You are on page 1of 24

DHG PHARMACEUTICAL PLANT (PHASE 1)

E&I PACKAGE

Project name : DHG PHARMACEUTICAL PLANT (PHASE 1)

WORK METHOD STATEMENT

Installation of LV Cable, Wire &


Termination

Revision : 00

Submitted by SC VIETPHAT Date :


Approved by, Reviewed by, Prepared by,

Approved by TTCL Date:


Approved by, Reviewed by, Prepared by,

Approved by DHG Date:

LV Cable ,Wire& Termination 1/24 Revision: 00 - Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Contents
1. Introduction..............................................................................................................................3

2. Scope.........................................................................................................................................3

3. Standards..................................................................................................................................3

4. References.................................................................................................................................3

5. Definitions And Abbreviations...............................................................................................3

6. Specification Clauses...............................................................................................................4

7. Resources Mobilization Plan..................................................................................................4

8. Construction Equipment.........................................................................................................4

9. Personnel..................................................................................................................................5

10. Materials...................................................................................................................................5

11. Construction Procedure and Construction Methods...........................................................6

12. Description Method for Installation of LV Cable & Wire.................................................12

13. Responsibility.........................................................................................................................22

14. Design & Drawings................................................................................................................23

15. Statutory Consents.................................................................................................................23

16. Work Program.......................................................................................................................23

17. Quality Assurance..................................................................................................................23

18. Health & Safety......................................................................................................................23

19. Environmental Policy............................................................................................................23

20. Relevant documentation........................................................................................................23

21. Subcontractor.........................................................................................................................23

22. Risk& Hazard Assessment....................................................................................................23

23. Organization Chart...............................................................................................................23

24. Inspection................................................................................................................................24

LV Cable ,Wire & Termination 2/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

1. Introduction.
This document defines the methods to be adopted to ensure that the works conducted at site
are in compliance with the approved designs and material approvals. That the materials are
installed in accordance with the approved design and using recognized installation practices
that are safe and compliant with the Project Safety Plan and associated Safety Procedures.
That the inspection and testing of the works are in compliance with the Project Quality Plan,
its associated Quality Procedures and approved Inspection and Test Plan for the work.
The method statement describes the procedure for Material Delivery Inspection, Installation,
Inspection and Testing of the Low Voltage Cable, Cable Termination & Wires.

2. Scope.
This document is concerned with on site inward inspection, installation and testing methods
to be adopted to ensure that all LV cables, cable termination & wires are supplied, installed,
tested and inspected for the works is in accordance with the Project requirements. It applies
for the laying of LV cables, wires, cable termination of the Cables (Glands & Lugs), testing
& commissioning of the LV Cable & wires.
The work methods are summarized as follows:
2.1 Preparation of the works
2.2 Delivery and inspection of LV Cable, cable termination & wiring materials
2.3 Setting out of the works.
2.4 Laying of Cables and wires as per approved shop drawing.
2.5 Termination of the cables and wires.
2.6 Testing & Commissioning of LV Cable & wires.

3. Standards
3.1 BS 6004; 6231; 6500; 7211; 5467; 6724
3.2 TCVN 4766:1989; TCVN 6610:2000; TCVN 5699:2002; TCVN 5064:1995;TCVN
5935:1995

4. References
This document has been prepared with reference to the following documents:
4.1 Project Safety Plan and associated procedures
4.2 Project Environmental Plan and associated procedures
4.3 Project Quality Plan and associated procedures
4.4 Specifications issued
4.5 Relevant design document approvals
4.6 Relevant materials approvals
4.7 Local Regulations and Codes and Standards

5. Definitions And Abbreviations


BS British Standard
TCVN Vietnam Standard

LV Cable ,Wire & Termination 3/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

DCP Design Control Point


DTLL Drop to Low Level
DWP Detailed Works Program
ENG The Engineer
EHS Environmental Health Standard
F/A From Above
F/B From Below
F&E Feed and Expansion
HL High Level
ITP Inspection and Test Plan
N/A Not applicable
RM Rising Main
RTHL Rise to High Level
PPE Personal Protective Equipment
R/A Rise to Above
T/A To Above
T/B To Below
TP Test Point
VFD Variable Frequency Drive
NCR Non-Conformance Report

