Raw material Supplier Identification : Groove Position Inspection

Inspection at set up :
After Sectioning the part,
mould is being made to
measure the Groove
position dimension
1.20 /0.80 & 2.20 / 1.80 in
profile projector.

Sectioned Sleeve Mould


Raw material Supplier Identification : Groove Position Inspection

First Grove position 1.20 / 0.80 Inspection

Inspection on Profile Projector

Observation

Mould
Raw material Supplier Identification : Groove Position Inspection

Inspection at per shift :


By Height Gauge with the help
of pin pointer(0.20Radius) dial

First Step : Pointer at middle of


the groove

Second Step : Pointer at face of


the Guide Sleeve

Observation measured through


Height Gauge at every shift
production.