Professional Documents
Culture Documents
Maintenace activities & their frequencies are subjected to change based on learnings , RCA
recommendations & OEM Recommendations.
Page 1 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Maintenance of OLTC driving mechanism .
1.21
Greasing of Bevel Gears . Tightness of connecting rods. Two Yearly
Two Yearly – If on load
operation of OLTC done
1.22 Checking of Diverter Contacts OLTC DCRM atleast once in year.
1.30 Earth Resistance of transformer Earth Pits ( With Grid) Six Monthly
1.31 Thermo-vision Scanning of Transformer Quaterly
Biannaul
1.37 Testing of Bushing CT – Resistance, IR, Knee Point
2 CIRCUIT BREAKERS
2.1 BREAKER OPERATION CHECKS
a CB Operating Timings (Main, PIR, Aux. Contacts Yearly
b Static Contact Resistance Yearly
Dynamic Contact resistance (DCRM), Contact wipe along Yearly – Bus Reactor CB.
d
with injected current and close/trip coil currents Two Yearly – Other CB
Page 3 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Checking of door sealing gaskets and replacement, if
b Yearly
necessary
Cleaning of MB , Hole Sealing & Illuminitation of Operating Yearly
c
Drive MB
Cleaning of MB , Hole Sealing & Illuminiation of Common
d Six Monthly
MB
Page 4 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
d Cleaning of marshalling box and junction box Six Monthly
e Thermal Scanning of CT Terminal Blocks Six Monthly
3.4 Other Checks
Checking of Earthing system
a. No Gaps in Flat Connection with Transfirmer / MB. Yearly
a b. No Rusting of Nut Bolts
c. No loose connections
d. Double Earthing provided to CT Structure & CTJB.
Checking of Tighness of Structure nut Bolts & foundation Two Yearly
b
nut bolts . Repalcing of rusted nutbolts.
4 CAPACITIVE VOLTAGE TRANSFORMERS
4.1 VISUAL CHECKS & CLEANING
Visual checking of earthing HF point (in case it is not being
a Two Yearly
used for PLCC)
Checking for any breakage or cracks in cementing joint &
b Fortnightly - Monthly
Inspection of bellows
c Checking of oil leaks Daily - Monthly
c Testing of EMU tank oil for BDV (if oil found discolored) Based on requirement
Page 5 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
e Checking of terminal Connectors Checking of Tightness Two Yearly
Contact resistance measurement including contact
f Two Yearly
assembly and current transfer assembly
g Tightness of Bolts, nuts and pins etc. Two Yearly
Cleaning of support insulators and checking of insulator Two Yearly
h
cracks, If any
i Checking of Interlock (mechanical and electrical) Two Yearly
j Thermovision Scanning Quaterly
Reference marking on moving contact for 765kV SPOLT Two Yearly
k
Isolators – GE Make.
L IR of Drive Motors Yearly – Two Yearly
5.3 EARTH SWTICH
a Checking & Alignment of earthing blades Two Yearly
b Cleaning of contacts Two Yearly
Only if some alignment
c Contact resistance work done / Hotspot
attended.
d Checking of earth connections of structure and MOM box Yearly
e IR of Drive Motors Yearly - Two Yearly
5.4 MARSHALLING BOX
a Visual check of auxiliary contacts Yearly – Six Monthly
8 WAVE TRAPS
a Thermography of all Clamp & Connectors Quaterly
b Tightness of top & bottom clamp connections Two Yearly
c Verify the Bird Guard Two Yearly
Two Yearly
d Checking for any cracks, Cleaning and Tightness of BPI
9.10 SCADA
a. Check for Persisting Alarms List with Reason Daily
b. Check for Heathiness of all Relays , Relay Communication Daily
Page 8 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
& GPS.- PMU & Subsation
Check for Heathiness of all Systems & System Daily
c
communication ( Server , OWS , Gateway)
d Check for All analog display parameters are in valid state. Daily
Check WTI/OTI/SF6 Gas Pressure readings matching with Quaterly
local readings.
e Check for any alarm in Ethernate Switches Weekly - Daily
Extract & Check relay settings is as per recommended Yearly
f
settings
Extract Settings & PSL for relay . Create Backup for Realy Yearly
g
Setting Project & upload on DMS.