6. Specification Clauses
Referring to the general specification of electrical system.

7. Resources Mobilization Plan


According to the work program, and planned site access availability at the respective work
sites, appropriate staff, labor, equipment and materials will be mobilized to the site to install
the LV cables & wires, cable terminations in accordance with the approved design shop
drawing.
The actual mobilization of staff, labor and equipment and the materials delivery schedule will
be dependent on site access. Actual site access dates will need to be notified at least four
weeks ahead of targeted handing over of the site and confirmation of site access date one
week before the access date. Notification and confirmation of site access dates shall be
provided as required.
It is understood that sub-contractor will be responsible for the provision of appropriate types
and quantities of cranes, cradles, working platforms and scaffoldings. Temporary
construction water supply, ventilation, power supplies and lighting systems will be provided
to all works locations.
Aspects of the mobilization of the various resources are described in detail in the following
sections of this method statement.

8. Construction Equipment
It is envisaged that no major plant or equipment will be required to be provided for the
activities involved in the supply and installation of the LV cable, cable termination & wires.
The typical construction equipment requirements is as listed below, and will be used for
erection activities at site.
8.1 PPE for all staff and labor
8.2 Measuring tapes and setting out markers

LV Cable ,Wire & Termination 4/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

8.3 5 & 10 Ton Capacity Cable Jack


8.4 Mild Steel Spindle for rolling the cable drum.
8.5 Cable Roller
8.6 Cable Cutter
8.7 Cable Lugs & Wires Terminals
8.8 Crimping Tools
8.9 Fitter's Tool Box
8.10 Electrician's Tool Box
8.11 Other Hand Tools
8.12 Certified Megger (Insulation Resistance Tester)
8.13 Hole Saw Cutter
8.14 Certified Mobile Scaffolds and step Ladders.
Note: All powered tools shall be suitable for use with a 220 volt power supply.

9. Personnel
Installation of the LV cables, cable termination & wires will be organized from a central
location by the project management team. It is envisaged that the installation of LV cables,
cable termination & wires on site will be conducted by the following:
Installation team shall be responsible for setting out the termination works and shall have
more installation groups based on the work load. Each installation team will comprise of a
supervisor for one to six installation groups. One installation group shall have two skilled
electricians/ fitters and two laborers.
Cable laying/ pulling team shall be responsible for setting out the cable pulling and cable
laying works and shall have more installation groups based on work load. Each installation
team will comprise of a supervisor for one to three installation groups. One installation group
shall have one electrician/ fitter and seven laborers.
The installation team and/or cable laying/pulling team will report to the site construction
management organization, in general, and the Site Electrical Engineer in particular.
The personnel on site will be fully competent to carry out the setting out and installation and
all related works associated with the project to the relevant standards.
The site personnel will have attended the required contractors induction safety and/ or
competency training and will abide by the health & safety plans, policy and procedures as
well as Environmental Plan.
Personnel will be deployed to the various sites on the basis of program requirement and site
access availability. It is intended that the works teams will be organized by geographical
areas.
Refer to the organization chart as per Project QA plan for further details.

10. Materials

LV Cable ,Wire & Termination 5/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

The LV cables, wires and cable terminations will be according to the site requirement and in
accordance with the approved design/ shop drawings. The LV cables, cable terminations &
wire materials will be inspected at the factory before being delivered to the site.
The unloading of the LV cables, cable termination & wires materials will be carried out at
site using a resident crane, forklift provided, if available at site, a licensed operator under
project safety rules and regulation will operate it. If a crane or forklift is not available at site,
the materials will be manually unloaded at the job-site either using a chain block, inclined
wooden planks, cable drum shaft and cable drum stopper. For short lengths and lighter
cables, it will be manually lifted
It should be noted that the materials used in this work are of valuable nature and that they
shall be stored in a secured location and access to these materials shall be strictly controlled.
All materials delivered to the site will first be inspected by the store in charge/ site in charge,
to check that it is in accordance with the site requirements, the approved design and approved
material submittals. The materials are free from any damage caused during delivery to site.
Delivery documents shall be checked for completeness. Defective or damaged material/s
shall either be returned to their supplier's facility or stored on site at a suitable quarantine
location. Allowance of reasonable period to remove this damage material/s from the site will
be given. The inward inspection of materials will be carried in accordance with the relevant
QA/ QC procedure.
The site engineer has the authority to perform any inspection for the stored materials from his
own point of view, to check the material quality or quantity whatever.
No materials will be permitted to enter the work locations without being inspected upon
arrival to the site.

