PTW l2 - Full Module
PTW l2 - Full Module
PDFelement
OUTLINE
MODULE
Permit to Work
COURSE SCHEDULE
Day 1 Day 2
0830 Introduction & Ice 0830 Recap of day 1
Breaking 0930 JHA
0930 ZeTo 1030 Break
1030 Break 1045 JHA
1045 General HSE and H&M 1230 Lunch
1230 Lunch 1400 Associated Procedures
1400 PTW 1530 Break
1530 Break 1545 Associated Procedures
1545 PTW 1700 End Day 1
1700 End Day 1
ZeTo Rules
Must be complied to at all times by all PETRONAS & Contractors staff and visitor when
working for PETRONAS Group.
All PETRONAS and Contractor staff are accountable for full compliance with ZeTo Rules.
1. Effective implementation of ZeTo Rules means the rules are understood and abided by all PETRONAS and contractors’ staff.
Management
Every observed breach and confirmed violation of ZeTo Rules is followed by
Consequence Management
Standardized consequence for Contractor staff following confirmed ZeTo Rule violation, e.g.
1st offense: Ban from entering Company’s site/facility for 1 month following
confirmation of offense.
Operational Level:
Issuance of warning letter.
Record non-compliance in PETRONAS’ Supplier Relationship Management (SRM)
system
Payment deduction for any lost work day (if applicable)
Cost of legal, fines, claims and damages incurred resulting from violation (if
applicable).
PETRONAS Level:
For ZeTo Rules violation linked to a major HSE incident, the Company shall
automatically be rated “D” in the Contractor Performance Evaluation (CPE)
Thank you
What is it?
• A statement describing PCSB’s
commitment and expectation with
regards to upholding HSE excellence.
Act 1994
• Duties of employers among others are:
Provide and maintain plant and system of work that are safe and without risk to health.
Provide information, training and supervision to ensure safety and health of employees.
Take reasonable care for the safety and health of himself and of others who may be
affected by his acts or omissions at work.
Wear or use at all times any protective equipment or clothing provided by the employer
for the purpose of preventing risks to his safety and health.
Comply with any instruction or measure on occupational safety and health instituted by
his employer or any other person by or under this Act.
• The followings are samples of our HSE communication slogans and their
intents:
HSE Compliance
• What is HSE Compliance?
– Complies with HSE requirements to prevent accidents at workplace
INCIDETNT / ACCIDENT
Rule-Based
Human Mistake
Mistake
Failures
Knowledge-Based
Mistakes
1.Routine
Violations 2. Situational
3. Exceptional
Internal
• Two types of skill based errors are slips of action and Lapses of memory
Thank you
OUTLINE
MODULE
Introduction
Supporting Certificates
Training
Objectives
By the end of this session, the participants are expected to:
What is PTW?
The PTW is a written document authorizing persons to carry out
out all the precautions needed for the job to be done safely.
What is PTW?
A permit does not, by itself, make a job safe, it can only be
achieved by those preparing for the work and those carrying it out.
all hazards and risks have been eliminated from the work area.
SECTION 1
INTRODUCTION
1.1 Purpose
This Procedure defines PETRONAS Carigali Permit to Work (PTW)
system and the process of obtaining work permits including the
requirements of obtaining Certificates where required
1.2 Scope
As a general principle, PTW shall be applied for all activities which
may harmfully affect the personnel, environment, asset or
reputation carried out on PETRONAS Carigali facilities.
1.2 Scope
Situation for special PTW arrangements:
2. Appointed Person (AP) The person trained for certain duties (e.g. isolation/ deisolation of electrical equipment, synchronising, etc.) and has sufficient
technical knowledge and experience to enable him to avoid danger.
3. Approving Authority The person authorised by the Approving Authority (AA) to carry out safety precautions prescribed in the PTW or Certificates prior
Representative (AAR) to commencement of work.
4. Approving Authority (AA) The person who is responsible for approving the PTW and shall ensure all precautions are specified and controls in place.
Offshore/Onshore Installation Manager, Terminal Superintendent, Warehouse Manager or any person authorized by PETRONAS
Carigali.
5. Approving Authority for The person who is appointed to approve and issues specific certificates, such as electrical isolation, physical isolation, excavation
Certificates (AAC) certificates. For PCSB the approving authority for the certificates is the PTW AA.
6. Authorised Competent Person The person registered with Energy Commission or equivalent local authority and authorised by Management. He has the authority
(ACP) to issue and cancel Electrical Isolation Certificate and Limit of Electrical Access on Electrical Equipment/System.
7. Authorised Gas Tester (AGT) A person who is trained and qualified to carry out gas testing. The AGT should attend training provided by PETRONAS Carigali
recognised training organisation.
8. Authorised Supervisor (AS) Supervisor authorised by PETRONAS Carigali Management to endorse PTW - Production Supervisor/Operation Supervisor or
Maintenance Supervisor or any person authorised by the Approving Authority can take the role of the Authorised Supervisor.
9. Certificate Written and signed statement that specified checks or tests have been carried out by an authorized person and that conditions
are acceptable. Certificates do not replaced the PTW but are complementary.
10. Display Board A board which displays all active work permits at an installation/facility. It is normally located in the main operations control
room.
12. Gas Testing Gas testing is done to check a workplace, prior to the commencement and during work activities for the level of oxygen,
flammable and toxic gases. This is to alert personnel involved should the environment become dangerous.
13. Greenfield Project Site Located more than 500 meters away from existing process facilities or infrastructures, starting from site preparation until
completion of construction activities defined below:
• Process Plants, Facilities or Infrastructures - Introduction of any hydrocarbons or hazardous chemicals into the system
(except for chemical cleaning purposes) or completion of tie-in with existing nearby process system whichever comes first.
• The Project Management Team should define the ending date of the construction period and include in the project
commissioning and start-up plan when to use operations PTW system.
In case where the 500 meters distance specified above still resides within the plot plan or fence of the existing process facility, the
PTW system and arrangement for the project shall be mutually agreed by the PMT and owner of the existing facility.
14. Isolation A physical barrier between a source of energy and a place of work.
15. Job Hazard Analysis (JHA) Job Hazard Analysis (JHA) is the application of the hazards and effects management process at the task level, identifying and
assessing the hazards of each element of the task and defining appropriate controls and recovery measures.
16. Override/Bypass The temporary bypass of a safety device, to allow certain work to proceed without causing an unnecessary process shutdown or
fire alarm (e.g.) fire detectors overridden during welding operations.
18. Radiation Protection Officer/ The Radiation Protection Officer/ Radiation Protection Supervisor is a person with the technical competency and approved by
Radiation Protection Supervisor Atomic Energy Licensing Board to supervise the implementation of the radiation protection programme including all the
(RPO/RPS) appropriate radiation protection regulations, measures and procedures.
19. Toolbox Talk A safety briefing carried out by the Work Leader (WL) highlighting to all those directly or indirectly involved in the work of the
potential hazards associated with the work and the precautions to be taken throughout the execution of the work. Carried out
before work begins, preferably at the worksite.
20. Work Crew A group of people working together led by the Work Leader (WL).
21. Work Leader (WL) The person who leads or carries out the work:
• explains Job Hazard Analysis (JHA) content and PTW conditions to workers;
• ensure all the safety precautions prescribed in the PTW/Certificates are carried out prior to commencement of work.
1. When Contractor PTW system is used, PETRONAS Carigali representatives (e.g. OIM, CSR,
Drilling Supervisor) shall be included as part of the signatory for acknowledgement.
