506.5.1 Duct supports shall be designed to carry duct.

the weight of the duct half fitted with material.


Where sprinkler protection is provided in the fi6.7.1.2 With all clearance reduction
duct, the hanger's design shall include the systems using a ventilated airspace, air
weight of the duct half filled with water or with circulation shall be provided as described in
the material being conveyed, whichever has the Table 5-2. There shall be at least one (1)
higher density. Loads shall not be placed on inch (25 mm) between the wall protector
connecting equipment. and combustible walls and ceilings for
Exception: Where adequate drainage is clearance, reduction systems using a
provided, the weight of the water shall not ventilated space.
req uire consideration.
506.7.'1.3 Mineral wool batts (blanket or
506.5.2 Hangers and supports exposed to cono- board) shall have a minimum density of
'3s'
sive atmospheres shall be Type 316 SS or
equivalent.
eight (8) lb./ft. (3.6 kq/m ) and have a
minimum melting point of '1,500oF (816oC).
506.5.3 To avoid vibration and stress on the
506.7.{.4 lnsulation board used as a part of
duct, hangers and supports shall be securely
fastened to the building or structure. a clearance reduction system shall have a
thermal conductivity of 1 Btu in./ft. hr oF
2
506.5.4 Hangers and supports shall be designed (0.14 W/m hr oC) or less. lnsulation board
to allow for expansion and contraction. shall be formed of noncombustible material.
lNFPA9l:4.5.61
506.7.1.5 There shall be at least one (1)
506.6 Fire Protection. Sprinklers or other fire inch (25 mm) between the duct and the wall
protection devices shall be installed within ducts protector. ln no case shall the clearance
having a cross-sectional dimension exceeding ten between the duct and the wall surface be
(10) inches (254 mm) when the duct conveys reduced below that shown in Table 5-2.
flammable vapors or fumes. Sprinklers shall be
installed at twelve (12) foot (3,653 mm) intervats in 506.7.2 Duct systems operating at elevated
horizontal ducts and at changes in direction. ln temperatures above 140oF (60oC) shall have
vertical runs, sprinklers shall be installed at the top clearances from combustible building construc-
and at alternate floor levels. tion or any combustible material of not less than
eighteen (18)inch (457 mm).
506.7 Duct Clearances.
506.7.3 Where clearance is reduced by using an
506.7.1 All ductwork and system components airspace between the combustible wall and the
handling combustible material and operating at wall protector, air circulation shall be provided
less than 140oF (60oC) shall have a clearance of by one of the following methods.
not less than eighteen (18) inches (457 mm)
from combustible construction or any 506.7.3.{ Air circulation shall be permitted
combustible material. to be provided by leaving all edges of the
Exception No 1: When the ductwork wall protector open with at least a one (1)
system is equipped with an approved auto- inch (25 mm) air gap.
matic extinguishing system designed for the
specific hazard, the clearance shall be 506.7.3.2 lf the wall protector is mounted on
permitted to be reduced to six (6) inches a single flat wall away from corners, air
(152 mm ) from combustible materials and circulation shall be permitted to be provided
112 inch (13 mm) from combustible by one of the following:
construction.
(A) Leaving top and bottom edges open to
Exception No. 2: When the combustible ' circulation by maintaining the one
material and construction is protected by the (1)inch (25 mm) air gap.
use of materials or products listed for
protection purposes or in accordance with (B) Leaving top and both side edges open
Table 5-2. to circulation by maintaining the (1) inch
(25 mm)air gap.
506.7.1.1 Spacers and ties for protection
materials shall be of noncombustible mate- 506.7.3.3 Wall protectors that cover two
rial and shall not be used direcfly behind the walls in a corner shall be permitted to be