New York Building Corporation uses the critical path method to monitor

construction jobs. The company is currently 2 weeks behind schedule on


Job #181, which is subject to a P10,500 per-week completion penalty.
Path A-B-C-F-G-H-I has a normal completion time of
20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time
of 22 weeks. The following activities can be crashed.

Activities Cost to Crash 1 Week Cost to Crash 2 Weeks


BC 8,000 15,000
DE 10,000 19,600
EF 8,880 19,500

New York Building desires to reduce the normal completion time of Job
# 181 and, at the same time, report the highest possible income for
the year. New York Building should crash