2. For workover/infill drilling work carried out on the rig floor, where Contractor’s PTW is used,
a photocopy of the Contractor’s PTW shall be provided to the OIM for reference
1. Hot Work:
2. Cold Work:
– Any activities or equipment which does not have the potential to generate
sparks (erecting/ dismantling of scaffolding, cold cutting, etc.).
1. No draining or venting of hydrocarbon within 15m radius of the location of hot work
2. Inspect all equipment used before and during hot work e.g. welding machine, cable, hose, gas cylinders,
torches, fire blanket, gas regulators.
3. Proper control of vehicle entry into process areas
©UPSTREAM HSE 2017 44
Open
Remove Watermark Wondershare
PDFelement
Limitation
Limitation
For open flame hot work e.g. oxy cutting, grinding etc. - the facility shall
be shutdown, depressurise, hydrocarbon-free and positively isolated.
For blasting - the activity shall only proceed after conversion of instrument
gas to instrument air, flanges are wrapped and the area is barricaded
For blasting on process piping where the remaining wall thickness is less than the corrosion
allowance, the piping/equipment shall be shutdown prior blasting.
©UPSTREAM HSE 2017 46
Open
Remove Watermark Wondershare
PDFelement
Limitation
Open flame hot work on live facility shall only proceed with use of
Pressurised Habitat
For blasting - the activity may only proceed after conversion of instrument
gas to instrument air, flanges are wrapped and the area is barricaded
For blasting on process piping where the remaining wall thickness is less than the corrosion
allowance, the piping/equipment shall be shutdown prior blasting.
©UPSTREAM HSE 2017 48
Open
Remove Watermark Wondershare
PDFelement
Rigorous risk assessment shall also be conducted for all hot work
activities and attach to the permit.
Regular gas testing at site shall be carried out for any hot work
activity.
For hot work inside confined space, in addition to the hot work
requirement, the confined space entry requirement (e.g. medical
declaration, CSE training, etc.) shall be fully complied with.
SECTION 2
Roles and Responsibilities
Signatories Personnel
Authorised Supervisor
Operations Supervisor/ Maintenance Supervisor
(AS)
Approving Authority
Senior Technician/Technician
Representative (AAR)
1. Shall be appointed by company, for a project at location that is out of sight of OIM/TS.
2. Shall be appointed by company and agreed with area/location OIM, a drilling activities not
on a platform, e.g. drilling rigs or jacket.
OIM/TS/Drilling Supervisor/CSR
Who Shall be formally appointed through issuance of appointment letter or approved list of AA signed by Head
of Asset or Equivalent
Prior to 1) All hazards associated with jobs are identified and risks have been reduced to ALARP;
approve
the PTW, 2) Authorized work does not endanger other ongoing operations;
AA shall 3) All personnel involved in work described in work permit are competent;
verify and
ensure: 4) All workers aware of conditions as stated in PTW/Certificate and precautions to be implemented
before start of work;
5) Other PTW/work activities that may interact are cross-referenced;
6) All approved supporting certificates/documents attached & made known to all concerned parties;
7) Required equipment and PPE are adequate for completion of work safely; and
8) Applicant/RA are aware on contents and requirements of PTW prior to work execution.
Responsible
1. Update list of authorised PTW signatories regularly.
2. Responsible to instruct AAR that work site shall be inspected and safe before and completion of work
3. Ensure handover for outstanding work is effective.
Who Production Supervisor, Maintenance Supervisor, Operation Supervisor, CSR, etc.
Prior to 1) All hazards associated with work are identified and risks have been reduced to ALARP;
endorse the
PTW & 2) Authorized work does not endanger other ongoing operations in the facility;
certificates, 3) Work preparation such as energy isolation/ LOTO have been completed and applicable
AS shall verify
and ensure: certificates have been approved;
4) JHA had been reviewed with RA/WL/Applicant before endorsing it;
5) Other PTW/work activities that may interact have been cross-referenced;
6) Supporting certificates ensure they are made known to concerned parties; and
7) Required equipment and PPE are adequate for completion of work safely.
To prevent ineffective work supervision, Approving Authority should decide the number of work
a WL can supervise at one time.
©UPSTREAM HSE 2017 57
Open
Remove Watermark Wondershare
PDFelement
Approving Authority has the right to limit the number of work permits RA can apply. This is to
ensure sufficient time is allocated to identify hazards associated with the work and to ensure
effective control barriers can be proposed.
2.3 Firewatcher
Prepare area for hot work, e.g. check fire extinguisher, barricade,
cover trenches, use fire retardant blankets, pressurised water
hose, etc.;
Make safe site and equipment when work stop or suspended; and
For a worker that required to go to worksite before attending and complere PTW Level 1
Competency Training, procedural management of change (PMOC) to be raised and obtain
necessary approval. He shall attend the training at the worksite and pass the assessment
before allowed to work at the worksite.
SECTION 3
PTW System Implementation
Display PTW forms for works within their sites on display board.
Specific Job Hazard Analysis (JHA) shall be developed for all PTW
application.
Procedures reviewed
Hazards discussed
The Toolbox Meeting shall only be conducted after the PTW has been approved.
For work that is conducted by Contractors where CSR is at site (e.g. drilling, construction), the
CSR shall be one of the mandatory parties to be informed of the work. He/she shall indicate
acknowledgement by signing in Section 6 of the Cold Work PTW form.
AAR shall provide the following information to AA for AA’s decision making:
• Applicant fill in the PTW form accordingly, after AAR obtained the approval from the AA,
write “Discussed and approved verbally” on the AA signatory section/column.
Applicant/RA and/or WL
PTW form & certificates displayed at work site & copy retained in CCR.
• For any work activity that to be extended beyond the normal shift period, the activity may
continue and the handover to the incoming AA & AAR shall be performed as part of the shift
handover process.
• Extended working hour shall observed the PCSB Fatigue Management at the Workplace
requirements
©UPSTREAM HSE 2017 79
Open
Remove Watermark Wondershare
PDFelement
During equipment test run, all PTW for cold work and wireline
operations suspended. All PTW for hot work shall be closed and re-
applied to resume the work.
START
RA & WL
Communicate the PTW requirements
Applicant/RA
Fill in Sect..1 to 4 of PTW
WORKERS
Sign on JHA to accept the requirements
NOTE:
Applicant/RA
At the end of the shift/work, JSV shall
Prepare & Attach required Certificates RA/WL be conducted by WL/RA/Applicant and
Monitor/Ensure safety & AAR to confirm housekeeping and site is
conditions of the worksite restore to it original conditions
Applicant/RA/WL & AS
Discuss works cope, hazards,
precautions and PPE requirements RA/WL
Applicant/RA Place & display copies of the
Raise required/additional WL/RA and/or
PTW as required AAR
certificates
AS Implement additional Applicant/RA
Verify attached Certificated & Record control to make safe Rectify, housekeeping and restore
Cert. No. in Sect. 5 AS and/or AAR the worksite the worksite to satisfactory
Check site regularly
NO
All certificates WL
available? Confirm completion by signing in
Safe worksite?
Sect.11
NO
YES
YES
Coordination Best achieved by one person i.e. AA to control the issue of PTW:
Retain overall responsibility for all work activity
Ensure each work is carried out efficiently
Ensure one work activity does not interfere with another work.
Planning Proper planning required to ensure:
Approval is obtained
All are aware of the safety precautions
All are aware that there shall be no interaction with other work activities
Adequate time is available for identification of potential hazards, implementation of precaution and worksite preparation
Note:
• All planned job/PTW should be discussed in the daily afternoon coordination meeting for advance planning.