Take backup of SCADA System ( Server , OWS , Quaterly – Six Monthly
h
Engineering PC , Ethernate Switches , Firewall Etc)
i Chageover of Server Six Monthly
j Data Communication Link Healthiness upto RLDC Daily
10 PLCC AND OPGW SYSTEM
SOS
a LMU composite/ Return loss
Page 9 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Service Test - Battery Capacity check on water / in house
d Yearly
resistance load for 4 -5 Hours .
a. Within the first two years
Performance capacity Test
of service.
b. After that once in five-
(Excessive capacity loss is indicated when the battery
year intervals.
e capacity drops more than an average of 1.5% per year of
c. Annually if the battery
rated capacity from its capacity on the previous
shows signs of
performance test. )
excessive capacity loss.
d Check for any leakage of oil from Oil drain pipe joints. Daily
13.4 MOTORS
a Tightness of Terminal connection checking Half Yearly
b Lubrication of Bearings Half Yearly
c Overhauling Half Yearly
13.5 PUMPS
Page 12 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Checking of operation of Hydrant pumps Sump pumps,
a Jockey pumps. Monthly
Yearly
d Checking of alignment of pump set
SOS
f Overhauling
Monthly
g Check leakage & Lubrication of Jockey Pump
13.6 HYDRANT SYSTEM
14. DG
a Diesel Level in DG (must be Greater than 25%) Daily
b Check for engine oil level Daily
c Check engine oil Quality Monthly
Page 14 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
b Relays testing Two Yearly
c Tightness of all electrical connections Yearly
d Checking of Indicating meters Yearly
e Check for change-over facility Yearly
LT CB Maintenace
1. Cleaning , hole sealing of control cabinets
2. Cleaning of LT switchgear contacts.
f Yearly
3. Tightening of power & control connections
4. Check close -open operation in test mode
5. Check for Heating Circuit & Illumination
Maintenance of all LT SFU
1. Cleaning , hole sealing of SFU cabinet
2. Cleaning of power connections Yearly
g 3. Tightening of power & control connections
4. Check close -open operation.
5. Gasket Healthiness
6. Proper Door lock
Maintenance of all BMK in yard
1. Cleaning , hole sealing .
2. Tightening of power & control connections Yearly
3. Ensure Proper Two earthings provided to BMK.
h 4. Check for any rusted nutbolt & replace same
5. No Gap in Earthfalt & BMK connection
6. Heater Circuit & Illumination
7. Gasket Healthiness
8. Proper Door Lock
15.2 LT SWITCHGEARS
Yearly
a Functional checking (Trip, close etc.) of 33/11 KV CBs.
Yearly
b Measurement of Operating timings if provided
16 Miscellaneous
17 EOT crane
17.1 Hoisting
Traversing
17.2
Page 16 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Motor Bearings- Routine check Monthly
17.3 Travelling
17.4 Control
Page 17 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
b. Ensure sufficient earth connection to terminal
provided.
19 Ventilation system
Exhaust Fan
20
Examine the airways in to the fan guards (if fitted) Six – Monthly
A
Page 18 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
Examine motor cooling fins Six – Monthly
B
Examine and operate vibration sensors (if fitted), and Six – Monthly
E temperature sensors (if fitted)
Examine condition of safety guards (if fitted) and their Six – Monthly
F fixings
CCTV
21
Page 19 of 25
CONFIDENTIAL INFORMATION
Sr. No. Activity Frequency
CCTV JB tightness and cleanliness Monthly
E
Daily
A Check for Daily Generation & Any Alarm on Invertor.
Also check them for any sorts of cracks and other Monthly
B mechanical defects.
Check the panels for any sort of animal infestation and Monthly
C remove it when found.
Cleaning the panels with normal water or gentle soap Half Yearly
D water.
Ensure that the wires that come to and go from the Half Yearly
F inverters are not loose.
Air Conditioner
23
Check for any water leakage from AC Indoor Unit & Quaterly
B Cooling efficiency of AC.
Yearly
C Cleaning of Air Filters for Indoor & Outdoor units.
Yearly
D Ensure Properr sealing of Outdoor Unit power connections
Note :-
Nut bolts tightness of Clamp , Structure , Bushing , CT , CVT , CB ,Transformer , Bus Bar ,
LT bus bar etc to be done with recommended torque with the help of torque wrench .
Refer respective clamp , structure drawings & respective equipment manuals for
recommended torque value.
Ensure Diagonal Tighness of nut bolts .
After tightening of nut bolts , wherever possible do marking with paint marker to avoid
overtightening in subsequent AMP work.
Page 20 of 25
CONFIDENTIAL INFORMATION
HV & EHV Bushng Visual Inspection Checklist
A
General condition of the bushing (surface condition, position, rating plate
presence and readability, porcelain condition and damages, etc.).