11. Construction Procedure and Construction Methods


The construction procedures and methods described here are based upon the scope and
application of the method statement summarized in Section 2 of this method statement and
the work methods structured accordingly.

11.1 Preparation of the works


Before the commencement of installation, the following are required to be carried
out:
11.1.1 Check the design of the LV cable & wires shop drawings are approved, and
that the drawings for the installation are issued with "Issued for
Construction" status, in accordance with document control procedures.
11.1.2 Check the design of the Builder's Work and requirements as applicable is
approved, and the Builder's Work and requirements drawings, if applicable,
are issued with "Issued for Construction" status, in accordance with
document control procedures.
11.1.3 Check the available site access to the work area for installation, the work
area is clean and safe, and the available temporary services are provisions.
Check the applicable builder's works and requirements works are complete.
If these provisions are available and adequate, a joint inspection undertaking
shall be conducted and recorded.

LV Cable ,Wire & Termination 6/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

11.1.4 Check that the LV cable, cable termination & wires material have been
ordered and inspected at the suppliers' facility and available for delivery to
store/ warehouse.

11.2 Delivery and inspection of cable, cable termination & wires on arrival at store.

11.2.1 All delivered material shall be inspected upon arrival at the store/ warehouse.
The inspection shall be advised, in advance, as required by the ITP.

11.2.2 The delivered materials shall be inspected in accordance with the appropriate
QA/QC and project procedures.

11.2.3 The delivered materials shall be in accordance with the approved design,
approved shop drawings; materials approvals and all applicable
documentation and certification shall be available with the delivery.

11.2.4 The materials shall be free from defects or damage.

11.2.5 Any material delivered to the site that does not conform to the above shall
either be returned to the point of supply or stored on site at a suitable
quarantine store. A NCR shall be raised for all such materials.

11.2.6 No materials will be permitted to enter the works locations without being
inspected on arrival to the site.

11.3 Installation Procedure: Pre-check.

11.3.1 Generally prior to commencement of the delivery of the cables and wires,
cable terminations & wiring materials, the setting out of the installation shall
be conducted to determine the location of any equipment.

11.3.2 The setting out of the works shall be on the basis of an "Issued for
Construction" installation shop drawings. And the setting out shall be from a
common reference point to be provided at the site. The common reference
point shall also be included in the “issued for construction" installation
drawings, with all setting out dimensions relative to the common reference
point.

11.3.3 Any discrepancy between the common reference point on the "Issued for
Construction" installation drawings and the actual site provisions shall be
notified to the Project Manager and a NCR shall be raised.

11.3.4 Installation of Cable/Wire route is clear & as per approved drawings.

11.4 Installation Procedure:

11.4.1 Laying Cable


Cable laying works shall be commenced in the following manner.
11.4.1.1 Latest approved drawing shall be made available to site personnel or
supervisor.

LV Cable ,Wire & Termination 7/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

11.4.1.2 List for proposed cables which shall be laid in each area shall be
prepared.
11.4.1.3 Cable identification tags shall be made available for above cables in
advance & also after glanding.
11.4.1.4 Required sizes cables drum shall be shifted to work area site by means of
crane, forklift & trailer/ trucks
11.4.1.5 Lift drum to designated level by using crane. Refer to illustration below
for proper lifting of the drum.
11.4.1.6 When drum reaches designated floor, provide wooden block/ plate below
the reel to prevent it from rolling
11.4.1.7 Before removing the hoist cable, check direction of arrow on the drum. It
must be the same direction as the pull.
11.4.1.8 After unloading of cable drums near working area, Insulation Resistance
Test shall be carried out for complete cable drum to ensure there is no
damage occurred during transportations
11.4.1.9 Assigned personnel to guide the cable while it passes through every
succeeding floor to avoid jamming with the building's structure.

