Revisions Details:
Revision History
Table of Contents
4............................................................................. introduction: 1.0
4.................................................................. policy and strategy 2.0
4.............................................................................. safety policy 2.1
5.......................................................................... safety strategy 2.2
5............................................................................ management: 3.0
5.................................................................... organization chart 3.1
5............................................................. safety responsabilities 3.2
6...................... safety responsibilities for management team: 3.3
9.............. statutory and contractual framework for safety: 4.0
9............................................................ statutory requirements 4.1
10.......................................................... contractual obligations 4.2
11............................................................... safety organization: 5.0
11...................................................... risk assessment at award 5.1
11........................................................... health and safety plan 5.2
13...................................................................... site supervision 5.3
13...................................................................site establishment 5.4
13............................................................. central safety library: 5.5
14............................................ safety training and promotion: 6.0
14..................................................... safety induction meeting: 6.1
14.................................................................. safety orientation: 6.2
14........................... specialized training - in-house / external: 6.3
14................................................................... safety promotion: 6.4
14................................................................. safety programme: 7.0
15......................... dail y on-site safety meeting of workforce 7.1
15......... weekly tool box meeting for workforce & foremen: 7.2
15.............................. weekly safety meeting - trade foremen: 7.3
15......... weekly staffs / mtg for site engineers & g. foremen: 7.4
15..................................... weekly safety walk with p.m./c.m.: 7.5
15monthly safety committee meeting for site management: 7.6
16........................................................................ safety reviews: 8.0
16.......................................................................... safety review 8.1
17.................................................................... safety committee 8.2
17........................................ accident prevention programme: 8.3
18.................................................... safety method statements: 9.0
18..... reporting and investigation of accidents / incedents: 10.0
18..................................................................... major accidents: 10.1
18............................................................. non-major accidents: 10.2
18..................... minor" accidents - class - iii accidents (l.t.a.): 10.3
18...............................non - lost time injuries (first aid cases): 10.4
19............................... dangerous occurences inear accidents: 10.5
19......................................... accident / incident investigation: 10.6
19.................................................................. accident statistics: 10.7
20.................................................................................... records: 10.8
20..............................................................safety responsibility: 11.0
20...........................................................................safety audits: 12.0
20.........................................................................safety awards: 13.0
21.................................................. contingency arrangements: 14.0
23.......................................................................... tools injuries: 15.0
23..................................................................................... general 15.1
23............................................................... avoid tools injuries: 15.2
23....................................................................... select the tools: 15.3
23........................................................................ ladder’s safety 15.4
24.................................................................... portable ladders: 15.5
24.......................................................................... fixed ladders: 15.6
24...................................................................... safety measures 15.7
25..................................... health safety & environments plan 16.0
25........... environments, safety & health rules & regulations 17.0
27................................ house keeping hse plan (if applicable) 18.0
27..................................................................................... general 18.1
28............................................... “fire & emergency” hse-plan 18.2
28.................................................. hse plan for assembly point 18.3
29...............“emergency preparedness facilities” in hse plan 18.4
29............................. hazards- health, safety & environments 18.5
29................................................................................... hazards: 18.6
29................................................ annual hse training matrix 19.0
30............. areas covered in SWC hse plan with closing note 20.0
31.......................................................Stonewood safety forms 21.0
40................................................................................ appendix: 22.0
40...................................................................... SWC hse policy 22.1
40........................................................ SWC organization chart 22.2
Scope of Work
Project:
1.0 INTRODUCTION:
The "HEALTH AND SAFETY PLAN & The HSE PROCEDURES MANUAL" have been produced
to formalize the Health and Safety System of the Stonewood Company Management. It is mean to
be used by all of our supervisory staff, workforce, subcontractors and all other interested parties
for improving and maintaining the health safety of our employees and the generated public who
might be affected by our work.
With a view to achieving our stated objectives we take safety as a matter of importance and intend
to actively manage all health and safety issues at all stages of construction by:
A- Identification of Hazards.
B- Assessing the Hazards.
C- Planning for controlling the Hazards & initializing risk management programmes
Monitoring.
D- Compliance and seek further improvements.
E- Communication of the agreed safety methods of construction.
