Professional Documents
Culture Documents
Lead Times
Product Structure Tree for Assembly A A 1 day
B 2 days
A C 1 day
D 3 days
E 4 days
F 1 day
B(4) C(2)
Demand
Day 10 50 A
D(2) E(1) D(3) F(2) Day 8
Day 6
20 B (Spares)
15 D (Spares)
their lead time. So, in the materials requirement plan below,
weFirst, the number of units of “A” are scheduled backwards to
allow for have to place an order for 50 units of “A” in the 9 th
week to receive them in the 10th week.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
Next, we need to start scheduling the components that make up “A”. In
the case of component “B” we need 4 B’s for each A. Since we need 50
A’s, that means 200 B’s. And again, we back the schedule up for the
necessary 2 days of lead time.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
B Required 20 200
Order Placement 20 200
LT = 2
Spares
A 4x50=200
B(4) C(2)
A
Part D: Day 6
40 + 15 spares
B(4) C(2)
Master
Engineering
production Inventory
design
schedule transactions
changes
(MPS)
Reports
Bill of Materials (BOM) File
A Complete Product Description
• Materials
• Parts
• Components
• Production sequence
• Modular BOM
– Component or Subassemblies BOM
• Planning BOM or kits
– create an artificial parent to the BOM used for inexpensive items like
washers or pins to group.
• Explosion: revealing the requirements for each component.
Classification and Coding
• If identical items exist at
various levels in the
BOM:
– Item is coded at lowest
level at which it occurs
– This number identifies the
part at the lowest level of
usage.
– D (Level 2 or Level 3)
Inventory Records File
• Buckets= time units in MRP system
– Week bucket vs. day bucket
• Each inventory item carried as a separate file
– Status according to “time buckets”.
• Pegging
– Identify each parent item that created demand.
• Parent vs. child
– Parent= Items above the current level
– Child = Items below the current level
Primary MRP Reports
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans
MRP SComputerized System tructure
Data Files Output Reports
MRP by period
BOM Master report
production schedule
MRP by date
report
Lead times
(Item master file) Planned order
report
Inventory data
Purchase advice
Material
requirement
planning programs
(computer and
software) Exception reports
Purchasing data
Order early or late or
not needed