Professional Documents
Culture Documents
Aramco Preparation
This article is about Material QC Engineer Questions, who wants to prepare
material engineer interview at international company or Aramco based CBT
Test.
1. Verifying that all required documents and records have been supplied by the
vendors.
2. Review Certified Material Test Report (CTMR) and other records received
from vendor.
3. Perform visual check that the items have not been damaged during
transportation.
4. Verify that all items meet all requirement on material requisition.
5. Verify that the identification markings of the items are identical with CMTR
and other relevant document received from vendor.
NON-CONFORMING ITEMS
Items found to be nonconforming at receiving inspection shall be clearly
identified and Controlled using Non Conformance Report (NCR) Procedure:
KGF-PM-6008-001, Segregate and place on the hold area and attached
“HOLD Tag”.
MATERIAL RECEIVING
Before inspection takes place, construction department should submit
Request for Inspection (RFI) to the QA/QC department.
– RFI includes
o SAIC.
o Purchase Order.
o Delivery Note.
o Packing List.
o Certificate of Compliance.
o Equipment Test Report.
o Approved Data Sheet.
o Approved Drawings.
o Inspection Release Certificate.
o Inspection Disposition Reports.
– Verify and validate the above documents.
– Installation Manual.
– Perform the equipment, material pre-inspection.
– See to it that the materials and or equipment are free from defects or
damaged during transportation
– Material or Equipment shall be in accordance with company Material
Requisition, approved Standard and Specification.
– Fill in the necessary information on the checklist liked, name of the item
received, serial number, vendor name, material requisition, material inspector
signature, inspection date…
– Once the inspection was carried out all the pertaining documents should be
submitted to Saudi Aramco for signature and acceptance.
MATERIALS:
All pipe and fittings SHALL have the material specification and grade
stamped, stenciled, or otherwise clearly marked with permanent marking
method.
STORAGE:
The following requirements shall apply to storage areas relevant to the
particular project which includes, but no limit to, layout yards, receiving areas,
warehouse etc.
1. Pipe shall not be stored directly on the ground. Pipe shall be placed on
mounds or sleepers.
2. Stacking of pipe shall be made in a manner to avoid damage to pipes or
coating. Refer to SAES-H-200
3. Fittings and valves shall be stored in shipping crates or on racks.
4. End protector on pipes, flanges, weld bevels, threads, and socket ends
SHALL be firmly attached.
HANDLING:
1 Lined and coated pipes and fittings shall be lifted with wide fabric or rubber
covered slings and padding’s shall be used to prevent damage to lining or
coating in accordance with SAES-H-200.
SAUDI ARAMCO, API, ASME AND
ASTM Standards for QC Engineers
This article is about SAUDI ARAMCO, API, ASME AND ASTM International
Standards and Codes for QC Engineers related to topic of Quality system
inspection for Petrochemical plants. This documents and notes can be useful
for who are attending CBT Aramco Test or other international test for QC
Inspector or Engineer.
COMPRESSOR REFERENCE STANDARDS
– SATIP-K-402 Centrifugal Gas Compressor.
– SATIP-K-403 Reciprocating Compressor for Process Air & Gas.
– 31-SAMSS-001 Centrifugal Compressor.
– 01-SAMSS-017 Auxiliary Piping for Mechanical Equipment.
– API 617 Centrifugal Compressor for Petroleum, Chemical.
– Schedule Q Contractor Quality Requirements.
– API 618 Reciprocating Compressor for Petroleum, Chemical.
Answer: Quality Control is the operational techniques (Inspection, Examination & Testing) that
are used to fulfill requirements for quality. Quality Assurance is the system of action
and planning needed to provide confidence that a Product or Service will satisfy quality
requirements.
3. Saudi Aramco has adopted the basic framework and definitions of the International
Quality Management System Standards ISO-9000 Series. This has been done to provide
universal understanding and improve communication between the COMPANY and
prospective CONTRACTORS who’s Quality Management System is congruent with the
ISO-9000 Series. Describe the basic elements of an ISO 9000 Series Quality Program?
Answer:
What is Quality Procedure? It is used to establish instruction for inspection and control of all
construction Activities. This will apply to the incoming materials, intermediary and final works.
What is QA? Quality Assurance system of action and planning needed to provide confidence
that a product or services will satisfy the quality requirements.
