Question # 1:-

1).AOA Network Diagram


2 5 6 7

1
3

Note:

Distance between the nodes is as follows:

1-2=A=10 1__3 -> B=12 1__4-> C=8 2__3-> D=4

3__4-> F=6 2__5-> E=8 4__5-> G=4 5__6-> I=6

4__6-> H=8 5__8->J= 12 6__7-> K= 8 7__8-> L=10

2).To Find out critical paths

As we know all durations estimates and estimated time are in days. So

Path 1: A-E-J Length = 10+8+12 = 30 days

Path 2: A-E-I-K-L Length = 10+8+6+8+10 = 42 days


Path 3: A-D-F-G-J Length = 10+4+6+4+12 = 36 days

Path 4: A-D-F-G-I-K-L Length = 10+4+6+4+6+8+10 =48 days

Path 5: A-D-F-H-K-L Length = 10+4+6+8+8+10 = 46 days

Path 6: B-F-G-J Length = 12+6+4+12 = 34 days

Path 7: B-F-G-I-K-L Length = 12+6+4+6+8+10 = 46 days

Path 8: B-F-H-K-L Length = 12+6+8+8+10 =44 days

Path 9: C-G-J Length = 8+4+12 = 24 days

Path 10: C-G-I-K-L length = 8+4+6+8+10 = 36 days

Path 11: C-H-K-L Length = 8+8+8+10 = 34 days

3). what is the critical path for this project and how long is it?

As we know critical path is the longest path through the network diagram so here Path 4 will be our
critical path that length is 48 days.

4). what is the shortest possible time needed to complete this project?

Path 1, A-E-J is the shortest path that is required only 30 days length to complete this project.