Chapter 16
Materials
Requirements
Planning
McGraw-Hill/Irwin ©The McGraw-Hill Companies, Inc., 2004
3
OBJECTIVES
Material Requirements Planning
(MRP)
MRP Logic and Product Structure
Trees
Time Fences
MRP Example
Material Requirements
Planning
Materials requirements planning (MRP)
is a means for determining the number
of parts, components, and materials
needed to produce a product
MRP provides time scheduling
information specifying when each of
the materials, parts, and components
should be ordered or produced
Dependent demand drives MRP
MRP is a software system
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
LT = 2
Spares
A 4x50=200
B(4) C(2)
A
Part D: Day 6
B(4) C(2) 40 + 15 spares
MPS
(Specific End Items)
Exhibit 15.5
Example of Time Fences
Moderately
Frozen Firm Flexible
Capacity
Forecast and available
capacity
Firm Customer Orders
8 15 26
Weeks
Aggregate Forecasts
Firm orders product of demand
from known
plan from random
customers
customers
Components
Production sequence
Modular BOM
– Subassemblies
Super BOM
– Fractional options
Pegging
– Identify each parent item that created
demand
Gross Requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved.
19
MRP Example
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
It takes LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
2 A’s for On-
hand
Net requirements
Planned order receipt
20
20
each X 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
It takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
1 B for hand Planned order receipt 20
each X 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 3 C
LT=2
Gross requirements
Scheduled receipts
45 40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 2 C
LT=2
Gross requirements
Scheduled receipts
45 40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 5 C
LT=2
Gross requirements
Scheduled receipts
45 40
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans
End of Chapter 16