Isolation To ensure safe execution of work, isolation principle shall be adopted, prior to carrying out maintenance or repair. This shall be
determined by a number of factors, such as potential for pressure, dangerous substances, moving machinery and other hazards.
PTW Display Usually located in the main operations control room or designated by the plant management.
On a remote area can be at a Central Location.
All permits for the day are displayed on the board so that:
Communication on simultaneous activities
Facilitate PTW planning and work coordination
PTW Log Book PTW and its associated certificates are approved, the details shall be recorded in a log book.
This record serves as an information source when tracking or issuing additional documents.
The log book must be maintained by AS for the facility.
SECTION 4
SUPPORTING CERTIFICATES
Safety System Bypass/ Certificate may remain active after completion of work.
Override Certificate E.g. due to spare parts unavailability, which requires
(SSBOC) bypass of SCPD to be extended.
Physical Isolation
Certificate Certificates may remain active if work is yet to complete
Electrical Isolation and energy need to remain isolated. However, PTW form
Certificate need to be suspended and revalidated accordingly, up to 7
days.
Radiation Certificate
START
Specialised
NO
work?
YES
END
• Authorized Gas Tester (AGT) responsible to conduct gas testing and fill form.
• Conducted as part of site preparation and JSV to qualify that work place is
safe for work to commence
2 Confined Space • Filled and attached to PTW for all work in confined space.
Entry Certificate
• Entry Supervisor shall be the person to declare all precautions required for
work in confined space has been implemented.
• RPO/RPS declare that all precautions required for work involving ionising
radiation source have been implemented.
5 Physical • Filled for work on process lines and equipment to confirm energy is positively
Isolation isolated.
Certificate (PIC)
• Lifting checklist shall be filled by Crane Operator for critical lifting which meets
criteria below:
i. Percent of capacity between 86% - 100% of load chart;
ii. Multiple cranes are used for lifting; or
iii. Any other criteria classified as critical lifting as per PTS 18.52.06: Lifting
(previous PTS no. 60.2103).
START
Issue reject/Red
Sticker
NO
WL request
Installed YES
equipment Acceptable?
equipment at site
inspection
Notify WL to
Installed Blue
rectify or NO Acceptable? Perform Test run
sticker
replace
YES
Site supervisor
Site Manager
Contractor Management
WAH Requirements
User shall inspect the full body harness and lanyard before used
and every 6 month by WAH Focal and Tagged.
WAH Rescue
Type of rescue
Snatch Rescue Ascent Rescue Descent rescue Cross Haul rescue Confines Space Stretcher Rescue
Tripod Rescue
A rescue where the A rescue where the A rescue where A rescue where the A rescue where the A rescue where the
casualty is slightly casualty is raised to the casually is casualty is casualty is raised casualty needs to be
raised so that their Fall the required lowered to the transferred from vertically out of a immobilized by the
Arrest Lanyard can be extraction location required one location to confined space is use of a Stretcher
removed from its extraction another location known as due to injury before
anchor and the location whilst in Suspension or after being
casualty can be either rescued
raised or lowered
Rescue Requirement
SECTION 5
TRAINING
SECTION 6
INSPECTION AND ASSURANCE
1 2 10
4 11
3
7
5
8
6
12
The gas test results shall be recorded in the Gas Test Form.
The signature may be obtained prior or during the JSV for acknowledgement by the relevant parties before the work start.
• During the site visit, the AAR shall bring along the whole set of the PTW with other relevant documents.
• Any nonconformity or new hazard observed/discovered during the JSV, AAR shall not sign and proceed with the Permit, until
the nonconformity/hazard has been mitigated, recorded and discussed with the AA.
• PTW shall be suspended until conditions are made safe. In the event conditions remain unsafe, PTW shall be closed.
• In the event that the work activity extended beyond the normal shift hours, the suspension may not be required upon
agreement between the current and incoming AAR & AA as part of the shift handover process.
• Toolbox briefing should be carried out at worksite before start of work (every shift) by Work Leader (WL) to his work crew
highlighting potential hazards associated with work and precautions to be taken throughout execution of work
• The WL/RA will inform on the completion of work to the AS or AA. The AS or AA will then instruct the AAR to carry out Joint
Site Verification. For work on remote installation, the completion of the work shall be informed to the AAR.
1 2 10
11
3 4
5 7
6 8
The gas test results shall be recorded in the Gas Test Form.
The signature may be obtained prior or during the JSV for acknowledgement by the relevant parties before the work start.
• During the site visit, the AAR shall bring along the whole set of the PTW with other relevant documents.
• Any nonconformity or new hazard observed/discovered during the JSV, AAR shall not sign and proceed with the Permit, until
the nonconformity/hazard has been mitigated, recorded and discussed with the AA.
• PTW shall be suspended until conditions are made safe. In the event conditions remain unsafe, PTW shall be closed.
• In the event that the work activity extended beyond the normal shift hours, the suspension may not be required upon
agreement between the current and incoming AAR & AA as part of the shift handover process.
• Toolbox briefing should be carried out at worksite before start of work (every shift) by Work Leader (WL) to his work crew
highlighting potential hazards associated with work and precautions to be taken throughout execution of work
• The WL/RA will inform on the completion of work to the AS or AA. The AS or AA will then instruct the AAR to carry out Joint
Site Verification. For work on remote installation, the completion of the work shall be informed to the AAR.
CERTIFICATES
Certificate Application Process
Supporting Certificates
The PTW system has fourteen (14) certificates and one (1) form. Each is intended for a
specific purpose, as the name implies, and each has a designated colored border
No Certificate/Form Color Indication
CERTIFICATES
Excavation Certificate
Excavation Certificate
• If the excavation work involved road obstruction, the Road Obstruction Certificate shall be filled up and attached together
with the PTW application
5. Section 5: The WL shall sign in Section 5 of the certificate to declare that the
precautions are in place for the work to be carried out safely.
8. The AA shall indicate the certificate validation and approve the work in Section 8 with
condition that all control and precautions to be in placed accordingly.
9. The AAR shall verify at site and sign the certificate to confirm that the precautions
have been implemented and the work can proceed and be carried out safely in
section 9
11. The AA shall then close the certificate by signing in Section 11 of the certificate to
acknowledge the work completion and agree with the worksite restoration.
CERTIFICATES
Lifting Certificate
Lifting Certificate
5. The Crane Operator (the SME for lifting) shall declare that he understands the
scope of work, the required lifting equipment and the precautions to be taken.
7. The AA shall indicate the duration allowed for the lifting work and approve the work
in Section 7 with condition that all control and precautions to be in placed
accordingly. The duration for the work may be determined via:
Discussion with the work parties.
Reference to the lifting plan
8. The AAR shall verify at site and sign the certificate to confirm that the precautions
have been implemented and the work can proceed and be carried out safely in
section 8
• For critical lifting, AS shall ensure that the lifting checklist and lifting plan are attached together with the certificate.
10. The AA shall then close the certificate by signing in Section 10 of the certificate to
acknowledge the work completion and agree with the worksite restoration.
• The closure of the certificate may be done in parallel with the closure of the PTW.
CERTIFICATES
Road Obstruction/Closure Certificate
2. The Applicant/RA shall describe the work activity (e.g. closure of road to allow for
lifting activities) and provide the reason for obstruction (e.g. lifting of K-1100 from
low loader to skid across the road) and Duration of the obstruction
4. The WL shall verify the precautions identified by the Applicant/RA and add any
additional precautions required in Section 4.
