Professional Documents
Culture Documents
Transient Stability Analysis On AHTS Vessel Electrical System Using Dynamic Positioning System
Transient Stability Analysis On AHTS Vessel Electrical System Using Dynamic Positioning System
net/publication/332264742
CITATIONS READS
4 352
4 authors, including:
Some of the authors of this publication are also working on these related projects:
Technical Review of Fin Addition Analysis of Air Intake Valve on Gas-Oil Fuel Engine View project
All content following this page was uploaded by Muhammad Badrus Zaman on 14 April 2019.
Semin
Professor of Marine Engineering, Department of Marine Engineering,
Institut Teknologi Sepuluh Nopember, Surabaya, 60111, Indonesia
Soedibyo
Department of Electrical Engineering, Institut Teknologi Sepuluh Nopember, Surabaya,
60111, Indonesia
ABSTRACT
The addition of dynamic positioning system on offshore auxiliary vessels leads to
the installation of a large powered bow thruster. Unpredictable fieldwork conditions
lead to uncertain loading. Changes in electrical system configuration and load
shedding scheme are just a few of the many ways to maintain electrical system
stability. This method is done in order to balance the generator mechanical power
generated with the load needs. The configuration changes has been made and the
result was that the closed bus of 2 generator thruster and 2 diesel generator
configurations have excellent stability that can reach stable conditions with 110%
loading on each bow thruster. While Rhe closed bus configuration of 1 thruster
generator and 2 diesel generator provides an opportunity to rest 1 generator thruster
to save generator usage. However, the stability of this configuration can be improved
by conducting a load shedding scheme
Keywords: Dynamic positioning system, transient stability, system configurations,
load shedding.
Cite this Article: Sardono Sarwito, Semin, Muhammad Badrus Zaman and Soedibyo,
Transient Stability Analysis on AHTS Vessel Electrical System using Dynamic
Positioning System, International Journal of Mechanical Engineering and
Technology, 10(2), 2019, pp. 461-475-.
http://www.iaeme.com/IJMET/issues.asp?JType=IJMET&VType=10&IType=2
1. INTRODUCTION
Anchor Handling Tug Supply (AHTS) vessel is a ships that assigned specifically to support
offshore work generally required to install a system that make them different from any other
ships [1]. Reviewing the field conditions and the level of accuracy needed at work, the ships
must be equipped with a dynamic positioning system, a system that serves to control the ship
movement [2].
Uncertain field condition correspond to environmental factor can cause a system to run
into failure, more over on a ship which used closed bus configuration [3]. This failure can be
cause by some interference, whether it is short term (transient) or interruption which has
longer disturbance time. An electrical system is prone to interference, therefore the system
needs to have the ability to maintain its sync condition. This ability is called transient
stability. This transient stability disturbance can occur on ships equipped with dynamic
positioning system in case of overload on one generator, motor starting, and also short circuit
on component.
The addition of a large powered bow thruster can affect system stability if the system does
not have resistance to transient disturbances that are temporary. In the event of a transient
disturbance and the system cannot maintain its stability, there has been be a loose
synchronization of the generator and more fatal has been cause failure of the electrical system
[3].
Objective of this paper is to analyze the transient stability on AHTS vessel electrical
system using dynamic positioning system. The study of transient stability has been provided
an assessment of the stability of the ship's electrical system so that practitioners can find a
way out of the problem. Some ways to prevent the occurrence of stability problems is to
change the system configuration and also by conducted load shedding when the motor with a
large power has been do the starting.
buses, the design of a split bus configuration has been impact only on the affected bus,
effectively isolating the problem in the affected area only. The goal is to avoid system failure
due to a mistake in which the entire system can experience blackouts by isolating failures on
only one redundancy system [3].
Table 1 Variations of Frequency and Voltage According to American Bureau of Shipping Standard
Voltage and Frequency Variations
for AC Distribution Systems
Quantity in Permanent Transient Variations (Recovery
Operation Variations Time)
Frequency ±5% ±10% (5s)
Voltage +6%, -10% ±20% (1.5s)
3. METHOD
Before performing a transient stability simulation using the software, a single line diagram of
the AHTS vessel must exist as a reference for performing redrawing in the software.
Referring to the single line diagram, a system replication is drawed in the simulation software
according to the equipment specifications contained in the wiring diagram.
