Professional Documents
Culture Documents
Question 1 of 10
The critical or essential elements of a network are:
Result:
Correct
Answer 1 is C
Feedback
Correct.
Question 2 of 10
Task identification is an essential part of creating the network to which the CPM will be applied. An
important task identification tip is:
a. Make tasks large enough so that they can be assigned to teams, rather than individuals, so that they get done.
b. Avoid linking tasks with deliverables.
c. When in doubt, make tasks small.
Result:
Correct
Answer 2 is C
Feedback
Correct.
Question 3 of 10
Estimating the duration of a task:
Result:
Test Review Report
Correct
Answer 3 is B
Feedback
Correct.
Question 4 of 10
Each task that is on the critical path:
c. Must be completed whereas tasks off the critical path are optional.
Result:
Correct
Answer 4 is B
Feedback
Correct.
Question 5 of 10
Repeated applications of the CPM to a variety of projects would reveal that any given project:
Result:
Correct
Answer 5 is B
Feedback
Correct.
Question 6 of 10
A Gantt chart:
b. Is not related to the CPM but is, instead, an alternative project management tool applicable to simpler projects.
c. Is useful only for construction projects.
Result:
Correct
Test Review Report
Answer 6 is A
Feedback
Correct.
Question 7 of 10
Once the network diagram is completed and the CPM performed, the CPM:
b. Should not be modified because it is the benchmark against which project progress will be measured.
c. Becomes irrelevant because its use is solely as a project planning tool; not a project execution tool.
Result:
Correct
Answer 7 is A
Feedback
Correct.
Question 8 of 10
CPM software:
c. Is intended for CPM analysis on actual planning, design, construction, and other projects.
Result:
Incorrect
Option B is not correct
Feedback
Incorrect.
Question 9 of 10
Once a project is completed:
a. The series of CPM analyses that were performed can be examined to identify lessons learned.
b. The project-specific CPM no longer has value because it is a forward-looking tool, not a retrospective one.
c. The software Open Workbench will automatically perform the analyses noted in “a” above.
Result:
Correct
Answer 9 is A
Test Review Report
Feedback
Correct.
Question 10 of 10
This webinar:
Result:
Incorrect
Option A is not correct
Feedback
Incorrect.