5. The WL shall then declare that the area is safe and all precautions have been
implemented by signing in Section 5.
7. The AA shall indicate the duration allowed for road obstruction and approve Section
7 with condition that all control and precautions to be in placed accordingly. The
duration for the work may be determined via:
Discussion with the work parties.
Reference to relevant work plan e.g. excavation plan, lifting plan, etc.
8. The AAR shall verify at site and sign the certificate to confirm that the precautions
have been implemented and the road closure can proceed safely in section 8
10. The AA shall then sign in Section 10 to provide acceptance on completion of work
and close-out the certificate.
• The closure of the ROC certificate may be done in parallel with the closure of the PTW.
CERTIFICATES
Vehicle Entry Certificate
2. The Applicant/RA shall specify the description of work in Section 2 of the certificate
4. The Applicant/RA shall fill up the details of vehicle e.g. vehicle model, registration
number, fuel type, vehicle height, etc., in Section 4 of the certificate
5. The Vehicle Operator shall conduct visual inspection on the vehicles and state the
status in Section 5 of the certificate. For any special precautions required, the Vehicle
Operator shall specify in this section
6. The Vehicle Operator shall sign in Section 6 of the certificate to declare that the
precautions are in place for the work to be carried out safely
8. The AA shall indicate the certificate validation and approve the entry in Section 7 of
the certificate with condition that all control and precautions to be in placed
accordingly.
9. The AAR shall verify the vehicle and site and sign the certificate to confirm that the
precautions have been implemented and the vehicle can enter the premises safely in
section 8
11. The AA shall then close the certificate by signing in Section 11 of the certificate to
acknowledge the work completion and agree with the worksite restoration.
CERTIFICATES
Gas Test Form
2. The AGT shall fill in his/her details e.g. name, personal ID, company, certification
number along with the issue date and expiry date in Section 2
• The frequency for gas testing shall follow the interval determined or agreed by the AS.
CERTIFICATES
Radiation Certificate
Radiation Certificate
2. The Applicant/RA shall specify the description of work in Section 2 of the certificate
including the purpose of the radiation work
8. The AA shall indicate the certificate validation and approve the work in Section 8 of
the certificate with condition all precautions and control to be put in placed
accordinglly.
9. The AAR shall sign in Section 9 of the certificate to confirm that all the precautions
have been implemented and the work can be carried out safely
10. Upon completion of work, the WL shall sign Section 10 of the certificate to indicate
that the work has completed and the worksite has been restored to its normal
condition
11. The AA shall then close the certificate by signing in Section 11 of the certificate to
acknowledge the work completion and agree with the worksite restoration.
CERTIFICATES
Diving Certificate
Diving Certificate
2. The Applicant/RA shall specify the description of work in Section 2 of the certificate
4. The Diving Supervisor shall verify the precautions are in place and indicate
confirmation in Section 4 of this certificate by writing ‘Y’ (Yes), ‘N’ (No) or ‘NA’ (Not
applicable).
• For any ‘N”, the Diving Supervisor shall not allow the diving operation to proceed until the issue is rectified
©UPSTREAM HSE 2017 177
Open
Remove Watermark Wondershare
PDFelement
6. The Diving Supervisor shall sign in Section 6 of the certificate to declare that
he/she has done the checks and that the precautions are in place for the work to be
carried out safely
8. The Diving Supervisor’s Superior on-Board shall sign in Section 8 of the certificate
to provide endorsement that all the required precautions have been implemented to
make safe the diving operation
9. The CSR shall sign in Section 9 of the certificate to acknowledge that the precautions
are implemented and the work is safe to proceed
10. Upon completion of work, the Diving Supervisor shall sign Section 10 of the
certificate to indicate that the work has completed and the worksite is safe and ready
to resume its normal operations
11. The AA shall then close the certificate by signing in Section 11 of the certificate to
acknowledge the work completion and agree that the worksite may return to its
normal operations .
CERTIFICATES
Limit of Electrical Access Certificate
2. The Applicant/RA shall specify the description of work in Section 2 of the certificate
6. The AS sign in Section 6 of the certificate to acknowledge that the precautions are
implemented and the work is safe to proceed
8. The AAR shall verify and sign in Section 8 of the certificate to confirm that that the
precautions have been implemented and the work can be carried out safely
10. The AA shall then close the certificate by signing in Section 10 of the certificate to
acknowledge the work completion and agree that the worksite may return to its
normal operations
CERTIFICATES
Temporary Electrical Installation Certificate
PETI Certificate
1. The Applicant/RA shall specify the Work Particular information on PTW No., Work
description, Location and required validity period of the installation.
2. Describe the details of the equipment i.e. Tag No, Model no. and Sticker Expiry Date
PETI Certificate
1. The Applicant/RA shall sign to request for the installation of the equipment.
2. The AP/ACP shall check, verify and sign if the equipment is safe for installation.
CERTIFICATES
Working at Height Certificate
2. The Applicant/RA shall specify the type of working at height to be performed abd
tick the appropriate boxes.
5. The WL shall then declare that the area is safe and all precautions have been
implemented by signing in Section 5.
6. The WAH Focal Person shall conduct verification inspection on equipment, tools and
area and satisfy it safe to proceed with the activities.
7. The AS shall sign in Section 7 to endorse and acknowledge that all the precautions
are in place for the work to be carried out safely
8. The AA to indicate the validity period and approve the working at height activity can
be proceed accordingly.
10. The AA shall then close the certificate by signing in Section 10 of the certificate to
acknowledge the work completion and agree with the worksite restoration.
Thank you
Permit to Work
Frequently Asked Question (FAQ)
3. Is PCSB PTW applicable for any work carried out within 500m radius of facility, even
though the activity is conducted on Contractor’s facility e.g. marine seismic?
√ No. Contractors may use their own system, provided that their system is acceptable by PCSB and
PCSB representative shall be one of the signatory parties for acknowledgment.
6. Does gas test need to be performed for hot work in non-hydrocarbon facilities?
√ No, gas test is not required for hot work at non-HC facilities.
8. Can the person who acts as AAR endorse and approve the PTW at remote location?
√ No, approval/endorsement can only be given by the respective AA/AS, through any mean possible,
provided it is recorded in the log book and the PTW form.
10. Is the AS the one who identified the hazards for the work?
√ Not exactly. The Applicant/RA shall be responsible of recognizing the hazards for the work. The AS
will then verify the hazards and add if necessary.
12. Can the AAR approve any unplanned COLD work on remote facility? (PTW)
√ Yes, subject to consultation and verbal approval from AS and AA. He has to get the AA and AS initial
immediately he comes back to the main platform
14. Can more than one certificate applied for a single PTW?
√ Yes a combination of a few certificates can be applied together with a PTW e.g. Road Closure
Certificate and Vehicle Entry Certificate.
16. Can more than one vehicle entry use the same Vehicle Entry Certificate?
√ Answer: No, one Vehicle Entry Certificate is applicable for one vehicle only.
21. Does Excavation Plan need to be attached with Excavation Certificate while seeking
for approval?
√ Yes, it does as additional documentation to supplement the PTW
22. When there is a change of team members or change of PTW, does the toolbox
meeting need to be re-conducted?
√ Answer: Yes, whether there’s a change of team member or change of PTW, new toolbox meeting
needs to be re-conducted
24. Who should record and track the closure of all PTW and certificates?
√ Answer: Authorised Supervisor.