After the system is fully illustrated, the simulation of transient stability can be done by
using Transient Stability module in the software.
The results obtained from the simulation is the data in the form of voltage and frequency
per time unit. This data has been then be processed and analyzed so that the assessment of the
stability of the system can be done.
The simulation was run by conducting 2 study cases, motor starting and load shedding
action. The system later to be set into 6 different scenarios of configuration stated on the
Table 2. and by performing load shedding in the last scenario due to its configuration that
allows system to put 1 generator on standby. The load shedding scheme was done to improve
the system stability into its maximum ability.
Voltage and frequency response in the split plant configuration scenario 1 thruster
generator for each bow thruster shows that all load variations up to 100% load on the bow
thruster can be borne by the system stably. Over 100% loading on each bow thruster results in
stability of the system being disrupted. This is because the thruster generator can only provide
power reserves for the start of the generator up to 100% load, above that value the generator
cannot provide enough starting from the bow thruster.
to oscillate between the values of 104.35% and 88.82% during the simulation. While on the
bus D, there is a similar transient condition due to starting bow thruster where the voltage
experienced up and down from seconds to 2.01 then tend to be decreased drastically to the
value 77.14% in seconds to 3.21 and then jumped dramatically to the point 140.3 % in
seconds to 3.61. This condition does not conform to the ABS standard which states that the
tolerance of the voltage values under transient conditions is only allowed up to 20% above or
under stable conditions as well as recovery time of 1.5 seconds cannot be satisfied by the
system. In addition, the system also cannot reach a stable state because the voltage continues
to oscillate between the values of 104.35% and 88.82% during the simulation.
1 60% - 75% 97,196 97,196 C,D 98,6027 100,508 99,8 Normal Normal
2 100% - 80% 96,2364 96,2364 C,D 98,0374 100,97 99,8 Normal Normal
3 100% - 100% 95,8057 95,8057 C,D 96,1454 101,043 99,7 Normal Normal
Voltage and frequency response in the split plant configuration scenario 2 thruster
generators for 2 bow thruster shows the same result with the first configuration that all load
variations up to 100% load on the bow thruster can be borne by the system stably. Over 100%
loading on each bow thruster results in stability of the system being disrupted. This is because
the paralleled thruster generator can only provide power reserves for the start of the generator
up to 100% load, above which the generator cannot provide enough starting from the bow
thruster. This happens because the ratio of the amount of power generators can generate with
the data required by the load is still the same as in the previous configuration.
Configuration of split plant 1 thruster generator to bear 2 bow thruster arranged to achieve
the purpose of saving the use of generator. However, the two connected C and D buses are
split with buses A and B supplied by diesel generators. In this scenario we get 1 thruster
generator savings of 800 kW, but due to power cuts of 800 kW, the loading on the bow
thruster cannot be maximized. The voltage and frequency response in this configuration
indicates that the system can only maintain stable conditions up to 50% loading on each bow
thruster. This is actually in line with the two previous configurations because the power
supply comparison and load requirements show the same value. In the two previous
configurations the total supply is 1600 kW with 1030 kW of power requirement, whereas in
this configuration the total supply is 800 kW with a power requirement of 515 kW.
that value. The value is still in accordance with the standards allowed so the system is still
allowed to operate.
1 60% - 75% 98,1305 98,1305 A,B,C,D 98,4459 101,402 99,8 Normal Normal
2 100% - 80% 97,4944 97,4944 A,B,C,D 97,7698 101,394 99,7 Normal Normal
3 100% - 100% 97,2089 97,2089 A,B,C,D 96,7504 101,285 99,7 Normal Normal
1 60% - 75% 98,6037 98,6037 A,B,C,D 98,7682 101,314 99,8 Normal Normal
2 100% - 80% 98,1312 98,1312 A,B,C,D 98,2702 101,524 99,8 Normal Normal
3 100% - 100% 97,92 97,92 A,B,C,D 97,9741 101,548 99,8 Normal Normal
4 110% - 110% 97,7082 97,7082 A,B,C,D 97,5131 102,309 99,7 Normal Normal
The configuration of the closed bus 2 thruster generator with 2 diesel generators is
designed by connecting all buses on the system with the supply of 4 generators. The voltage
and frequency response in this configuration is the best compared to the previous
configuration scenario because this configuration can maintain its stability up to 110%
loading on each bow thruster. This configuration can be used if you want to get maximum
loading from the bow thruster.