Stonewood Company have produced this health and safety plan to serve as a reference point
regarding safety management for all parties involved in our activities and it will be updated as arid
when required.
3.0 MANAGEMENT:
It is our belief that the execution of any safety plan must originate from the senior management i.e.
adopting a top-down approach , We therefore stress that the overall success of our safety plan
hinges upon the efforts of all those involved in Stonewood Company management Team.
The site management will be assisted in the implementation and monitoring of Safety matters by a
General Manager
a) Promote an interest, enthusiasm and commitment to Health & Safety issues throughout the
organization.
b) Enforce that all personnel are fully aware of their individual and collective responsibilities
regarding all safety issues.
a) Have the overall control of the Health & Safety Management system. He ensures the proper
implementation of the organizational Safety policy through the HSE Coordinator / Safety
Engineers.
c) Ensure the provision of adequately staffed and resourced Safety Management teams including
the provisions of full time Safety Engineers / Safety Officers, Safety Inspectors, where required.
b) Promote an interest, enthusiasm and commitment to Health & Safety issues throughout the
project activities.
c) Ensure the provision of an adequately staffed and resourced Safety Management Team
including the provision of the site Safety Officers as required.
d) Ensure that an appropriate risk assessment is produced within the first two to three weeks of
commencement of works and is to be reviewed every three months as required.
e) Ensure that the work is effectively planned and managed including the requirement to minimize
risks to Health & Safety matters to all employees and the general public and the adoption of
appropriate safety standards.
f) Ensure that the operation of the project Health & Safety plan is monitored Through the Site
Safety Officer and that the plan is reviewed as when necessary.
A) The Section Engineers report to the Construction Manager. The Foremen report to the Section
Engineers.
B) Promote an interest, enthusiasm and commitment to Health & Safety Issues Throughout the
project.
C) Plan and maintain a tidy site and organize it in such a way that the work can be carried out
with minimal risk to Health and Safety.
D) Check that the proposed methods of work are effective and have recognized the relevant
safety requirements.
E) Ensure that the work is carried out as planned and regularly inspect all work areas to ensure the
safety of all operations, plant, equipment and materials.
F) Ensure that the workforce is provided with and use the appropriate Personal Protective
Equipment [PPE] and the right tools for their job.
G) Ensure that others, including the general public are protected from our work.
H) Incorporate safety inspections into routine orders and ensure that the operative
Are not required or permitted to take unnecessary risks or short cuts.
I) Ensure that the construction methods are planned and executed with the need to minimize risk to
Health and Safety as an essential Requirement.
J) be aware of the project Health and Safety plan and ensure that it is suitably Implemented and
propose new ideas to be incorporated for the next revision.
M) Ensure that all site accidents / incidents are reported immediately and all of They are to be
formally accounted for.
O) Encourage those who perform safety and reprimand those who do not perform.
Foreman:
D) Responsible to the site management in the implementation of the Health and Safety plan.
F) Every prior to job allocation to the workforce, a quick tool box type meeting Shall be held
on site to explain them about their job, safety system of work and must provide / arrange for them
the relevant equipment. This will be a key obligation of the Foremen.
Safety Officer:
B) Inspect and audit all site operations to monitor compliance with all statutory Regulations
and comply with the H & S Policy.
C) Inspect all relevant files, forms and registers required to be kept at site to ensure the
routine tests and inspections required by the safety plan have duly been carried out and the results
properly recorded.
D) Monitor observance of site safety rules and issue warnings to workers, work supervisors,
site management staff and subcontractors for rectification purposes in case of non-compliance and
unsatisfactory safety performances. Site improvement notices shall be raised wherever necessary.
E) Investigate all accidents / incidents, etc. and generate the necessary recommendations.
H) Liaise with the appropriate representatives of the Municipality & Government of Public
Local Authorities.
I) Monthly safety reports from the sites should preferably be produced by the last day of
every month and to be submitted to the Project Manager with copies to the Head Office soon after.
L) Review and approve Risk assessments and the H & S Method statements.
