Professional Documents
Culture Documents
Production and Operations Management - Session 15-16
Production and Operations Management - Session 15-16
&
OPERATIONS MANAGEMENT
SESSION 15-16
MATERIAL REQUIREMENTS PLANNING (MRP)
• Material Requirements Planning (MRP)
• Is a computerized information system that aids in the planning of materials in
organization
• MRP systems exploit certain unique characteristics of the production items
• Utilize information on lead time, inventory status and master production schedule to
make material available exactly at the time of requirement
• The logic applied to plan materials could be extended to other resources
required in any operations system. Therefore, these planning methodologies
can be broadly defined as resources planning
PLANNING FOR MATERIALS: TYPES OF INVENTORIES
• Two types of inventories exist in any operations system
• Operating Inventory:
• Denotes all the resources (broadly of material and capacity) that are available for the
operating system to consume in the production process
• Example: Number of steering wheels required for a day’s production of 5,000 cars in Maruti Plant
• Exhibit Dependant demand attributes
• Distribution Inventory:
• Meant for market consumption
• Exhibit Independent demand attributes
• Example: Number of Alto’s to be stocked to meet a day’s demand
• They differ in their demand attributes & therefore require alternative planning
methodologies
PLANNING FOR MATERIALS: TYPES OF INVENTORIES
• Demand Attributes
PLANNING FOR MATERIALS: TYPES OF INVENTORIES
• Demand Attributes
Attribute Dependant Demand Independent Demand
Nature of Demand No uncertainty; Dependant; Parent - Considerable Uncertainty,
Child relationships cause dependency Independent
When to order? (Timing) Very critical, can be estimated Cannot be answered directly
DEVELOPING MRP LOGIC BASIC BUILDING BLOCKS
• Existence of multiple levels of dependency
• Product Structure – Bill of Materials (BOM)
• Time phasing the requirement
• Determining Lot Size
• Incorporating lead time information
• Establishing the planning premises
DEVELOPING MRP LOGIC BASIC BUILDING BLOCKS
• Existence of multiple levels of dependency
Basic Telephone
Hand Set
Cover Plate
A fastener secures a
Handset pair of the cover plates Basic
in the handset Telephone
DEVELOPING MRP LOGIC BASIC
• Existence of multiple levels of dependency
BUILDING BLOCKS
• Level-by-Level computation
Method A Method B
Basic Telephone Basic Telephone
Required :100 Required :100
On hand Inventory : 30 On hand Inventory : 30
Planned Quantity : 70 Planned Quantity : 70
Handset Hand set
Required :100 Required : 70
On hand Inventory : 27 On hand Inventory : 27
Planned Quantity : 73 Planned Quantity : 43
Cover plate* Cover plate*
Required :200 Required : 86
On hand Inventory : 16 On hand Inventory : 16
Planned Quantity :184 Planned Quantity : 70
* (Each handset requires 2 cover plates) *(Each handset requires 2 cover plates)
MRP INPUTS & OUTPUTS
Master Production Schedule
Source: http://www.penhero.com/PenGallery/MabieTodd/MabieToddVisofilSystem.htm
PRODUCT STRUCTURE
PRODUCT STRUCTURE
Telephone Level 0
Button Control
Assy. (1) Panel (1) Level 3
Period (Week)
1 2 3 4 5 6 7 8
On hand 50
On order 300
Required 200 120 150
Net Quantity 50 50 -150 -150 30 30 30 -120
Assemble
200 base units
LT for manufacture of Operating Unit
Assemble
Offset Offset 200 telephones
Explode Lot
Lot sizing
BOM rule
Offset
Lead
Shop Procurement Time
Orders Notices
MRP
A manufacturing organization needs to plan the materials required for the next six weeks for the
manufacture of its end-product (Product A), as per a master production schedule. In addition to the end
product, there is an independent requirement of Component C, as it is sold as a spare in the market. The
MPS for both the end product and the spares are given in Table. In order to assemble one unit of Product
A, Components B to G are required. Figure shows the product structure. The number alongside each
component denotes the number of each component required to assemble its immediate parent. An
extract of the inventory status (Table) reveals the inventory on hand. There are no pending orders for
delivery. Different lot-sizing rules are used for the components of Product A. Moreover, the components
have different lead times. All this information is available in Table. Perform an MRP exercise to estimate
the quantity and timing of the components required for the manufacture of Product A as per the MPS.
Master Production Schedule for the next six periods
1 2 3 4 5 6
Product A 100 150 200 100 0 200
Component C 50 60 70
Product Structure
G 1
MRP
MRP
MRP
MRP
MRP: SAFETY STOCK
MRP: SAFETY STOCK
MPS – MRP – CRP
Begin
No
Modify MRP
Material Requirements
Feasible?
Planning (MRP)
Yes No
Capacity Requirements
Feasible?
Planning (CRP)
Yes
Finalise
Plan
MRP: ISSUES & CHALLENGES
• Problems MRP systems potentially face:
• Bad data integrity
• Lack of discipline in updating the required data bases as and when changes
take place elsewhere in the organisation
• Uncertainties associated with issues that lie outside the control of people
and the system
• How often MRP must be updated and rerun?
• Regenerative Method
• Net Change Method
• Handling uncertainties affecting the system by incorporating:
• Safety Stock
• Safety Lead times
UPDATING THE SYSTEM
• An MRP is not a static document
• As time passes
• Some orders get completed
• Other orders are nearing completion
• New orders will have been entered
• Existing orders will have been altered
• Quantity changes
• Delays
• Missed deliveries
UPDATING THE SYSTEM
• Two basic systems
• Regenerative system
• Approach that updates MRP records periodically
• Essentially a batch system that compiles all changes that occur within the time interval and periodically
updates the system
• A revised production plan is developed in the same way the original plan was developed
• Net-change system
• Approach that updates MRP records continuously
• The production plan is modified to reflect changes as they occur
• Only the changes are exploded through the system
MRP BENEFITS
• Enables managers to easily
• determine the quantities of each component for a given order size
• To know when to release orders for each component
• To be alerted when items need attention
• Additional benefits
• Low levels of in-process inventories
• The ability to track material requirements
• The ability to evaluate capacity requirements
• A means of allocating production time
• The ability to easily determine inventory usage via backflushing
• Exploding an end item’s BOM to determine the quantities of the components that were used to
make the item
MRP REQUIREMENTS
• To implement an effective MRP system requires:
• A computer and the necessary software to handle computations and maintain records
• Accurate and up-to-date
• Master schedules
• Bills of materials
• Inventory records
• Integrity of data files
MRP DIFFICULTIES
• Consequence of Inaccurate Data
• Missing parts
• Ordering incorrect numbers of items
• Inability to stay on schedule
• Other problems
• Assumptions of constant lead times
• Products being produced differently from the BOM
• Failure to alter a BOM when customizing a product
• Inaccurate forecasts