Predecesso Normal Normal Max.

Crash Crash cost Days to


Activity rs Time Crash Time Cost Crash Cost Time per day crash Y
A 8 6 100 200 2 50
B 4 2 150 350 2 100
C A 2 1 50 90 1 40
D A 10 5 100 400 5 60
E B 5 1 100 200 4 25
F C, E 3 1 80 100 2 10

VAR.
Realized Critical
ES EF LF LS SLACK Time Path
0 8 8 0 0 8 A
0 4 10 6 6 4
8 10 15 13 5 2
8 18 18 8 0 10 D
4 9 15 10 6 5
10 13 18 15 5 3
Normal Normal Max. Crash Crash cost
Activity Predecessors Time Crash Time Cost Crash Cost Time per day
A 8 6 100 200 2 50
B 4 2 150 350 2 100
C A 2 1 50 90 1 40
D A 10 5 100 400 5 60
E B 5 1 100 200 4 25
F C, E 3 1 80 100 2 10

Total Costs 580


Min. Total crash costs 0
Umur proyek yang diinginkan 14
Days to Realized Critical
crash Y ES EF LF LS SLACK Time Path
0 8 8 0 0 8 A
0 4 10 6 6 4
8 10 15 13 5 2
8 18 18 8 0 10 D
4 9 15 10 6 5
10 13 18 15 5 3

VAR.