You are on page 1of 48

Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

SECTION 16: MONITORING SYSTEM EQUIPMENT

1 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

TABLE OF CONTENTS

1. TECHNICAL DESCRIPTION, REQUIREMENTS AND DATA ....................................... 4


1.1. General ........................................................................................................................... 4
1.2. Technical Description and Data of Existing Equipment .................................................. 4
1.3. Technical Data, Descriptions and Requirements for Reconstruction and Modernization 6
1.4. Guarantees and Rejection ............................................................................................ 10
2. SCOPE AND LIMITS OF WORKS ................................................................................ 11
2.1. General ......................................................................................................................... 11
2.2. Scope of Works ............................................................................................................. 11
2.3. Extent of the Works ....................................................................................................... 12
2.4. Limits of Works.............................................................................................................. 12
3. DOCUMENTATION ...................................................................................................... 13
3.1 Documentation to be Submitted with the Tender .......................................................... 13
3.2 Documentation to be submitted After Contract Commencement Date......................... 13
4. INSTALLATION REQUIREMENTS .............................................................................. 14
4.1 Scope of Installation Works .......................................................................................... 14
4.2 Requirements for Installation Works ............................................................................. 14
5. DESIGN, MATERIAL AND WORKMANSHIP ............................................................... 16
5.1 Standards ...................................................................................................................... 16
5.2 Design ........................................................................................................................... 17
5.3 Quality of Materials ...................................................................................................... 19
5.4 Requirements for Software ......................................................................................... 19
5.5 Insulation Level ............................................................................................................ 19
5.6 Electromagnetic Compatibility .................................................................................... 19
5.7 Corrosion Protection .................................................................................................... 20
6. SPECIFIC REQUIREMENTS ..................................................................................... 21
6.1 General Considerations .............................................................................................. 21
6.2 Unit vibration system ................................................................................................... 21
6.3 Monitoring of partial discharges on the generator stator windings ............................... 24
6.4 Air gap monitoring ......................................................................................................... 28
6.5 Magnetic flux monitoring system................................................................................... 33
6.6 Monitoring the temperature of the rotor ........................................................................ 36
6.7 Computer for monitoring vibration, partial discharges, magnetic flux, air gap and rotor
temperatures ................................................................................................................. 37
6.8 Laptop for programming the configuration of vibrations, partial discharges, magnetic
flux, air gap and rotor temperature................................................................................ 38
6.9 Step-up Transformer monitoring system ...................................................................... 39
6.10 Requirements for the generating unit monitoring cubicles ........................................... 40
6.11 Low voltage power, control and signaling cables ......................................................... 41
6.12 Maintenance Criteria ..................................................................................................... 41
6.13 Availability, Reliability, Maintainability and Safety ........................................................ 41
6.14 Training of the Employer’s Personnel ........................................................................... 42
6.15 Spare Parts ................................................................................................................... 43
7. INSPECTIONS AND TESTS ........................................................................................ 44
7.1 General ......................................................................................................................... 44
7.2 Shop Tests .................................................................................................................... 44

2 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

7.3 Site Tests ...................................................................................................................... 46

3 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

1. TECHNICAL DESCRIPTION, REQUIREMENTS AND DATA

1.1. General

These Special Technical Specifications together with the General Technical


Specifications refer to the special technical requirements for the Detail design,
manufacture, workshop tests, delivery at the site, dismantling of existing equipment,
installation of new equipment, site tests, trial operation and elaboration of as-built
design of Monitoring System Equipment on Hydro Power Plants in a scope of HPP
Bistrica.

These specifications consist of specific requirements for Monitoring System


Equipment and its accessories. All General Technical Specifications are valid for
Monitoring System Equipment and shall also be applied.

Wherever it is possible, these Special Technical Specifications shall be applied in


conjunction with the General Technical Specifications. In case of discrepancies
between the General and Special Technical Specifications, the Special Technical
Specifications shall prevail.

Data, information, requirements and conditions from this Section, shall be relevant,
where applicable, to other Sections of this Tender documentation.

1.2. Technical Description and Data of Existing Equipment

1.2.1 Vibration Monitoring system

The existing vibration monitoring system is only installed on the aggregate B and
consists of the following equipment:

- sensors with associated transducers

- rack with modules,

- cable installation by which measurements from the sensor are introduced


into the rack.

After processing signals from the sensor, the following output solutions are possible:

- Relay contact outputs for each two-level signal (warning and


disconnection) and

- Ethernet communication with the central computer in the control room of


the power plant, where it is possible to display the vibration state of the
generator through the monitor.

Vibration measurement refers to the following measurement sizes:

- Relative vibration of the shaft of the generator - radial direction,

- Relative movement of the shaft of the generating unit - axial direction,

- Speed of rotation of the shaft of the generating unit,

- Absolute vibration of the generator bearing - radial direction,

4 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

- Absolute vibration of the generator bearing - axial direction,

- Absolute Vibrations of Stator Core and

- The position of the turbine governor.

The vibration monitoring system will be implemented as a distributed system. The


distributed system implies the installation of special units - IED for monitoring
vibrations for each generating unit, connected through a special communication
network with a common computer for vibration analysis and diagnostics, or a central
monitoring computer. The vibration monitoring system of each generating unit
consists of the following equipment:

 sensors with necessary electronics (transducers) and carriers;


 connecting cables, connection boxes with accessories (protective hoses,
cable glands, etc.);
 Data collection units (IED) of vibration monitoring.

In addition to this equipment, the following common equipment is also foreseen

 software for analyzing and diagnosing the vibrations of both generating


units, installed in the central computer monitor and
 laptop for programming and configuring the vibration monitoring system.

As the vibration parameters of the generating unit directly depend on its operating
mode (rotational speed, load, etc.), all the necessary data for vibration analysis and
diagnostics will be provided via the IED connection for vibration monitoring with the
appropriate generating unit process station, i.e. generating unit control system.

The vibration monitoring system will also have a protection function. For this purpose,
a hard-wired connection will be realized with the control and protection systems of
the generating unit, which will be used for signaling of alerts and alarms, as well as
the issuance of the emergency alarm command for generating unit. Warning and
alarm signals from the vibration monitoring system, refer to signals such as: vibration
above the permitted level, IED monitoring vibration failure, etc.

1.2.2 Generator Partial Discharge Monitoring

The existing partial discharge monitoring system in HPP Bistrica consists of


differential capacitive sensors and a portable analyzer:

The existing partial discharge monitoring system in HPP Bistrica comprises the
following:
- High-voltage capacitive sensors,

- Terminal boxes and

- Portable analyzer of partial discharges.


The partial discharge monitoring system consists of 6 (six) high-voltage capacitive
sensors, 2 (two) per phase, permanently installed at certain intervals (at generator
terminals) and connected to the terminal box by means of coaxial cables, with the
impedance of 50 , and a portable test instrument PDA-6D that is connected to
portable personal computer (PC).

Sensors detect high-frequency pulses occurring at the locations of partial discharges.


External pulses from a source outside generator (transformer and/or other external

5 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

sources) are eliminated in the PDA-6D analyzer itself.

The probe consists of capacitive sensors directly connected to copper busbars of


high- voltage generator phase terminals. This sensor is further connected to terminal
box by means of 50  coaxial cable. This cable should be as short as possible in
order to reduce disturbances and partial discharge signal weakening. The probes are
installed on outer busbars.

Terminal box is connected to partial discharge analyzer by means of 6 coaxial cable


with 50  impedance. It is located in the area of generator neutral point and has the
following two functions:

- Fixing of coaxial cables from partial discharge sensor to permanent spot so


that the analyzer can be disassembled without disconnecting coaxial cable
ends from the sensor;

- Connection and earthing of coaxial cable armour armature. Terminal box is


also connected to the analyzer by means of 50  cable.

Received signals are preliminarily processed in the analyzer by using computer-


controlled amplifier. Signals are then converted into digital signals by using A/D
converter and they are recorded on hard disk. Data are further analyzed by a special
algorithmic program package. Noise is removed in frequency and time range.

The number and value of positive and negative PP pulses are displayed at any
moment on the display on the front side of the analyzer for each phase equipped with
a sensor. At the same time, results of measurements from two difference measuring
points are displayed as well. The analyzer front contains tree-colour LED indicators of
stator winding condition.

The analyzer provides the following indications of winding condition:

- Green colour - normal condition,

- Orange colour - increased discharge - alarm signal and

- Red colour - increased discharge - emergency signal.

1.3. Technical Data, Descriptions and Requirements for Reconstruction and


Modernization

1.3.1 Scope of Modernization

The new system will be designed as a monitoring system that supports the following
separate entities:

- vibration monitoring system;


- monitoring the air gap between the rotor and the stator;
- monitoring of partial discharges;
- monitoring of magnetic flux,
- Monitoring the temperature of the rotor,
- monitoring of step-up transformer.

The generating unit monitoring system must provide integration at several levels. The
system should be implemented to allow for the viewing of measurement data and

6 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

various analyzes of all subsystems that it encompasses with any computer in the TCP
/ IP network.

The central part of each subsystem will be placed in the common control cubicle of
the generating unit 1 (+ 1UM1) and the generating unit 2 (+ 2UM1) with the
accompanying process unit and other equipment for receiving signals from measuring
sensors and signals taken from other systems (control system, excitation system etc.).
Each of the subsystems will forward the information to the central computer of
monitoring, i.e. central server that will store measurement data and the results of
various analyzes and processing into a database will perform certain analysis of
measurement data and allow users to access data from a database.

