Professional Documents
Culture Documents
D.J. Lennon
Stent Foundations Limited, Balmore, UK
E. Watt
Stent Foundations Limited, Balmore, UK
T.P. Suckling
Stent Foundations Limited, Basingstoke, UK
ABSTRACT: Comparative thermal conductivity testing of piles and a borehole are described. The results of
installation and testing of both precast concrete and steel driven energy piles are presented. There is currently
no standard UK specification for thermal conductivity testing and the three tests de-scribed were all undertaken
using different procedures. It is demonstrated that piles can be used to measure the thermal properties of the
ground. Foundation piles which incorporate a ground source pipe can offer a cost effective sustainable method
of providing heat energy for a wide range of construction developments. Procurement and the construction
sequence must be properly planned and managed to give the Client the best value for money.
The sustainable use of resources is now an impor- The heat pump for the extraction of ground source
tant part of the construction process. In the United energy was invented in the 19th Century. In Europe
Kingdom (UK) statutory requirements currently ground temperature is reasonably constant below
require a proportion of the energy usage of any new about 8 m depth. This phenomenon can be used in
building to be provided from a renewable source. In the design of seasonal thermal ground storage, with
the future the proportion required is likely to increase excess energy transferred between a building and the
and when at levels above 10% ground source energy ground throughout the year as the seasons and the
storage systems are likely to become viable in many building’s energy requirements change.
cases. The available energy capacity from the ground
Designers of piles have the opportunity to spec- beneath or surrounding any building depends on factors
ify energy piles whenever piles are required to pro- including geometry, geology, groundwater and ground-
vide structural support to any building. However, water flow. Other aspects such as whether the ground
it is currently very difficult to ensure that energy surface is covered and thus not able to receive replen-
piles are compatible with the architectural, struc- ishing solar energy also influence the available ground
tural and energy design requirements unless intro- source energy. Every project will thus be different and a
duced into the building design concept at an early calculation is essential for each and every building.
stage.
Full scale thermal testing of in-situ piles is unfor-
tunately still rare in the UK. Comparative tests are 3 ENERGY PILES
described on a driven concrete pile, a driven steel pile
and on a pushed-in plastic coaxial pipe, all installed Energy piles can be either bored or driven piles, nor-
on a test site in Balmore, Scotland. This is the first mally comprising reinforced concrete. The piles con-
time ever worldwide that side-by-side thermal tests on tain plastic pipes which transport a heat transfer fluid.
piles and a pushed-in coaxial pipe have been under- From the pile heads these pipes are connected to a
taken, and also the first time that such tests have been network of pipes leading to the heat exchanger within
carried out on piles in Scotland. the building. The double use of piles to provide both
349
structural support and to realise ground source energy 5 TEST PILE DETAILS
has been successfully employed in central Europe
since the 1980s. The first such use of piles in the UK Two 12 m long precast concrete piles were manufac-
did not take place until the 21st Century. tured with a plastic U-tube embedded in the centre
An important component of the economic viability of the pile (Figure 1). The 270 mm square piles were
of energy piles is that the length of pile appropriate fabricated in the normal way, but with the plastic
for structural and geotechnical capacity is then used tube held in position using a cross piece shear link
to provide the energy, i.e. piles should not be length- reinforcing bar.
ened purely for energy purposes. Piles were manufactured with 32 mm diameter
HDPE plastic pipe cast inside with the top of the pipes
200 mm from the pile head in one pile and 500 mm
4 BALMORE TEST SITE GEOLOGY from the pile head in a second pile (Figure 2). This
was to investigate whether there was any difference in
Balmore lies in the valley of the River Kelvin to the the handling and driving characteristics of the piles,
north of Glasgow, a short distance west of the town compared to a standard pile.
of Torrance. The area is underlain by Drift deposits
comprising glacial till and glaciofluvial sands and
gravels, with alluvium in the Kelvin Valley. Beneath
the Drift deposits is Carboniferous (Namurian) bed-
rock. Groundwater is encountered 0.75 m below
ground level, flowing downhill towards the river.