28. Are all the signatories for certificates required to attend the PTW Certification
training?
√ Answer: Yes.
31. How is the application (usage) of PTW at PCSB’s construction worksite e.g. SSGP,
SOGT, etc.?
√ Ideally, PCSB PTW should be used. However, for project that has few stakeholders involved where
special concerns need to be addressed, a dedicated PTW system for the project may be developed,
but shall be in line with PCSB’s PTW system. The new PTW shall be approved by Managements from
all stakeholders.
32. If the new/specific PTW system above is used, when shall PCSB PTW system be
implemented?
√ For facilities that will be operated by PCSB, the PCSB PTW system shall be applied during
commissioning of the facilities (first gas).
34. For the same work at different location i.e. different platform module, is 1 PTW
suffice?
√ Different PTW should be applied for work at different work location, to cater for hazards at the
specific location.
36. How many number of PTW that the Applicant/RA can apply?
√ The AA will decide the number of PTW that the Applicant/RA can apply.
39. For diving activity that has 2 types of diving e.g. saturation diving and ROV, is 1
diving certificate suffice?
√ For diving activities within the same diving plan and under the care of the same Diving Supervisor,
only 1 diving certificate should be applied. The different type of diving shall be indicated in Section 3
of diving certificate. However, for diving activities that are managed separately (different diving plan
and different Diving Supervisor), different diving certificate shall be required.
40. When does the PCSB PTW system applicable during hook-up and commissioning?
√ The Contractors’ PTW may be used during hook-up activities while PCSB PTW shall be applicable
during introduction of hydrocarbon i.e. during commissioning.
44. For extension of Cold Work Permit from one shift to another, shall the new crew sign
the 4 hour PTW extension? (PTW)
√ No, since the validity of the PTW is revised to 7 days, any incomplete activity from the pervious shift
shall be communicate and handover to the incoming crew via Shift handover process.
46. For any wireline work for 7 days, should 2 permits be raised (one for day and one for
night shift)?
√ Yes, two permit will be required, since two work leader will be involved in the activity.
47. Does other OPUs (who have the interest to work at PCSB facilities) have to attend
PCSB PTW training as well? e.g. auditors, PML (downstream clients) etc.?
√ Depending on the roles that these people will be playing. If they are the signatory parties, the shall
attend the 3-day PTW Certification training and pass the assessment. However, if they are not the
signatory parties they shall attend the half-day PTW Awareness training only.
49. Can pressurised habitat be used for open flame Hot Work at Zone 1?
√ No, the requirement is clearly stated as below
50. How many jobs (work permit) that Work Leader can supervise?
√ WL shall discuss with AA.
51. If there is no unique number assigned to Offshore Crane and Operator in Section 9 of
Lifting Certificate, what shall we do?
√ Insert Not Applicable (NA).
52. Do we need close the current PTW and apply a new test-run PTW to do test-run and
troubleshooting of equipment?
√ No, we do not require to close the current PTW and apply for test run Permit for that particular job.
Test run is already included in the 1st permit.
54. For JHA retention – does it need to be kept for 1 year as per PTW as well?
√ Yes, the retention period of JHA is same as PTW – at least 1 year.
55. On Diving Certificate: Section 3 “Any No, Certificate cannot be issued”. For ROV
Diving/Operation, would the certificate be issued?
√ Based on discussion with P&E, certificate shall not be issued. The CSR would be able to provide
advice as well.
56. If the main worker in the group changes, e.g. the Lead Mechanic only, does a new
PTW need to be applied?
√ No, however he is required to be brief on the PTW, JHA and Certificate requirements.
57. If all unskilled labor changes, does a new PTW need to be applied?
√ OIM’s judgment is needed in such cases, where common sense prevails. If the OIM decided to used
the same PTW, the Work Leader is required to brief them on JHA and PTW and obtained all their
initial as an evidence of acknowledgment.
Thank you
OUTLINE
MODULE
Introduction
Exercises
Objectives
By the end of this session, the participants are expected to:
Introduction of JHA
WHAT is Job Hazard Analysis (JHA)?
Scope
WHO/WHEN to apply Job Hazard Analysis (JHA)?
Shall be applicable for all activities that require PTW at all work
locations throughout PETRONAS Carigali global operations,
including works/activities carried out by Contractors and Sub-
Contractors engaged for work on Company facilities
Detail/Action Page
Approval Page
Glossary of Terms
No. Terms Description
1. Consequence An event or chain of events that results from the hazard being released; consequence is defined in
terms of impact to people, environment, asset and reputation.
2. Hazards Anything that has the potential to cause harm, ill health or injury, damage to property, plant,
products or the environment, production losses or increased liabilities. This definition can be extended
to include social/cultural disruption.
3. Job Hazard Analysis JHA is the application of the hazards and effects management process at the task level, identifying
(JHA) and assessing the hazards of each element of the task and defining appropriate controls and recovery
measures.
5. Recovery Barrier Also referred to as Recovery Preparedness Measures. All technical, operational and organizational
measures that limit the chain of consequences arising from a hazardous event (or the top event).
These can reduce the likelihood that the first hazardous event or top event will develop into further
consequences and provide life-saving capabilities should the top event develop further.
6. Pre-job meeting A meeting that is conducted prior job starts that addresses, amongst others, the procedure and work
permit conditions for the work.
7. Permit to Work (PTW) A formal written system used to control certain types of work which are identified as hazardous. It is
also a mean of communication between site/installation management, plant supervisors and
operators and those who carry out the work.
8. Residual Risk Residual Risk refers to the risk that remains after the identified actions have been put in place.
9. Risk The measure of likelihood of occurrence of an undesirable event and of the potentially adverse
consequences which this event may have upon people, the environment or economic resources. It is
a combination of probability of occurrence of any HSE hazards and the severity of its effects
(consequences) to people, environment, asset and reputation.
Glossary of Terms
No. Terms Description
10. Toolbox meeting A safety briefing carried out by the Work Leader (WL) highlighting to all those directly or indirectly
involved in the work of the potential hazards associated with the work and the precautions to be
taken throughout the execution of the work.
11. Top Event The first event as a result of the hazard being released.
12. Work Leader (WL) The person who leads or carries out the work:
explains Job Hazard Analysis (JHA) content and PTW conditions to workers;
ensure all the safety precautions prescribed in the PTW/Certificates are carried out prior to
commencement of work.
• Ensure that all personnel who involved in preparing JHA and execution supervisors
and team leaders are trained and competent.
Contractor’s Management
• Ensure all their authorised personnel understand PETRONAS Carigali JHA system and
are trained and competent.
JHA Approver
• Activity/Task with low and medium risks, JHA approver shall - Production Supervisor/
Maintenance Supervisor/ Base Supervisor/ Functional Supervisor (PS/MS/BS/FS).
• Activity/Task with high risk, JHA shall be approved by the OIM/TS/Project Manager.
• Review the JHA prior work execution and communicate it to the work team members
• Ensure all precautions are specified, controls in place, and work is performed in a
safe and efficient manner.
• Actively monitor the work area and surrounding for any change and identify any new
hazard.
• STOP work when there is any concern on safety or when any one of the barrier is
missing or compromised.
