You are on page 1of 8

Deep Foundations on Bored and Auger Piles – Van Impe & Van Impe (eds)

© 2009 Taylor & Francis Group, London, ISBN 978-0-415-47556-3

Energy piles in Scotland

D.J. Lennon
Stent Foundations Limited, Balmore, UK

E. Watt
Stent Foundations Limited, Balmore, UK

T.P. Suckling
Stent Foundations Limited, Basingstoke, UK

ABSTRACT: Comparative thermal conductivity testing of piles and a borehole are described. The results of
installation and testing of both precast concrete and steel driven energy piles are presented. There is currently
no standard UK specification for thermal conductivity testing and the three tests de-scribed were all undertaken
using different procedures. It is demonstrated that piles can be used to measure the thermal properties of the
ground. Foundation piles which incorporate a ground source pipe can offer a cost effective sustainable method
of providing heat energy for a wide range of construction developments. Procurement and the construction
sequence must be properly planned and managed to give the Client the best value for money.

1 INTRODUCTION 2 GROUND SOURCE ENERGY SYSTEMS

The sustainable use of resources is now an impor- The heat pump for the extraction of ground source
tant part of the construction process. In the United energy was invented in the 19th Century. In Europe
Kingdom (UK) statutory requirements currently ground temperature is reasonably constant below
require a proportion of the energy usage of any new about 8 m depth. This phenomenon can be used in
building to be provided from a renewable source. In the design of seasonal thermal ground storage, with
the future the proportion required is likely to increase excess energy transferred between a building and the
and when at levels above 10% ground source energy ground throughout the year as the seasons and the
storage systems are likely to become viable in many building’s energy requirements change.
cases. The available energy capacity from the ground
Designers of piles have the opportunity to spec- beneath or surrounding any building depends on factors
ify energy piles whenever piles are required to pro- including geometry, geology, groundwater and ground-
vide structural support to any building. However, water flow. Other aspects such as whether the ground
it is currently very difficult to ensure that energy surface is covered and thus not able to receive replen-
piles are compatible with the architectural, struc- ishing solar energy also influence the available ground
tural and energy design requirements unless intro- source energy. Every project will thus be different and a
duced into the building design concept at an early calculation is essential for each and every building.
stage.
Full scale thermal testing of in-situ piles is unfor-
tunately still rare in the UK. Comparative tests are 3 ENERGY PILES
described on a driven concrete pile, a driven steel pile
and on a pushed-in plastic coaxial pipe, all installed Energy piles can be either bored or driven piles, nor-
on a test site in Balmore, Scotland. This is the first mally comprising reinforced concrete. The piles con-
time ever worldwide that side-by-side thermal tests on tain plastic pipes which transport a heat transfer fluid.
piles and a pushed-in coaxial pipe have been under- From the pile heads these pipes are connected to a
taken, and also the first time that such tests have been network of pipes leading to the heat exchanger within
carried out on piles in Scotland. the building. The double use of piles to provide both

349
structural support and to realise ground source energy 5 TEST PILE DETAILS
has been successfully employed in central Europe
since the 1980s. The first such use of piles in the UK Two 12 m long precast concrete piles were manufac-
did not take place until the 21st Century. tured with a plastic U-tube embedded in the centre
An important component of the economic viability of the pile (Figure 1). The 270 mm square piles were
of energy piles is that the length of pile appropriate fabricated in the normal way, but with the plastic
for structural and geotechnical capacity is then used tube held in position using a cross piece shear link
to provide the energy, i.e. piles should not be length- reinforcing bar.
ened purely for energy purposes. Piles were manufactured with 32 mm diameter
HDPE plastic pipe cast inside with the top of the pipes
200 mm from the pile head in one pile and 500 mm
4 BALMORE TEST SITE GEOLOGY from the pile head in a second pile (Figure 2). This
was to investigate whether there was any difference in
Balmore lies in the valley of the River Kelvin to the the handling and driving characteristics of the piles,
north of Glasgow, a short distance west of the town compared to a standard pile.
of Torrance. The area is underlain by Drift deposits
comprising glacial till and glaciofluvial sands and
gravels, with alluvium in the Kelvin Valley. Beneath
the Drift deposits is Carboniferous (Namurian) bed-
rock. Groundwater is encountered 0.75 m below
ground level, flowing downhill towards the river.

