Professional Documents
Culture Documents
Homework/Assignment 4
Full Name of submitter: Nguyễn Hải Phong Student ID: IELSIU20059
Contents of questions
Exercise 1: Product A is made according to the bill of materials diagram shown below. Fifty
as are needed in week 3, 250 in week 5, and 150 in week 7. Product A has a lead-time of one
week.
The table below shows additional data (master file) for the items B, C, and D.
B C D
Lead-time 2 1 1
Exercise 2:
Production Management
Product A is made according to the bill of materials diagram shown below; 200 units of A
are needed in week 5; 300 in week 8. Product A lead-time = 1 week.
The table below shows additional data for the items B, C, D, and E.
B C D E
Lead-time 2 3 1 2
Exercise 3:
Products A and B are made according to the bill of materials diagram shown
below. Scheduled quantities of the end products are, for A, 95 units in week 4, 150 units in
week 6, and 130 units in week 8, and for B, 80 units in week 3, 70 units in week 6. Lead-
times: A = 2 weeks, B = 1 week.
Production Management
The table below shows additional data for the items C, D, and E.
C D E
Lead-time 2 1 3
Exercise 4:
There are for 103 units of product A in period 8 and 200 units of product Q in period
7. The on hand inventory levels for each item are A = 18, Q =6, B = 10, C = 20, D = 0
and E = 30. A safety stock of five units is maintained on product A and six on units of
product Q with no safety stock on other components. Additionally, ten units of 18 units
on hand of product A are already allocated to particular customers. There are no open
orders (scheduled receipts) on any item. The lot size for items A, Q, B, and C is the same
as the net requirements (lot-for-lot ordering), while the lot size for D is 200 units and
for E is 500 units.
Production Management
Develop an MRP for product A and Q with the product structures (BOM) given below.
What should be the size of the orders for each item, and when should orders released?
Exercise 5:
The Alpha Beta Company produces two products; A and B, that are made from components
C and D. Given the following product structures, master scheduling requirements, and
inventory information, determine when orders should be released for A, B, C, and D and the
size of those orders
Exercise 6:
Production Management
Files and More, Inc. (F&M), a manufacturer of office equipment, uses MRP to schedule its
production. Because of the current recession and the need to cut costs, F&M has targeted
inventory as a prime area for cost reduction. However, the company does not want to reduce
its customer service level in the process. Demand and inventory data for a two-drawer file
cabinet are given in the following table. Complete an MRP matrix for the file cabinet using:
(a) L4L
(b) EOQ
(c) POQ lot sizing.
Which lot-sizing rule do you recommend?
Note:
- Continue using this form to complete your works and submit on Blackboard
- Name your file
o If you submit individually: Promana_HW4_StudentID_FullName
o If you submit for a group (Group # are as per the number you have registered as
guided in the file “Semester Project Requirement” and be finalized by lecturer):
2122Promana_HW4_G#
- Due Date is defined in detail at each “ ASSIGNMENT INFORMATION” from Blackboard
- Maximum score of late submission is two third of “Point Possible”
- If you can’t submit on Blackboard: Email your work to TA, copy it to your Lecturer, attached
also the screenshot of your Blackboard showing error in that transaction
---------
Answers/Works
Exercise 1:
Item: A LLC: 0 WEEK
Lot size: L4L LT: 1 1 2 3 4 5 6 7
Gross Requirements 50 250 150
Scheduled Receipts
Projected on Hand 0 0 0 0 0 0 0 0
Production Management
Exercise 2:
Projected on Hand 200 200 100 100 600 200 200 200 200
Net Requirements 300
Planned Order Receipts 500 500
Planned Order Releases 500 500
Exercise 3:
Item: A LLC: 0 WEEK
Lot size: L4L LT: 2 1 2 3 4 5 6 7 8
Gross Requirements 95 150 130
Scheduled Receipts
Projected on Hand 0 0 0 0 0 0 0 0 0
Net Requirements 95 150 130
Planned Order Receipts 95 150 130
Planned Order Releases 95 150 130
LLC:
Item: D WEEK
1-2-3
Lot size: 800 LT: 1 1 2 3 4 5 6 7 8
Gross Requirements 250 600 550 140 260
Scheduled Receipts
Projected on Hand 350 100 300 300 550 410 150 150 150
Net Requirements 500 250
Planned Order Receipts 800 800
Planned Order Releases 800 800
Exercise 4:
Production Management
Product: A
LLC: 0 PERIOD
(Safety stock: 5)
Lot size: L4L LT: 4 1 2 3 4 5 6 7 8
Gross Requirements 103
Scheduled Receipts
Projected on Hand 8 8 8 8 8 8 8 8 5
Net Requirements 100
Planned Order Receipts 100
Planned Order Releases 100
Product: Q
LLC: 0 PERIOD
(Safety stock: 6)
Lot size: L4L LT: 2 1 2 3 4 5 6 7 8
Gross Requirements 200
Scheduled Receipts
Projected on Hand 6 6 6 6 6 6 6 6 6
Net Requirements 200
Planned Order Receipts 200
Planned Order Releases 200
Projected on Hand 20 20 20 20 0 0 0 0 0
Net Requirements 180 200
Planned Order Receipts 180 200
Planned Order Releases 180 200
Exercise 5:
Exercise 6:
20+ 40+30+10+ 45
d= =29
5
a. L4L
Production Management
b. EOQ
EOQ=
√ 2 Co d
Cc
=
√
2×100 × 29
1
=77
c. POQ
Q 77
POQ= = ≈ 3
d 29
Product: cabinet LLC: 0 PERIOD
Lot size: POQ 3 LT: 1 1 2 3 4 5
Gross Requirements 20 40 30 10 45
Scheduled Receipts
Production Management
Projected on Hand 25 5 40 10 0 0
Net Requirements 35 45
Planned Order Receipts 75 45
Planned Order Releases 75 45
Conclusion:
The POQ should be recommended because the total cost is the lowest