• Share knowledge and experience on task hazards during Tool Box or Pre-Job meeting
(Production / Maintenance
e.g. GM / Project Manager
/ Base / Warehouse)
/ Engineer In charge
(OIM / TS / Base /
Work Leader
(Technician)
Supervisor
PTW AAR
PTW AA
PTW AS
the JHA
Worker
CSR
ACTIVITY
JHA Process
Preparation
JHA inputs:
Conduct daily
Pre-job planning for
Tool Box Proceed/
next day’s Job st Develop/Write Review & Increase level
START New JHA / 1 day of job? YES Meeting/ re- Execute END
• 1st time JHA to be New JHA Approve JHA of supervision
communicate Job
developed/written
the JHA
NO
NO
Photocopy the
JHA (with daily
validation)
JHA to be
Pre-job Planning Conduct Daily Tool
START reviewed/ NO Approved JHA
Box on PTW & JHA
Develop the JHA
updated?
YES
Crew Sign Daily
1. Change of work scope JHA form
2. After incident/near miss
3. New/ unforeseen hazard observed Review/ amend/
4. Change of work leader/worker write new JHA
WL monitor and
supervise the
workers and
activities
END
3.1 Preparation
There are two sources of input for JHA development
Direct
Recall & Recheck JHA Worksheet
Observation
Work Leader
• The person who leads
or carries out the work
OIM/TS/
PS/MS
FSO/FPSO Master
Active Passive
Control Control
E.g.
1. Inform and apply the PTW for the site survey and photo taking
activities.
2. Identify and familiarize with the site/ location/ area for the photo
taking
3. Prepare the Camera for the photo taking
E.g.
• Site Chemical, Mechanical and Biological Hazard
• Slip, trip and fall
• Sharp Edges
• Pinch point
• Source of ignition / spark
E.g.
• Equipment Damage
• Hand and finger injury
• Personnel Injury
• Pollution to the environment
E.g.
CONTROL BARRIERS ACTION PARTY RECOVERY BARRIERS ACTION PARTY
Correct body posture. (to indicate specific posture during depending on site condition) • Photographer team Report to Medic (Fitness to Work Photographer team
When operating manual valves, ensure correct hand placement. (to indicate specific Programmed).
hand placement depending on site condition) Wear proper hand gloves.
Avoid congested area • Photographer team • Correct Position during working • Photographer team
Don’t stand in between the pipes
Gas testing/monitoring conducted as per approved / specified interval • AGT Adequate and proper PPE Photographer Team
ERP ERT Team
Correct hand placement (to indicate specific hand placement depending on site • Photographer Wear hand glove Camera Handler
condition) First aid treatment First Aider
• After PTW has been approved, toolbox meeting shall be conducted onsite so that the
workforce can be aware of the potential hazards, control, etc. and familiar themselves with
the site and its environment
Sample of JHA
• Sample of JHA Worksheet
Competency
• The person involved as members or leading the JHA should have a level of
technical competence relevant to the job to be performed
V. Unforeseen hazards/barriers;
5.2 Assurance
• Shall be conducted as part of PTW assurance per PETRONAS
Carigali PTW procedure.
Are team members wearing the designated PPE for the task?
3
Do members believe the JSA improved their safe execution of the task
6
• The JHA along with PTW relating to any incident in the OPU’s shall
be kept throughout the duration of the life of the plant.
2. For project activities during SIPROD, who should review and approve the JHA? (JHA)
√ The work pack complete with JHA needs to be submitted in advance by the
project team to be reviewed and approved by Production Supervisor
(PS)/Maintenance Superivisor (MS)
3. Normally when does the briefing and communication of JHA to be done to the team
members? (JHA)
√ After PTW and JHA are approved by AA and PS/MS respectively. It shall be done
during the toolbox meeting and to be conducted at worksite such that the
workforce can see the real sites and the potential hazards, control, etc.
5. Can the same JHA be used for more than one shift?
√ Yes, because the validity of the JHA will depend on the PTW validity applied.
1. Choose any of the tasks/main activities below and complete the pre-filled
JHA by using the Prompter as guidance
Thank you
ENERGY ISOLATION
Shall be approved through Risk Assessment shall be The mode of operation during
the application and issuance conducted prior isolation in the duration of energy
of: order to: isolation shall be
communicated to all parties
Energy Source
Mechanical
Hydraulic
Thermal
Pneumatic
Chemical
Electrical Chemical
Electrocution, burn Chemical burn, cold burn
Pneumatic Mechanical
High impact injury, cut Cut, flying object
Radiation Hydraulic
Burn, cell mutation Injury, cut
Thermal
Burn
Positive Isolation
How to apply Positive Isolation
Spool Removal, i.e. removal of piping section; and
Blind/Spade Isolation, (rating, material & size)
A standard isolation/blinding/spade list, shall be prepared and approved by the AA
prior to physical isolation of equipment or process.
• For heat exchangers, positive isolation shall be used on both sides of the exchanger.
• If positive isolation is not feasible, use of double block and bleed isolation may be used
after a specific procedure has been developed and approved. However for hot work and
for CSE it is not allowed.
Shutdown valves (SDV) may be used as part of DBB isolation, provided the
valve is reliable and able to be fully closed.
Valve Closed
Valve Open
vent/drain to
safe location
A valve used for SVI shall have a reliable seal and shall be tested
Valve Closed
1. Non-return valves (NRV), flow control valves (FCV) and other valves which may not provide tight shut-
off shall not be used
2. Double block valves without a bleed or a single block with downstream bleed may reduce the risk of
leakage, but does not provide an equivalent standard to DBB without the application of additional
safeguards.
3. Closing several valves in series in the absence of a bleed or vent shall be classified as SVI.
©UPSTREAM HSE 2017 271
Open
Remove Watermark Wondershare
PDFelement
Switch Breaker Vacuum Contactor Unit Vacuum Circuit Breaker Air Circuit Breaker
• Push buttons, selector switches and other control circuit-type devices are not energy
isolating devices
EIC is not a permit to work. The necessary work permit request shall follow
the normal PETRONAS Carigali PTW Procedure and shall be issued only
after approved PIC is produced.
Earthing:
Required - For low voltage (LV) and high voltage (HV) electrical equipment to ensure
current safely flow to the ground.
Not Required - If the equipment is disconnected from the distribution of the supply
system. But other approved means e.g. portable earth connections should be
adopted to flow the current to earth.
To confirm de-energisation:
When an ionising radiation source has been isolated or removed from its
operating location, a lockout device and tag shall be installed at that
location by the RPO/RPS/RPW or RA assigned.
The lockout device and tag shall be recorded on the RC and the key placed
in the Lockout Box. These lockout devices shall have a key separate from
those used to secure the other energy isolating devices in the system
When the related work is completed, the Approving Authority shall request
the RPO/RPS/RPW to remove the lockout device and tags, reinstating it to
its operating location or condition.
Radiation restricted area shall be barricade with warning sign to keep non-
classified personnel out of the radiation area. E.g. flashing warning lamp or
audible alarm.
What is LOTO?
Lock Out
The placement of a locking device on
an energy isolating device to hold
energy isolating devices in the safe
position to prevent inadvertent re-
energising of a machine, equipment or
piping
Tag Out
The placement of a tag on an energy
isolating or lock out device to warn
other personnel that energy isolating
device and the equipment shall not be
removed/operated, until the tag is
removed
LOTO Device
Type Device Sample
a) Clamp
Lock Out
b) Lock
(with
individual c) Chain
number)
d) Lock Out Box
Blue Tag
Operations or equipment
owner isolation
Permanent Tag (Plastic)
Blue – HTML Colour Code :
Tag Out (with
#3333FF
individual
Size :6 in x 3.5 in
number)
Green Tag
Used to identify Space/Blind
location
Disposable tag with serial
number, duplicated on
perforated section.