The hardware and software of the aggregate monitoring system will be of a modular
type, so that they can provide future upgrades to the system. It is important that the
monitoring system has a high level of autonomy and requires minimal maintenance.

Vibration monitoring

A stationary system of permanent monitoring of generating unit vibration parameters


is a modern system that enables simultaneous registration and diagnostic analysis of
a large number of different dynamic sizes relevant for the evaluation and monitoring
of the state of the generating unit.

The Contractors obligation shall be to dismantle the existing sensors, reinstall them
on the new Units, setting the Vibration Monitoring System parameters, perform the
necessary tests on the equipment and put system in operation.

Partial discharges

Monitoring of partial discharges in stator windings is obsolete (off-line) and it does not
provide timely information about possible breakdown of winding insulation. For that
reason, the latest standard for this type of equipment is a system with on-line
continuous monitoring of generator parameters, which improves the main role of this
system. Additionally, in this way, power monitoring results will be reliably compared
with the results of off-line testing and diagnostics. Additionally, in this way, power
monitoring results will be reliably compared with the results of off-line testing and
diagnostics. This Tender documentation envisages replacement of the entire system,
without retaining the existing sensors.

Air gap monitoring

Measurement of air gap is one of the most important parameters necessary for safe
and efficient exploitation of the generator. Touching the rotor to the stator is often the
cause of long-term and expensive overhaul of the hydrogenerator. The air gap control
together with the rotor / stator / rotor / stator / shape control can provide a timely alert
about the possibility of touching. Shoving the shaft in relation to the central axis of the
rotor or distorting the stator concentration also reduces the efficiency of the generator's
operation at the expense of increasing the magnetic attraction of the rotor to the stator
in the area of the minimum gap and corresponding growth of the stator winding and
losses.

Monitoring of the magnetic flux will allow continuous (continuous) monitoring of the
magnetic flux in the air gap of the generator (intermediate). The monitoring of the
magnetic flux will allow testing of the insulation state during the operation of the
generator, during working conditions in which electrical, magnetic, temperature and
mechanical stresses are present.

7 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

Since there are no air gap and magnetic flux monitoring systems on the HPP Bistrica,
the Contractor will deliver and install new monitoring equipment on new generators,
adjust the parameters of the monitoring system, perform the necessary tests on the
equipment and let the system work.

Since there are no systems for air gap of monitoring and monitoring of magnetic flux
on the Units in HPP Bistrica, the Contractor will deliver and install new equipment for
monitoring on new generators, adjust parameters of monitoring systems, performing
necessary equipment tests and interconnecting to operating mode.

Monitoring the temperature of the rotor

The temperature monitoring system of the rotor consists of measuring the temperature
of the poles of the rotor and, above all, the temperature of the intermediate pole bonds,
in order to create a thermal image of the rotor.

The contractor will deliver and install new equipment for monitoring the temperature
of the rotor on new generators, adjust the system parameters, perform the necessary
tests on the equipment and let the system work.

Step-up Transformer Monitoring System

In order to carry out on-line monitoring (monitoring) of the condition of the step-up
transformer, measurements and analyzes of the temperatures of the transformer parts
and the content of gases in the oil will be performed.

1.3.2 Basic Requirements for Unit’s Monitoring Systems

Reconstruction of the main electromechanical equipment of HPP Bistrica, which


involves replacement of reconstruction of unit monitoring system and monitoring of
step-up transformer.

For a purpose of premature diagnostic of possible generator faults, it is necessary to


install the monitoring system for observing of the generator’s vibrations, partial
discharges parameters of generators and air-gap values in the zone between rotor
and stator and monitoring of temperature of rotor.

These systems shall be realized in accordance to the newest technical and


technological achievements and shall be complied with the systems which shall be
applicable on the generators of this type and capacity.

Systems shall be “user friendly” meaning that the end-user may perform their own
testing and trending with minimal training from the Contractor. Systems shall not
require the services of the Contractor to obtain meaningful results. However, the
Contractor shall be capable of providing a formal analysis report of the collected data
at the request of the end- user. Systems shall be controlled from PC Computers, and
the following software functions shall be provided:

 System setup and alert definitions,

 Data acquisition from all installed sensors,

 Data processing in real time and

8 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

 Data Analysis using dedicated software application for specific monitoring


functions.

Monitoring systems shall be used to collect the data as a permanent online monitoring
system with protection capability as well as to be used to view data in real-time during
commissioning or maintenance.

The unit monitoring system shall enable integration at several levels.

The system shall be implemented in such a manner so that it enables review of


measurement data and various analyses of all subsystems that it covers from any
computer in TCP/IP network.

The concept of the unit monitoring system has

three levels:

Level 1 - Measuring part

Measuring string arrays that include sensors and signal

transducers.

Level 2 – Units for data acquisition and processing

Each unit is an autonomous, automated and fully functional continuous monitoring


unit. It contains modules for measuring, data acquisition and processing,
communication, power supply and software for alarm (protection), data processing
and storing.

Level 3 - Application part

Central monitoring computer (CRM), specialized software for condition diagnostics


and evaluation, database, client server, etc.

Data acquisition and processing unit of each subsystem shall be housed in a joint
monitoring system cubicle of Unit 1 (+1UM1) and Unit 2 (+2UM1) in HPP Bistrica.
Each subsystem shall transmit information to the central monitoring computer i.e.
central servers that will store measuring data and results of various analyses and
processing in a database, perform certain analyses of measuring data and provide
insight in data from the database to the users.

Hardware and software of the unit monitoring system shall be of modular type in order
to enable future expansions of the system. The monitoring system should have a high
level of operation autonomy and it should require minimum maintenance.

Alarm signalization, when set parameters of the system are overreached, shall be
transferred to Units master station, by hardwire connection. When set parameters of
the system are overreached and immediate tripping of Unit is necessary hardwired
commands should be transferred to the binary inputs in Unit Protection Relay (System
A and B).

The Contractor shall supply and install all necessary support structure, cable
accessories and all other required installation material, for the purpose of Monitoring
Systems Equipment proper installation, according to relevant technical standards and
safety regulations.

9 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

1.4. Guarantees and Rejection

1.4.1 Guarantees

The Contractor shall guarantee that all Monitoring Systems equipment comply with
requirements stated in this Special Technical Specifications and in Schedules of
Technical Data.

1.4.2 Rejection of Delivery

In case that delivered equipment does not fulfill the requirements stated in this
Special Technical Specifications and in Schedules of Technical Data, the Employer
has the right to reject the delivery.

10 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

2. SCOPE AND LIMITS OF WORKS

2.1. General

Delivery and services to be performed by the Contractor will include design,


production and factory testing, packaging, transport, insurance, unloading, site
storage, construction works and installation of new equipment, corrosion protection,
site testing, documentation submission, handover and warranty works related to the
equipment of the Monitoring System.

This clause defines only the significant works being performed and the equipment
that is the subject of the Contractor’s delivery in order to fulfill the contractual
obligations.

The Contractor is obliged to provide complete equipment and works, even if such
equipment or works that are the subject of performance are not specifically
mentioned in this document or are explicitly defined in the drawings, but are
necessary for completing the works and achieving the proper functioning of the
monitoring system and system as a whole, in accordance with the characteristics
required by these Technical Terms, without prejudice to the price of the contract.

The scope of the Works will be in accordance with Section 2.2 and General Technical
Specifications.

2.2. Scope of Works

The contractor will deliver the equipment and perform the following works:

 Collection of plant and equipment data;

 Design, procurement of materials and production of equipment

 Factory tests, in accordance with General technical conditions and item


7.2. of these Special Technical Terms;

 Packing and transport of equipment in accordance with General


technical conditions;

 Insurance, in accordance with the contractual terms;

 Design and delivery of Project Documentation, in accordance with


General Technical Requirements and Count 3 of this Section;

 Dismantling of existing equipment, store dismantled equipment and hand


over to the Employer;

 Installation of the new monitoring system equipment, in accordance with


Section 1.3 of this Section and responsibility for the work performed, in
accordance with the General Technical Terms and Conditions of
Contract

 On-site testing and commissioning of monitoring equipment, in


accordance with General technical conditions and item 7.3. of these
Special Technical Terms;

 Commissioning tests and Trial run;

11 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

 Work insurance;

 Spare parts, in accordance with the General Technical Terms and Item
6.11 of these Special Technical Specifications

 Special tools in accordance with the General Technical Terms and Item
6.12 of these Special Technical Specifications.

 Corrosion protection, in accordance with General technical specification

 Providing the necessary information to the Employer in accordance with


the General Technical Specifications

 Liabilities during the Warranty Period.

 Training of the Staff of the Employer, in accordance with the General


Technical Specifications.

2.3. Extent of the Works

Extent of the Works shall be in accordance with appropriate Clauses of General


Technical Specifications.

2.4. Limits of Works

The material and equipment encompassed by this Section shall be junctioned to


other works as it is specified here above and in accordance with scope of works of
other Sections. In case of any ambiguity the same shall be presented to the Employer
for solving.

Generally, the Limits of Works for this Section are as follows:

- Connection to structure earthing system,

- Terminals and ports for connection of cables for power supply to system
equipment and communication connections with the generating unit control
system,

- Units tripping circuits,

- Place of installation of sensors and monitoring system probes, such as


generator stator windings, bearing hub-bell, etc.

- Existing Vibration Systems Acquisition Units.

