Task Assigned to

1 re-galvanisation-TT-Connector.
1.1 Factory-3
1.1.1 Choosed Factory-3 because factory-1 still don’t have Aseem Shiraz & Casper Cao.
the HCL licence so if we go with this factory it has
potential risk.
1.1.2 Discussion needs to be done with factory-3 for start Aseem Shiraz & Casper Cao.
of the work.
1.2 Mobilisation plan of Post from Factory to site and
Vice-versa.
1.2.1 Co-ordination with Factory for the mobilisation. Aseem Shiraz.

2 Onsite-work
2.1 TT-Connector Quotation finalisation. Chris.
2.2 Checking of the AI-2 Control Box with supplier. Asshad
2.3 Checking of the Purlin clamp issues. Asshad
2.4 The purlins clamp data management. Ashhad/Shahid
2.5 TT-Connector MTN. Ahmed
2.6 Offloading of re-galvanized posts from factory to site. Ahmed

3 MIR
3.1 After receiving at site from factory get re-check with Khalid/Ahmed
the Intertek inspector and get it certified.
3.2 After certification from Intertek invite CMEC to Khalid/Ahmed
inspect.
3.3 After CMEC confirmation invite OE for MIR. Khalid/Ahmed

4 RFI
4.1 Installed TT-Connector RFI. Khalid/Ahmed

4 On-Site Rejected TT-Connector De-Assembly


4.1 Rejected TT-Connector will need to re-galvanized Ahmed.
and for that need to De-assembly of those
connectors.

5 re-galvanized TT-Connector Assembly


5.1 Rejected TT-Connector will need to re-galvanized Ahmed.
and after re-galvanization need to do assembly of
those connectors.

6 Commissioning Plan Submittal Next 200 MW


6.1 Commissioning Plan Submittal to CMEC. Ashhad/Shahid
6.2 Troubleshooting Plan Submittal & Execution
internally.
6.3 Calibration of 200MW plan and Execution.
6.4 Communication Box Commissioning.
6.5 Commissioning report submission to CMEC. Khalid.
6.6 Operation & Maintenance training to CEMC and Khalid/Ashhad/Ahmed/Hussain.
Training Document.

7 B16-T31-NCR
7.1 The replacement of the damage Slew driver. Khalid/Ahmed/Ashhad.
7.2 Casper is co-ordinating with supplier to send the Casper.
Slew driver to China for Analysis.
7.3 Reply to CMEC for NCR. Khalid/Casper

8 Comissioning spare parts & Battery


8.1 Request raised to Casey. Rock Li
8.2 Need to discuss for the Batteries shipment. Aseem Shiraz

9 Team Mobilization plan


9.1 Local Hiring Aseem Shiraz

9.2 Aseem Shiraz leave Plan. Aseem Shiraz


9.3 Khalid leave Plan. Aseem Shiraz

10 DPR
10.1 Construction Summary. Ahmed
10.2 Weekly site summary. Ahmed/Khalid.
10.3 NCR-list & Observation from CMEC submission. Khalid/Ahmed.
10.4 Weekly Quality issues summary. Casper

11 Driving Licence.
11.1 Khalid's driving Licence. Khalid.

11.2 Aseem's driving licence. Aseem Shiraz

12 Health Insurance.
12.1 Khalid's health Insurance. Khalid.
12.2 Aseem's health Insurance. Aseem Shiraz
Follow-Up Update Start-Date End-date

Yisong Liu.
10/10/2022 10/15/2022

Yisong Liu.
10/10/2022 10/15/2022

Casper Cao. *Prepared one-whatsapp group for the Co-


ordination. DONE) 10/10/2022 10/15/2022

Aseem Shiraz. 10/10/2022 10/15/2022


Aseem Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz. In Progress
Aseem Shiraz.
Completed 10/11/2022

Aseem Shiraz.
10/10/2022 10/15/2022
Aseem Shiraz.
10/10/2022 10/15/2022
Aseem Shiraz. 10/10/2022 10/15/2022

Aseem Shiraz. 10/10/2022 10/15/2022

Aseem Shiraz.
10/10/2022 10/15/2022

Aseem Shiraz. 540 Pcs Pre-Assembled in our yard, 9


Boxes. 10/10/2022 10/15/2022

Khalid/Aseem
Shiraz. 10/10/2022 10/15/2022
Aseem Shiraz.
Aseem Shiraz.

Aseem Shiraz. Done 10/10/2022 10/15/2022


Aseem Shiraz.
10/10/2022 10/15/2022
Aseem Shiraz. 10/10/2022 10/15/2022

Aseem Shiraz. 10/10/2022 10/15/2022


Yisong Liu 10/10/2022 10/15/2022

Yisong Liu Shortlisted 1-Guy to be hired for 3-months


basis. 10/10/2022 10/15/2022
Yisong Liu Need to Discuss with Yisong. 10/10/2022 10/15/2022
Yisong Liu *Khalid need to go to Egypt for 1~2 days to
attend her mother knee operation.
* Need to discuss with Yisong once date is 10/10/2022 10/15/2022
finalised.

Aseem Shiraz. Daily report submission. 10/10/2022 10/15/2022


Aseem Shiraz. Weekly submission. 10/10/2022 10/15/2022
Aseem Shiraz. each weekly submission. 10/10/2022 10/15/2022
Yisong Liu each weekly submission. 10/10/2022 10/15/2022

Aseem Shiraz. As it needs 2-months training so he will


apply after coming back from leaves. 10/10/2022 10/15/2022
Yisong Liu After the resident card received. 10/10/2022 10/15/2022

Aseem Shiraz. 10/10/2022 10/15/2022


Yisong Liu 10/10/2022 10/15/2022