(Paper/Tyvek)
Green - HTML Colour Code :
#00B050
Size: 6in x 3.5in + perforated
Open
tag 1in x 3.5in. ©UPSTREAM HSE 2017 281
Remove Watermark Wondershare
PDFelement
LOTO Device
Type Device Sample
Red Tag
Us by Electrical Chargeman for
Electrical Isolation
Permanent (Plastic)
Red - HTML Colour Code:
#FF00000
Size: 6in x 3.5in
LOTO Device
Type Device Sample
Yellow Tag
Use by RPO/RPS for ionising
radiation isolation
Permanent (Plastic)
Yellow – HTML Colour Code:
#FFFF00
Size: 6in x 3.5in
Tag Out
Black Tag
Use by the OIM for Equipment
not in use
Permanent (Plastic)
Black – HTML Colour Code:
#000000
Size: 6in x 3.5in
Shall be installed after
appropriate MOC raised.
Group LOTO
What is Group LOTO?
A series of locks and keys (or with a single common master key*) along
with tags which are used to isolate the system after which the key/keys is
placed in a secure Lockout Box.
1. Spare keys shall be available under strict control by the AA or AAR for remote facilities or satellite
platform
OIM/TS
Operation/AAR
ACP/AP/RPS/RPO
• Execute physical isolation
• Install blue tag on breaker
• Authorised the after red & yellow tag
isolation installed
• Conduct electrical
• Keep the master
equipment testing with
keys ACP/AP to confirm energy is
isolated. • RPS/RPO perform isolation of
• ACP/AP perform electrical
• Conduct mechanical/ equipment containing radiation
isolation
hydraulic equipment testing source
to confirm the energy is • First and last to place/remove
isolated. • First and last to place/remove LOTO
LOTO for electrical (red tag)
for radiation source (yellow tag)
• First and last party to
place/remove LOTO for
Physical Isolation
EXTENSION
• For an energy isolation period of more than 24 weeks, a MOC and proper risk assessment shall be raised
accordingly.
©UPSTREAM HSE 2017 287
Open
Remove Watermark Wondershare
PDFelement
Documentation
Tracking
printed as follows: dedicated logbook for each
PIC – an A3 single- be tracked to completion type of energy isolation
sided paper printed and the certificates are PIC/EIC/RC number
EIC – an A3 single- Name of equipment
sided paper printed; closed including tag number
and Date and time of
RC – a carbonised A4 2. Prolong isolation shall be isolation
single-sided printed tracked Date and time of
with 3 copies normalization
2. A photocopy of the 3. Log book shall be updated Name and signature
PIC/EIC should accompany of AA or AA
the Permit to Work, to delegates/ ACP or AP/
indicate that equipment to RPS or RPO
be worked on has been
securely isolated by all
parties responsible for and 2. Padlock and Key
who will be working on the management logbook to
equipment. monitor lock utilization
3. Tags at site Lock Number
Lockout Box number
Date taken
Date return
Name and signature
A space which:
Large enough, so configured that a worker can bodily enter and perform assigned
work
Tank Tunnel
A space which:
Includes all excavation more than 1.5 meters deep (refer to Excavation Safety
Guideline for detailed requirements)
Trench
1.5 meters
space incidents
Risk Assessments
• Incomprehensive JHA e.g. too
generic
• Failed to anticipate /
recognize hazards
Communication
• Lack/insufficient understanding of
SSOW e.g. PTW, EIS, ERP
• None/Less effective hazard
communication e.g. toolbox, safety
briefing
Physical Hazards
Chemical Hazards
(e.g. structural failure, falling
(e.g. glycol, biocide) tools, inadequate lighting)
Equipment
Preparation
Working in
Work
Confined
Completion
Space
Purging/Flushing/Steaming of
Confined Space from • Freed from hazardous materials, e.g. hydrocarbon gas <1% LEL, H2S, etc. purging with inert gas, flushing with water or steaming.
Hazardous Materials/ • draining, venting and cleaning.
Substances
• Blinding, disconnecting and blanking of lines, Equipment de-energized, Energy Source Isolated, Physical isolation, Electrical isolation,
Isolation
Disconnect control signal on Pneumatic/Electrical Solenoids, Mechanical Couplings.
•Lock-out and Tag-out process shall be conducted as per requirements described in the PETRONAS Carigali Energy Isolation Procedure to
Lock-out and Tag-out
prevent inadvertent/ accidental use
• After purging/flushing/steaming - remove the PSV (Pressure Relief Valve), open the low point drains and install an air extractor to ventilate
Opening the vessel the vessel. The vessel shall only be opened after ventilating the vessel and all the necessary safety precautions taken.
Note: At this point no entry shall be allowed into the confined space.
Ventilation Appropriate and continuous ventilation to displace flammable or toxic gases, continuous wetting (pyrophoric materials ) to avoid auto ignition.
• Gas test represents the condition of the entire area of the confined space measured at the manhole.
• Vent point, drain point, gas accumulation, etc. shall also be tested at regular intervals or continuous monitoring.
Gas Testing
• Explosimeter/gas testing equipment used shall be Suitable, Intrinsically safe, Maintained and Calibrated.
• Gas testing by a Confined Space Entry Authorised Gas Tester (CSE AGT), Test results shall be recorded
Radiation Monitoring i.e. sludge or from radiography activity, works need to be within the safe working radius or distance as determined by the
RPS/RPO. The radiation exposure to worker shall be monitored to ensure the exposure is within the allowable limit.
Other requirements
TENORM - proper arrangement for measurement and cleaning to be considered special protective clothing is required.
Any present of mercury - Mercury Decontamination
Condition of Entry
CSE - nontoxic, non-flammable, and non- Entry may be permitted subject to very stringent
asphyxiate, for persons to enter and work in. precautions documented in the PTW.
Gas test by Confined Space Entry Authorised Gas Entry with appropriate breathing apparatus and with
Tester (CSE AGT) before entry to check the level of continuous gas monitoring:
oxygen and the presence of flammable and/or
Oxygen Less than 19.5% by vol.
toxic gases. Flammable gas 1 - 10% of LEL
Adequate ventilation provided before entry, and Toxic Vapors More than 50% of the PEL
during the period of any person is inside the
confined space, manhole lids, access covers and
outlets shall be opened to improve natural
ventilation.
Entry without breathing apparatus shall only be
permitted subject to the following conditions:
Oxygen 19.5-23.5 % by vol.
Flammable gas Less than 1% of LEL
Toxic Vapors Less/equal to 50% of the PEL
Atmospheric Testing
Condition of Entry
Requirements for the different atmospheres
Breathing apparatus –
Not required Required Required
SCBA or supplied air
Head of Production or
Approving Authority PTW AA Head of Asset
equivalent
Examples of inert entry work includes work to service or replace catalyst in reactors or inspection of vessels containing pyrophoric material, where
the flammability cannot be eliminated
Ventilation
Due to the unique characteristics of confined
spaces, natural ventilation is usually not adequate
and would require the use of mechanical
ventilation.
Mechanical ventilation can largely be classified into
two main types:
Forced (supplied) ventilation; and
Local exhaust ventilation (LEV)
Ventilation
Factors to consider in determining the type of
ventilation to use include:
DUST
The nature of contaminants;
Rate of contaminants
generation (m3/min)
Target concentration (ppm)
Safety factors
Rescue
Pre-Incident Action Plan (PIAP) shall be in place to rescue person/s working in a
confined space if there is an emergency.
Drills prior commencement of confined space entry work and subsequently once a month;
Specific CSE Pre-Incident Action Plan (PIAP) approved before commencement of CSE work;
First Aider.