12 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

3. DOCUMENTATION

3.1 Documentation to be Submitted with the Tender

Together with the Tender, completed with appropriate Schedules of Technical Data
duly filled in, the Contractor shall submit the following information:

- Drawings concerning the proposed equipment, giving dimensions, weights,


foundations, and support system details;

- Schematic diagrams;

- Detailed descriptions with characteristics of all types of equipment included in


the Specifications (catalogues, descriptive literature, manufacturing
Specifications);

- General outline and arrangement drawings;

- Copies of Testing Reports all equipment similar to the equipment specified in


this Special Technical specification, which were subject of the type testing.

- Working phases description and time-chart.

- List of Standards which shall be used for materials, production and testing of
equipment; list shall contain code name and date of issue of the Standard used.

3.2 Documentation to be submitted After Contract Commencement Date

The Contractor shall submit all necessary information to the Employer in accordance
with the procedure and requirements stated in General Technical Specifications.

13 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

4. INSTALLATION REQUIREMENTS

4.1 Scope of Installation Works

The installation works shall include works related to dismantling of the existing
equipment and the installation of all equipment to be supplied by the Contractor under
this Section and reinstallation of the existing Units vibration monitoring and air gap
equipment, as well as the all necessary temporary works.

Specific installation requirements specified herein shall be in addition to applicable


general installation requirements, as specified in General Technical Specifications.

The Contractor shall furnish all supervision, labour, material, equipment and services,
and shall perform all work required to install the specified equipment and accessories
ready for commercial operation. The work includes transportation of all materials to
the site, storing the materials at the site and transporting the materials from storage
to the place of installation. Everything required for complete and operating
equipment, although not expressly called for in the Specifications or Drawings, shall
be performed and furnished by the Contractor at no additional cost to the Employer.

4.2 Requirements for Installation Works

In addition to General Technical Specifications, the following requirements shall be


applied:

 The Contractor shall install the equipment accurately in accordance with the
specifications, instructions and drawings. The Contractor shall perform the
installation works under the supervision of the Employer;

 Contractor is obligated to carry out all the necessary civil works related to
installation (entering of the equipment/pre-assembled cubicles and its erection
at spot) of the new equipment related to this Section;

 Contractor shall complete the cubicles construction, factory mounting and


installation of all the equipment in to cubicles and to perform all required tests
in the factory;

 Dismantling and installation works, especially considering connections


between new and existing equipment shall be performed on the base of
available existing as-build documentation, which shall be submitted by
Employer, and Detail Design submitted by Contractor (according to Clause 3).
The Contractor shall have obligation to check on the Site, before dismantling
and installation works commencement, all data from available existing as-build
documentation;

 All work on the existing equipment and assemblies to be effected in a manner


to prevent damage to the existing equipment;

 The monitoring systems equipment (signal cables and sensors) shall have an
adequate additional thermal isolation, at the locations of high risk in
vulnerability due the high ambient temperature;

 The Contractor shall submit documents showing the schedule of installing all
equipment, piping and pipe supports, electrical conduits and appurtenances
to the Employer for approval prior to the beginning of the installation works;

 The necessary test record and data during the installation work shall be

14 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

submitted to the Employer for approval;

 Field test reports shall also be submitted to the Employer by the Contractor;

 Rust on the metal surfaces, oil and dirt’s on the surface of the parts to be
embedded in concrete shall be removed and cleaned thoroughly before
installing;

 Matching numbers or marks shall be stamped on the joints assembled at the


site.

The Contractor shall include all the works required for dismantling of the existing
equipment and erection of the supplied equipment all in accordance with the Time
Schedule. These works shall comprise:

 dismantling and disposal of the existing equipment which shall not be more in
operation,

 erection of new equipment,

 dismantling of the existing equipment subject to reconstruction and its re -


erection,

 dismantling and erection of the existing equipment in order to connecting the


new and the old equipment,

 dismantling and disposal of existing cables which shall not be in operation.

All internal handling works inside Site shall be performed and secured by the
Contractor.

All activities envisaged inside Site shall be in accordance with the Plan for
organization and safety on the Site.

15 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

5. DESIGN, MATERIAL AND WORKMANSHIP

Prior to starting the preparation of the design documentation, the Contractor shall
forward a list of documents which refer to the existing equipment and which are
expected to be in the possession of the Employer.

The Employer shall make these documents available to the Contractor in order to
enable them to prepare for approval proper documentation.

Nevertheless, in case that any required drawing shows to be un available or lacking


all necessary data the Contractor is obliged to obtain in-situ the required information
by personally performing necessary surveying.

5.1 Standards

Unless otherwise specified, the Monitoring Systems Equipment shall be designed


fully in accordance with these Technical Specifications, as well as according to the
latest revisions of the following IEC Standards:

IEC 60034-27-2 Rotating machines - On-line partial discharge


measurements on the stator winding insulation of
rotating electrical machines

IEC 60270:2000/
BS EN 60270:2001 High-Voltage Test Techniques - Partial Discharge
Measurements

IEEE 1434-2000 IEEE Trial-Use Guide to the Measurement of Partial


Discharges in Rotating Machinery

IEC 60034-14 Rotating electrical machines - Part 14: Mechanical


vibration of certain machines with shaft heights 56 mm
and higher - Measurement, evaluation and limits of
vibration severity

ISO 20816-5:2018 Mechanical vibration Evaluation of machine vibrations by


measurements on rotating shafts (Part 5 – Machine sets
in hydraulic power generating and pumping plants

ISO 20816-5:2018 Mechanical vibration – Evaluation of machine vibration


by measurements on non-rotating parts (Part 5: Machine
sets in hydraulic power generating and pumping plants)

ISO 13373-1:2001 Condition monitoring and diagnostics of machines —


Vibration condition monitoring — Part1: General
procedures and Part 7: Diagnostic techniques for
machine sets in hydraulic power generating and pump-
storage plants

IEC 61158-1 Digital data communications for measurement

and control IEC IEC 61131-1 Programmable Controllers – Part I:

General Information

IEC 61131-2 Programmable Controllers – Part II: Equipment

16 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

requirements and test

IEC 61131-3 Programmable Controllers – Part 3: Program Languages

ISO/IEC 11801 Information technology – Generic cabling for customer


premises (Industrial premises, also EN 50173-2)

ISO/IEC 14763-2 Information technology – Implementation and operation


of customer premises cabling – Part 2: Planning and
installation

IEC 61000-6-5 Electromagnetic compatibility (EMC)


–Genericstandards; immunity for power station and
substation environments

IEC 61000-4-x Electromagnetic compatibility (EMC) – Basic immunity


standards

IEC IEC 60870-2-2 Telecontrol Equipment and Systems - Part 2: Operating


conditions – Section 2: Environmental Conditions

IEC 60068 Environmental testing

IEC 60529 Degrees of protection provided by enclosures

IEC60664 Insulation coordination for equipment within low-voltage


systems

IEC IEC 60050-301 International Electrotechnical Vocabulary, Scientific and


Industrial Measuring Instruments

IEC 61010-1 Safety Requirements for electrical equipment for


measurement, control and laboratory use - Part 1:
General requirements

If the Tenderer offers design, equipment, workmanship and tests conforming to any
National Standard deviating from the abovementioned, such deviations shall be
submitted along with his Tender.

Application of Standards other than the abovementioned shall be subject to the


Employer’s approval.

5.2 Design

The rehabilitation design and manufacture of Monitoring systems equipment shall be


in accordance with the latest state of technology development in this field. Special
attention shall be paid to a good overall design, easy access, simple operation and
logical arrangement of individual parts. Spare parts shall be so fabricated as to be
easy for erection and exactly fitted without a need for latter adjustments.

In continuous operation, no part of equipment shall sustain damage due to


overheating. Also, change in position and form shall not occur.

The Contractor shall carry out the prescribed preparation of all surfaces to be welded
on the site and all connections with bolts.

All the elements exposed to significant wear shall be provided with wearing parts that

17 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

can be dismantled in order to ensure an easy and economical repair or replacement.

Contractor shall also pay particular attention and take into account all relevant
requirements specified in the Special Technical Specifications, Section 8: Generator
with the Excitation System.

18 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

5.3 Quality of Materials

All materials used shall be of the best quality and of a kind most suitable for the work
and the conditions specified. Quality of all used materials shall be in line with
requirements laid down in Technical Specifications.

5.4 Requirements for Software

5.4.1 System, Application and Process Software

Contractor shall include in his Tender all the system, application and process
software packages required for the Unit Monitoring Systems.

The Contractor shall procure all necessary permits, licenses and authorizations for
the system, application and process software of the Monitoring Systems. Licenses
for software providing development and configuration of the Monitoring Systems
equipment shall be provided with no additional cost for the Employer.

Listing and source code shall be provided for the application and process software to
be applied in the Monitoring Systems. Provisions shall be made to modify/change the
software as well as to enable full system recovery. Functionality of the software shall
be subject to the approval of the Employer.

5.4.2 System Generation

All system, application and process software necessary for system generation (back-
up) shall be supplied at the optic/magnetic medium, where the system can be fully
restored.

5.4.3 Software Upgrade

The latest version of the software shall be offered for system, application and process
software. If, during implementation of the Contract a new generation of software will
be developed, the Contractor shall deliver the latest version with no impact on the
Contract price. Should some upgrades and functional modifications of specific
software be made by the Contractor after the Contract completion time, the Employer
shall be entitled to such upgrades/modification at the additional cost calculated as
difference between the contract price and the actual price of so modified/upgraded
software.

5.4.4 Earthing

All the cubicles and boxes shall be provided with an earth bus of copper (PE) of the
cross section not less than 50 mm 2. All the metal parts to be earthed for safety
reasons shall be bonded to that bus. This bonding shall be factory-assembled and
shall form an integral part of the wiring system. The earth bus shall be provided with
terminals for earth conductors. The earth bus shall be neither switchable nor fused
and shall be solidly earthed.

