This work progress report provides updates on construction activities for Project G+1+R Villa E-139 from August 22nd to 27th. Plastering was completed in the main guest bedrooms 1 and 2 and steel columns of the main villa's first floor. Filling cuts with mortar and plastering and demolition of floors and rubbish removal in the main villa's ground and first floors are underway. Sheeting works at the top roof were finished and steel works are in process.
This work progress report provides updates on construction activities for Project G+1+R Villa E-139 from August 22nd to 27th. Plastering was completed in the main guest bedrooms 1 and 2 and steel columns of the main villa's first floor. Filling cuts with mortar and plastering and demolition of floors and rubbish removal in the main villa's ground and first floors are underway. Sheeting works at the top roof were finished and steel works are in process.
This work progress report provides updates on construction activities for Project G+1+R Villa E-139 from August 22nd to 27th. Plastering was completed in the main guest bedrooms 1 and 2 and steel columns of the main villa's first floor. Filling cuts with mortar and plastering and demolition of floors and rubbish removal in the main villa's ground and first floors are underway. Sheeting works at the top roof were finished and steel works are in process.
01 Plastering in main guest bedroom 1 and 2 Completed
02 Plastering in steel column in main villa 1st floor Completed
03 Filling of cuts with mortar and plastering Under Process
04 Demolition of the floor and rubbish removal Completed
completed in main villa G.F and F.F 05 Sheeting works at top roof completed, steel works Under Process Plastering in main guest bedroom 1 and 2 Plastering in steel column in main villa 1st floor
Filling of cuts with mortar and plastering
Demolition of the floor and rubbish removal completed in main villa g f and f.f Sheeting works at top roof completed, steel works