Rescue Procedure
Action during incident/emergency in confined space:-
Standby person shall raise the alarm and inform the Entry Supervisor;
Rescue team shall ensure continuous supply of air through the air line for rescue team inside the
confined space; and
Immediate evacuation of victim unless if IP is seriously injured and requires special handling.
Rescue Equipment
The required rescue equipment shall be clearly identified in the Pre-Incident Action
Plan.
Breathing Apparatus;
Harness; and
Lifeline
BYPASSING OF SAFETY
CRITICAL PROTECTIVE
DEVICES
Faulty SCPD
• Faulty instrumentations due to unavailability of spare parts (e.g. I/O cards,
processor cards, communication cards, power supplies, etc.)
• Faulty of F&G detection/protection system (e.g. emergency alarm, detection
device)
Startup
• Bypassing/isolating/defeating of SCE during startup shall be incorporated in
the Startup Operating Procedure of the particular facility.
• Plant startup and shutdown
BSCPD Exception
1. Bypassing of SCPD shall not involve any changes
logic, set points, alarm points or
any site mechanical modifications, i.e. the equipment shall be returned to
its original state upon normalization of the bypass
2. SCPD Maintenance not affecting the protection system but changing of the
philosophy of the overall operation/protection system.
E.g. one of the 3 x 50% fire water pumps was taken out of service for
maintenance, whereas the overall platform firefighting capability remains
intact with the 2 x 50%, operational philosophy has temporary changed,
no back up, therefore this maintenance activity should be addressed by
MOC.
3. Alarm enforcement or bypassing, i.e. Alarm Shelving, Alarm Suppression, Alarm
Silencing or Alarm off (AOF).
4. Any temporary or permanent change of critical operating parameter settings
should be handled by MOC.
5. Non-critical settings changes or bypass shall be handle by operational
procedures.
Is it a Check tag
NO protective NO in SAP – is it
function? SCE?
YES
SSBOC not required
YES
Is it intended
bypass on an
NO instrumented
component of
the SCE??
YES
Apply MOC
Structural
Process
Integrity Ignition
Containment Detection Protection
Control Shutdown Emergency
Systems Systems Systems Response
Safe Lifesaving
Operation
Escalating
Consequences
PS016
Metocean Data Gathering Systems
Record and
Risk Assessment
implementation
• Applicant specify the • Review and endorsed • Normalise the SCPD
requirement for bypass the RA by relevant soonest after
• BSCPD Coordinator TP/TA rectification
• Coordinate risk • Implemented all
register the BSCPD assessment for SCPD • Approved the SSBOC by precaution and control • Closed the SSBOC
bypass/override by the appropriate level of AA barrier
SME • Record in logbook
• Implement LOTO
SSBOC Endorsement &
Initiated the SSBOC Normalization and
Approval based on
application Closed
bypass duration
SSBOC can be raise for bypass period of 24 hours and can be extended to 7 days but maximum up to 12
week only with appropriate Risk Assessment and Approval. .
Immediate
Normal bypassing Residual Risk bypassing or
Emergency
A Pre-Prepared Risk Assessment (PPRA) Where the residual risk is o Pre-prepared Risk Assessment (PPRA)
may be prepared for various bypasses Very High, exhaustive efforts
shall be taken to reduce the to be prepared by site team to
scenarios to facilitate timely execution facilitate the verbal approval by the
of SSBOC. PPRA shall be endorsed by level of risk to High or
Medium. appropriate Approving Authority (AA)
relevant TPs/TAs/SME and approved by and shall be recorded in the daily
relevant AAs If the residual risk is still Very
High, bypassing may be operations log.
RA shall identify adequate alternative o The approved SSBOC shall be initiated
controls to as low as reasonably allowed if only the risk level
is not directly correlated to within 48 hours after bypassing of the
practicable (ALARP).
the SIL. SCPD.
RA for IPF loops shall be based SIL
ratings..
RA for non-IPF loop shall be based on
PETRONAS HSE Risk Matrix.
HAZID
Equivalent - same Job Grade with relevant technical competency and position, Certified as PTW/Certificates signatory and officially appointed by the
Company E.g. Production Head equivalent are Head of Production from other Sectors, Head of Infrastructure, Head of Technical Services, Head of Terminals
etc.; OIM/TS equivalent are Roving OIM/TS, Field Managers, Head of Specialised Maintenance etc.
1. Very High Risk or SIL 4 rated SCPDs shall not be bypassed at any time
2. Appointed signatories shall be endorsed by BSCPD Custodian
3. Appointed SMEs shall be endorsed by relevant discipline GTAs
The duration for SCPD bypass shall not exceed 12 weeks from the
date of initiation.
5.1
Date and time of normalization
Supporting documents shall be attached to the SSBOC.
E.g.:
All SSBOC shall be retained for at least one year. However any SSBOC related to any incident shall be retained throughout the
Open
duration of the facility or as per local authority imposed.
©UPSTREAM HSE 2017 332
Remove Watermark Wondershare
PDFelement
Monitoring Performance
Site/location/asset on a monthly basis shall report
a) No. of assurance conducted on SCPD bypass system against planned;
b) No. of NCR raised against SCPD bypass system;
c) No. of overdue action items;
d) No. and duration of the bypass more than 7 days;
e) No. of overdue Bypasses (yet to be extended based on escalation
requirement)
Report of all bypasses shall be submitted to UHSE, PTS – Standard & Performance
for management review once every 6 months:
a) No. and duration of the bypass;
b) No. of overdue bypasses (yet to be extended based on escalation
requirement);
c) Potential risk caused by the overdue bypasses;
d) Reason for the overdue;
e) Mitigation to address the risk;
f) No. of NCR raised against SCPD bypass system
g) Mo of overdue action items arising from assurance
Assurance
BSCPD assurance shall be conducted as per current requirements
of PETRONAS Assurance process using guided Functional
Checklist for BSCPD.
Open
At the daily operations. ©UPSTREAM HSE 2017 334
Remove Watermark Wondershare
PDFelement
ACP/AP
RPO/RPS/RPW
2. Relevant AA, TA, TP and SME shall attend the BSCPD (SSBOC) Awareness
training to understand the work/process flow and the requirements on
bypassing of the SCPD.
Attended and passed the competency Attended and passed the Authorized Trained to use properly, the personal
assessment for the Authorized Entrant Gas Tester and Entry Supervisor protective equipment and rescue
and Standby Person training for training for Confined Space and possess equipment necessary for rescue from
Confined Space minimum of three (3) years confined spaces.
experienced working in confined space
• Authorised Entrant, Standby Person, Authorised Gas Tester and Entry Supervisor shall
undergo a refresher training every two (2) years.
©UPSTREAM HSE 2017 340
Open
Remove Watermark Wondershare
PDFelement
Daily Inspection
AA shall instruct site personnel to carry out daily inspection.
Assurance shall cover all phases of PTW system and Associated Procedures
(PTW, EI, CSE, BSCPD & WAH).
Assessment prolong energy isolation, the integrity of the LOTO at isolation points;
and
Assessment on the adequacy of energy isolation system compliance.
• Action items arising from the compliance audit shall be tracked to closure
• All PTW, Certificates, checklist and all other relevant documents shall be kept for a period of
at least one year as stated in the PETRONAS Carigali Permit to Work Procedure (WW ALL S
05 002).
• The fitness to work assessment record or a copy shall be maintained in good order and the
record kept for a period of 30 years
Thank you