5.5 Insulation Level

The insulation level for all the equipment supplied and installed in compliance with
these Special Technical Specifications shall conform to the IEC 60664 (Insulation
coordination for equipment within low-voltage systems).

5.6 Electromagnetic Compatibility

19 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

The equipment shall meet the requirements of electromagnetic compatibility within


its environment (IEV 161-01-07 and IEV 161-01-01). The equipment shall be tested
in accordance with Clause 7. of these Special Technical Specifications.

5.7 Corrosion Protection

Wherever applicable, corrosion protection shall be applied in accordance with the


General Technical Specifications.

20 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6. SPECIFIC REQUIREMENTS

6.1 General Considerations

The Monitoring systems equipment shall be in compliance with “up-to-date” technology,


experience in monitoring systems in hydro power plants and relevant international
standards. The design criteria shall be according to the modern engineering practice:
availability, limitation of number of links, accessibility, separation between different sub-
systems, etc. With applied technology, the Contractor shall ensure operational safety
and installation availability.

The equipment supplied under the Contract shall be new, unused, of the most recent
or current models and they incorporate all recent improvements in design and materials
unless provided otherwise in the Contract. The equipment shall have no defect, arising
from design, materials, or workmanship or from any act or omission of the Contractor,
that may develop under normal use of the supplied equipment in the conditions
prevailing in the country of final destination.

The performance of the monitoring system devices (settings, accuracy, etc.) specified
by the Contractor in the design documentation shall be strictly guaranteed.

All electronic components shall be from proven technology design and in accordance
with electromagnetic compatibility standards.

Since this system is particularly important for installation safety, the Contractor shall
take all necessary steps to obtain a Monitoring system having a high availability factor.

The system shall be insensitive to external perturbation. Accordingly, the Contractor is


required to ensure that the supply corresponds to the criteria of the specification
concerning perturbation.

The Contractor shall ensure that equipment using different technologies and employed
in this system is capable of operating together without causing system unwanted
operation or miss operation.

The Contractor can offer lesser or greater number of cubicles than specified, provided
that they comprise all the specified equipment and that they retain the required
functions distribution, but any change in number of cubicles shall be possible only if
approved by the Employer.

Cubicles shall be completely equipped, wired and tested.

Number of cubicles, their respective sizes, arrangement of the components etc. shall
be subject to the Employer’s approval.

6.2 Unit vibration system

6.2.1 General

The vibration monitoring system will be implemented as a distributed system. The


distributed system implies the installation of special units - IED for monitoring
vibrations for each generating unit, connected through a special communication
network with a common computer for vibration analysis and diagnostics, or a central
monitoring computer.

The vibration monitoring system of each generating unit consists of the following
equipment:

21 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

 sensors with necessary electronics (transducers) and carriers;


 connecting cables, connection boxes with accessories (protective hoses,
cable glands, etc.);
 Data collection units (IED) of vibration monitoring.
 In addition to this equipment, the following common equipment is also
foreseen:
 Software for analyzing and diagnosing the vibrations of both generating unit,
installed in the central computer monitor and
 A laptop for programming and configuring the vibration monitoring system.

6.2.2. Functional requirements

As the vibration parameters of the generating unit directly depend on its operating
mode (rotational speed, load, etc.), all necessary data for vibration analysis and
diagnostics will be provided via the IED connection for vibration monitoring with the
appropriate generating unit process station, i.e. generating unit control system.

The vibration monitoring system will also have a protection function. For this purpose,
a hard-wired connection will be realized with the control and protection systems of
the generating unit, which will be used for signaling of alerts and alarms, as well as
the issuance of the emergency alarm command for generating unit.

Warning and alarm signals from the vibration monitoring system, refer to signals such
as: vibration above the permitted level, IED monitoring vibration failure, etc.

6.2.3. Monitoring equipment

6.2.3.1. Sensors

The sensors will be selected taking into account the following:

 part of the generating unit on which the measurement is performed


(measuring point);

 possibility of setting the sensor;

 the type of measurement performed by the vibration monitoring system;

 the conditions governing the measuring site and its surroundings;

 the number of sensors needed to obtain the necessary data;

 measuring parameter;

 output sensor size;

 necessary conditioning of the signal for its adjustment to the input of the
monitoring system.

The vibration monitoring sensors will be installed on each unit at the following
locations:

 Relative vibrations
 a combined generator bearing in the upper cross, in two radial
interconnected steering axes (X, Y);
 the guide generator bearing in the lower cross, in two radial
interconnected steering axes (X, Y);

22 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

 turbine guide bearing, in two radial axes (X, Y).


 Absolute vibrations
 a combined generator bearing in the upper cross, in two radial
interconnected steering axes (X, Y);
 a guide generator bearing the upper cross, in the axial direction (Z);
 the generating bearing in the lower cross, in two radial
interconnected steering axes (X, Y);
 generator housing, in two radial interconnected steering axes (X, Y);
 turbine guide bearing, in two radial axes (X, Y).
 turbine cover, in axial direction (Z).

6.2.3.2. IED vibration monitoring

The basic functions of IED monitoring of aggregate vibration will be:

 Acquisition of signals from vibration sensors (including monitoring of working


conditions based on defined criteria for evaluation of measured quantities);
 processing of protection signals (warnings and disconnections) based on
programmed limit values;
 preparing data for the operator panel and forwarding to the panel;
 Receiving orders from the operator panel and their execution;
 processing of signals for analysis and diagnostics;
 communication with the central monitoring computer;
 transfer of data to the generating unit processing station to the control system
and protection of generating unit
 monitoring the correct operation of sensors and other inferior devices, as well
as the correctness of their own work and reporting errors to the superior
system;

The IED will have a modular system that achieves:

 the flexibility of the device in terms of the possibility of adjusting the input of
the type of measurement and the sensor;
 cost-effectiveness with regard to the need to store spare parts;
 Easy maintenance;
 the ability to quickly reconfigure the device;
 Easy diagnostic failure.

The IED will be based on a microprocessor and will be equipped with a


communicational controller for network operation with a master computer, a real-time
clock, and an operator panel with a display. It will have enhanced mechanical
protection and will be designed to operate under conditions of significant
electromagnetic influences operating in the power plant.

The IED will be equipped with coupling modules for connecting with vibration
sensors, complete with a unit that provides data transfer between the coupler
modules and the microprocessor.

Each measuring channel within the IED will contain a complete measurement system
with implemented functions necessary for reliable monitoring of the vibration
condition of the generating unit. Microprocessor control ensures easy adjusting of the
system's generating unit characteristics (adjusting the frequency characteristics of
the measuring chain, warning and hazard warning limit values, relay response mode,
time tensing, etc.). With regard to the programming of IED functions, IEC 61131-3 is
envisaged to be used.

6.2.3.3. Signal cables

The contractor will deliver all the necessary signal cables, including the necessary

23 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

cable accessories and installation material, in order to connect the sensors from the
IED monitoring vibrations, as well as the cables and accessories used to connect the
IED equipment to the vibration analysis computer. All cables entering the machine
will have a maximum temperature of 200 C degrees.

Signal cables for connecting sensor outputs will be screened and paired.

The contractor will determine and deliver cables of certain lengths and types, which
will be insensitive to the disturbances.

The signal cable must not interfere normal operation and maintenance of the
generating unit.

6.2.3.4. Terminal boxes

The contractor will deliver the connection boxes in order to enable the continuous on-
line monitoring equipment to be switched off without disconnecting the generating
unit operation.

The connection box will be mounted outside,on the generator housing and will be
designed for internal mounting and there will be at least an IP55 degree of mechanical
protection class.

The terminal boxes will be of such size that they accept all signal cables.

6.2.3.5. Software for vibration analysis and diagnostics

The software for vibration analysis and diagnostics should provide the following
analysis: forecast of the trend, spectrum and harmonics. It should also enable
dynamic determination of limit values (alarm thresholds) based on standard deviation
of stored measured values, envelope transient vibrations, etc. and their forwarding to
the appropriate IED monitoring vibrations.

The software for vibration analysis and diagnostics performs the main part of signal
processing in order to determine complex real-time monitoring parameters, such as:

- the trend of the quantities determined on the basis of measurements in a


wide frequency band;

- obtaining spectra of vibrations and their analysis;


- the trend of the spectral components of the discrete spectrum of vibrations;
- the trend of the quantities determined on the basis of measurements in a
narrow frequency band;

- cascading analysis ("waterfall");


- Bode diagrams, Nyguist diagrams and polar diagrams;
- orbit the shaft.

6.3 Monitoring of partial discharges on the generator stator windings

6.3.1 General

The system for measurement and monitoring of partial discharges is intended for
continuous monitoring of important parameters of the state of insulation of the
winding of the stator, as well as for monitoring their dependence on dynamics and

24 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

changing the conditions during the operation of the generator.

This method will meet the following requirements:

The level insulation will be tested during the operation of the generator, in working
conditions in which the electric, magnetic, thermal and mechanical stresses of the
generator are present;

The tests will not require a change in the generator operating mode;

Permanently installed sensors for measuring partial discharges, which represent safe
passive components, will be selected in order not to endanger and disturb the
operation of the generator.

The partial discharge monitoring system will consist of 4 permanently installed high
voltage capacitive sensors, 1 (one) per phase (on the generator rotor), and 1 (one)
in the star connected with the connection box and the acquisition coaxial cable,
impedance 50 .