What is QC? Quality Control is the operational techniques (Inspection, Examination & Testing)
that are used to fulfill quality requirements.
QUALITY CONTROL PROCEDURE – Is a document that details the specific steps needed to
fulfill the Quality activity in the ITP.
QUALITY CONTROL FORM – Is a writing documentation detailing a specific activity in the
ITP and QC procedure.
A CODE – is a body of laws as of a nation, state or industry group, arranged systematically for
ease of use and reference.
A STANDARD – is a rule or a basis of comparison in measuring quality, quantity, and content,
relative value and etc.
P&ID – Is a Piping & Instrument diagram show piping layout and detailed notes relating to
piping Instrumentation. This drawing is commonly referred to as the P&ID its object is to
indicate all process service lines, instrument and controls, equipment & data necessary for the
design group. The process flow diagram is the primary source of information for developing the
P&ID.
Is all about document based on detailed manufacturing, fabrication and construction program
that identifies each process description, sets out related sequence of activities to be inspected,
examined and tested with relevant approved procedures for particular materials, components and
assembly. It includes identification of required documents, acceptance criteria, which is
responsible, the inspection surveillance and the type and level of inspection including hold,
witness and review points of the contractor, sub-contractor and Saudi Aramco.
o Process descriptions.
o Quality Control Requirements.
o Notification Requirements for Supplier Inspection (min. 10 day calendar days).
o Responsibilities for Inspection / Test.
o Acceptance Criteria.
o Verifying Document.
o Inspection Points (Hold, Witness, Review and Surveillance).
What are Inspection Action Points?
What is Hold Point (H)?
An inspection point, defined in an appropriate document, beyond which an Activity must not
proceed without the approval of the designated organization or authority.
An inspection point, defined in an appropriate document, beyond which an Activity can proceed
after notifying the designated organization or authority. Contractor’s QC Inspector has the full
responsibility for performing detailed Inspection during the work activity.
Defined in an appropriate document is the point in which a work activity cannot Proceed without
first ensuring the review and approval of applicable documents Or personnel qualification by a
designated organization or authority
QA/QC organization to monitor work in progress without notice from construction organization.
What is NCR? It stands for Non Conformity Report and A record reporting the variation from
the specified requirements.
What is CAR? It stands for Corrective Action Report, It is a record reporting the action take to
eliminate the effect & causes of an existing Non Conformity defect or other undesirable situation
in order to prevent recurrence.
Piping QC Aramco CBT | Pressure Testing General
Requirements
PRESSURE TESTING REFERENCE STANDARD
o
– A pressure test conducted using water or other approved liquid as the test
medium.
– A pressure test to ensure tightness of flanged and threaded joints at the test
Pressure. It is normally conducted before initial start-up, during
commissioning or after T&Is.
PNEUMATIC TEST
– A pressure test conducted using air or other approved gas as the test
medium or in conjunction with liquid.
PRESSURE TEST
REVALIDATION TEST
STRENGTH TEST
SYSTEM TEST
TIGHTNESS TEST
– A pressure test to ensure tightness of the piping system (i.e., no leaks in the
system) at the test pressure.
1. RELIEF VALVE (s) of adequate capacity set to relieve at 5% above the test
pressure shall be installed unless the test pressure is less than 85% SMYS at
which time it can be set at 10%
above the test pressure. Sizing of these relief valves used for testing shall
follow the requirements of API RP 520, Part 1. The relief valve(s) shall be
tested, dated, and tagged within One Week prior to the pressure test for new
construction projects, and within One Month for maintenance operations.
2. In addition to the pressure relieving device, a bleed valve shall be provided to
protect the piping and equipment from over pressure. The bleed valve shall be
readily accessible in case immediate depressurization is required.
3. An isolation valve shall be provided between the pressure testing manifold and
the system being tested. The isolation valve shall be rated for the manifold test
pressure when in the
closed position.
4. PRESSURE GAUGES and pressure recorders shall be calibrated before the
Test. The calibration interval shall not exceed one (1) month. Calibration
certificates shall be made available to Inspection personnel prior to
commencement of the pressure test. Stickers shall be applied indicating the
latest calibration date.
5. All gauges shall have a range such that the test pressure is within 30 to 80% of
the full range.
