…)
4.11 Hydraulic Jump within the Basin & Length of d/s Apron
• Hydraulic jump is the jump of water that takes place when a super-critical
flow changes into a sub-critical flow.
• It is a useful phenomenon for Dissipating Energy in irrigation structures;
• Length of the downstream horizontal floor is kept equal to the length of
this jump, which is equal to 5 to 6 times the height of the jump i.e.
4.12 Thickness of Downstream Apron
• To determine the thickness of the apron both dynamic and static case
should be considered:
Where, t = thickness of apron at any point (m); f = factor of safety = 1.3; H max
= differential (maximum) head u/s and d/s head, m; Lc= weighted creep
length total (m), LV =vertical creep length and LH = Horizontal creep length
Required condition: Lc C*Hmax where C = Percolation coefficient (Bligh’s
creep ratio, to be taken from literature for bed material at the weir site)
GIRDC 35 September 2015
Weir Hydraulic Design(ctd…)
Table : Bligh's Safe Hydraulic Gradient for different types of Soils
Value Safe Hydraulic gradient
SN Type of soil of C it should less than
1 Fine micaceous sand 15 1/15
2 Coarse grained sand 12 1/12
3 Sand mixed-with boulder & graver and for loam soil 5 to 9 1/5 to 1/9
4 Light sand and mud 8 1/8