Workforce:
a) Use only the right tools for every job and keep them in good condition.
c) Totally avoid talking work shortcuts which might lead to unnecessary risks then leading
to accidents.
d) Report all accidents / incidents / dangerous occurrences to the supervisors / Safety Officer
immediately. This is for the benefit of individual's own safety as well as all others around.
e) Report any defect of plant or equipment or any other risks that might lead to accidents.
f) Comply with all work and safety regulations& Communications.
g) HSE manuals are available to all literate workers, be explained to the rest.
j) A regular health monitoring system is set up for the health risk exposure of the workforce as and
when they are identified.
Stonewood Company shall comply with relevant legislation and contractual requirements
including:
A) Client's requirements
B) Country legislation
C) The Municipality's Code of Construction safety practice and the Ministry of Labors guidance
notes.
Such documentation as is relevant will be available from the Central Safety Library.
A) Main Contractor
All Stonewood Company Projects shall comply with any specified health and safety Requirements
of the client whenever stated in the contract.
This includes where specified, preparation and submission of Project specific Health and Safety
plan and meet other requirements if any, in the form of an addendum.
B) Subcontractors
All subcontractors will be selected as per the H&S competency requirements and they will be
required to comply with all relevant legislation, Stonewood Company Health and Safety plan,
relevant safety procedures, all Site rules and the Municipality’s Code of Construction safety
practice. Health and Safety audits shall be conducted on them every month or as required.
Where necessary the subcontractors will be required to provide relevant information as to how
they intend to carry out their works safely.
5.0 SAFETY ORGANIZATION:
To implement the safety strategy, the project Risk Assessment should be issued within two to three
of commencement of the projects. This will be Produced by the site Safety Officer on a simple
subjective judgment (S.S.J.) basis and will be reviewed from time to time but not exceeding six
months.
Each site will have a Safety Folder forming the project Health and Safety plan. This folder will
contain the following documentations:
10. Crane / Hoist / Lift &, Cradle Inspection reports (if applicable).
2- Safety launch meeting at the beginning of a project chaired by the Project Manager and assisted
by the Safety engineer must be held at site.
G. Adequate P.P.E. in stores with the minimum stock being always maintained.
All company employees and the subcontractors will be required to attend safety induction meetings
before starting their works on site. This will be mandatory for each employee new or old, coming for
work on a new site.
Weekly Staff safety meetings & Daily / Weekly Tool box meetings (Workforce and the Trade
Foremen). Trade or the, General Foremen should conduct TBT on a daily basis.
These will be carried out by the Site Safety Officer on a regular basis and the minutes recorded along
with their attendance.
Stonewood Company will recognize all those trades where specialized trainings are required and
ensure that all those personnel who require training are properly trained and where necessary
certified.
An in-house training center for the site supervisory as well as the management staff will be provided
along with the Central Safety Library to facilitate ongoing training on a regular basis.
Every day while allocating job to the workforce the foremen concerned shall explain the nature of
their jog, how to perform the job safely and shall arrange for them the right tools, equipment and
personal protection.
At least every week or more frequently as the case demands, tool box meetings must be conducted
by the Safety Engineer and / or Officer for the workforce preferably on their sites. Only the safety
topic chosen and the total number of attendees will be recorded, These meetings may not extend
beyond 10/15 minutes and only 2/3 job relevant bullet topics be discussed. It would be advisable to
group them trade wise.
Safety Engineer will hold weekly safety meetings with the Trade Foremen regularly on affixed day
and time of a week. The agenda should however mainly focus on the latest accidents / incidents and
dangerous occurrences or any other relevant topic. The topics and the attendance must be minuted.
Safety Officer will also conduct weekly safety meetings for the Section Engineers and the Foremen
on a fixed day and time of a week. The agenda will again be mainly focusing on the latest accidents /
incidents / dangerous occurrences around and other relevant Safety topics. The Safety topics and the
attendance shall be minuted.
On a fixed day and time of a week P.M. or C.M. relevant section engineer(s) and the Safety Officer
will go around the site to ensure that safety is being maintained. Shortfalls are to be recorded based
on which site improvements are to be recommended at the earliest opportunity. Weekly Site
Inspection Checklist Form must be prepared and submitted to management.
The meeting shall be chaired by the Project Manager and is to be Assisted by the Safety Engineer.