6. A minimum of two pressure gauges are required for the test system. One
pressure gauge shall be on the test manifold and the other(s) on the test
system. Their accuracy shall be within 5% of one another.
7. When large systems are tested, Inspection personnel will determine the need
for additional gauges.
8. Recording gauges shall be used where it is necessary to keep a permanent
record, e.g., when the test duration exceeds four hours, or otherwise as
required by this standard.
9. PRESSURE TESTING MANIFOLD in the actual system pressure test, it shall
be separately pressure tested to at least 1.2 times the system test pressure but
not less than the discharge pressure of the pump used for the pressure testing.
HYDRO-TEST Package Content Test procedure shall be
available at site all times.
1. Flow chart.
2. Hydro test index.
3. SIS / Test press diagram / legend.
4. Piping plan drawing.
5. P&ID drawing.
6. Isometric drawing.
7. Welding summary report including NDT report & RTFI assessment.
8. Support type & drawing.
9. Valve test certificate.
10.Flange joint inspection report.
11. Internal cleaning & flushing report.
12.Pre-test punch list – punch “A” should be close prior for proceeding test
package review & testing.
13.Reinforcing pad pneumatic test report.
14.Calibration report.
15. Filling & pressurization report.
16.Pressure test report.
17. Lay-up report.
18.Reinstatement.
19.Final inspection report.
20. Coating report.
2) The procedures in this standard are designed to prevent corrosion due to
oxygen (air) ingress and to prevent microbial induced corrosion. Lay-Up
procedure shall prevent oxygen ingress except as specially allowed in this
procedure.
4) No deviation shall be made from this procedure without written approval
from COMPANY. However, Company and Contractor can mutually agree to
change the lay-up method, if site condition required modification.
REFERENCE DOCUMENTS
Project Specifications
Piping Material Specification
SAIC-A-2018 SA Check List – Test Medium for Hydrostatic Testing & Lay-up
3. RESPONSIBILITIES
3.1 Site Manager
Site Manager shall responsible for overall management and HSE of all
Construction and Pre commissioning activities at site including fabrication,
installation and testing.
3.2 Pre-commissioning Manager
1. Responsible for the overall implementation of the work procedure,
coordination with parties involved in the lay-up activities. The Pre-
commissioning Manager will ensure that specified preparatory works and
associated documentation are prepared in accordance with this procedure.
2. As for Lay-up after Pressure Test, Piping manager will handle it as
construction activity.
3.3 QC Manager
Ensure the adequate implementation and application of this procedure
according to SAUDI ARAMCO Standards and Specifications, Applicable
Codes and Manufacturer Recommendations.
3.4 QC Inspector
1. Responsible for witnessing/approval of the activity, to ensure that the in-situ
Layup of piping/equipment is performed and developed in an orderly
controlled manner in compliance with the Saudi Aramco Standards, Project
Specifications and applicable SATIP/SAIC inspection and test plan.
2. QC Inspector shall be responsible to coordinate the communication way for
the lay-up activities between CONTRACTOR and COMPANY (PIO and
SAPMT) by issuing RFI.
3. QC Inspector will be responsible for monitoring the compliance of the lay-up
3.5 Pre-commissioning Supervisor
1. The Pre-commissioning Supervisor shall be responsible for executing the
work in strict compliance of this procedure, following and controlling the
safety procedure during the lay-up activities. Secure all necessary work
permits prior to carry out the activity.
2. The Pre-commissioning Supervisor shall be responsible for ensuring that
System Lay-up is maintained.
3. As for Lay-up after Pressure Test, Piping supervisor will handle it as
construction activity.
4. SAFETY CONSIDERATION DURING
HYDROSTATIC TEST
5. LAY-UP METHOD
Equipment shall be laid-up after hydrostatic test, unless it can be ensured that
it will be returned to service within 30 days from the first introduction of
hydrostatic test water to the system. Use one of the lay-up methods detailed
below.
1. These methods shall be applied for piping and equipment which are made of
Carbon Steel, Galvanized Carbon Steel, Low Alloy Steel, and Stainless Steel,
as per SAES-A-007.
2. At the end of the lay-up, commission and start up heat exchangers within 14
days, and other equipment within 60 days.