LV Cable ,Wire & Termination 8/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

LV Cable ,Wire & Termination 9/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

11.4.2 Horizontal Tray Cable Pull Set Up


11.4.2.1 Mount cable rollers on top of the cable tray.
11.4.2.2 Use cable roller placed at three (3) meters (or as close as possible) of the
entire length of the cable pulling (from starting point to end point).
11.4.2.3 Install cable roller at every corner or bends.
11.4.2.4 Manually lay the rope above the tray until it reaches the starting point of
cable pulling. Rope must be above the rollers.
11.4.2.5 Attach pulling rope to the cable and pull until it a little tension is felt.
11.4.2.6 Guide the cable while feeding into tray end.

11.4.3 Pulling the Cable


11.4.3.1 Manually feed the cable to the tray at starting point and pull the rope
without unreeling cable on the drum to develop certain pressure.
11.4.3.2 After checking the grip and everything is satisfactory, the Site Engineer
issue the order to commence pulling of the cable to the workers assigned
at the rope side.
11.4.3.3 Sufficient leadmen/ foremen shall be deployed at every turn of the cable
duct to ensure cable rollers are intact.
11.4.3.4 Temporary markings shall be provided to each run of the cable.
11.4.3.5 Each run of the cable shall be neatly arranged.
11.4.3.6 Cables shall be continuous from power source to equipment.
11.4.3.7 All cables and wires shall be identified in accordance to the Design
Criteria specification.
11.4.3.8 After laying the cable ensure that all ends of the cables are sealed by
poly-vinyl chloride electrical tapes before cable termination.
11.4.3.9 Insulation Resistance and Continuity Test shall be carried out for
complete cable to ensure there is no damage occurred during pulling
cable on cable Ladder/ Tray/ Trunking

11.4.4 Glanding & Cable Terminations


11.4.4.1 Measure the distance from the gland plate to the cable termination point
and accordingly remove the outer sleeve insulation.
11.4.4.2 Remove the armor unto the gland plate.
11.4.4.3 Insert the shroud into the cable.
11.4.4.4 Remove sheath of the cable unto the gland plate and separate the cores
for inserting the lugs/ copper tube terminals.
11.4.4.5 Insert the bottom part of the gland into the cable, put the armor ring and
terminate the armor wire into the ring.
11.4.4.6 Insert the upper part of the cable gland and tighten the upper and lower
part by a spanner.

LV Cable ,Wire & Termination 10/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

11.4.4.7 Cables shall be properly sleeved with appropriate color coding at each
cable termination end.
11.4.4.8 Cables are properly marked with approved markers before & after the
entry in the switchboard.
11.4.4.9 Crimp the cable lugs with correct crimping tool. Connect to terminal as
per requirement.
11.4.4.10 The holes made for taking the cables inside the switchboard should
be properly covered and sealed after checking of the cable termination
point.
11.4.4.11 Cables shall be properly terminated & torque.

11.4.5 Wires
11.4.5.1 Ensure all the related documents like current approved shop drawings
and load schedules are available with the installation team.
11.4.5.2 Transfer the required amount of wires from stores/ warehouse from the
crane access point by pickup and lifted by crane to the particular level
and/ or by wheel barrow or manually to the work place
11.4.5.3 Prior to pulling of wires, check and ensure there are no sharp edges or
burrs in the raceways to prevent damage of materials while pulling the
cables.
11.4.5.4 Identify the correct cable size, cable color code (According to the
specified color coding), and cut the cable to the required length.
11.4.5.5 In case of trunking each circuit shall be taped or strapped together at
intervals, and place the wires in trunking. Pulling is not allowed in
trunking.
11.4.5.6 Do not bunch two circuits together, if done so easy for installation, it
should be removed after installation.
11.4.5.7 Pull the wires in the conduits with the help of pull wires.
11.4.5.8 Comb the wires in trunking for better flexibility during replacement.
11.4.5.9 Ensure no joints are made inside conduits.
11.4.5.10 Where wire insulation is damaged in trunking, The use of straight
sleeves of same color code shall be used.
11.4.5.11 Where trunking installed of more than 5000 mm vertically, pin
racks shall be provided at 3 m centers to avoid strain on conductors.
11.4.5.12 Leave wires of 250 mm length or sufficient length to ensure it
meets the minimum requirement for the connection to the desired
terminals before cable termination.
11.4.5.13 Cover the trunking with appropriate cover/s and pull boxes as in
case of conduits.
11.4.5.14 The wires in the distribution board should be neatly arranged after
ensuring enough wire length and proper circuit no. are tagged before
termination of the wire.