The agenda for the meeting will be flexible but accident / loss report shall be a standard inclusion
along with the minutes of the previous meeting. To keep uniformity between sites,
These meetings should preferably be held by the first week of every month for the previous month.
The progress of the meetings must be minuted and distributed to the participants and other
interested parties. The main objective of the meeting will be to assess the implementation of the
Health & Safety plan, to develop hazard control programme, coordinate training, adopt spreading
useful information and control the safety activities within the organization.
Safety reviews will be carried out every three months and the findings will be included in the
Monthly safety Committee Meeting for that month.
The reviews of safety issues are fundamental to the safety strategy of all projects & activities and
"Safety" will be on the agenda for the following meetings:
A) Mobilization Meeting
The primary purpose of the Safety Review will be to provide for an Exchange of information and
The Safety Committee members on site will be the Project Manager, Construction Manager, Section
Engineers, Safety Officer and the Major subcontractor's representatives.
1. A safe work environment will be provided by careful design of new Facilities and purchase of safe
equipment and by the elimination of hazards. Where existing hazards cannot be eliminated their
harmful effects shall be minimized through engineering controls, training in Safe work practices and
by providing the personal protective equipment.
2. Sufficient qualified and trained manpower will be provided to meet Operating services and
maintenance requirements.
3. Employees are continuously trained to develop and maintain the skills Required in their works.
4. Each employee has a responsibility to prevent injury to himself and others and to prevent damage
to property around.
5. All effective motivation methods will be implemented to encourage Employee participation in loss
prevention.
6. Work permits / written job instructions are readily available and enough to be used by employees
when performing hazardous jobs in conjunction with the Project Manager.
7. Concern for employees are shown by Management participation in Inspection and prompt
correction of any hazardous conditions and unsafe acts.
8. Communication between employees and supervisors are encouraged to expedite suggestions for
the elimination of work hazards.
9. All accidents / incidents & dangerous occurrences shall be reported and thorough investigation
will be conducted for the purpose of identifying causes and initiating action to prevent recurrences.
10. An "Object setting" program shall be adopted by the Safety Engineer, changing or rotating the
"Objective" and the "Target" every two months And the relevant notifications would be displayed
on site.
9.0 SAFETY METHOD STATEMENTS:
Where the risk assessment for the project identifies an activity or operation that is not usually
carried out by its operatives or management, a specific Method Statement shall be produced By the
Project Manager or his nominee. This shall be routed through the Safety Officer for his approval, at
least three clear days before its implementation.
The Method Statement will include:
c- The Method Statement once produced will be filed in the project safety folder.
These types of injuries are not included in the list of major injuries But involve an absence from
work for more than three days, Excluding the day of accident. They are generally temped as "Three
Day Reportable"
An accident resulting in an absence from work for up to 3 days or less, excluding the day of
accident is known as "lost Time Accident". These lost days are NOT to be included in the Accident
statistical reports. But will be useful for internal information.
Dangerous Occurrences, which are often termed as Near Accident or Near Misses, are those
occurrences where an accident or loss had somehow been averted but which had enough potential
to have caused one.
All accidents / incidents. & Dangerous occurrences must be reported to the Head Office
immediately. Section and Safety Engineer / Officer shall have the primary responsibility of
reporting these, although nobody is exempted from the obligations. Initial findings in writing are to
follow soon after but not later than twenty-four hours. The area in question should not be disturbed
in any way until the accident / incident case has been investigated. Serious disciplinary action shall
be taken against all those who do not report accidents or try to suppress or distort the case.
The findings will be reported to the Project Manager and the senior staff as appropriate so that
necessary remedial actions may be advised and relevant lessons learnt so as to prevent recurrences.
problems lie and identify the trends, which are essential components of the safety upkeep. We shall
direct our efforts to the prevention of accidents on the basis of the statistical Data collected and
compiled by the Head Office and is projected in the form of Accident Frequency Rate AFR.
(A) The total number of Accidents / Incidents / Dangerous occurrences Every month.
(E) Compile the yearly Accident Statistics basing on the monthly figures and project those bar / Pie
10.8 RECORDS:
All records, be it standard or accident related will be maintained on site. Copies of important ones
shall be sent for filing to the Head Office.