The partial discharge monitoring system for measuring on generator stator windings
shall be consisted of the following:

- sensors,

- coupling / clamp boxes with connecting terminals,

- analyzers and other equipment for data collection (for signal conditioning,
preamplifiers, etc.).

- VN cables used for connections between the stator windings and the
sensor and

- connecting cables, distribution boxes with accompanying accessories (pipe


and cable boxes, cable seals and connectors), used for connection
between sensors and connecting boxes, as well as for connection between
connection boxes and data collection equipment.

6.3.2 Functional requirements

The main goal of continuous monitoring and analysis of partial discharge parameters
is the clear identification of their origin, the identification of location and type of failure,
and the tracking of defect development trends in insulation.

The system will enable and evaluate the type and location of the increased values of
partial discharges (approximate location), following the following parameters:

- the value of the partial discharge current (expressed in pA), which directly
affect the integral values of the partial discharges, and

- maximum magnitude (expressed in pC), which represents the current


value of partial discharges.

- Phase distribution of impulses of apparent discharge polarization.

The alarm system function for monitoring and analyzing the partial discharge
parameters is formed on the basis of exceeding one of the following two criteria:

25 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

- the level of electrical impulse of partial discharges (pC), i

- partial discharge current level (pA)

Analysis of the results and partial discharge diagrams serve to identify the basic
problems in stator windings at the following locations:

- between the surface of the insulation of the rods and the stator core,

- near the copper surface of the rod

- in the isolation cavities,

- at the output of the rod from the stator core (head of the rod),

- at inter-phase distances (distances between rods of different phases),

- partial discharges caused by impurities, residual conductive materials (for


example during overhauls, etc.), unwanted shards caused by damage, etc.

For the purpose of continuous monitoring of the stator winding isolation status, the
analog signals of the operational status of the generating unit will be forwarded from
the control system to the system for monitoring and analyzing the partial discharge
parameters.

The generating unit control system will collect the following alarms generated by
the IED monitoring of partial discharges:

- partial discharge parameters – high alarm,

- IED partial discharges - error and

- measuring loop (sensor) - error.

6.3.3 Monitoring equipment

6.3.3.1 Sensors

The sensors will be designed for high-frequency pulse signals of partial discharges
occurring in the rotary machine. The sensors will be permanently mounted in the
vicinity of the generator outgoing bus bars, with the connection of the high voltage
sensor and bus bar connections. Sensors must be made in accordance with IEC
60034-27-2, point 6.4.

The sensors will be capacitive, with a capacitance of 80 pF, 6.9 kV, made from mica
epoxy capacitors (EMCs), known as PDA coils. In this way, the required sensitivity
and necessary voltage levels of the test are achieved, which will allow the sensors to
be adapted and the out-of-line partial emission tests, that is, the results of the online
and on-line tests and diagnostics will be directly comparable.

The sensors will be specially designed for PD applications including appropriate anti-
tracking functions. They should include a cyclo-alfa epoxy surface and an electric trail
of at least 25 mm / kV phase voltage.

The sensors will have an extremely low inductance so that the simulated PD pulse
with a rise time of 1 ns result in an output impulse less than 3 ns.

26 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

The sensor design, that is, the measuring impedance, should enable proper signal
filtering.

The contractor will also supply and install installation accessories including sensor
mounts, and HV connecting cables.

6.3.3.2 Partial discharge analyzer

The subject analyzer should be constructed for the analysis of measured partial
discharges. It will be connected to the sensors via the appropriate signal cables.

The analyzer will be designed as an independent unit, that is, it will not require
external control.

The data analyzer must have functions to allow the following:

- eliminating noise in the time and frequency domain,

- elimination of disturbances in the frequency domain,

- collecting data on current measurements on the generator,

- displaying the number, value and phase distribution of positive and


negative impulses for each winding,

- indication of the stator winding status

- adjustment of the refresh rate of measurement,

- self-diagnostics to ensure proper functioning and reliable measurement,

- archiving on the hard disk server according to the given dynamics,

- the alert level, which can be selected for each input pair,

- data archived every day, in a maximum of three sensitivity ranges: user


defined, automatically adjusted based on recent measurements and a
certain PD level of alert

- memory capacity up to 24 months, with data exchange on the base first in


the first out.

6.3.3.3 Signal cables

The contractor will deliver all necessary signal cables, including the necessary cable
accessories and installation material, in order to connect the sensors with the partial
discharge analyzer, as well as the cables and accessories used to connect the
analyzer equipment and the computer to analyze the partial discharges.

Signal cables for connecting the sensors will be 50 Ω RG58 C / U coaxial cables and
must be guided along the conductive, grounded metal surface or inside the earthed
metal hoses (pipes).

The contractor will determine and deliver cables of certain lengths and types, which
will be insensitive to the disturbances.

The signal cable must not interfere with the normal operation and maintenance of the
generating unit.

27 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6.3.3.4 Sensor connection boxes

The contractor will deliver the connection boxes to enable the separation of
continuous on-line monitoring equipment without interrupting the operation of the
machine.

The connection box will be mounted from the outside, to the housing of the generator
and will be designed for indoor installation with at least IP55 degree of mechanical
protection class.

The terminal box is connected to the partial discharge analyzer using 4 coaxial
impedance cable 50 . It has three functions:

fixing coaxial cables from the partial discharge transmitter to a permanent position so
that the analyzer can be separated without breaking the ends of the coaxial cables
from the encoder;

- connection and grounding of coaxial cable arrays.

- overvoltage protection.

The terminal box will be of such a size that it functionally accepts all signal cables
and should include:

- BNC connectors

- Earthing point (screw)

- Overvoltage protection circuitry to prevent the occurrence of dangerous


voltages on every part of the box and at any time

- resistor connectors for generating a voltage reference signal of the


industrial frequency required for continuous on-line PD monitoring
instruments.

The connections in the sensor connection boxes between the signal cables and the
corresponding terminals will be performed by soldering.

6.4 Air gap monitoring

6.4.1 General

The air gap of the generator is variable during exploitation, but it is important that
the air gap value does not exceed the permissible limits. Therefore, it is
necessary to install the appropriate number of measuring sensors (encoders) in
several positions that will be able to monitor the gap

gap and which will pass the measured values into the monitoring system.

The system will enable continual on-line monitoring of the parameters of the
generator's jamming, without interrupting the generator operation.

The air gap monitoring system of each generating unit includes the following
equipment:

- sensors with the necessary electronics (transducers),

- connecting cables, distribution boxes with accompanying accessories


(pipes and boxes for cable protection, cable seals and connectors) and

28 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

- analyzer and other data acquisition equipment.

6.4.2 Functional requirements

The system must be able to monitor the air gap parameters and be used to collect
data as a continuous monitoring system with a protective function, and to be used
for review of real-time data during commissioning or maintenance.

The main functions of the subject monitoring will be:

- The minimum value of the air gap and the number of poles to which the
value relates, per one rotation,

- The maximum value of the air gap and the number of poles associated
with the value, per revolution,

- Mean air gap value,

- The current value of the air gap shown as the sex profile in real time,

- Stator and rotor shape with static and dynamic reference center,

- Stator circle,

- Concentricity of the stator and

- Concentricity of the rotor.

The air gap monitoring system will also have a protective function. For this
purpose, a cable connection with the unit control and protection systems will be
realized and will be used for signaling of alerts and alarms, as well as for issuing
the command for unit emergency shutdown. Warnings and alarm signals from
the air gap monitoring system refer to the following signals:

- Air gap values low - alarm,

- Air gap values too low – the generating unit stopping,

- IED air gap - error and

- Measuring loop (sensor) - error.

29 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6.4.3 Monitoring equipment

6.4.3.1 Sensors

The contractor will deliver and install the necessary sensors for detecting the air
gap value between the stator and the rotor.

The air gap sensor will be installed directly on the iron core of the stator at the
height of the rotor, in radial direction at an angle of 90 ° and as minimum
workload, 4 sensors will be installed.

The contractor will determine the optimum location of the air gap monitoring
sensor.

The subject sensors will be capacitive, non-contact type, which have temperature
compensation.

The linear measurement range should be 5-25 mm, operating temperature 0-125
° C and contamination should not have any effect on the operation of the sensor.

6.4.3.2 Air gap monitoring analyzer

The contractor is obliged to provide equipment for the continuous collection and
analysis of airborne data for the purpose of permanent installation in the
monitoring cabinet. The air gap analyzer will be specially designed for use with
permanently installed sensors on hydro-generators.

The subject analyzer should be designed to analyze the air gap parameters
between the stator and the rotor of the generating unit. It will be connected to the
sensor connection block via the appropriate signal cables.

The analyzer will be constructed as a separate unit and will not require external
monitoring and control or a computer.

The basic functions of an analyzer for monitoring the air gap will be:

- collecting data from the sensor;

- monitoring of working conditions based on predefined criteria for


estimation of measured variables (current value, minimum, maximum,
mean value and difference of the air gap in the poles of the rotor at
which the measurement is performed)

- generate alert and alarm signals (alarm, stop aggregates) based on


predetermined limit values and provide output contacts for selected
signals. The alarm setting will be enabled in accordance with the
different operating conditions of the generating unit.

- processing of signals for the purpose of analysis and diagnostics;

- accepting the selected data on the generating unit from the power
plant control system;

30 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

- communication with the computer for the analysis and diagnostics of


the air gap of all generating units, ensuring the transmission of data
on measured and exceeded limit values (alerts and alarms).