On the connected bus, a transient condition occurs due to the starting bow thruster where
the voltage rises and then falls within 0.6 seconds with the highest value of 102.31% at 2.01
seconds and the low of 97.51% at 2.61 seconds later can reach steady state condition at
99,7%. In this condition the voltage deviation value and its stable condition have met the
standard so that this condition can be classified as stable.
1 75% - 75% 97,9151 97,9151 A,B,C,D 96,8481 100,653 99,7 Normal Normal
1 80% - 80% 98,5969 98,5969 A,B,C,D 98,3969 100,051 99,8 Normal Normal
2 85% - 85% 98,4567 98,4567 A,B,C,D 98,2498 100,051 99,8 Normal Normal
3 90% - 90% 98,3163 98,3163 A,B,C,D 97,9875 100,051 99,8 Normal Normal
The configuration in this scenario is the same as configuration 6 but continues with a
non-essential load-loaded load. This load release is done to provide backup power to meet the
starting bow thruster requirement. The voltage and frequency response of this scenario
indicates that the system has grown by 15% from 70% to 90%. This condition is achieved
because the power obtained from the load release can be sufficient for starting bow thruster up
to 90% loading on each bow thruster. Any loading above 90% has been cause the system to
become unstable.
5. CONCLUSION
Based on the research results that have been done, it can be taken some conclusions as
follows: (1) Modeling of AHTS ship's electrical system yields 6 different configuration
scenarios, ie split plant 2 thruster generator to supply 2 separate bow thruster, split plant 2
thruster generator to supply 2 bow thruster in parallel, split plant 1 thruster generator to
supply 2 bow thruster, closed bus 2 thruster generator and 1 diesel generator to supply all the
load on the ship, closed bus 2 thruster generator and 2 diesel generator to supply all the load
on the ship, and closed bus 1 thruster generator and 2 diesel generator to supply all the load
on the ship. (2) From 6 scenarios of AHTS vessel system configuration configuration with
dynamic positioning system under DP manouvering condition, closed bus configuration
scenario 2 thruster generator with 2 diesel generator can bear 2 bow thruster load up to 110%.
This condition can be achieved because the availability of power for the starting motor bow
thruster becomes larger due to the addition of 2 diesel generators. While the generator usage
savings materialized in the configuration scenario of closed bus 2 thruster generator and 1
diesel generator and configuration of closed bus 1 thruster generator and 2 diesel generator. In
the configuration scenario of closed bus 2 thruster generator and 1 diesel system generator
stable until 100% loading on each bow thruster, while in scenario 1 thruster generator and 2
diesel system generator stabilized up to 75% loading on each bow thruster. (3) In the closed
bus configuration scenario of 1 thruster generator and 2 diesel generator, the system stability
can be improved by non-essential load shedding on the system. The results can be seen in
scenario 7 release load, seen the progress of the system stability increased up to 90% loading
on each bow thruster.
REFERENCE
[1] G. Ritchie, Offshore support vessels: a practical guide, 1st. ed. London: The Nautical Inst,
2008.
[2] IMCA, “Guidelines for the design and operation of dynamically positioned vessels,”
IMCA, 2007.
[3] M. Roa, “Demonstration of fault ride through capability for closed bus operation on
dynamic positioning vessels,” 2016.
[4] IEEE, “Definition and Classification of Power System Stability IEEE/CIGRE Joint Task
Force on Stability Terms and Definitions,” IEEE Transactions on Power Systems, vol. 19,
no. 3, pp. 1387–1401, Aug. 2004.
[5] P. Kundur, Power System Stability and Control. California, CA: McGraw Hill, Inc., 1994.
[6] American Bureau of Shipping, Rules for Bulding and Classing Steel Vessels, Part 4 Vessel
Systems and Machinery. New York, NY: American Bureau of Shipping, 2016.
[7] S Sarwito, Semin, T Hidayaturrahman. Analysis of transient response first order and
second order theory in pneumatic control system using feedback instrument type
PCM140. ICAMIMIA, 2017.
[8] S Sarwito, Semin, M Hanif. Analysis of unbalanced load effect of three phase transformer
feedback 61-103 performance on the various connection windings, ICAMIMIA, 2017.