MULLER INDIA PVT. LTD.

Work Instruction
Document No. MI-QD-WI-004/030
Edition No. 01
Work CRITERIA FOR ACTION PLAN
Instruction Revision No. 00
Title: DURING PFMEA Effective Date 20.03.2017
Page No. 1OF 1

S. No. Criteria for recommended actions during PFMEA


1 RPN > 150
2 SEVERITY S>8
3

1. NO ACTION PLAN WITHIN THE ABOVE CRITERIA IS REQUIRED.

2. MAKE ACTION PLAN & IMPLEMENT ACCORDINGLY WITHIN


TARGET DATE TO BRING THE CONSEQUENT RPN, OCCURANCE &
DETECTION NO. TO THE DEFINED ACCEPTANCE LEVEL.

Checked By Approved By CONTROL STAMP

ENGG/F/18, Rev. No.: 00