6.4.3.3 Signal cables

The Contractor will supply all required signal cables, including the necessary
cable accessories and installation material, in order to connect the sensor to the
air gap analyzer, as well as the cables and accessories used to connect the
analyzer equipment and the computer to analyze the air gap. All cables entering
the machine will have a maximum temperature of 200 C.

Signal cables for connecting sensor outputs will be screened and paired.

The contractor will determine and deliver cables of certain lengths and types,
which will be insensitive to the disturbances.

The signal cable must not interfere with the normal operation and maintenance
of the unit.

6.4.3.4 Terminal boxes

The contractor will deliver the connection boxes in order to enable the continuous
on-line monitoring equipment to be switched off without interrupting the
generating unit operation.

The connection box will be mounted from the outside, to the generator housing
and will be designed for internal mounting and there will be at least an IP55
degree of mechanical protection class.

The terminal boxes will be of such size that they accept all signal cables.

6.4.3.5 System data analysis and diagnostic equipment

Subsystems of the monitoring system will be implemented as distributed


systems.

The distributed system implies a separate IED monitoring for each generating
unit connected to a shared computer for monitoring analysis.

The computer will be used for reading data, tracking trends (measurement
history), setting system software parameters and diagnostic analysis.

Well-designed procedures, obligations and responsibilities, as well as the way of


presenting the results, the time and frequency of measurement, the limits of
acceptable values, the occurrence of alarms and a number of other computer
conditions will be set to measure the monitoring system, after installing the whole

31 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

system, in order to get usable diagnostic results.

32 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6.5 Magnetic flux monitoring system

6.5.1. General

The system will enable continuous on-line testing of the total magnetic flux (induction)
of the rotor, in order to recognize the change in the state of interconnected insulation
on the pole of the rotor, that

is, to recognize the broken rotor winding coils, without interrupting the generating unit
operation.

This method will meet the following requirements:

- the testing of the condition of the rotor winding insulation will be carried out
during the operation of the generator, under operational conditions in
which the electric, magnetic, thermal and mechanical stresses of the
generator are present;

- the tests will not require a change in the generator operating regime;

- permanently installed sensors for measuring magnetic induction, which are


reliable components, will be selected so as not to endanger and disturb the
operation of the generator.

The monitoring of the magnetic flux for measurements on the windings of the
generator rotor consists of the following equipment:

- sensors,

- sensor signal conditioning boxes,

- analyzers and other equipment for data collection,

- connecting cables, distribution boxes with accompanying accessories (pipe


and cable protection boxes, cable seals and connectors), used for
connection between sensors and data collection equipment.

6.5.2 Functional requirements

The basic functions of the subject monitoring system will be to identify the following
states of the magnetic circuit of the generator:

- Minimum and maximum magnetic flux of the pole,

- The magnetic flux profile of the pole,

- Interconnected short circuit of the winding of the half rotor,

- The state of the magnetic circuit symmetry, as well as other magnetic sizes.

For the purposes of continuous monitoring of the status of the interconnected


insulation of the winding of the rotor, as well as the magnetic circuit conditions, the
analog signals of the operational status of the generating unit will be transferred from
the control system to the system for monitoring and analyzing magnetic flux
parameters.

The unit control system will collect the following alarms generated by the IED

33 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

monitoring of the magnetic flux:

- high / low magnetic flux parameters - alarm,

- IED magnetic flux error and

- measuring loop (sensor) error.

34 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6.5.3 Monitoring equipment

6.5.3.1 Sensors

Magnetic flux sensors will be installed directly on the iron core of the stator to avoid
any damage to the package. It will be fixed to the stator core using a special epoxy
resin.

The contractor will determine, create and install an optimum type and number of
magnetic flux sensors for each of the generating units. The contractor will determine
the optimum location of the magnetic flux monitoring sensor.

Magnetic flux sensors must be specified and designed for application. One sensor
will be a semiconductor (Hole probe) that will allow the measurement of maximum
pole induction and the other will be inductive (winding) which will allow monitoring of
changes in magnetic induction.

The contractor will determine, create and install an optimal type of synchronization
sensor for each of the generating units, if the application so requires.

The synchronization sensor will be dimensioned to produce one signal after the
rotation of the generating unit and will be mounted at the height of the shaft, on a
fixed structure (such as the bearing housing).

If the Contractor delivers a synchronization sensor, it will provide specifications for


the composition of the material, dimensions and the intended marker mark on the
shaft.

6.5.3.2 Magnetic flux monitoring analyzer

The contractor is obliged to provide equipment for continuous collection and analysis
of magnetic flux data for the purpose of permanent installation in the monitoring
cabinet. The magnetic flux analyzer will be specially designed for use with
permanently installed sensors on hydro-generators.

The subject analyzer should be designed for the analysis of magnetic flux parameters
between the stator and the rotor of the generating unit. It will be connected to the
sensor connection block via the appropriate signal cables.

The analyzer will be constructed as a separate unit and will not require external
control and control or a computer.

The analyzer will use predefined algorithms for detection of an interconnecting


winding connection without the need to change the load of the generator.

The analyzer will sort flux data, like alarms and regular, depending on whether the
data exceeds the set detection threshold of the interconnect, or not.

The analyzer will have at least 3 integrated relay outputs (for transmission of system
failure signals, exceeded set alarm values on the generator) and 3 integrated relay
inputs as well as communication outputs (Ethernet TCP / IP RS485, Modbus - TCP,
Modbus - RTC).

6.5.3.3 Signal cables

The contractor will supply all required signal cables, including the necessary cable
accessories and installation material, in order to connect the sensor to the analyzer,
as well as the cables and accessories used to connect the equipment of the analyzer

35 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

and the computer to analyze the magnetic flux parameters. the cables will be securely
fixed to the tooth of the magnetic core of the stator, using the supplied epoxy resin
compound, to prevent displacement due to vibration or air flow.

Signal cables for connecting sensor outputs will be screened and paired, and
resistant to high temperatures.

The contractor will determine and deliver cables of certain lengths and types, which
will be insensitive to the disturbances.

The signal cable must not interfere with the normal operation and maintenance of the
generating unit.

6.5.3.4 Boxes for signal conditioning

The contractor will deliver the connection boxes, in order to enable the continuous
on-line monitoring equipment to be switched off without interrupting the generating
unit operation.

The connection box will be mounted from the outside, to the housing of the generator
and will be intended for internal mounting and there will be at least an IP55 degree
of mechanical protection class.

The terminal boxes will be of such size that they accept all signal cables and
appropriate coupling equipment.

6.6 Monitoring the temperature of the rotor

6.6.1 General

The temperature monitoring system of the rotor consists of measuring the


temperature of the poles of the rotor and, above all, the temperature of the
intermediate bonds, in order to create a thermal image of the rotor.

The rotor temperature monitoring system will consist of the following parts:

 a series of intelligent encoders (sensors) for measuring temperature;


 data transmission system (stationary part on the stator and moving part
on the rotor);
 Measuring acquisition units for measurement control and data collection
and processing;
 cables for connecting with auxiliary equipment (protective pipes, cable
glands, etc.);

6.6.2 Functional requirements

The data transmission system consists of two units:

 The first unit is located on the rotor,


 The other unit is on the stator.

Data transfer between units is done using radio waves.

Data exchanged between the monitoring system and the generating unit process

36 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

station are:

 actual temperature values at all measuring points;


 Overstatement of the first degree temperature - alarm;
 Overstatement of the second degree temperature – shut down;

6.6.3 Monitoring equipment

6.6.3.1 Sensors

Since the rotor of each generator has 10 salient poles and 20 electrical couplings,
the total number of measuring points or sensors is 40, because it is necessary to set
up 2 sensors per gender (1 main and 1 spare) and one per coupler. Fans are placed
in the hottest places on the poles.

6.6.3.2 Unit for Measuring and Acquisition

The Unit for Measuring and Acquisition is designed for permanent installation at the
plant and collects data from the permanently installed temperature sensor from the
rotor of the hydro generator. The analyzer should have such hardware ship-software
performance to maximize the capabilities of the encoder. The conditioner of the signal
and should have such performance to optimally condition the encoder signals.

The analyzer will function as an independent unit, but it is also intended for work in
the complex monitoring system. The analyzer exchanges data with the database
(central monitoring computer) and the process station of the generating unit so that
for the diagnosis of the situation, no procedure of changing the regime and power of
the generator is necessary. The acquisition unit should have a certain number of
inputs for temperature measurements.

6.7 Computer for monitoring vibration, partial discharges, magnetic flux, air gap and
rotor temperatures

The software package for process control, acquisition and data analysis in connection
with partial discharges and air gap will allow the following:

- programming the process of measurement and their processing;

- control of the conditions under which the measurements will be performed;

- a graphic representation of the parameters being monitored;

- defining alarm levels and recording alarm events;

- monitoring trends of selected values;

- monitoring of operating parameters of the generator;

- monitoring other selected data;

- collecting vibration data, partial discharges, magnetic flux, air gap and rotor
temperatures and their archiving into a database, those measurements

37 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

available to the user for display and trending.

- collecting data on vibration by partial discharges, magnetic flux and air gap,
and their archiving into the database, the latest measurements to the user's
account.

- display in the form of a table relating to the impulses detected and classified
according to the following:

• Partial discharge impulses from the machine,


• noise and interference impulses coming from a connected system,
• other impulses.
- graphical representation of the air gap schedule according to the number of
the given sex (gender profile);
- numerical result of the state analysis (minimum air gap, maximum
differences in induction and gap);
- display of the shape of the stator and the rotor (circular shape and shape)
and the polar view of the stator and the rotor on the same diagram with the
dynamic representation of the rotor exertion in the orbit shape.