The prime responsibility for the safe of a work place rests with the immediate supervisor or the
Foreman for that area. The relevant Foreman and the Section Engineer will therefore inspect all
work areas under his control including those of Subcontractors. Random samples of work areas
shall be inspected by the Project Manager and the Construction Manager.
Safety personnel will also routinely inspect all the work areas, advice remedial actions and
routinely report their observations to the Project Manager in writing, always saving a copy for the
safety folder. They will also ensure that all necessary remedial actions are taken within a
reasonable time period.
The Policy of Auditing will be followed and will be conducted every six months for the following
purposes:
(A) To make a comprehensive evaluation of the safety performance of the sites or activities.
(B) To obtain a trend of site accidents for analysis and policy making.
(C) To review and comment on the effectiveness of the safety policy.
The "Audit Team" shall be composed of the relative member of Head Office in consultation with
the Site Safety Engineer and / or Officer.
The Audit reports will then be compiled and finally issued to the Project Manager who will
instigate any necessary action in respect of the recommendation made by the Audit Team. Audits
will also allow traceability to assess judgment and Safety perception of the auditors.
All activities shall display instructions on Emergency procedures in the site office and at
conspicuous locations within the site or activity.
A list of contact telephone numbers shall be made available on the site offices where site
In the case of any emergency situation the following procedure will be adopted:
1. Depending on the seriousness of the situation sound the SITE ALARM so that everybody
around knows about the Emergency Situation and can respond quickly.
2. The Telephone Operator shall contact the Site Management immediately.
3. Call the local Emergency Telephone Number- 997/999 and provide the following information if
the situation so Serious :
(A) The exact location of the accident (preferably stay there to guide them)
(B) The nature of the assistance required.
(C) Brief statements of the latest situation & the number of persons involved.
(d) Names and the means of contacting the caller.
For an accident with a large number of injured persons, the Hospital authorities must be notified
in advance for their Preparedness.
ON WORK SITE:
(a) Evacuate personnel from the Emergency scene and let them gather at a pre determined
"Muster / Assembly Point".
(b) The site Firs-Aider shall render First-aid to the injured at the scene without delay and
wherever possible will try not to remove fall victims (if bone fracture is suspected).
(c) Ensure that the scene of accident is untouched wherever possible to facilitate subsequent
investigations by the police or other government bodies.
(d) Notify the Project Manager who will inform the Senior Management, the Consultant or the
Client as required.
(e) A flow chart of actions is as follows:
FLOW CHART OF ACTIONS:
Evacuate the Area (Danger / Affected Zone) Immediately call 997/999 for assistance, if it serious
Call the First-Aider for administering First Aid on site:
Notify the Safety Officer Tel: ........
Notify the Safety Engineer Tel: ........
Notify the Project Manager Tel: ........
Notify the Construction Manager Tel…....
Wait for the Emergency Services to arrive & direct them to The injured parties Do not disturb the
site if possible and assist the Safety Engineer / Officer in the investigation.
15.1 GENERAL
Many injuries can be caused by tool use. Serious eye injuries can result if materials shatter while
using hammers or mallets.
Filling or Chiseling creates chips that can get into the eyes while you are looking up to use above
your hands. Dust and Debris can fall into your eyes... A screw driver Could Slip and cause puncture
wound. If knife slips you could be a tendon, artery, cuts or bruises.
The minimum clear distance between side rails for all portable ladders must be 11.5” = 29cm
The rungs and steps of P.Ls must be corrugated, knurled, dimpled, coated with skid-resistant
materials or treating to minimize slipping.
Each steps or rungs of a fixed ladder must be capable of supporting a load of at least 250lbs=114kg
applied in the middle of a rung or step.
The rungs and steps of P.Ls must be corrugated, knurled, dimpled, coated with skid-resistant materials
or treating to minimize slipping.
If the total length of a climb on a fixed ladders equals or exceeds 24f=7.3m, the following requirements
must be met: fixed ladders must be equipped with either (a) ladders safety devices (b) self-retracting
lifeline, and rest platforms at intervals not exceeds 150f=45.7m (c ) a cage or well and multiple sections
each section not to exceed 50f in length. These ladders sections must be offset from adjacent sections,
and landing platforms must be provided at maximum intervals of 50f.