5.1 No Lay-up
1. According to SAES-A-007 Para 7.7, water shall not require treatment if used
to pressure test completely internally coated or lined equipment, or systems
entirely fabricated with non metallic materials. No lay-up procedure is
required for totally non-metallic systems (e.g., PVC or RTR pipe).
2. Regardless of piping material, “No Lay-up” will be applied to all piping which
is open to the atmosphere such as trim vents and drains, which are categorized
as visual, gravity and service test package.
5.2 Ambient Lay-up
1. Ambient lay-up will be used on services where all of the following conditions
apply:
A. Drains are available at all low points to ensure complete removal of water
B. Corrosion allowance has been provided,
C. Pitting can be tolerated; and
D. Particulate rust can be tolerated.
2. Water from the system will be removed. For facilities other than pipelines,
drain the system completely, sweep and mop as required to ensure that no
visible traces of water remain.
3. Dewatering condition shall be confirmed with monitoring no more water
coming out from the test package for a minimum ten (10) minutes.
4. After confirming that the test package is drained, , the system will be
protected to prevent the entry of sand or rainwater. Holding positive pressure
will not be required for Ambient Lay-up.
5.3 Dry Lay-up
1. Dry lay-up using dew point controlled air may be performed in systems where
the dew point can be successfully reached within 1 week. Longer drying
periods using air may contribute to the generation of excessive quantities of
corrosion products in lines. Therefore, dry lay-up using air is only appropriate
for systems that can be easily dried. One means to assure effective drying
within the required time is to limit the length of the system being hydrotested
at one time.
2. After hydrotest, water from the system shall be removed. For facilities other
than pipelines, the system will be completely drained, sweep and mop as
required to ensure that no visible traces of water remain, when applicable.
3. Immediately after dewatering, the system will be dried until ensure a dew
point of -1C or less at all exit points. Drying operation will be done by blowing
dry air through the system for not less than 12 hours to allow any remaining
moisture to come to equilibrium with the dry air.
4. After drying operation it will be checked and ensured that all measurement
locations are at or below the required dew point. In case that a measured dew
point at any one location is above the set limit drying procedure will be
repeated.
5. Dew point temperature readings at each test location and the pressure of the
line or system at the time of dew point measurement will be recorded. If
different to the actual system or line pressure, the pressure at which the dew
point measurement is made will be recorded.
6. When the required dew point is reached (lower than -1°C), the system will be
pressurized with dry air to the final lay-up pressure (30 psig) and hold
pressure during bubble test to be done to ensure no leak in the piping system.
7. The system will be shut in, maintaining and monitoring the pressure during
the lay-up period.
8. Some equipment, such as soft seated valves and control valves will be removed
from the line, prior to hydrotest, as per SAES-A-004 Para. 8. However,
remaining equipment must be carefully dewatered. As the final stage of the
dewatering process, remove water from pipeline valves and all other valves
that may be damaged by trapped hydrotest water by blowing through the top
drain and displacing fluid out of the bottom of the valve.
5.4 Inert Gas (Nitrogen) Lay up
The way will consist in displacing the hydrostatic test water by positive
pressure with nitrogen or sweet gas until no water drains out of the system.
Shut in the system under positive pressure until commissioning and start-up.
Oil Lay–up
Lube oil lines are tested by lube oil as per SAES-A-004 and SAES-L-150. Therefore, after testing and cleaning,
system will be left with oil until Commissioning stage, when the oil will be replaced by new brand one.
Special Requirement
1) Utility Systems
1. Utility and potable water systems shall be tested in accordance with SAES-S-
060 or SAES-S-070, as appropriate.
2. Potable water systems shall be tested with fresh potable water only
following the requirements of SAES-S-070, Paragraph 18 . 2 . Oxygen
scavengers and biocides shall not be used in potable systems.
2) Dry Gas and Refined Hydrocarbon Product Pipelines and
Piping
A. Prevent corrosion during hydrotest and lay-up procedures for sweet sales gas,
ethane, refined products such as gasoline, kerosene, diesel, etcetera, and
processed Corrosion products and other contaminants introduced during
construction, hydrotesting, and start-up can create major problems for many
years.
