TDL-10-Oct To 15-Oct-2022
TDL-10-Oct To 15-Oct-2022
1 re-galvanisation-TT-Connector.
1.1 Factory-3
1.1.1 Choosed Factory-3 because factory-1 still don’t have Aseem Shiraz & Casper Cao.
the HCL licence so if we go with this factory it has
potential risk.
1.1.2 Discussion needs to be done with factory-3 for start Aseem Shiraz & Casper Cao.
of the work.
1.2 Mobilisation plan of Post from Factory to site and
Vice-versa.
1.2.1 Co-ordination with Factory for the mobilisation. Aseem Shiraz.
2 Onsite-work
2.1 TT-Connector Quotation finalisation. Chris.
2.2 Checking of the AI-2 Control Box with supplier. Asshad
2.3 Checking of the Purlin clamp issues. Asshad
2.4 The purlins clamp data management. Ashhad/Shahid
2.5 TT-Connector MTN. Ahmed
2.6 Offloading of re-galvanized posts from factory to site. Ahmed
3 MIR
3.1 After receiving at site from factory get re-check with Khalid/Ahmed
the Intertek inspector and get it certified.
3.2 After certification from Intertek invite CMEC to Khalid/Ahmed
inspect.
3.3 After CMEC confirmation invite OE for MIR. Khalid/Ahmed
4 RFI
4.1 Installed TT-Connector RFI. Khalid/Ahmed
7 B16-T31-NCR
7.1 The replacement of the damage Slew driver. Khalid/Ahmed/Ashhad.
7.2 Casper is co-ordinating with supplier to send the Casper.
Slew driver to China for Analysis.
7.3 Reply to CMEC for NCR. Khalid/Casper
10 DPR
10.1 Construction Summary. Ahmed
10.2 Weekly site summary. Ahmed/Khalid.
10.3 NCR-list & Observation from CMEC submission. Khalid/Ahmed.
10.4 Weekly Quality issues summary. Casper
11 Driving Licence.
11.1 Khalid's driving Licence. Khalid.
12 Health Insurance.
12.1 Khalid's health Insurance. Khalid.
12.2 Aseem's health Insurance. Aseem Shiraz
Follow-Up Update Start-Date End-date
Yisong Liu.
10/10/2022 10/15/2022
Yisong Liu.
10/10/2022 10/15/2022
Aseem Shiraz.
10/10/2022 10/15/2022
Aseem Shiraz.
10/10/2022 10/15/2022
Aseem Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz.
10/10/2022 10/15/2022
Khalid/Aseem
Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz.
Aseem Shiraz.