LV Cable ,Wire & Termination 11/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

11.4.5.15 Wires shall be properly sleeved with appropriate color coding at


each termination end.
11.4.5.16 Insulation Resistance and Continuity Test shall be carried out for
complete cable to ensure there is no damage occurred during pulling
cable on cable Ladder/ Tray/ Trunking

11.5 Inspection and Testing of LV Cable, Wires and cable terminations

11.5.1 Upon completion of the cable & wire installations, the same shall be
offered up for inspection and, if necessary, testing, in accordance with the
project requirement.

11.5.2 Notice of testing shall be advised to the ENG. for their discretionary
attendance and witnessing. Notice shall be advised at least 24 hours prior
to the proposed inspection and testing.

12. Description Method for Installation of LV Cable & Wire.

12.1 Scope of works


This method statement covers works relating to areas having Installation of Low-
Voltage Power Cables and Extra Low Voltage Cables . Works are carried out base on
construction schedule and approved shop drawings.

12.2 References
- Approved materials: Approved catalogues of Low-Voltage Power Cables and Extra Low
Voltage Cables.
- Approved Shop-drawings.

12.3 Sequence of works

LV Cable ,Wire & Termination 12/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Method of Statement/Materials/Shop Drawings Via RFA/CDT to Electrical Engineer’s Approval

Submission
Rejected Decision
Electrical Engineer's Comment
Engineer's Verdict

Approved

Material Procurement & Delivery

Rejected

Material Inspection

Approved

Confirmation of all Handover Related Building Works and Substation Areas.

Cleaning of Cable Trays, Trunkings Installed in preparation for Cable Pulling.

Preparation of Cable Pulling Materials and Cables

Completion of Pulling Cables Prior for Inspection


Requisition
IR/AFI 24 hours in Advance
Electrical Engineer's inspection

Rejected Decision

Engineer's Verdict Electrical Engineer's Site Inspection

Approved

Proceed to Other Works

LV Cable ,Wire & Termination 13/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

12.4 Methodology

12.4.1 Material:

12.4.1.1 LV Cables & Extra Low Voltage Cables


- The LV Cables used should be standard upon manufacturer’s approved type.
- The Extra Low Voltage Cables used should be standard upon manufacturer’s
approved type.
- All Color coding of Cables used should follow as per manufacturer’s approved
type.
- Size of Cables should follow as per “Approved” Shop drawings.

12.4.1.2 Approved cable ties should secure for all cable installed.

12.4.2 Preparation:
- Machineries & Tool: Fork Lift, Mobile Crane, Steel Pipe, Cable Drum support,
Cable Roller (Cleat), Hacksaw, Ropes, Cable Markers, Insulation Tape, Cable
Grip, Hydraulic Jack, Cable Cutter, Rubber Hammer etc.
- Scaffoldings:
a. Setting of scaffoldings where the work to be carried out at elevated area,
please refer to Detail – 1.
b. Guardrails shall be provided when working with height exceeds 3 meters.
c. Scaffolds that are to be used on site must be inspected and deem safe by
the sub-contractor’s Safety Supervisor before use. Tagging shall be
provided by the respective sub-contractors.
d. Defective scaffolds are to be dispose off immediately.

Detail – 1
Setting of Scaffolds

LV Cable ,Wire & Termination 14/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Detail – 2A
Setting of boom lift

Detail – 2B
Setting of scissor lifts

LV Cable ,Wire & Termination 15/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Installation:
Material: Gather & ensure sufficient of cables, tools, man powers & check-
up cable routing prior to start work execution.

