Adjustable Hanger
A adjustable hanger is used to adjust the
ceiling levels.
Main Runner
Main runners are hanged to the adjustable
hanger using the hooks.
Cross Tee
Cross tee introduced between the main
runners to maintain the distance between the
main runners.
Baffle Clip
Baffle clips slide into the main runner to hang
the solo baffle.
Solo Baffle/Hook
Solo Baffles introduces into the baffle clips
using hook at the top surface of solo baffle.
Guiding Pin
Guiding pins are used to join two solo baffle &
to maintain the alignment of the baffles.
WORK METHODOLOGY AND SEQUENCE
• INSTALLATION
Considering a
typical project of 3,000 Sq. Ft.
20,000 Sq. Ft 7
Remark: The above mentioned quantity is based on a specific project of 20,000 Sq. Ft. The quantities may
vary according to the Layout and design of Project.
Area Timeline/Manhours 7
7
Type of Labour Required
Considering an
area of 3000 sq.
4 Skilled Workers 3 Days
ft. For
2 Unskilled Labors (Including Framing Works, Services/Electrical
installation of
and Baffling)
baffle Ceiling .
Remark: The timelines is based on typical labor output on 8 hours working days and single shift a day. If
no. of working hours a day is lessor, it may take more days for completion of job. In case of projects with
short deadlines, the man power may be increased to reduce the time required for given task.