B. When water is finally removed from the pipe, either ai the end of the hyrotest
or at the end of a wet lay-up, the system shall be thoroughly dried. Air drying
shall not be used for pipelines. Air drying may be used for small in-plant
piping systems if drying can be completed in no more than one wee
3) Plant Piping
A. In general, new or existing pipework in plants and refineries will be
hydrotested either on site or in a plant fabrication shop. Due to the shorter
physical length of this equipment, hydrotest can be effected in a shorter time
than that which would require chemical treatment with oxygen scavengers or
biocides per SAES-A-007 5.1, 6.3, or 5.2.2. Therefore, unless these time limits
are exceeded, no chemical treatment is required.
B. Due to the complexity of plant construction operations, often new plant
pipework is laid up by drying following the requirements of SAES-A-007
Para. 5.2.3 to achieve a dew point of -1C . Drying is normally achieved within
a plant using dry air or sometimes nitrogen.
C. Chloride limits for 3xx-series stainless steels must be strictly followed.
D. Water shall not require treatment if used to pressure test completely internally
coated or lined equipment, or systems entirely fabricated with non-metallic
materials. No lay-up procedure is required for totally non-metallic systems
(e.g., PVC pipe).
E. Lube oil systems shall be pressure tested following the requirements of SAES-
L-150. Water shall not be used.
F. Instrument air systems shall be pressure tested following the requirements of
SAES-J-901 and SAES-L-150. Water shall not be used.
G. Boilers shall be laid up per SAEP-1026.
H. For heat exchangers, lay-up shall be required unless start up occurs within 14
days of commencing the hydrostatic test.
4) Stainless Steel Equipment
A. Type 300-series stainless steels shall be tested only with water that has very
low chloride content in order to avoid pitting and stress corrosion cracking.
The maximum allowable chloride concentration is 50 ppm. Verify the quality
of the water following the requirements of SAES-A-007 Para. 4.2.
B. Type-400-series stainless steels are highly prone to atmospheric corrosion.
Type 400 series stainless steel trimmed stainless steel (SS) valves shall be
removed from pipelines before hydrotest. If it impossible to remove such SS
valves from the line, then written hydrotest procedures must be prepared and
approved ahead of time allowing the SS valves to remain in place. When
stainless steel equipment containing any Type-400 series stainless steels is left
in place, it shall be hydrotested in accordance with the requirements of SAES-
A-007 Para. 6.3, 6.4, and 6.5. The hydrotest procedure shall carefully detail
measures prevent corrosion including lay-up of the equipment. Do not use
ambient lay-up for equipment made of 400-series stainless steels.
6. IMPLEMENTATION
6.1 Water Quality
1. Water used for any part of the hydrotesting or subsequent lay-up shall have a
sulphate reducing bacteria (SRB) count of 10³ per ml or less as determined by
the RapidChek II Method or alternative test method approved by
Supervisor, CTU/ME&CCD/CSD. Water that has a higher bacteria count may
be accepted at the discretion of the Concerned authority, after treatment with
biocide and retesting. Measurement of SRB shall be carried out as close as to
the introduction of the water to the system.
2. It will be ensured that the mixing of the waters will not cause scaling if water
used for Hydrotest or subsequent lay-up is coming from more than one
source.
3. Water used for any part of the hydrotesting or subsequent lay-up shall be
clean and free from suspended matter. Suspended matter in the water shall be
extracted, before use, by a filter capable of removing 99% of all particles 53m
(2.1 mil) in diameter and larger, or equivalent to using a 270 mesh wire mesh
screen.
4. See Section 5.7.4}, paragraph “a” for restrictions on the quality of water used
for testing/lay-up austenitic stainless steels. Seawater or high TDS aquifer
water shall not be used for this purpose. The construction contractor shall
keep a permanent written record of the water supplied for testing stainless
steels including a record of tests performed on the water.
5. Potable water systems shall be tested with fresh potable water only following
the requirements of SAES-S-070, Paragraph 18.2. Oxygen scavengers and
biocides shall not be used in potable systems.
6. An approved oxygen scavenger (see Appendix 1) shall be added to the
hydrostatic test water, when the equipment contact time with hydrotest water
may exceed 14 days for carbon steel and low alloy steel equipment or 4 days
for stainless steel equipment. Treat the water before it enters the system.
6.2 Precaution
Special attention shall be paid to the following precautions when lay-up is
performed: