DAILY ACTIVITY PROJECT PULLING AREA PT.

FAJAR SURYA WISESA TBK


PT. MEGA ENERGY INDONESIA
Duration
No Description Area Jumlah Date Progres (%) Name User Manpower Name Clasification Picture Work Problem/Finding Remark
(Hour)
1 >>Pulling Cable Side Hill Algas dan 2 Tarikan 12/8/2021 7 Hours 100% Hariadi Waryo Group Leader <Banjir area DAF dari jam
2 tarikan DAF Primery Tomi Iskandar Helper 8:00 Continue
>>Perapian kabel Naufal Daffa Helper Hujan area DAF
Azis Bustomi Helper
Jajajng Sarip Helper
M Alfiansyah Helper
Lukman Sanusi Helper
Dani Agustin Helper
Ichsan Hariyanto Helper
Marulloh Helper
Irpan Helper
Andra Pratama Helper
M. ismail Helper
Lili Abdul Ahmad Helper
Bayu Helper
2 >>Pulling Cable Side Hill Algas dan 2 Tarikan 12/8/2021 7 Hours 100% Hariadi Waryo Group Leader <Banjir area DAF dari jam Continue
2 tarikan DAF Primery Tomi Iskandar Helper 8:00
>>Perapian kabel Naufal Daffa Helper Hujan area DAF
Azis Bustomi Helper
Jajajng Sarip Helper
M Alfiansyah Helper
Lukman Sanusi Helper
Dani Agustin Helper
Ichsan Hariyanto Helper
Marulloh Helper
Irpan Helper
Andra Pratama Helper
M. ismail Helper
Lili Abdul Ahmad Helper
Bayu Helper

Note : Absen
Nama Posisi Keterangan

Admin Officer Prepared by Owner

Reggi Supervisor PT. Fajar Surya Wisesa Tbk


PT. FAJAR SURYA WISESA TBK
Jl. Kampung Gardu Sawah No. 1, RT.01 / RW.01, Kalijaya, Kec. Cikarang Barat
Bekasi, Jawa Barat 17530

DAILY ACTIVITY OF PULLING CABLE PROJECT - REPORT


( 08 Desember 2021 )

Subcontractor : PT. Mega Energy Indonesia


NO AREA / EQUIPMENT / MATERIAL ACTIVITY PROGRESS PIC REMARKS
1 Algas and DAF / Cable 300mm DAF-1 Cable 10 (1x300mm) 100% Hariadi Done
2 Algas and DAF / Cable 300mm Screw Press Cable 7 (1x300mm) 100% Hariadi Done
3 Algas and DAF / Cable 300mm Side Hill 16 (1x300mm) 100% Hariadi Done
4 Algas and DAF / Cable 300mm MCC 3,4 10(1X300mm) 0% Hariadi
5
6
7
8
9
10
11
12
13
14
15
16

Dibuat oleh

Dimas Fahmigafur