Figure 3. Driving of precast concrete energy piles.

Figure 1. Precast energy pile before casting concrete.

Figure 2. Heads of precast energy piles before casting. Figure 4. Driven steel energy pile.

350
An 18 m standard pile (i.e. without pipes) was
pitched and driven into the ground. This was achieved
by a 6 m length driven in first, followed by joining a
12 m length on top. Second and third piles were then
driven, similarly with a 6 m standard section but fol-
lowed by a 12 m energy pile section attached to the
top (Figure 3). All piles had a driven length of about
17 m with approximately 1 m pile left upstanding.
All piles withstood pitch and drive conditions for
the different configurations of plastic tube location,
and for loose and hard driving, and no differences
were observed between the standard pile and the two
energy piles.
In addition to the three precast concrete piles, a
steel tubular pile of 244 mm diameter with a welded
closed end steel shoe was also driven 17 m into the
ground. A plastic U-tube, similar to before, was
installed full depth and a standard cementitious grout
was used to fill the pile (Figure 4).
All of the above test piles were driven during
June 2007.

Figure 5. Coaxial pipe being installed.


6 PUSHED-IN PIPE DETAILS

During August 2007, Lankelma Ltd were employed


to install a pushed-in coaxial pipe (Figure 5). The
borehole was advanced by cone-penetrometer push-
ing techniques and the 40 mm/25 mm outside diam-
eter HDPE plastic pipe was installed to 15.8 m depth.
It is presumed that after installation the soils have
collapsed against the outer wall of the coaxial pipe.
There is no borehole backfilling or grouting between
the closed coaxial pipe and the borehole wall.

7 THERMAL CONDUCTIVITY TESTING

The testing procedure for a thermal conductivity test


needs to be able to differentiate between the thermal
resistance of the pile or borehole and the thermal con-
ductivity of the ground. The general arrangement of
the testing apparatus is shown in Figure 6.
The procedure is to inject heat at a constant flow
rate into the pile or borehole, whilst measuring the
change with time of the inlet and outlet water tem- Figure 6. General arrangement for a thermal conductivity
test.
perature. After sufficient time the effects of thermal
storage in the plastic tube and in the pile or borehole
will be overcome, and after this any temperature rise
will be due only to the conductivity of the ground. 8 THERMAL CONDUCTIVITY TEST RESULTS
The most common approach is then to plot the mean FOR THE PILES
of the inlet and outlet temperatures against log time,
and when the plot becomes linear the slope of this A testing company was employed to undertake testing
portion is used to estimate the thermal conductivity of the piles. Only one of the concrete energy piles, the
of the ground. It should be noted that there is cur- one manufactured with the pipe cast 200 mm from
rently no standard UK procedure or specification for the pile head, was tested (Figures 7 and 8) plus the
thermal conductivity testing. steel pile (Figures 9 and 10).

351
Figure 7. Thermal test on concrete pile.
Figure 9. Thermal test on steel pile.

Figure 8. Test result for concrete pile.


Figure 10. Test result for steel pile.

For the test on the concrete pile, the testing com-


pany quoted that the ground thermal conductivity is
2.56 Wm-1K-1 with the thermal resistance of the
pile being 0.17KmW-1. For the test on the steel pile,
quoted values for the ground thermal conductivity
are 2.37 Wm-1K-1 and the thermal resistance of the
pile 0.11 KmW-1.

9 THERMAL CONDUCTIVITY TEST


RESULTS FOR THE PUSHED-IN PIPE

Another testing company was employed to undertake


testing of the borehole (Figures 11 and 12), which
was located 10 m from the nearest pile.
For the test on the borehole, this testing company
quoted that the ground thermal conductivity is 2.1 ±
0.5 Wm-1K-1 with the thermal resistance of the Figure 11. Thermal test on pushed-in pipe.