Figure 2. Heads of precast energy piles before casting. Figure 4. Driven steel energy pile.
350
An 18 m standard pile (i.e. without pipes) was
pitched and driven into the ground. This was achieved
by a 6 m length driven in first, followed by joining a
12 m length on top. Second and third piles were then
driven, similarly with a 6 m standard section but fol-
lowed by a 12 m energy pile section attached to the
top (Figure 3). All piles had a driven length of about
17 m with approximately 1 m pile left upstanding.
All piles withstood pitch and drive conditions for
the different configurations of plastic tube location,
and for loose and hard driving, and no differences
were observed between the standard pile and the two
energy piles.
In addition to the three precast concrete piles, a
steel tubular pile of 244 mm diameter with a welded
closed end steel shoe was also driven 17 m into the
ground. A plastic U-tube, similar to before, was
installed full depth and a standard cementitious grout
was used to fill the pile (Figure 4).
All of the above test piles were driven during
June 2007.
351
Figure 7. Thermal test on concrete pile.
Figure 9. Thermal test on steel pile.
352
11 PROCUREMENT PROCESS AND
CO-ORDINATION OF SUBCONTRACTORS
353
ventilation solution. The clarity of these documents the UK may restrict which types can be used in the
is essential. future. A future ban on standard antifreeze types may
The Ground Source Installation Contractor could be mean that existing systems need to replace their fluid
a single source design and installation service, incor- which could be a large expense for industrial scale
porating Ground Source Designer and Heat Exchanger systems currently in operation.
Supplier. It would be possible for Ground Source If boreholes or energy piles are to be adopted
Installation Contractor, Ground Source Designer, within the footprint of a proposed building, there is
Heat Exchanger Supplier, Foundations Contractor and a large construction phase interface between the sub-
the Site investigation Contractor to work together to structure construction and the pipe laying and trench-
provide one package of works. It is also possible that ing works. When pipework is within the building
the Ground Source Installation Contractor can pro- footprint, the installation head manifold needs to be
vide associated specialist construction services such constructed and the pipework should then be taken by
as underfloor heating pipe installation including the the shortest route into a single trench. This trench can
screed and finishes. then be routed straight to the plant room. This is the
In both project management models, it is criti- quickest method of clearing the substructure such that
cal that the overlap between the ground source sys- pile caps can be constructed. This requires a clearly
tem installation and substructure construction is defined order of responsibility for pile head prepara-
planned. At tender stage in the Contractor led model, tion, trenching, pipelaying, backfilling and pile cap
the Ground Source Installation Contractor should construction including manifold protection.
include written proposals for installation and connec- Alternatively, if the borehole field or energy pile
tion methods. The pile head preparation (for energy array (where the piles are not to be loaded) is located
piles) or the borehole head connection, together with outside of the building footprint, the trenching and
trenching, pipe-laying, backfill materials, timescales pipe laying operation will have no interface with the
and plant involved need to be described in detail. substructure and could be simultaneous to pile cap
Attendances required from the Main Contractor by construction. If an energy pile array is used, there is
each party can then be identified. no structural head preparation. The pipework can then
be placed and the pile head buried.
354
Ennigkeit, A. and Katzenbach, R., 2001, The double use of Suckling, T.P. and Cannon, R., 2004, Energy piles for Pallant
piles as foundation and heat exchanging elements, 15th House Art Gallery, Chichester, UK, Ground Engineering,
International Conference on Soil Mechanics and Geo- July.
technical Engineering, Istanbul, Turkey. Lennon, D.J., Watt, E. and Suckling, T.P, 2009, Thermal
Suckling, T.P. and Smith, P., 2002, Environmentally friendly response tests on driven piles and a pushed-in pipe
geothermal piles at Keble College, Oxford, UK, Deep at Balmore, Scotland, Thermal Characteristics of the
Foundations Institute Conference, Nice, France. Ground, Geotechnique Symposium in Print.
355