12.4.3 Preparation:
1. The work shall be started by orienting workers how to do the pulling cable in
a proper sequence of work. Inform workers about safety matters
2. Check cable support system have completed, clean & approval of installation
schedule.
3. Checking cable routing follow to approved shop drawing at areas where the
cables are ready for installation. Cable routing installation shall
accommodate the minimum curve radius.
4. Determine actual length, type of cable need for installation. Draw the correct
drum cable.
5. Check at inspected starting point area, the draw wire for embedded conduits
& cable ducts.
6. Coordinate workers at both side of cable duct, cable ladders, tray &trunking.
7. When cable is to be cut, the length of both ends shall be checked & protected
by PVC insulation tape with marking installed properly.

12.4.4 Installation Work:


1. General Cable / Wire Installation:
 The cable drum may be lifted by lorry crane & unloaded on the lorry crane or
from the front by a forklift. Material care handling must be taken during
lifting & must be secured by a chain during transport.
 Cable drums shall be placed at locations where the cable laying are pulling
can be easily to conduct.
 For LV/ELV cables, to furnish & install all supports, cable cleats & supports
required to make a neat & substantial cable installation & without any twists
or kinks.
 Remove any remaining packing of cable drum.
 Place the cable drum on the cable drum support by hydraulic jack.
 Place the cable cleats (rollers) according to the cable routing, basically at
beginning part of cable support.
 Workers should roll the cables drum & pull the cable on a sequence method.
 When cable grip is used it should cover more than 500mm in length of the
cable end & be bound to the cable sheath.
 Prior to cable pulling, the direction indicated on cable drums should be in
correct position.
 To use red color marker to have clear marking (circuit nos or panel nos.) at
both side of cables end after cables have installed, to wrap on both ends of

LV Cable ,Wire & Termination 16/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

cable by PVC insulation tape after cutting cables to prevent the ingress of
moisture.
2. LV Cables, ELV Cables and Wires Installation in Cable Ladders, Trays and
Trunkings.
 Determine the actual length, type of cable need to install. Draw the correct
drum of cable, cut the cable after sure of a proper estimation of cable
allowance.
 For cables install in ladder, trays & trunkings, to place the cable rollers on
the cable support system, by using manpower to pull the cables.
 Place a ply-wood on the floor or slab for the standby cables (coiled cables).
 By using cable tie to temporarily fasten cable on cable ladder & tray in order
to proceed to the next cables.
 All cables shall be installed in orderly rows.
 Straighten each big diameter cable by a rubber hammer.
 Cable to secure to transverse members of cable rack & slots in trays with
approved cable ties in every 800mm vertical run & maximum 1400mm
horizontal run for straight and tidy. As for trunking only use approved cable
tie to secure between cable.
 Arrange the cable of each circuitry separately and make sure its no scratch
and effected to each others for insulation requirement.
3. LV Cables, ELV Cables and Wires Installation in Cable Ducts / Conduit.
 Determine the actual length, type of cable need to install. Draw the correct
drum of cable to the nearest pulling of cable area..
 For cables install in embedded conduit & cable ducts, to use the draw wire
grip with the cable end and be bound to the cable sheath by tape & pull. That
will make cable straight & no damage to cables when pulling.
 For cable size <50mm², after installed the 1st cable, to proceed with the same
manner for the 2nd cable.
 No splicing shall be allowed inside conduit. Cable runs shall be continuous
or if jointing is necessary in junction box with approved connectors shall be
used.

LV Cable ,Wire & Termination 17/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Detail - 3
To Handle Cable Drum by Lorry Crane

Detail - 4
Typical Power Cable Installation

LV Cable ,Wire & Termination 18/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Detail - B
Safety belt

Detail – 5
Typical Detail of Power Cable Installation in EPS (RISER)

LV Cable ,Wire & Termination 19/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Detail – 6
Typical Detail of Power Cable Arrangement in EPS (RISER)

Notes: Cables shall be arranged on the metallic or ferrous cable tray, trunking in such a
way that attain the trefoil formation and the three leaves of each trefoil are due to be
used for three different phases of the same circuit.

