Automatic vacuum conveying system

Technical datas, Price list


Part One: Spare parts
Time: 2023-01-11
Unit
No. Item name&main technical data Qty. Price Remarks
price
1.1 Solenoid valve 30 30 900

1.2 Manual gate valve at the bottom of silo 300 2 600

1.3 Ball valve Model:DN32 80 15 1200

1.4 Pulse valve 45 20 900

1.5 Butterfly valve Model:DN80 150 15 2250

1.6 Ball valve Model:DN80 400 10 4000


1.7 Butterfly valve Model:DN200 420 5 2100

1.8 Rotary valves for vacuum hopper discharge 1000 2 2000

1.9 Filter element of dust remover 55 110 6050

1.91 Impeding type level indicator Model:SR80 100 15 1500

1.92 Pressure transmitter 350 5 1750

1.93 Water mist separator 20 20 400

1.94 Rotary valves motor 170 2 340

1.95 Root blower motor 330 2 660

1.96 Filter blower motor 380 2 760


1.97 Connecting cloth bag 1 5m
1.97 Rubber mat 1 10m
Total 25410 Dollar
Part Two: FOB ShangHai Cost
Unit
No. Item name&main technical data Qty. Price Remarks
price
2.1 FOB ShangHai(Including packing forklift etc) 900 1 900 Dollar
1*20feet container

Total cost 26,310

The commerce clause:


1. 总价(Total amount): 26,310 $
2. 运输条款(Delivery terms): FOB ShangHai
3. 包装(Packaging): Wooden pallet+wooden box+wrapping film
4. 装运口岸(Port of loading): ShangHai
5. 发货期限(Time of delivery): 5-10 days after receiving the deposit.
6. 付款条件(Terms of payment): 30% of the total price should be paid by the buyer
after the conclusion of the contract for work. The balance 70% should be paid
by the buyer after checking the machine but before the delivery of the machines.
7. 安装调试(installation & debugging)
If the buyer requires, the seller will send the engineers for the installation,
debugging and training services in the buyer’s factory. The buyer shall prepare
the necessary machines and tools for the installation and necessary raw materials
for the debugging. The installation and debugging time may take 3 or 4 weeks,
depending on the real conditions. The buyer is responsible for the rounds flight
tickets for the seller’s engineers. The cost of the seller’s engineers
accommodation and transportation shall be at the buyer’s expense. The buyer is
required to pay 100 USD/day to each engineer as allowance.
8. 卖方银行账户信息:Seller’s bank information
BENEFICIARY BANK:
BENE’S OPENING BANK: BANK OF CHINA ZHANGJIAGANG SUB-BRANCH
SWIFT CODE:
9. All spares for BKCHCNBJ95L
1 years operation including filters etc.
ADD:111 MIDDLE RENMIN ROAD,ZHANGJIAGANG CITY, SUZHOU, JIANGSU PROV.,P.R.CHINA.
10.本合同为中英文两种文本,两种文本具有同等效力。本合同一式两份。自双方签字(盖章)
BENEFICTARY:
之日起生效。
ACCOUNT NUMBER:466371822943
This agreement
BENEFICIAL is made both in Chinese
NAME:Zhangjiagang and Automation
Chiyu English. TheEquipment
two versions of
Co.,Ltd.
agreement shall have equal status in law
Buyer:
Seller: Zhangjiagang ChiYu Automation Equipment CO., LTD.
ADD:No. 3, Fusang Road, Leyu Town Zhangjiagang City, Suzhou, Jiangsu, China 215600

You might also like