352
11 PROCUREMENT PROCESS AND
CO-ORDINATION OF SUBCONTRACTORS

The management of building works involving ground


source heating systems can quickly become complex
if the multiple specialist disciplines are not controlled
from one source. There are two project management
models developing in the UK at present and these are
described below;
(1) Led by the Engineer
Here a typical project organization would involve
a) the Client with a Quantity Surveyor, b) the Struc-
tural Engineer, c) the Mechanical and Electrical
Consultant, d) Main Contractor, e) Ground Source
Figure 12. Test result for pushed-in pipe. Installation Contractor, f) Ground Source Designer,
g) Heat Exchanger Supplier, h) Foundations Contrac-
tor and i) Site investigation Contractor.
It is best if the Structural Engineer and the Mechan-
borehole being in the range 0.005 to 0.11 KmW-1. ical and Electrical Consultant are the same organisa-
It was stated that the latter portion of the test data tion. This organisation then needs to be capable of
indicated that global thermal conductivity of the managing the Ground Source Installation Contractor,
ground could be as high as 7 Wm-1K-1, due to Heat Exchanger Supplier, Foundations Contractor
advection with the flow of groundwater. This bore- and the Site investigation Contractor. Interfaces of
hole was expected to be able to exchange 1 kW of responsibility reduce if the Mechanical and Electrical
heat with the ground over 3 days. Consultant is the designer for both internal heating
and cooling plant, including air-conditioning, and for
external ground source energy supply. Problems com-
monly arise in this model when one contractor cannot
10 REVIEW OF RESULTS
provide the full range of services specified, or when
the specification is inconsistent or incomplete.
Measured ground thermal conductivity values are;
For example, the Site Investigation Contractor may
• concrete pile; 2.56 Wm-1K-1 also be able to provide the services of Ground Source
• steel pile; 2.37 Wm-1K-1 Installation Contractor. Alternatively, the Foundations
• borehole; 2.1 ± 0.5 Wm-1K-1. Contractor may be able to provide the services of both
Site Investigation Contractor and Ground Source
Measured thermal resistances are;
Installation Contractor. Here the Foundations Contrac-
tor may claim that he can also provide the services of
• concrete pile; 0.17KmW-1 Heat Exchanger Supplier, however in reality this will
• steel pile; 0.11KmW-1 be another supplier. It is clear that the Ground Source
• borehole; 0.005 to 0.11KmW-1. Installation Contractor, Ground Source Designer and
Heat Exchanger Supplier require a very close work-
The values of ground thermal conductivity range ing relationship. For example the flow rate and car-
1.6 to 2.6 Wm-1K-1. Moisture content has a signifi- rier fluid used, combined with the characteristics of
cant influence on measured values and published data the ground and the ground-pipe contact material, will
can be summarised as; all have a direct influence on the ability of the heat
saturated clay <2.5 Wm-1K-1 exchanger to work at full capacity.
saturated sand <3.5 Wm-1K-1 (2) Led by the Contractor
concrete 1.3 Wm-1K-1 The second model is contractor led and here the
water 0.6 Wm-1K-1. Main Contractor is responsible for the manage-
Thus the results from the three tests all appear to ment of design and build specialists. The ideal sce-
be reasonable although it is not known which particu- nario is once again that Structural Engineer and the
lar value would be most appropriate for design. Mechanical and Electrical Consultant are the same
The borehole offers least resistance to the transfer organisation. The Mechanical and Electrical Consult-
of heat between the fluid in the plastic pipe and the ant calculates and provides the heating and cooling
ground. The concrete pile offers more resistance than load requirements for the building and prepares ten-
the grout filled steel tubular pile. der documents which require a heating, cooling and

