Daily Sheet pile Progress Report

SUBCONTRACTOR PILEX for Soil works EST.

CONTRACTOR MID CONTRACTING Co.

Weather Temparature Date Day


Sunny Rainy Foggy Stormy High Medium Low
February 5, 2023 Sunday
* *
PERSONNEL MACHINERY, PLANT & EQUIPMENT
DESCRIPTION NO TOTAL HRS DESCRIPTION NO HRS ACTIVE IDLE
ENGINEER 1 10 IMPACT HAMMER 1 5 YES NO
FOREMEN & OPERATOR 1 10 VIBRO HAMMER 1 4 YES NO
LABOURER 3 10 TOYOTA CAR 1 10 YES NO
0 0 YES NO
0 0 YES NO
Sheet Piles (15m) Notes

No. Location DRIVEN PILE NO STATUS * start driving the sheet piles with impact Hammer

1 PREVIOUS PRODUCTION (# of sheets) 0 * Impact hammer head has been broken due to sheet piles is not penetrate the ground because presence of
extremely strong granite boulders in backfill material

3 DAILY TOTAL PRODUCTION (# OF SHEETS) 0


4 TOTAL CUMULATIVE DRIVEN SHEETS 0
5 REMAINING SHEETS 120
6 TOTAL SHEETS IN DOWN STREAM AREA 120
sheet Pile
0%

100%

TOTAL CUMULATIVE DRIVEN SHEETS REMAINING SHEETS