Condition of the sheds (pollution, hydrophobicity –Good Condition -water
droplets are round and do not wet
B
the surface , if silicone sheds losing their original shape may be a sign of oil
leaking somewhere above, etc.
Oil level . If the oil level gauge is equipped with a floating ball, misreading
C happens occasionally because of oil absorption by the ball can cause it to
sink.
Oil Colour (via the gauge) Oil should be of light colour and transparent.
D Darkening of the oil and/or opacity (cloudy appearance) is a sign of ageing,
excessive moisture or carbon particles.
E
Gasket condition at the bushing head and flange and between
transformer’s tank/turret and flange. Look for oil leaks and moisture ingress.
F
Cement condition between the upper porcelain envelope and the head
or flange. Look for oil leaks.
Mechanical condition of connections to the switchyard (flexibility,
G connection should not be too rigid, prevention of mechanical overloading
caused by thermal dilatation).
Upper contact condition (overheating traces appearing as a colour
H change, mechanical tightness) & Condition and position of corona rings
and arcing horns.
Condition of test tap and/or voltage tap (leakage and/or moisture
I
ingress, internal connection –•often performed during diagnostic testing).
J
Grounding connection between the bushing flange and transformer
tank/cover/turret.
GIS Substations
Page 21 of 25
CONFIDENTIAL INFORMATION
Maintenace activities & their frequencies are subjected to change based on learnings , RCA
recommendations & OEM Recommendations.
Frequency
Sr. No. Activity
All compartments-Finding SF6 gas leaks (if more than one Yearly
1.2
alarm per year)
Checking pressure using the permanent pressure gauge (if
1.3
applicable) or BW3 Yearly
Gas density, Moisture and Gaspressure- Check and if 5 years
1.4
necessary , replenish SF6
5 years
1.5
Gas humidity- Carryout due point measerement
5 years
1.6
Checking of SF6 gas Purity
Density monitor- Check switching points of micro switches 5 years
1.7
with portable density monitor tester.
Control cubicle and operating mechanisms- Check heaters 5 years
1.8
with correct functioning
Contact resistance measurement- Test as per circuit 5 years
1.9
proposed during commissioning
PD Measurement (Only for GIS with embedded UHF 5 years
1.10 sensors)- Background noise measurement and PD
measurement at system voltage
Circuit Breaker, Fast Acting earth switch, maintenance earthing 5 years
1.11 switch, disconnector switch- Check End position of Switching
elements
Static elements (especially with outdoor installations)- Check for 5 years
1.12
Corrosion
5 years
1.13
Bay Structure-Retighten all Anchor bolts to normal torque
2 Circuit Breakers Operating Mechanism
Percentage- Carry out % - SF6 measurement 5Y
2.1
Optical indicator- Spring & On/off position check 5Y
2.2
Auxiliary contacts- Change over position check 5Y
2.3
Spring Charge motor- Charging time and current measurement 5Y
2.4
Operating Mechanisms- Check Switching times, oil level, 5 Y or 5000
2.5 Carbon brushes, possible leaks, electrical connections, Operations
Circuit Breaker- Major inspection (5 days per CB) 15 Y
2.6
Operating mechanism- DCRM and Travel measurement 15 Y
2.7
2.8 Arcing unit 5000 CB
Operations
Inspection/overhaul,
replacement of spring & pins
Page 22 of 25
CONFIDENTIAL INFORMATION
Frequency
Sr. No. Activity
Opening the pole and inspection of contacts and the 5,000 operations
2.9 nozzle.
Major Overhauls
3.10 Recording the movement curves (opening & closing)- 12Y to 18Y or 3000 CB
Operations
Inspection of the CB Contacts & Disconnector & operating Every 5000 operations or
mechanism when electrical wear is
reached
Page 23 of 25
CONFIDENTIAL INFORMATION
Frequency
Sr. No. Activity
Major Overhauls
Disconnectors/Eart switch
4
Operating Mechanism 5Y
4.2
Check Switching times, on/off Current measurement, Check
end positions if necessary. Check operation functionality.
Operating Mechanism 5Y
4.3
Optical position indication check for change over
Earth Switch- 5Y
4.4
Insulated Earth Switch External Earthing link installation
and tightness check
Operating mechanism- Check maximum operating torque 5Y
4.5
SF6/Air bushing
6
Page 24 of 25
CONFIDENTIAL INFORMATION
Frequency
Sr. No. Activity
Miscellaneous checks
9
Counters Yearly
9.2
Page 25 of 25
CONFIDENTIAL INFORMATION