Detail –7
Detail of Cables Installation at Beam Sleeve – Plan View

LV Cable ,Wire & Termination 20/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

Section A – A
Detail of Cables Installation at Beam Sleeve

Detail – 8
Typical Installation of Cables in Concealed Conduit

12.4.5 Safety method


a. General:
The safety procedures have to be applied for all Engineers, Supervisors and
Workers as stated below:
- Make sure that all personal protection equipment (PPE) be provided on site
before starting of work such as helmet, safety boots, safety goggles, glove,
mask etc.
- Make sure that PPE must be worn in the correct way when working.
- Tools and equipment shall be inspected by authorized person before carried
out to work.

LV Cable ,Wire & Termination 21/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

- All Electrical Equipment shall be provided with separate circuit breaker to


avoid overload fault system.
- Barricades and sign posts for warning shall be provided on site.
b. Working at Elevated area:
- Ensure every worker to wear PPE& use safety harness when working at more
than 2 m height.
- Use of scaffold shall be only on level and firm ground. Scaffolds shall be tied
to prevent movement at the top.
- Safety protected handrail on top layer of scaffolding shall be provided.
- Scaffolding and ladders shall be provided and be ready to use at any time in
order to prepare for all contingencies.

12.5 Inspection Procedures

12.5.1 Internal Inspection.


- Materials shall be checked for quality, quantity and size.
- Check technical installation after setting.
- Check installed cable:
o Material approved.
o Check size, type and condition of cables installed.

12.5.2 Engineer's Inspection Procedures


- Materials shall be checked for quality, quantity and size by Kajima’s
Engineer.
- Check technical installation after setting.
- Check installed cables, cable ties & cable markings.
o Material approved.
o Visual Inspection:
- Check quality of installed cables on site.
- Check size, type and condition of cables installed.

12.6 Completion status:


- As-built documents.

12.7 Appendix:
- AFI (Availability for Inspection).
- IR (Inspection Record).

13. Responsibility
The Project Manager is the overall responsible person for the process implementation of the
works. The Construction Managers will be responsible for all construction activities at the

LV Cable ,Wire & Termination 22/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

site and will directly supervise through erection supervisor/ skilled workmen the work at site.
The Construction Manager will also be responsible for arranging and controlling the
inspection and testing activities. Notwithstanding the above, it is the responsibility of each
individual employed in the project to take due care to ensure their own personal safety and
that of their work colleagues.

14. Design & Drawings


Construction shop drawings will be prepared based on approved design to be prepared and
will be submitted separately for approval before commencement of works.

15. Statutory Consents


There is no requirement in respect. However we will follow the local Regulations for
Electrical Installation.

16. Work Program


Latest coordinated installation program will be strictly followed and strictly complied,

17. Quality Assurance


All applicable procedures described in the approved quality plan for the Project contract will
be followed.

18. Health & Safety


The execution of works will strictly follow the Project Safety Plan, Manual and Procedures.

19. Environmental Policy


The Execution of works will strictly follow the Project Environmental Plan.

20. Relevant documentation


20.1 Approved Design Drawings,
20.2 Approved Shop Drawings (To be submitted later)
20.3 Relevant codes as in approved design documents to be issued
20.4 Approved Materials submissions.
20.5 ITP
20.6 Method statement

21. Subcontractor
VIETPHAT has been appointed as Electrical subcontractor for the Lixil Project. It is
envisaged that the LV Cable, Wires, Cable Termination installation works will be undertaken
by VIETPHAT direct workforce.

22. Risk& Hazard Assessment


As per attached risk assessment form

23. Organization Chart


As per Organization Chart of the project

LV Cable ,Wire & Termination 23/24 Version:00-Effective date: 10-02-2023


DHG PHARMACEUTICAL PLANT (PHASE 1)
E&I PACKAGE

24. Inspection
As per Attached ITP

LV Cable ,Wire & Termination 24/24 Version:00-Effective date: 10-02-2023

You might also like