The bottom cage must be between 7f to 8f above the point of access to the bottom of ladders.
The top of the cage must be a minimum of 42” above the Top of the platforms or point of access at the
top of ladders.
The area around the top & Bottom must be kept clear.
Do not move, Shifted, Extend while in use.
Keep safe distance from Exposed Electrical cable.
The top or top stepladder must not be used as a step
Do not use rear cross-brass as a steps
Keep 3 point of contact with the ladder at all times
Must face the ladder during ascending & descending
Section ladder shall overlap the adjacent section by at least the number of feet as follows.
Length up to 36f 3f overlap
Length up to 36f up to 48f 4f overlap
Over 48f up to 60f 5f overlap
16.0 HEALTH SAFETY & ENVIRONMENTS PLAN
SWC is committed to insure the availability of medical personnel for advise and consultation on matters
of Occupational health & diseases.
Provision shall be made prior to commencement of the project for prompt medical attention in case of
degree of injury.
In the absence of an infirmary, clinic, hospital & physicians that is reasonable accessible in term of time
and distance to the worksite which is available for the treatment of the injured employees, A person who
has valid certificate in first Aid training that can be verified by the documentary evidence, shall be
available at the worksite to render first Aid.
First Aid supplies shall be easily accessible when required, and the contents of the F.A. kit shall be
placed in weatherproof containers. Weekly checking to ensure that expended items are replaced.
Prompt transportation of the injured person to physician, shall be provided.
Telephone numbers of Physician, Ambulance, Hospital shall be posted at Entrance points.
The safety regulations apply to all work carried out with in the premises by the Contractors &
subcontractors.
1. Contractors:
Contractor is responsible for ensuring that their site representatives are in possession of these
regulations and that all their employees are familiar with them. They are also responsible for
ensuring their subcontractors are aware of, and familiar with, the regulations. Copies are
obtained on request.
2. Observance of Regulations:
Contractor’s employees are required to observe these regulations and any other safe working
procedures made known to them by the Technical Services Manager or his nominated
representatives. In the events of any contractor’s employees willfully failing to comply with any
such regulations the company reserve the right to require the instant and permanent removal of
these employees from the site.
3. Guidelines for Contractors to Manage HSE Issues:
Contractors and subcontractors should develop procedures to manage health, safety and
environments issues in manner that is compatible with the HSE Guidelines, which may be issued
from time to time.
All Contractors subcontractors shall recognize HSE issues and shall provide an HSE manual
demonstrating their commitment to HSE Issues. They should implement plans for the following :
Employee health surveillance.
Hearing Conservation.
Heat stress abatement.
Minimizing exposure to chemicals or substances hazardous to health
Complying with safety procedures such as the permit to work system
Site supervising and monitoring
Arranging safety meetings
Driver Training and vehicle inspection.
Working in confined spaces
Using scaffolds and ladders
Electrical systems and equipments.
Handling gases
Fire fighting
Managing waste
Environmental regulation and guidelines
4. INSURANCE COVER:
Contractors will be required to produce satisfactory evidence of Insurance cover in respect of their legal
liabilities to 3rd parties and their own employees. It is condition of contract and subcontract that any
main contractor assumes the legal liabilities to the 3rd parties which may be occasioned through the
actions of any subcontractor or other body employee engaged by the contractor.
5. SMOKING REGULATIONS:
The high risk of fire associated with the use of flammable liquids and gases, SMOKING are strictly
confined to authorized area only. This authorized area is clearly marked. SMOKING is strictly forbidden
elsewhere on the site. In event of infringement of this rules will be require the instant and permanent
removal from the site of contractor’s employees concerned.
6. SECURITY CONTROL:
All Contractors must comply with security regulations. Contractors and subcontractors have no
authorized to enter any other buildings other than the connection with their work.
7. Contractor’s Equipments:
Contractors are responsible for ensuring that all equipments brought on the site confirms to acceptable
standard of safety. Contractors HSE the right to inspect equipment and reject any considered unsafe.