353
ventilation solution. The clarity of these documents the UK may restrict which types can be used in the
is essential. future. A future ban on standard antifreeze types may
The Ground Source Installation Contractor could be mean that existing systems need to replace their fluid
a single source design and installation service, incor- which could be a large expense for industrial scale
porating Ground Source Designer and Heat Exchanger systems currently in operation.
Supplier. It would be possible for Ground Source If boreholes or energy piles are to be adopted
Installation Contractor, Ground Source Designer, within the footprint of a proposed building, there is
Heat Exchanger Supplier, Foundations Contractor and a large construction phase interface between the sub-
the Site investigation Contractor to work together to structure construction and the pipe laying and trench-
provide one package of works. It is also possible that ing works. When pipework is within the building
the Ground Source Installation Contractor can pro- footprint, the installation head manifold needs to be
vide associated specialist construction services such constructed and the pipework should then be taken by
as underfloor heating pipe installation including the the shortest route into a single trench. This trench can
screed and finishes. then be routed straight to the plant room. This is the
In both project management models, it is criti- quickest method of clearing the substructure such that
cal that the overlap between the ground source sys- pile caps can be constructed. This requires a clearly
tem installation and substructure construction is defined order of responsibility for pile head prepara-
planned. At tender stage in the Contractor led model, tion, trenching, pipelaying, backfilling and pile cap
the Ground Source Installation Contractor should construction including manifold protection.
include written proposals for installation and connec- Alternatively, if the borehole field or energy pile
tion methods. The pile head preparation (for energy array (where the piles are not to be loaded) is located
piles) or the borehole head connection, together with outside of the building footprint, the trenching and
trenching, pipe-laying, backfill materials, timescales pipe laying operation will have no interface with the
and plant involved need to be described in detail. substructure and could be simultaneous to pile cap
Attendances required from the Main Contractor by construction. If an energy pile array is used, there is
each party can then be identified. no structural head preparation. The pipework can then
be placed and the pile head buried.

12 PILE INSTALLATION AND CONNECTIONS


13 CONCLUSIONS
Typically the material used for a ground source system
is HDPE plastic pipe. The ground loop can be installed Comparative thermal conductivity testing of piles and
in a borehole or cast into a pile, or it can be pushed a borehole are described. The results of installation
directly into the ground. When drilled boreholes are used and testing of both precast concrete and steel driven
it is important to note that thermally enhanced grout is energy piles are presented.
required to improve thermal conductivity between the There is currently no standard UK specifica-
pipework and the ground. A bentonite backfill will act tion for thermal conductivity testing and the three
as an insulator and inhibit heat conduction. tests described were all undertaken using different
When heat exchangers are operational they are procedures.
pumping the carrier fluid through a pipe network. The It is demonstrated that piles can be used to measure
pipe network requires to be sealed at all connections the thermal properties of the ground and this form of
and should be pressure tested continuously as part of testing could be considered in future to be included
the installation works. The best and quickest method as an additional part of any proposed programme of
of jointing the pipework is by fusion welding. This pile load testing.
process involves melting a collar onto two butt ended Foundation piles which incorporate a ground source
sections of the pipe. Fusion welding is an electrical pipe can offer a cost effective sustainable method of
technique which creates a full circumference seal if providing heat energy for a wide range of construc-
used with purpose made equipment. tion developments. However, procurement and the
When carrier fluid in a closed pipe loop is likely to construction sequence must be properly planned and
be exposed to very low temperatures it will be neces- managed to give the Client the best value for money.
sary to ensure that freezing does not occur. Antifreeze
is often included in the fluid to overcome this. Prop-
erly sealed pipework will provide efficient flow to the REFERENCES
heat pump and avoid any possible contamination of
groundwater. The use of antifreeze in the carrier fluid Brandl, H., 1998, Energy piles for heating and cooling build-
raises the issue of ground contamination in the event ings, 7th International Conference on Piling and Deep
that pipes leak or burst. The Environment Agency in Foundations, Vienna, Austria.

354
Ennigkeit, A. and Katzenbach, R., 2001, The double use of Suckling, T.P. and Cannon, R., 2004, Energy piles for Pallant
piles as foundation and heat exchanging elements, 15th House Art Gallery, Chichester, UK, Ground Engineering,
International Conference on Soil Mechanics and Geo- July.
technical Engineering, Istanbul, Turkey. Lennon, D.J., Watt, E. and Suckling, T.P, 2009, Thermal
Suckling, T.P. and Smith, P., 2002, Environmentally friendly response tests on driven piles and a pushed-in pipe
geothermal piles at Keble College, Oxford, UK, Deep at Balmore, Scotland, Thermal Characteristics of the
Foundations Institute Conference, Nice, France. Ground, Geotechnique Symposium in Print.

355

You might also like