- calculation of the excentricity between the stator and the rotor;

- calculation of the real minimum and position of the air gap;

- minimum air gap for each individual sensor and minimum polar rotation index
for each sensor;

- maximum difference between adjacent poles and gender index;

- Diagnosing vibrations, partial discharges and air gap to ensure proper


functioning.

The computer will be based on PC technology, with a 24 "LCD color monitor and
keyboard with a mouse, and will be equipped with a controller for working in the"
Office "LAN, through which data exchange with other systems within the hydro power
plant is performed, as well as with the controller for operation in its local network,
through which it exchanges data with IED monitoring of partial discharges and air
gap.

6.8 Laptop for programming the configuration of vibrations, partial discharges,


magnetic flux, air gap and rotor temperature

The laptop will be used for:

- configuration of partial discharge monitoring system, magnetic flux and air gap
monitoring,

- "on-line" and "off-line" diagnostics and testing of monitoring systems,

- setting / setting parameters,

- modification and maintenance of service programs,

- Creating and modifying screen displays,

- Creation and modification of the report.

For this purpose, the laptop must have all the necessary interfaces to connect with

38 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

the monitoring system equipment.

6.9 Step-up Transformer monitoring system

6.9.1 Functional requirements

For the needs of continuous (on-line) monitoring of the condition of the step-up
transformer, measurements and analyzes of the temperatures of the transformer
parts and the content of gases in the oil will be carried out as follows:

 Monitoring the temperature of the active components of the transformer


(winding, magnetic core), as well as the oil temperature;
 monitoring / analysis of the content of gases in oil;
 processing of signal protection (alarm and switch-off) based on programmed
limit values;

 Diagnosing and evaluating the life of transformers.

As a minimum requirement, for monitoring transformer conditions, the following


values and events will be detected by the sensors:

 the content of gas in oil;


 presence of moisture in oil;
 humidity of the air in the conservator;
 oil temperature in the transformer vessel;
 oil temperature in the conservator;
 winding temperature;
 core temperature.

As a minimum requirement, during the operation of the transformer, the following


gases will be detected:

 hydrogen (H2);
 carbon monoxide (CO);
 methane (CH4);
 acetylene (C2H2);
 Ethylene (C2H4).

6.9.2 Monitoring equipment

The system for monitoring new block transformers will include the following
equipment:

 sensors including temperature detectors (thermal sensors);


 IED transformer monitoring unit;
 measuring converters;
 connecting cables;
 Computer for analysis and diagnostics.

The transformer temperatures will be measured continuously (on-line) and will be


displayed on the IED monitoring units (via measuring converters). Temperatures will
be measured through installed resistor thermometers (Pt100 probes).

All the measured values will be processed from the sensor to the IED monitoring of
the transformer, and the values saved for diagnostics and analysis. The
measurements will be on - line type and given that the values obtained depend on

39 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

the transformer 's operating mode, the following parameters will be taken into
account:

 transformer voltage;
 transformer current;
 transformer power (active and apparent).

In order for all the above parameters to be available, IED will receive current and
voltage data.

IED monitoring will have serial communication interfaces that will be used to connect
to the block of transformers (RBT) analysis and diagnostics computer.

The IED of each step-up transformers T1 and T2 will be placed in a separate


enclosure for mounting in the transformer cabinet (+ 1TM1) and (+ 2TM1).

The monitoring cabinet will be standard metal structures, designed for wall mounting,
completely mechanically finished and equipped with all electrical installations and
devices for the purpose of monitoring step-up transformers. Monitoring cabinets will
be placed in vicinity to the transformer.

The control blocks of step-up transformer will be the degree of mechanical protection
IP54

according to IEC 60529.

6.10 Requirements for the generating unit monitoring cubicles

The cubicles must comply with the requirements defined in the General Technical
Specifications.

The cubicle monitoring unit will be free-standing, measuring 800 x 800 x 2000 mm
(WxDxH), degree of mechanical protection IP54, in accordance with IEC 60529
standard.

The cubicle will be located next to the excitation system, in the powerhouse, at the
generator level 437.28 m.a.s.l.

The cubicles will be for indoor installation, fully equipped, wired and tested.

The cubicles will be equipped with fans and condensation heaters. In addition, each
cubicle will be equipped, on the inside, with a fluorescent lamp, which is switched on
/ off using a door-mounted switch, providing even light in all parts of the cubicle.

The thickness of the steel sheet must not be less than 2 mm.

The cubicle will be available only from the front. Access from the back will be subject
to the approval of the Employer. The equipment inside the cabinet will be mounted
on a steel plate.

In addition, each cabinet will be equipped, on the inside, with a fluorescent lamp that
is switched on / off using a door-mounted switch, ensuring even light in all parts of
the cabinet.

All doors must be equipped with an opening and closing handle and properly sealed
on the edges and equipped with a lock and a key.

The construction of the cubicle must be such that it allows the input and output of the
cables from the bottom of the cabinet.

40 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

The internal arrangement of the equipment should be such as to provide easy access
to any part of the equipment fixed to the carriers.

The equipment of individual generating unit monitoring systems will be located in the
appropriate racks, and access to the equipment will be enabled on the front of the
cabinet. The cabinet will be equipped with the appropriate auxiliary equipment for
indoor lighting, heating and ventilation.

The equipment in the cubicle will be powered by a voltage of 230 V, 50 Hz


uninterruptible power, ie voltage 0,4 kV, 50 Hz for the needs of general consumers
(heating, cabinet lighting, sockets, etc.) from the sub-distribution board of the control
panel. Other voltage levels required for the operation of individual equipment in
monitoring systems, such as 24 V jss and the like, will be formed within the system
itself, suitable converters, isolation transformers, and the like.

The appropriate operator panel will be installed on the cabinet door, which will allow:

• display of the state of the generating unit;


• display of the current parameters of the measured values of the monitoring of
the generating unit;
• reading data from a database with the appropriate display format (tables,
graphics, data grouping, etc.);
• configuration of individual IEDs;
• Switching the IED to the test mode.

6.11 Low voltage power, control and signaling cables

All cables shall comply with requirements stated in General Technical Specifications.

Connecting equipment includes cables, cable accessories and necessary erection


material as well as cable trays and racks at places where the existing trays and racks
cannot be used.

The Contractor is obliged to supply and provide the connections (control, signaling,
measuring, power supply and communication cables) between the equipment specified
in this Section.

6.12 Maintenance Criteria

The Contractor shall take all necessary steps to facilitate equipment maintenance.

The equipment shall be designed to minimize the number of different parts normally
requires replacement for wear and tear during operation.

The Contractor shall ensure the supply of all the components of the monitoring systems
subject to maintenance, for the life time of the equipment. In addition, if some of these
components are liable to evolve, the Contractor shall guarantee the compatibility of
these components with the supplied systems without the need for adaptation.

6.13 Availability, Reliability, Maintainability and Safety

The equipment described in this specification shall have the following availability

criteria. The failure shall be defined as:

– any failure leading to inadvertent operation

– any failure leading to non-operation.

41 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

The real availability shall be measured during the availability test.

The required reliability shall be defined by two (2) years for each circuit comprising
measurement circuits, function block, output relay and power supply. To meet the
reliability and availability objectives of each piece of equipment, and for the entire chain,
the Contractor shall submit to the Employer a file including:

– a reliability breakdown for each main function

– a description of the calculation method used

– the mean value adopted for failure rates affecting each component with all
necessary sources and justifications.

6.14 Training of the Employer’s Personnel

6.14.1 General

Training of the Employer’s personnel for operation and maintenance of the Units
Monitoring Systems equipment shall be fully in compliance with the stipulations of the
General Conditions of Contract.
Training for the Employer’s Staff will be executed in factories and on the Site in
accordance with Factory Training Program and Site Training Program of the Employer’s
staff.

The Contractor cannot limit the number of trainees, whereas the technical
documentation and other papers shall be provided for at least 5 representatives of the
Employer.

6.14.2 Training Scope

The training shall be arranged in such a way as to provide knowledge required for
efficient and successful operation and maintenance of monitoring systems. The
training shall be organized in various disciplines thus fully preparing the trainees to
take over particular responsibilities for system availability, i.e.

– Base training (management, operator and maintenance staff) on hardware


and software components and the system operation

– Training on maintenance of the system components (hardware and


software) and devices

– Data entry display and report creation (editing) training.

Training shall be held in Serbian language, whereas the pertaining documents may be
partly in English. Technical instructions and manuals for operators shall be in Serbian.
Training instructions for operation shall be separately prepared for this purpose.

Training shall comprise:

– Theoretical courses at the Contractor’s works

– Practical course at the Contractor’s works

– Structured courses at the Employer premise

– Practical work during site test and commissioning of the equipment and
devices (hardware and software)

42 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

6.15 Spare Parts

6.15.1 General

The spare parts shall include the items listed in the Schedules of Prices for the
specified spare parts.

All spares furnished shall be interchangeable with the corresponding original parts.

All spares shall be suitably treated for long storage under the climatic conditions
prevailing at site. Each spare shall be clearly marked and labeled on the outside of
its package with description and purpose, and when more than one spare is packed
in a single case or container, a general description of the contents shall be shown on
the outside of such case or container and a detailed list enclosed inside.

For the proposed additional spare parts, the Contractor shall indicate the estimated
quantity necessary for a ten (10) years operation period.

6.15.2 Supply of Mandatory Spare Parts

The supply shall include the following specified spare parts for the Monitoring
systems equipment:

– two of each type of used sensors for Monitoring systems,


– 10 % of complete auxiliary equipment per system, but at least two units of
each relay type used in the Monitoring systems, specified by Detail Designs
for all Equipment Manufacture and Detail Design for Systems approved by
Employer.

6.15.3 Special Tools

If there is a need for some special tools and devices, necessary for the installation
and maintenance of the equipment defined by this Section, the Contractor shall
supply them with no additional costs to the Employer. Upon completion of works,
these special tools and devices remain property of the Employer.

The Contractor shall recommend and include in his scope of delivery a set of special
tools enabling the Employer to ensure proper maintenance and testing of the
Monitoring systems.

Maintenance software used for parameters or configuration adjustment, tests, or any


equipment lifetime operation shall also be included.

43 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

7. INSPECTIONS AND TESTS

7.1 General

In addition to General Technical Specifications, which shall apply relative to the


general test requirements, the following shall be also applied:

- Tests shall be carried out in order to determine whether the materials and
apparatus comply with the Specifications. All tests shall be arranged to represent
the working conditions as closely as possible. All test results shall be subject to
the approval of the Employer,

- All tests on the equipment both at the Manufacturer's factory and after completion
of installation at the site shall be made in accordance with IEC recommendations
if not otherwise agreed by the Employer. If the IEC recommendations are not
available for the particular tests, the scope, standard and methods applied shall
be specified by the Contractor and will be subject of approval by the Employer,

- Any additional tests apart of those specified below as may be needed to confirm
guaranteed data or to ensure the completeness and safety of the equipment shall
be performed as required by the Employer with no additional cost to the
Employer,

- Appropriate standard instruments and other measuring equipment necessary to


carry out the tests shall be provided by the Contractor,

- A written notice of the time and place of all shop tests shall be given to the
Employer at least 2 (two) weeks in advance, in order that he may be present if
he so desires. The Contractor will perform the testing in the presence of the
expert team of the Employer in order to introduce the Employer in detail with the
equipment that is going to be used in future. Contractor's records of all tests shall
be furnished to the Employer immediately on conclusion of each test,

- Following the tests at site, the Contractor shall at his own expense and within the
terms of the Contract, rectify any defect and replace any defective part, as
directed by or to the satisfaction of the Employer. After the rectifying of the
defects, upon the Employer’s request, it is mandatory for the Contractor to
perform the Tests once again, at his own expense,

- The details of the tests are given here below.

The Detailed Test Programs for workshop (factory) acceptance test (FAT) and site
tests shall be submitted at least 60 days before tests. The tests shall include at least
those tests specified in Clauses here below. These test programs shall contain, inter
alia, the procedures and all details on the methods and schemes of measurement,
conditions and conduct of the test procedures and the sequence of equipment
preparation and operation procedures to be followed, etc.

The Detailed Test Programs shall be approved by Employer 30 days after receiving
the documents.

7.2 Shop Tests

7.2.1 Tests During Manufacturing

Tests during manufacture for the monitoring equipment shall include tests and
verification of all properties and characteristics of all pertaining components,

44 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

assemblies and equipment (hardware and software).

All the material shall be tested by the Contractor and confirmed by the Employer,
prior to its use, in order to confirm compliance with applicable standards and nominal
characteristics. Suitability of application for the purpose shall be also tested.

The tests can be omitted if the Contractor possesses relevant type test certificates
and reports of the authorized laboratories for components, assemblies and other
equipment, subject to approval by the Employer.

As regards electromagnetic compatibility, the Contractor shall furnish certificates and


reports of the authorized laboratories confirming that the following tests have been
performed:

– Low frequency disturbance and interference (IEC 61000-1, IEC 61000-2-1-,


IEC- 61000-2-2, IEC 60034-1) that relate to the resistance of the equipment to
harmonics, intermediate harmonics, voltage fluctuations, voltage drop and
short-time interruptions of supply, voltage unbalances, changes of network
frequencies, DC components in AC power supply.

– Transient and high frequency disturbances and interference (IEC 61000-4, IEC
61000-4-4, IEC 61000-4-5, IEC 61000-4-6, IEC 61083-1, IEC 60255-26)
related to
testing of equipment on voltage and current impulses, such as:

 voltage/current impulse of the form 100/1300 s


 voltage impulse of the form 1.2/50 s; current impulse of the form
8/20s
 package of high frequency transient impulses (400 pack./s)
 oscillatory waves (repetitive transient waves)
 conductive radio frequency interference
 high frequency induced voltages etc.

– Electrostatic disturbances and interference – electrostatic discharges (IEC


61000-4- 2).

– Magnetic disturbance and interference (IEC 61000-4-8, IEC 61000-4-9, IEC


61000- 4-10, IEC 62052-11, IEC 62053-11) related to the resistance of the
device to mains frequency magnetic field and damped oscillating magnetic
field.

7.2.2 Factory Acceptance Tests (FAT)

Prior to start of the testing, all the equipment specified in Detailed Test Programs
shall be fully assembled and connected. The required hardware and software
simulation aids and interfaces for missing equipment shall be available.

The tests shall be conducted and documented in accordance with mutually accepted
tests configurations and procedures (specified in Detailed Test Program) at the
discretion of the Employer, who shall witness the tests.

Inspection and tests shall include at least the following:

Visual Inspection

Visual inspection of the Units monitoring cubicles complete assemblies for

45 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

mechanical construction and completeness; this inspection includes accessibility,


spacing, interchangeability of the components as well as terminals for connection of
control and power cables and earthing. Visual inspection also includes checking of
matching between documentation and manufactured equipment (e.g. circuit
diagrams, terminal diagrams, parts lists, layouts, labels, etc.).

Industrial frequency tests

All auxiliary voltage busbars and control circuits shall be subject to standard industrial
frequency tests.

These tests shall be carried out:

– between electric circuits of apparatus and instruments and their metal cover
lids, metal supports they are fixed upon and/or all other metal parts, between
cables and each conductor to earth by 2000 V, 50 Hz, AC for the period of 1
min, and by 500 V for DC circuit.

– On voltage to current circuits, i.e., and other independent circuits of


measuring instruments by

500 V, 50 Hz voltage.

Partial discharge sensors shall test according to IEC 60270:2000/BS EN 60270:2001.

Partial discharge sensors shall be subjected to a minimum of or 33 kV AC RMS for 1


minute.

The Contractor shall provide proof that the Partial discharge sensor design passes
the requirements of IEEE 1553 and meets ANSI/IEEE C37.20.2-1987. In addition,
proof shall be supplied that the Partial discharge sensors are capable of withstanding,
without breakdown, five (5) impulses of 150 kV crest.

Functional Tests

These tests shall be conducted on the Units monitoring equipment and they shall
include:

– Point to point tests for air gap channels, process parameter channels, digital
input/output channels.

– Installation tests for all groups of sensors, as well as for digital input/outputs.

– Power supply failure simulation.

7.3 Site Tests

7.3.1 General

On arrival at Site, during and after completion of erection, during commissioning and
trial operation period, all items of the equipment shall be inspected and tested.

The Site tests are subdivided into two stages:

- Tests during and after completion of erection

46 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

- Tests on Completion

7.3.2 Tests During and After Completion of Erection

In order to ensure correct installation of the equipment as well as to prove that the
equipment has been correctly installed, the following tests shall be performed during
and after completion of erection but before the commencement of Tests on
Completion the following shall be supervised and witnessed:

– Verification of proper and complete installation of the system cubicles

– Verification of proper and complete installation of monitoring sensors

– Checking of the wiring and interconnections, between the various parts of


systems and between these systems and other station equipment for conformity
with circuit and connection diagrams;

– Measuring of the insulation resistance of L.V. circuits in all cubicles and


comparison with the results from shop tests;

– Verification of wiring and connections with the power supply and earthing
systems.

7.3.3 Tests on Completion

Tests on Completion of the equipment shall take place after successful termination
of erection, tests during and after completion of erection and the issue of Ready for
Commissioning Certificate by the Employer.

Tests on Completion of the equipment shall be divided in three stages:

- Pre-commissioning Tests

- Commissioning Tests

- Trial Operation

7.3.3.1 Pre-commissioning Tests

Pre-commissioning tests which include the appropriate inspection and functional


tests to ensure the completeness and correctness of the equipment installed and to
demonstrate that each item of plant equipment can safely undertake the
commissioning tests.

At least the following tests on the control system equipment shall be performed:

- Verification of proper and complete installation of the equipment

- Test and checking of proper and complete installation of wiring and


interconnections between the supplied equipment;

- Verification of proper and complete connection to earthing system

- Withstand voltage tests of all low-voltage circuits

- Functional tests of monitoring equipment, including

47 / 48
Electric Power Industry of Serbia, Belgrade Tender Documentation ________________

 Checking of I/O modules operation


 Checking of all signalling circuits using signal simulation
 Checking of monitoring system equipment restart upon interruption of
power supply and redundant servers’ operation upon failover

7.3.3.2 Commissioning Test

Main objective of the tests is to check on proper and safe operation of the equipment
and functions execution and, in particular to verify and confirm performances and
characteristics as required in the Special Technical Specifications and the Schedules
of Technical Data.

Verification of the Monitoring system performances shall be conducted after the last
delivered piece of equipment has been delivered and put into operation.

For tests performing the applicable approved standards, essentially IEC Publications,
shall be observed.

The details of the methods of measurement, of the conditions, procedures, sequence


of tests and conduct of the test at site shall be in accordance with detailed site
commissioning program approved by Employer.

7.3.3.3 Trial Operation

Trial operation shall be performed in accordance with General Technical


Specifications.

48 / 48

You might also like