Portable tools are to be center tapped earth type, operable from 110 volt supply.
Equipments, tools, utilities, supplies, vehicles, etc. must not use without written permission. All defects
and breakdown occurring in such authorized equipment are to be notified to the workshop
immediately.
Supplies of engine fuel, solvents, flammable liquids and cylinders of flammable gases, etc. must not be
brought to site without prior agreement. These products should be stored in proper place
Contractors are required to take adequate precautions to protect personnel from injury due to falling
objects in all instances where work is carried out above ground level
12. Emergencies:
In an emergencies all contractors and subcontractors with the exception of visitors, should follow
normal site emergency procedures.
Any connections or disconnections for the contractors use shall only be made to electrical, water, air, gas,
steam or any other installations with the written permission of the site Manager.
A permit to work will be required for any such work, prior to first use of any utilities, the contractor
shall notify and obtain authorization from the concerned department.
All electrical equipments and materials are to be approved by the SWC Electrical Engineer. The
Installation of temporary electrical lighting and power circuits shall comply with SWC requirements in
all areas.
Specific precautions are laid down covering the isolation and de-isolation of electrical installations and
the valid electrical permits must be obtained prior to the issue of work permits.
18.1 GENERAL
It is essential that good housekeeping is maintained throughout the periods of any work, both in
the actual work area and in or around any temporary buildings, Access ways must be kept clear,
surplus or scraps materials removed daily and working areas kept tidy.
The Contractor shall make arrangements for the disposal of surplus and scrap material. No
grade of oil or solvent with a flash pint less than 55 Celsius shall be used for cleaning purpose
18.2 “FIRE & EMERGENCY” HSE-PLAN
The SWC is strictly committed to adhere safety rules and regulations. FIRE & EXIT Plan is designed for
that purpose.
The following Emergency Contact Numbers are being mentioned the following numbers have been
conspicuously stroked at “SAFETY FIRST” main Entrance signboard.
The SWC is dedicated to follow up safety plan and procedure. The Assembly point is also in our HSE
Plan and it is designated at the suitable and appropriate place.
SWC is fully aware for any kind of mishap at working site as well as site office and it’s H/Q. The
HSE lectures has been delivered to all employees about emergency such as fire, incidents,
accidents, fire breakout, emergency evacuation, routes, Exit, by our HSE Engineer / Officer.
How to use Fire extinguishers, different types of fire extinguishers for different purpose,
Housekeeping to be maintained, No Smoking, corridors, paths, Runways must be clear from all
Hazards, Hazards identifications, Firefighting equipments awareness.
Co2, DCP, Foam, Water are main agents for fire extinguisher.
Safety Inductions are very essential for every employees, visitors, and subcontractor.
Tool Box talks is to be given on one time in a week
SCBA system ( self-Container Breathing Apparatus)
Oxygen mask (in smoke and where there are toxic, dust etc.)
Fire Detector
H2s , Carbon monoxide, Toxic materials, Gases, Chemical Hazards
HAZARDS Identification & method of elimination, Minimizing
SWC has considered & analysis the existing HAZRDS non-existing HAZARDS, forthcoming and
predictable Hazards at Job site. Hazards identification as for as control and eliminate that on spot or
minimize hazards, the degree of Hazards, all hazards is to be analyzed. The following Hazards are to be
predicted at site for health Safety and Environments, as well as control Measures has been taken thereof
so for The Contractor’s SWC HSE Plan policy is to Rectifying, Eliminate, Minimize all following
HAZARDS at job site as well as site offices & H.Q also.
18.6 HAZARDS:
1- Fall from the height such as (scaffolds, Platforms, Ladder, Buildings) etc.
2- Fire (paper, cloth, gasoline, Petro-chemicals, wood, Electricity) etc.
3- Unsafe Scaffolding (erection & Dismantle)
4- Unguarded Equipments & Machineries (Earth moving, non-earth moving)
5- Unsafe Access and Egress, Excavations, Ladders, Falling Objects, Vehicles accidents/incidents,
Loading, unloading from mobile cranes, Tower Crane.
6- Unsafe lifting manners, lifting Gears, Collapse, Collision.
7- Water in the excavation, Ground water, heap of waste materials, toxic, gas
8- Used material at job, unsafe storage
9- Sharp edges of objects, Steel or Iron bars upright in naked condition.
10- Sparks, Unearthing Electrical cable, Electric Earth, Occupational disease Injury, Vehicle
Accident, Sand Collapse, Lock out/ Tag out procedure not followed,
Bad Tools, Noise Hazard, Heat & Humidity, PPE not followed, bad planking, Erection of
scaffolds on unsafe ground & not leveled, Handrail, mid-rail top rail, Toe Board not erected
Name:____________________________
Signature:_________________________
The SWC has covered all areas of safety health & environment related to our site jobs, by the following
format:
Hot Work permit (HWP)
Confined Spaces Work Permit
Daily Site Report
Weekly Site report
Monthly Report
Welfare checklist
Incident/Accident Report
Near-Miss Report
First Aid Report
Safety Induction/Tool Box Talks
Fire Drill
Safety Meeting
Site Safety Inspection Report
Scaffolding Inspection Report
Welding, Cutting, Brazing, Soldering check list
Risk Assessment Format
It is hoped that our HSE PLAN would be recognized to our Consultant, ADM.
We are committed to adhere HSE PLAN and try to improve in the forthcoming period & time. Any
guidelines & suggestions, advise would be appreciated by our deep respected Consultants, ADM or
Third Party
Project Name
Project No.
Location
Month of
Date Time Details& Status Remarks
Checked by :-
Page
Weekly/Monthly Inspection Checklist
1 0f 3
Project/Site Manager :
a Access
b Stairways/ Ladders
c Storage
d Lighting
e Ventilation
f Disposal of Materials
e Gloves
f Overall / Apron
g Filter/Dust Mask
j Reflecting jacket
3 Hygiene/Welfare
a Food handling
c Toilets/Washing facilities
d Accommodations
e Kitchens/Canteens
f Exhaust Fan/
Page 2 0f 3
c Fire Alarm
d Emergency Exit Way
e Assembly Point
5 Emergency Back-up
e First Aider
a Guards
b Refueling Procedure
c Cables
d Informatics / Signs
f Backing Horn
h Indicators/Mirrors
7 Scaffoldings
a Access / Platform
b Ladders Condition
d Foundations/Footing /Base
e Standards
f Ledgers
g Bearers
h Transoms
i Braces
Page 3 0f 3
k Fittings
l Anchors
n Ties
o Scaffolding Tags/
8 Lifting Gears/operations
b Color Coding
9 Procedures
a Safety Meetings
c Safety Inductions
d Trainings
e Fire Drill evacuation Exercising One in 4th month (3 times in a year)
g Permit Systems
Name:
Designation/Position
Sign Date
Comments if any:-
HSE PLAN - RISK ASSESSMENT
1 8
2 9
3 10
4 11
5 12
6 13
7 14
D EXISTING CONTROL MEASURES: (In full details)
1 8
2 9
3 10
4
11
5 12
6 13
7
14
(J) DESIGNATION:
SIGNATURE:
(K) DATE:
(L) RE ASSESSMENT DATE:
MONTHLY HSE REPORT
PROJECT NAME:
PROJECT NO.
Location
TO BE COMPLETED ON THE LAST DAY OF EVERY MONTH
Sr. DESCRIPTION LAST THIS CUMULATIVE REMARKS
MONTH MONTH
1 MEN HOURS WORKED
2 FIRST AID INJURIES
3 LOST TIME INJURIES (LTI)
4 DAYS LOST TO LTIS
5 FATALITIES
6 FIRE INCIDENTS
7 VEHICLE ACCIDENTS
8 PROPERTY DAMAGE
9 NEAR MISS REPORT
10 FREQUENCY RATE (F.R) LTI
11 SEVERITY RATE OF LTI
12 HSE INDUCTION TRAINING
13 IN-HOUSE HSE TRAINING
14 TOOL BOX TALK
15 HSE MEETING
16 HSE INSPECTION
17 HSE AUDITS
18 FIRE DRILL After 4 month
19 SAFETY VIOLATION REPORT
22.0 Appendix: